SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
Search
Test your basic knowledge |
Comptia Project + Project Management
Start Test
Study First
Subjects
:
certifications
,
comptia-project-+
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Logical relationship where initiation of work of the successor activity depends on the completion of work of the predecessor activity
finish to start (FS)
template
external deliverable
project management office (PMO)
2. Subdivision (fragment) of a project schedule network diagram - usually representing a subproject or work package.
enterprise environmental factors (Input/Output)
sub network
project calendar
performing organization
3. Point in time that work was scheduled to finish on a schedule activity. called planned finish date
budget
sensitivity analysis
executing processes (Process Group)
scheduled finish date (SF)
4. A histogram - ordered by frequency of occurrence - that shows how many results were generated by each identified cause
activity attributes (Output/Input)
initiating processes (Process Group)
work breakdown structure (WBS) (Output/Input)
pareto chart (Tool)
5. A point in time associated with schedule activity's completion.
finish date
staffing management plan
functional manager
communications management plan (Output/Input)
6. Performing the work defined in the project management plan to achieve the project's objectives
identify stakeholders (Process)
manage project team (Process)
direct and manage project execution (Process)
project time management (Knowledge Area)
7. Fixed date imposed on a schedule activity or schedule milestone. usually - start no earlier than - finish no later than
imposed date
specification
project life cycle
probability and impact matrix (Tool)
8. Deliverable that is subject to approval by the project sponsor or customer
sub phase
external deliverable
root cause analysis (Technique)
change requests
9. Processes to purchase or acquire the products - services or results needed from outside the project team to perform the work
free float
analogous estimating (Technique)
start date
project procurement management (Knowledge Area)
10. Authorized budget assigned to the scheduled work to be accomplished for a schedule activity or work breakdown structure component
planned value (PV)
node
organizational process assets (Output/Input)
project management system (Tool)
11. Graphic display of cumulative costs - labor - hours - percentage of work or other quantities - plotted against time. used to depict planned value - earned value and active costs.
s-curve
project management system (Tool)
define scope (Process)
monitor and control project work (Process)
12. A condition or situation favorable to the project - a positive set of circumstances - a positive set of events - a risk that will have a positive impact.
schedule baseline
stakeholder
opportunity
planned value (PV)
13. Analyzing activity sequences - durations - resource requirements and schedule constraints to create the project schedule
close project or phase (Process)
project schedule network diagram (Output/Input)
develop schedule (Process)
matrix organization
14. A group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually.
risk tolerance
preventative action
quality
program
15. A source of variation that is inherent in the system and predictable. on a control chart - it appears as part of the random process variation and is indicated by random pattern of points within the control limits. also referred to as random cause
project initiation
common cause
slack
project cost management (Knowledge Area)
16. Schedule activity that follows a predecessor activity as determined by their logical relationship
subproject
successor activity
schedule management plan (Output/Input)
time and material contract (T&M)
17. The statue - quality or sense of being restricted to a given course of action or inaction. an applicable restriction or limitation - either internal or external to a project - which will affect the performance of the project or a process.
constraint (Input)
simulation
path divergence
identify stakeholders (Process)
18. Extending or generating parallel schedule network paths from the same node in a project schedule network diagram. characterized by schedule activity with more than one successor activity
node
threshold
path divergence
approved change request (Output/Input)
19. The latest possible point in time that a schedule activity maybe completed based upon schedule network logic - the completion date and any constraints assigned to the schedule activities without violating a schedule constraint or delaying the project
risk
application area
late finish date (LF)
role
20. Measure of schedule efficiency on a project. ratio of earned value (EV) and the planned value (PV). SV = EV minus PV.
lessons learned knowledge base
planned value (PV)
distribute information (Process)
schedule performance index (SPI)
21. Multiple attributes associated with each schedule activity that can be included within the activity list. activity attributes include activity codes - predecessor activities - successor activities - logical relationships - leads and lags - resource r
activity attributes (Output/Input)
total float
result
develop schedule (Process)
22. Centralized management of one or more portfolios - which includes identifying - prioritizing - authorizing - managing and controlling projects - programs and related work - to achieve specific strategic business objectives
portfolio management (Technique)
specification limits
sponsor
change control system (Tool)
23. Modification that allows an acceleration of the successor activity.
organizational process assets (Output/Input)
project schedule (Output/Input)
requirements traceability matrix
lead (Technique)
