SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Comptia Project + Project Management
Start Test
Study First
Subjects
:
certifications
,
comptia-project-+
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The smallest unit of time used in scheduling a project. calendar units are generally in hours - days - or weeks - but can also be in quarters years - months - shifts - or even minutes
develop project team (Process)
calendar unit
risk avoidance (Technique)
resource calendar
2. Communicating and working with stakeholders to meet their needs and address issues as they occur
percent complete
manage stakeholder expectations (Process)
specification
methodology
3. Analysis. a statistical technique that calculates the average outcome when the future includes scenarios that may or may not happen. used in decision tree analysis.
activity identifier
perform qualitative analysis (Process)
expected monetary value (EMV)
earned value (EV)
4. Calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal. ratio of remaining work to funds remaining
to complete performance index (TCPI)
analogous estimating (Technique)
virtual team
sponsor
5. Technique that computes or iterates the project cost or project schedule many times using input values selected at random from probability distributions of possible costs or durations - to calculate a distribution of total project costs or completion
projectized organization
Monte Carlo analysis
sponsor
project management process group
6. Request for proposal - but may have a narrower or more specific meaning
fast tracking (Technique)
invitation for bid (IFB)
Monte Carlo analysis
perform quality control (Process)
7. Logical relationship where completion of work of the successor activity cannot finish until the completion of work of the predecessor activity.
network path
contingency reserve(Output/Input)
finish to finish (FF)
inspection (Technique)
8. A short unique numeric or text identification assigned to each schedule activity to differentiate that project activity from other project activities. typically unique within any one project schedule network diagram
report performance (Process)
schedule network analysis (Technique)
successor activity
activity identifier
9. Defined systematic procedure employed by a human resource to perform an activity to produce a product or result or deliver a service that may employ one or more tools
workaround
technique
schedule network analysis (Technique)
claim
10. Calendar of working days and non-working days that determines those dates on which each specific recourse is idle or can be active
resource calendar
portfolio management (Technique)
forward pass
project phase
11. Planned dates for performing schedule activities and planned dates for meeting schedule milestones
budget at completion (BAC)
activity attributes (Output/Input)
project risk management (Knowledge Area)
project schedule (Output/Input)
12. Person or organization that is actively involved in the project or whose interests may be positively or negatively affected by execution or completion of the project
percent complete
stakeholder
node
execute
13. Reserve
logical relationship
role
project scope
buffer
14. Processes required to track - review and regulate the progress and performance of the project - identify any areas in which changes to the plan are required and initiate the corresponding changes.
contingency reserve(Output/Input)
monitor and controlling processes (Process Group)
earned value technique (EVT) (Technique)
develop project charter (Process)
15. A point that is not settled or is under discussion or over which there are opposing views or disagreements
early start date (ES)
issue Point or matter in question or dispute
schedule management plan (Output/Input)
plan quality (Process)
16. Risk response planning technique associated with threats that seeks to reduce the probability of occurrence or impact of a risk to below an acceptable threshold
project management team
project cost management (Knowledge Area)
risk mitigation (Technique)
administer procurements (Process)
17. Logical relationship where completion of the successor schedule activity is dependent upon the initiation of the predecessor schedule activity
activity identifier
risk
start to finish (SF)
schedule performance index (SPI)
18. The expected total cost of a schedule activity - a work breakdown structure component or the project when the defined scope of work will be completed. Calculated based on performance to date or estimated by the project team based on other factors
risk management plan (Output/Input)
rework
estimate at completion (EAC)(Output/Input)
flowcharting (Technique)
19. Describes how the project management team will implement the performing organizations quality plan.
project scope management (Knowledge Area)
quality management plan (Output/Input)
invitation for bid (IFB)
secondary risk
20. A request - demand or assertion of rights by a seller against a buyer or vice versa for consideration - compensation - or payment under the terms of a legally binding contract (such as for a disputed change)
claim
finish date
reserve analysis (Technique)
activity list (Output/Input)
21. A category of projects that have common components significant in such projects - but are not needed or present in all projects. application areas are usually defined in terms of either the product or the type of customer or industry sector
plan quality (Process)
application area
technique
forecast
22. Developing a document that formally authorizes a project or phase and documenting initial requirement that satisfy the stakeholders needs and expectations
develop project charter (Process)
identify stakeholders (Process)
project charter (Output/Input)
variance analysis (Technique)
23. Documenting the actions necessary to define - prepare - integrate and coordinate all subsidiary plans
develop project management plan (Process)
verify scope (Process)
staffing management plan
activity duration
24. Collection of logically related project activities - usually culminating in the completion of a major deliverable. project phase is a component of the project life cycle
perform integrated change control (Process)
risk register (Output/Input)
project management process group
project phase
25. The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule activity is complete
actual duration
lag (Technique)
lessons learned knowledge base
inspection (Technique)
26. Permission and direction to begin work on a specific schedule activity or work package or control account. sanctions project work to ensure that the work is done by the identified organization - at the right time - and in the proper sequence
work authorization
performing organization
change control board (CCB)
request for quotation (RFQ)
27. An organizational placement strategy where the project team members are physically located close to one another in order to improve communication - working relationships and productivity
co-location (Technique)
project procurement management (Knowledge Area)
network logic
plan risk management (Process)
28. Approximating the number of work periods needed to complete individual activities with estimated resources
start date
develop schedule (Process)
defect
estimate activity durations (Process)
29. Graphic display of cumulative costs - labor - hours - percentage of work or other quantities - plotted against time. used to depict planned value - earned value and active costs.
