SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Comptia Project + Project Management
Start Test
Study First
Subjects
:
certifications
,
comptia-project-+
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Narrative description of products - services or results
project time management (Knowledge Area)
project management
statement of work (SOW)
milestone
2. Approved integrated scope-schedule-cost plan for the project work against which project execution is compared to measure and manage performance
close procurements (Process)
activity
performance measurement baseline
request for information (RFI)
3. Logical relationship where initiation of work of the successor activity depends on the completion of work of the predecessor activity
finish to start (FS)
start date
portfolio
risk category
4. Information system consisting of tools and techniques to gather - integrate and disseminate the outputs of project management processes.
project management information system (PMIS) (Tool)
preventative action
conduct procurements (Process)
project management team
5. Schedule network diagramming technique in which schedule activities are represented by boxes or nodes. schedule activities are graphically linked by one or more logical relationships to show the sequence in which the activities are performed
precedence diagramming method (PDM) (Technique)
specification limits
procurement management plan (Output/Input)
administer procurements (Process)
6. Document that describes how procurement processes from developing procurement documentation through contract closure will be managed
procurement management plan (Output/Input)
external deliverable
program
contingency reserve(Output/Input)
7. Developing an approximation of the monetary resources needed to complete project activities
acceptance criteria
objective
logical relationship
estimate costs (Process)
8. One or more numerical or text values that identify characteristics of the work or in some way categorize the schedule activity that allows filtering and ordering of activities within reports
monitor and control risks (Process)
activity code
percent complete
scheduled start date (SS)
9. An estimating technique that uses the values of parameters - such as scope - cost - budget - and duration or measures of scale such as size - weight - and complexity from a previous similar activity as the basis of estimating the same parameter or me
variance analysis (Technique)
percent complete
work breakdown structure dictionary
analogous estimating (Technique)
10. Specific version of the schedule model used to compare actual results to the plan to determine if preventive or corrective action is needed to meet the project objectives
schedule baseline
sub phase
project human resource management (Knowledge Area)
request for information (RFI)
11. A table that links requirements to their origin and traces them throughout the project life cycle
perform quantitative analysis (Process)
variance analysis (Technique)
brainstorming (Technique)
requirements traceability matrix
12. Point in time that work was scheduled to finish on a schedule activity. called planned finish date
activity
simulation
procurement documents (Output/Input)
scheduled finish date (SF)
13. The approved estimate for the project or any work breakdown structure component or any schedule activity
contingency reserve(Output/Input)
budget
work authorization
start to finish (SF)
14. Assumptions are factors that - for planning purposes - are considered to be true - real - or certain without proof or demonstration
schedule performance index (SPI)
parametric estimating (Technique)
assumptions
develop schedule (Process)
15. Smaller portion of the overall project created when a project is subdivided by their logical relationship
claim
successor activity
expected monetary value (EMV)
subproject
16. A diagram that describes a decision under consideration and the implications of choosing one or another of the available alternatives. it is used when some future scenarios or outcomes of actions are uncertain. it incorporates probabilities and costs
forecast
decision tree analysis (Technique)
start date
staffing management plan
17. Degree - amount or volume of risk that an organization or individual will withstand
direct and manage project execution (Process)
matrix organization
risk tolerance
logical relationship
18. Defining how to conduct risk management activities for a project
plan quality (Process)
plan risk management (Process)
defect repair
close project or phase (Process)
19. Calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal. ratio of remaining work to funds remaining
perform quality control (Process)
to complete performance index (TCPI)
develop schedule (Process)
activity attributes (Output/Input)
20. Requests to expand or reduce the project scope - modify policies - processes - plans or procedures - modify costs or budgets - or revise schedules
Gantt chart (Tool)
finish to finish (FF)
change requests
direct and manage project execution (Process)
21. Tracking - reviewing - regulating the progress to meet the performance objectives defined in the project management plan
scheduled finish date (SF)
monitor and control project work (Process)
activity list (Output/Input)
risk register (Output/Input)
22. Approach to optimize project life cycle costs - save time - increase profits - improve quality - expand market share - solve problems - and use resources more effectively
estimate (Output/Input)
value engineering
schedule management plan (Output/Input)
activity
23. An organizational placement strategy where the project team members are physically located close to one another in order to improve communication - working relationships and productivity
project calendar
co-location (Technique)
develop project charter (Process)
reserve analysis (Technique)
24. Number of labor units required to complete a schedule activity or work breakdown structure component
effort
Delphi technique (Technique)
program evaluation and review technique (PERT)
project initiation
25. The latest possible point in time that a schedule activity may begin based upon the schedule network logic - the project completion date and any constraints assigned to schedule activities without violating schedule constraint or delaying project com
assumptions
scheduled finish date (SF)
project schedule network diagram (Output/Input)
late start date (LS)
26. Centralized coordinated management of a program to achieve the program's strategic objectives and benefits
program management
lessons learned knowledge base
technique
activity
27. Identifying - documenting - approving or rejecting and controlling changes to the project baselines
expected monetary value (EMV)
flowcharting (Technique)
request for information (RFI)
change control
28. Action taken to bring a defective or nonconforming component into compliance with requirements or specifications
project management body of knowledge
rework
estimate activity durations (Process)
produce scope
29. Processes required to ensure that the project includes all the work required and only the work required to complete the project successfully
project scope management (Knowledge Area)
risk register (Output/Input)
projectized organization
technical performance measurement (Technique)
30. Examining or measuring to verify whether an activity - component - product - result of service conforms to specified requirements.
