SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Comptia Project + Project Management
Start Test
Study First
Subjects
:
certifications
,
comptia-project-+
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Implementing risk response plans - tracking identified risks - monitoring residual risks - identifying new risks and evaluating risk process throughout the project
monitor and control risks (Process)
verify scope (Process)
requirements traceability matrix
triggers
2. Analytical technique that uses three cost or duration estimates to represent optimistic - most likely and pessimistic scenarios.
verification
lead (Technique)
three point estimate (Technique)
plan risk management (Process)
3. Specific version of the schedule model used to compare actual results to the plan to determine if preventive or corrective action is needed to meet the project objectives
free float
output (Process)
failure mode and effect analysis (FMEA) (Technique)
schedule baseline
4. One of the defining points of a schedule network; a junction point joined to some or all of the other dependency lines
actual duration
node
specification limits
master schedule (Tool)
5. Method of resolving the total variance in the set of scope - cost - and schedule variables into specific component variances that are associated with defined factors affecting scope - cost and schedule variables
performance measurement baseline
variance analysis (Technique)
close project or phase (Process)
work breakdown structure dictionary
6. Any item - internal or external - that is required by a process before that process proceeds
duration (DU or DUR)
Monte Carlo simulation
baseline
input (Process) input
7. Uncertain event or condition that has a positive or negative effect on projects objectives
perform quality assurance (Process)
actual cost (AC)
project phase
risk
8. Project schedule compression that changes network logic to overlap phases that would normally be done in sequence
fast tracking (Technique)
change control board (CCB)
estimate at completion (EAC)(Output/Input)
code of accounts (Tool)
9. Describes each component in the work breakdown structure (WBS). for each WBS component - the WBS dictionary includes a brief definition of the scope of statement of work - defined deliverables - a list of associated activities and list of milestones.
project organization chart (Output/Input)
work breakdown structure dictionary
administer procurements (Process)
project scope statement (Output/Input)
10. A collection of formal documented procedures that define how project deliverables and documentation will be controlled - changed and approved. in most application areas - the change control system is a subset of the configuration management system
standard
change control system (Tool)
organizational process assets (Output/Input)
voice of the customer
11. Budgeted cost of work performed
rolling wave planning (Technique)
authority
project management process group
BCWP
12. The process of completing each project procurement
actual duration
common cause
close procurements (Process)
free float
13. Structure in which the project manager shares responsibility with the functional managers for assigning priorities and directing the work of persons assigned to the project
risk management plan (Output/Input)
matrix organization
acceptance criteria
change control
14. Processes to purchase or acquire the products - services or results needed from outside the project team to perform the work
project procurement management (Knowledge Area)
Monte Carlo analysis
close project or phase (Process)
request for proposal (RFP)
15. Bar chart showing the amount of time that a resource is scheduled to work over a series of time periods.
work breakdown structure (WBS) (Output/Input)
monitor and control risks (Process)
configuration management system (Tool)
resource histogram
16. Identifying - documenting - approving or rejecting and controlling changes to the project baselines
backward pass
program management
change control
s-curve
17. The statue - quality or sense of being restricted to a given course of action or inaction. an applicable restriction or limitation - either internal or external to a project - which will affect the performance of the project or a process.
flowcharting (Technique)
planned value (PV)
constraint (Input)
matrix organization
18. Process which generates hundreds or thousands of probable performance outcomes based on probability distributions for cost and schedule on individual tasks. the outcomes are used to generate a probability distribution for a project as a whole.
organizational process assets (Output/Input)
Monte Carlo simulation
planning package
executing processes (Process Group)
19. Developing a detailed description of the project and product
request for proposal (RFP)
milestone
work authorization system (Tool)
define scope (Process)
20. Model used in conjunction with manual methods or project management software to perform schedule network analysis to generate the project schedule for use in managing the executing or a project
schedule model (Tool)
identify stakeholders (Process)
backward pass
risk register (Output/Input)
21. Provider of products - services or results
request for information (RFI)
estimate costs (Process)
seller
s-curve
22. Processes that organize and manage the project team
summary activity
develop human resource plan (Process)
project human resource management (Knowledge Area)
project calendar
23. Narrative description of the project scope - including major deliverables - project assumptions - project constraints and a description of work that provides a documented basis for making future project decisions and for confirming or developing a co
specification limits
enterprise environmental factors (Input/Output)
project scope statement (Output/Input)
organizational process assets (Output/Input)
24. Technique for estimating that applies a weighted average of optimistic - pessimistic and most likely estimates when there is uncertainty with the individual activity estimates
start to start (SS)
program evaluation and review technique (PERT)
Monte Carlo simulation
BCWS
25. Collecting and distributing performance information - including status reports - progress measurements and forecasts
residual risk
portfolio management (Technique)
activity attributes (Output/Input)
report performance (Process)
26. The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule activity is complete
project life cycle
quality management plan (Output/Input)
scope baseline
actual duration
27. Calendar of working days or shifts that establishes those dates on which schedule activities are worked and nonworking days that determine those dates on which schedule activities are idle
sponsor
project calendar
define activities (Process)
requested change(Output/Input)
28. Document that establishes criteria and activities for developing and controlling the project schedule
schedule network analysis (Technique)
schedule management plan (Output/Input)
rework
activity list (Output/Input)
29. Identifying early and late start dates as well as early and late finish dates for the uncompleted portions of project schedule activities
template
schedule network analysis (Technique)
finish date
baseline
30. Document that describes how procurement processes from developing procurement documentation through contract closure will be managed
workaround
procurement management plan (Output/Input)
project human resource management (Knowledge Area)
external deliverable
31. Group of related schedule activities aggregated at some summary level and displayed as a single activity at that summary level. same as summary activity.
