SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Comptia Project + Project Management
Start Test
Study First
Subjects
:
certifications
,
comptia-project-+
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A point that is not settled or is under discussion or over which there are opposing views or disagreements
fast tracking (Technique)
issue Point or matter in question or dispute
decision tree analysis (Technique)
project schedule network diagram (Output/Input)
2. Schematic display of the logical relationships among the project schedule activities. drawn from left to right.
statement of work (SOW)
acquire project team (Process)
project schedule network diagram (Output/Input)
successor activity
3. An entry in the work breakdown structure that can be at any level
risk category
start to start (SS)
log
work breakdown structure component
4. A change request that has been processed through the integrated change control process and approved
residual risk
schedule baseline
approved change request (Output/Input)
plan risk management (Process)
5. Developing a detailed description of the project and product
baseline
estimate at completion (EAC)(Output/Input)
define scope (Process)
precedence relationship
6. Term used in precedence diagramming method for a logical relationship in current usage. precedence relationship - logical relationship and dependency are interchangeably used
activity duration
precedence relationship
earned value management (EV
value engineering
7. Summary level project schedule that identifies the major deliverables and work breakdown structure components and key schedule milestones
special cause
three point estimate (Technique)
workaround
master schedule (Tool)
8. The smallest unit of time used in scheduling a project. calendar units are generally in hours - days - or weeks - but can also be in quarters years - months - shifts - or even minutes
risk mitigation (Technique)
resource histogram
firm fixed price contract (FFP)
calendar unit
9. Type of procurement document used to request proposals from prospective sellers of products or services.
portfolio
resource
project time management (Knowledge Area)
request for proposal (RFP)
10. The latest possible point in time that a schedule activity maybe completed based upon schedule network logic - the completion date and any constraints assigned to the schedule activities without violating a schedule constraint or delaying the project
organizational breakdown structure (OBS) (Tool)
claim
late finish date (LF)
special cause
11. A short unique numeric or text identification assigned to each schedule activity to differentiate that project activity from other project activities. typically unique within any one project schedule network diagram
acquire project team (Process)
authority
project charter (Output/Input)
activity identifier
12. A collection of formal documented procedures that define how project deliverables and documentation will be controlled - changed and approved. in most application areas - the change control system is a subset of the configuration management system
change control system (Tool)
lead (Technique)
scope
scheduled finish date (SF)
13. An approved plan for a project - plus or minus approved changes. it is compared to actual performance to determine if performance is within acceptable variance thresholds. generally refers to the current baseline - but may refer to the original or so
execute
baseline
monitor and controlling processes (Process Group)
reserve
14. Making relevant information available to project stakeholders
quality
distribute information (Process)
triggers
historical information
15. Logical relationship where initiation of the work of the successor schedule activity depends upon the initiation of the work of the predecessor schedule activity
start to start (SS)
invitation for bid (IFB)
variance
scope baseline
16. Slack - Total amount of time that a schedule activity maybe delayed from its early start date without delaying the project finish date or violating a schedule constraint.
buffer
stakeholder
estimate (Output/Input)
float
17. Processes involved in estimating - budgeting - and controlling costs so that the project can be completed within the approved budget
request for proposal (RFP)
earned value (EV)
project cost management (Knowledge Area)
organizational process assets (Output/Input)
18. A documented tabulation of schedule activities that shows the activity description - activity identifier - and a sufficiently detailed scope of work description so project team members understand what work is to be performed
technical performance measurement (Technique)
activity list (Output/Input)
baseline
external deliverable
19. The process of completing each project procurement
estimate at completion (EAC)(Output/Input)
budget at completion (BAC)
lessons learned(Output/Input)
close procurements (Process)
20. Model used in conjunction with manual methods or project management software to perform schedule network analysis to generate the project schedule for use in managing the executing or a project
earned value (EV)
schedule model (Tool)
procurement documents (Output/Input)
closing processes (Process Group)
21. System of practices - techniques - procedures and rules used by those who work in a discipline
fixed price incentive fee contract (FPIF)
functional organization
methodology
project
22. Project schedule network diagram drawn in such a way that the position and length of the schedule activity represents its duration. bar chart that includes schedule network logic
forecast
total float
schedule performance index (SPI)
time scaled schedule network diagram (Tool)
23. Collect project performance data with respect to a plan - produce performance measures and report and disseminate performance information
earned value (EV)
monitor
actual cost (AC)
change control
24. Analytical technique used to determine basic underlying reason that causes a variance or defect or risk
root cause analysis (Technique)
brainstorming (Technique)
grade
quality
25. Risk response planning technique associated with threats that seeks to reduce the probability of occurrence or impact of a risk to below an acceptable threshold
value engineering
acquire project team (Process)
risk mitigation (Technique)
reserve analysis (Technique)
26. Analytical procedure in which each potential failure mode in every component of a product is analyzed to determine its effect on the reliability of that component and - by itself or in combination with other possible failure modes - on the reliabilit
flowcharting (Technique)
near critical activity
failure mode and effect analysis (FMEA) (Technique)
perform integrated change control (Process)
27. Person or organization that is actively involved in the project or whose interests may be positively or negatively affected by execution or completion of the project
sponsor
stakeholder
planned value (PV)
scope creep
28. A category of projects that have common components significant in such projects - but are not needed or present in all projects. application areas are usually defined in terms of either the product or the type of customer or industry sector
application area
total float
percent complete
role
29. Work breakdown structure component below the control account with known work content but without detailed schedule activities.