24. Graphic display of schedule related information.
plan risk management (Process)
free float
Gantt chart (Tool)
portfolio
25. Total costs actually incurred and recorded in accomplishing work performed during a given time period for a schedule activity or work breakdown structure component. actual cost can sometimes be direct labor hours alone - direct costs alone - or all c
scope creep
staffing management plan
actual cost (AC)
master schedule (Tool)
26. Shortening the project schedule duration without reducing the project scope
schedule compression
risk breakdown structure (RBS)
schedule network analysis (Technique)
estimate to complete (ETC)(Output/Input)
27. Documented direction to perform an activity that can reduce the probability of negative consequences associated with project risks
plan risk management (Process)
specification
path divergence
preventative action
28. Float (total float - free float)
logical relationship
three point estimate (Technique)
slack
project scope statement (Output/Input)
29. An entry in the work breakdown structure that can be at any level
work breakdown structure component
progressive elaboration (Technique)
simulation
perform quality control (Process)
30. Temporary endeavor undertaken to create a unique product - service or result
enterprise environmental factors (Input/Output)
actual duration
project
earned value management (EV
31. Amount of time that a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities.
change control board (CCB)
procurement management plan (Output/Input)
free float
estimate costs (Process)
32. Dependency between two project schedule activities or between project schedule activity and schedule milestone.
organizational process assets (Output/Input)
logical relationship
project management
variance
33. Document that describes how procurement processes from developing procurement documentation through contract closure will be managed
procurement management plan (Output/Input)
resource leveling (Technique)
plan quality (Process)
milestone schedule (Tool)
34. The value of work performed expressed in terms of the approved budget assigned to that work for a schedule activity or work breakdown structure component. ALSO BCWP.
earned value (EV)
project team directory
early start date (ES)
verification
35. Indications that a risk has occurred or is about to occur. also called risk symptoms or warning signs. should be watched or monitored in the risk monitoring and control process.
triggers
scheduled finish date (SF)
work breakdown structure component
project management plan (Output/Input)
36. Subsystem of overall project management system. collection of formal documented procedures that defines how project work will be authorized to ensure that the work is done by the identified organization - at the right time and in the proper sequence.
scope management plan(Output/Input)
start to finish (SF)
defect repair
work authorization system (Tool)
37. Depiction in a diagram format of the inputs - process actions - and outputs of one or more processes within a system
project initiation management (Knowledge Area)
plan risk management (Process)
flowcharting (Technique)
methodology
38. Those processes performed to complete the work defined in the project management plan to satisfy project objectives
triggers
planning package
objective
executing processes (Process Group)
39. Narrative description of the project scope - including major deliverables - project assumptions - project constraints and a description of work that provides a documented basis for making future project decisions and for confirming or developing a co
project team directory
quality
value engineering
project scope statement (Output/Input)
40. Information system consisting of tools and techniques to gather - integrate and disseminate the outputs of project management processes.
conduct procurements (Process)
imposed date
acceptance criteria
project management information system (PMIS) (Tool)
41. Quantifiable deviation - departure or divergence away from a known baseline or expected value
late start date (LS)
variance
activity code
perform qualitative analysis (Process)
42. Identifying - documenting - approving or rejecting and controlling changes to the project baselines
perform quality assurance (Process)
change control
project management process group
rolling wave planning (Technique)
43. The earliest point in time on which the uncompleted portions of a schedule activity can start - based on the schedule network logic - the data date and any schedule constraints.
inspection (Technique)
project management information system (PMIS) (Tool)
secondary risk
early start date (ES)
44. Structure in which the project manager shares responsibility with the functional managers for assigning priorities and directing the work of persons assigned to the project
baseline
project management process group
matrix organization
close procurements (Process)
45. Collection of projects or programs and other work that are grouped together to facilitate effective management of that work to meet strategic business objectives
portfolio
perform qualitative analysis (Process)
project management team
master schedule (Tool)
46. Analytical technique used to determine basic underlying reason that causes a variance or defect or risk
risk register (Output/Input)
root cause analysis (Technique)
sensitivity analysis
subproject
47. Bar chart showing the amount of time that a resource is scheduled to work over a series of time periods.
project scope
sponsor
resource histogram
scope creep
48. Group of related schedule activities aggregated at some summary level and displayed as a single activity (at the summary level)
buyer
summary activity
plan risk response (Process)
requirement
49. Management methodology for integrating scope - schedule and resources and for objectively measuring project performance and progress. performance is measured by determining the budgeted cost of work performed (earned value) and comparing it to the ac
earned value management (EV
change control system (Tool)
external deliverable
statement of work (SOW)
50. Risk response planning technique for a threat that creates changes to the project management plan that are meant to either eliminate the risk or to protect the project objectives from its impact.
path divergence
project initiation
risk avoidance (Technique)
decision tree analysis (Technique)