Delphi technique (Technique)
hammock activity
network path
imposed date
32. Work that must be performed to deliver a product - service or result with the specified features and functions
project scope
path divergence
value engineering
change requests
33. Approximating the number of work periods needed to complete individual activities with estimated resources
develop project management plan (Process)
estimate activity durations (Process)
Monte Carlo simulation
network path
34. Narrative description of products - services or results
develop project charter (Process)
statement of work (SOW)
estimate (Output/Input)
activity duration
35. Analysis. a statistical technique that calculates the average outcome when the future includes scenarios that may or may not happen. used in decision tree analysis.
decision tree analysis (Technique)
initiating processes (Process Group)
project manager
expected monetary value (EMV)
36. The process of managing procurement relationships - monitoring contract performance - and making changes and corrections as needed
activity duration
deliverable (Output/Input)
activity code
administer procurements (Process)
37. Schedule network diagramming technique in which schedule activities are represented by boxes or nodes. schedule activities are graphically linked by one or more logical relationships to show the sequence in which the activities are performed
precedence diagramming method (PDM) (Technique)
conduct procurements (Process)
time scaled schedule network diagram (Tool)
quality management plan (Output/Input)
38. The sum of all budgets established for the work to be performed on a project or a work breakdown structure component or a schedule activity. the total planned value for the project
earned value technique (EVT) (Technique)
budget at completion (BAC)
Monte Carlo simulation
earned value management (EV
39. The process of confirming human resource availability and obtaining team necessary to complete project assignments
virtual team
administer procurements (Process)
probability and impact matrix (Tool)
acquire project team (Process)
40. Analytical procedure in which each potential failure mode in every component of a product is analyzed to determine its effect on the reliability of that component and - by itself or in combination with other possible failure modes - on the reliabilit
network logic
manage project team (Process)
failure mode and effect analysis (FMEA) (Technique)
actual cost of work performed
41. Continuously improving and detailing a plan as more detailed and specific information and more accurate estimates become available as the project progresses and thereby producing more accurate and complete plans that result from the successive iterat
develop project team (Process)
early start date (ES)
progressive elaboration (Technique)
stakeholder
42. Tracking - reviewing - regulating the progress to meet the performance objectives defined in the project management plan
scope change
expected monetary value (EMV)
project management plan (Output/Input)
monitor and control project work (Process)
43. Person or group that provides financial resources in cash or in kind for the project
fast tracking (Technique)
parametric estimating (Technique)
work breakdown structure component
sponsor
44. The smallest unit of time used in scheduling a project. calendar units are generally in hours - days - or weeks - but can also be in quarters years - months - shifts - or even minutes
validation
early finish date (EF)
functional manager
calendar unit
45. Describes when and how human resource requirements will be met
staffing management plan
bottom-up estimating (Technique)
close project or phase (Process)
deliverable (Output/Input)
46. Collection of logically related project activities - usually culminating in the completion of a major deliverable. project phase is a component of the project life cycle
contract (Output/Input)
sequence activities (Process)
project organization chart (Output/Input)
project phase
47. A source of variation that is inherent in the system and predictable. on a control chart - it appears as part of the random process variation and is indicated by random pattern of points within the control limits. also referred to as random cause
master schedule (Tool)
schedule compression
common cause
functional organization
48. Summary level schedule that identifies the major schedule milestone
milestone schedule (Tool)
conduct procurements (Process)
BCWS
project organization chart (Output/Input)
49. Risk response planning technique that indicates the project team has decided not to change the project management plan to deal with a risk - or is unable to identify any other suitable response strategy
input (Process) input
reserve analysis (Technique)
risk
risk acceptance (Technique)
50. Approved specific version of the detailed scope statement - work breakdown structure (WBS) and its associated WBS dictionary
project charter (Output/Input)
scope baseline
activity duration
scheduled finish date (SF)