sub phase
finish to start (FS)
s-curve
late finish date (LF)
30. Something toward which work is to be directed - a strategic position to be attained - or a purpose to be achieved - a result to be obtained - a product to produced or a service to be performed
resource breakdown structure
schedule baseline
objective
product
31. Budgeted cost of work performed
close project or phase (Process)
BCWP
failure mode and effect analysis (FMEA) (Technique)
historical information
32. Point in time that work was scheduled to start on a schedule activity. called planned start date.
request for proposal (RFP)
scheduled start date (SS)
project management
parametric estimating (Technique)
33. Launching a process that can result in the authorization of a new project
project initiation
slack
project risk management (Knowledge Area)
workaround
34. Model used in conjunction with manual methods or project management software to perform schedule network analysis to generate the project schedule for use in managing the executing or a project
monitor and control risks (Process)
successor activity
estimate activity durations (Process)
schedule model (Tool)
35. Document that describes how procurement processes from developing procurement documentation through contract closure will be managed
procurement management plan (Output/Input)
flowcharting (Technique)
defect
close project or phase (Process)
36. Those processes performed to complete the work defined in the project management plan to satisfy project objectives
executing processes (Process Group)
perform integrated change control (Process)
monitor and controlling processes (Process Group)
budget
37. Describes when and how human resource requirements will be met
staffing management plan
manage stakeholder expectations (Process)
summary activity
portfolio
38. Analytical technique that uses mathematical models to forecast future outcomes based on historical results. it is a method of determining the variance from a baseline parameter by using prior progress reporting periods data and projecting how much th
project calendar
input (Process) input
trend analysis (Technique)
contract (Output/Input)
39. The amount of funds - budget - or time needed above the estimate to reduce the risk of overruns of project objectives to a level acceptance to the organization
contingency reserve(Output/Input)
grade
activity
plan risk response (Process)
40. A component of work performed during the course of a project
value engineering
activity
effort
close procurements (Process)
41. Method of resolving the total variance in the set of scope - cost - and schedule variables into specific component variances that are associated with defined factors affecting scope - cost and schedule variables
variance analysis (Technique)
log
perform quality assurance (Process)
baseline
42. The aggregate of things used by an organization in any undertaking such as equipment - apparatus - tools - machinery - gear - material.
preventative action
co-location (Technique)
material
schedule management plan (Output/Input)
43. Logical grouping of project management inputs - tools and techniques and outputs. includes initiating processes - planning processes - executing processes - monitoring and controlling processes and closing processes. NOT project phases
decision tree analysis (Technique)
successor activity
near critical activity
project management process group
44. Organizational body or entity assigned various responsibilities related to the centralized and coordinated management of those projects under its domain.
administer procurements (Process)
functional organization
progressive elaboration (Technique)
project management office (PMO)
45. Risk that remains after risk responses have been implemented
residual risk
initiating processes (Process Group)
work performance information
methodology
46. A general data gathering and creativity technique that can be used to identify risks - ideas or solutions to issues by using a group of team members or subject matter experts
predecessor activity
request for proposal (RFP)
activity duration
brainstorming (Technique)
47. An approved plan for a project - plus or minus approved changes. it is compared to actual performance to determine if performance is within acceptable variance thresholds. generally refers to the current baseline - but may refer to the original or so
activity
baseline
brainstorming (Technique)
scheduled start date (SS)
48. Defined function to be performed by a project team member
role
opportunity
develop project team (Process)
forward pass
49. Smaller portion of the overall project created when a project is subdivided by their logical relationship
product
perform quality assurance (Process)
subproject
external deliverable
50. Hierarchal structure of resources by resource category and resource type used in resource leveling schedules and to develop resource limited schedules and which may be used to identify and analyze project human resource management
resource breakdown structure
responsibility assignment matrix (RAM) (Tool)
project life cycle
project initiation management (Knowledge Area)