sponsor
claim
project manager
planning package
30. Any item - internal or external - that is required by a process before that process proceeds
input (Process) input
earned value technique (EVT) (Technique)
assumptions
start to start (SS)
31. Developing an approximation of the monetary resources needed to complete project activities
stakeholder
precedence diagramming method (PDM) (Technique)
estimate costs (Process)
distribute information (Process)
32. Improving the competencies - team interaction - and the overall team environment to enhance project performance
develop project team (Process)
precedence diagramming method (PDM) (Technique)
deliverable (Output/Input)
predecessor activity
33. The degree to which a set of inherent characteristics fulfills requirements
activity duration
risk category
requested change(Output/Input)
quality
34. Identifying all people or organizations impacted by the project and documenting relevant information regarding their interest - involvement and impact on project success
estimate costs (Process)
grade
manage stakeholder expectations (Process)
identify stakeholders (Process)
35. A point in time associated with schedule activity's completion.
schedule network analysis (Technique)
finish date
project management plan (Output/Input)
projectized organization
36. Calendar of working days or shifts that establishes those dates on which schedule activities are worked and nonworking days that determine those dates on which schedule activities are idle
project calendar
early finish date (EF)
scheduled finish date (SF)
work authorization system (Tool)
37. Collection of logically related project activities - usually culminating in the completion of a major deliverable. project phase is a component of the project life cycle
project phase
resource calendar
change control board (CCB)
variance analysis (Technique)
38. Identifying the specific actions to be performed to produce the project deliverables
estimate activity durations (Process)
develop project management plan (Process)
define activities (Process)
perform qualitative analysis (Process)
39. Documented direction to perform an activity that can reduce the probability of negative consequences associated with project risks
preventative action
change control
threshold
workaround
40. Budgeted cost of work scheduled
resource breakdown structure
BCWS
program management
budget
41. Document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organization resources to the project activities
standard
schedule baseline
project charter (Output/Input)
technical performance measurement (Technique)
42. Temporary endeavor undertaken to create a unique product - service or result
project
functional organization
statement of work (SOW)
verification
43. An estimating technique that uses a statistical relationship between historical data and other variables (sq. foot in construction - lines of code in software development) to calculate an estimate for activity parameters such as scope - cost - budget
estimate activity resources (Process)
assumptions
request for information (RFI)
parametric estimating (Technique)
44. Risk response planning technique for a threat that creates changes to the project management plan that are meant to either eliminate the risk or to protect the project objectives from its impact.
s-curve
risk avoidance (Technique)
work package
start to start (SS)
45. Quantifiable deviation - departure or divergence away from a known baseline or expected value
variance
milestone schedule (Tool)
define scope (Process)
project management
46. Logical relationship where completion of the successor schedule activity is dependent upon the initiation of the predecessor schedule activity
rolling wave planning (Technique)
start to finish (SF)
perform quality assurance (Process)
threshold
47. Skilled human resources - equipment - services - supplies - commodities - material - budgets or funds
develop project management plan (Process)
resource
buyer
Monte Carlo analysis
48. Inclusive term - describes the sum of knowledge within the profession of project management. includes proven traditional practices that are widely applied and innovative practices that are emerging.
input (Process) input
resource histogram
monitor and controlling processes (Process Group)
project management body of knowledge
49. Total costs actually incurred and recorded in accomplishing work performed during a given time period for a schedule activity or work breakdown structure component. actual cost can sometimes be direct labor hours alone - direct costs alone - or all c
path convergence
requirements traceability matrix
actual cost (AC)
slack
50. Communicating and working with stakeholders to meet their needs and address issues as they occur
approved change request (Output/Input)
plan procurements (Process)
organizational process assets (Output/Input)
manage stakeholder expectations (Process)