stakeholder
inspection (Technique)
workaround
scope
31. ACWP
procurement documents (Output/Input)
actual cost of work performed
failure mode and effect analysis (FMEA) (Technique)
backward pass
32. Temporary endeavor undertaken to create a unique product - service or result
pareto chart (Tool)
practice
issue Point or matter in question or dispute
project
33. Processes required to ensure timely and appropriate generation - collection - distribution - storage - retrieval - and ultimate disposition of project information
functional manager
buyer
project communications management (Knowledge Area)
plan communications (Process)
34. A planning technique that subdivides the project scope and project deliverables into smaller - more manageable components - until the project work associated with accomplishing the project scope and providing the deliverables is defined in sufficient
decomposition (Technique)
verification
Delphi technique (Technique)
activity duration
35. Process of numerically analyzing the effect of identified risks on overall project objectives
perform quantitative analysis (Process)
technical performance measurement (Technique)
actual cost (AC)
procurement management plan (Output/Input)
36. A point in time associated with schedule activity's completion.
risk category
precedence relationship
initiating processes (Process Group)
finish date
37. Permission and direction to begin work on a specific schedule activity or work package or control account. sanctions project work to ensure that the work is done by the identified organization - at the right time - and in the proper sequence
work authorization
requirements traceability matrix
logical relationship
plan risk response (Process)
38. Total amount of time that a schedule activity maybe delayed from its early start date without delaying the project finish date or violating a schedule constraint.
result
project scope management (Knowledge Area)
standard
total float
39. Members of the project team who are directly involved in project management activities
project management team
earned value management (EV
BCWP
verification
40. Communicating and working with stakeholders to meet their needs and address issues as they occur
threat
decision tree analysis (Technique)
manage stakeholder expectations (Process)
earned value management (EV
41. Estimate of the amount of work that has been completed on an activity or a work breakdown structure component
float
percent complete
actual duration
define scope (Process)
42. Risk response planning technique associated with threats that seeks to reduce the probability of occurrence or impact of a risk to below an acceptable threshold
forecast
role
activity code
risk mitigation (Technique)
43. The process of managing procurement relationships - monitoring contract performance - and making changes and corrections as needed
administer procurements (Process)
estimate activity durations (Process)
progressive elaboration (Technique)
assumptions
44. Document that graphically depicts the project team members and their interrelationships for a specific project
threshold
risk breakdown structure (RBS)
project organization chart (Output/Input)
external deliverable
45. Analyzing activity sequences - durations - resource requirements and schedule constraints to create the project schedule
effort
develop schedule (Process)
portfolio management (Technique)
lessons learned(Output/Input)
46. The statue - quality or sense of being restricted to a given course of action or inaction. an applicable restriction or limitation - either internal or external to a project - which will affect the performance of the project or a process.
scheduled start date (SS)
conduct procurements (Process)
constraint (Input)
monitor
47. An information gathering technique used as a way to reach a consensus of experts on a subject. experts on the subject participate in the technique anonymously. a facilitator uses a questionnaire to solicit ideas about the important project points rel
Delphi technique (Technique)
duration (DU or DUR)
project schedule network diagram (Output/Input)
plan quality (Process)
48. Those processes performed to complete the work defined in the project management plan to satisfy project objectives
forecast
executing processes (Process Group)
activity duration
lag (Technique)
49. Collection of generally sequential - non overlapping product phases whose name and number are determined by the manufacturing and control needs of the organization.
external deliverable
product life cycle
develop schedule (Process)
technical performance measurement (Technique)
50. Cost - time - quality - technical or resource value used as a parameter and which may be included in product specification. crossing the threshold should trigger some action.
log
product life cycle
verify scope (Process)
threshold