Test your basic knowledge |

Comptia Project + Project Management

Instructions:
  • Answer 50 questions in 15 minutes.
  • If you are not ready to take this test, you can study here.
  • Match each statement with the correct term.
  • Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.

This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The earliest point in time on which the uncompleted portions of a schedule activity (or the project) can finish - based on the schedule network logic - the data date and any schedule constraints.






2. Significant point or event in the project






3. A request - demand or assertion of rights by a seller against a buyer or vice versa for consideration - compensation - or payment under the terms of a legally binding contract (such as for a disputed change)






4. Technique for estimating that applies a weighted average of optimistic - pessimistic and most likely estimates when there is uncertainty with the individual activity estimates






5. Risk response planning technique associated with threats that seeks to reduce the probability of occurrence or impact of a risk to below an acceptable threshold






6. The time in calendar units between the start and finish of a schedule activity






7. Identifying quality requirements and/or standards for the project and product and documenting how the project will demonstrate compliance






8. Point in time that work was scheduled to start on a schedule activity. called planned start date.






9. Output from performing project management processes and activities. results include outcomes and documents.






10. Work that must be performed to deliver a product - service or result with the specified features and functions






11. Smaller portion of the overall project created when a project is subdivided by their logical relationship






12. Identifying and documenting project roles - responsibilities - and required skills - reporting relationships and creating a staffing management plan.






13. Float (total float - free float)






14. Structure that relates the project organizational breakdown structure to the work breakdown structure to help ensure that each component of the project scope of work is assigned to a person or team






15. A formally constituted group of stakeholders responsible for reviewing - evaluating - approving - delaying or rejecting changes to a project - with all the decisions and recommendations being recorded






16. Developing a document that formally authorizes a project or phase and documenting initial requirement that satisfy the stakeholders needs and expectations






17. Type of procurement document whereby the buyer requests a potential seller to provide various pieces of information related to a product or service or seller capability






18. Condition or situation unfavorable to the project - a negative set of circumstances - a negative set of events - a risk that will have a negative impact on a project objective if it occurs - or a possibility for negative changes






19. The person assigned by the performing organization to achieve the project objectives






20. Defined function to be performed by a project team member






21. Features and functions that characterize a product - service or result






22. The formally documented identification of a defect in a project component with a recommendation to either repair the defect or completely replace the component






23. Any form of schedule network analysis in which scheduling decisions are driven by resource constraints






24. Deliverable that is subject to approval by the project sponsor or customer






25. An estimating technique that uses a statistical relationship between historical data and other variables (sq. foot in construction - lines of code in software development) to calculate an estimate for activity parameters such as scope - cost - budget






26. Amount of time that a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities.






27. Reviewing all change requests - approving changes - and managing changes to the deliverables - organizational process assets - project documents and project management plan






28. Calculation of the early start and early finish dates for the uncompleted portions of all network activities






29. Type of procurement document used to request price quotations from prospective sellers of common or standard products or services






30. A subsystem of the overall project management system. it is a collection of formal documented procedures used to apply technical and administrative direction and surveillance to identify and document the functional and physical characteristics of a p






31. Graphic display of schedule related information.






32. Risk response planning technique that indicates the project team has decided not to change the project management plan to deal with a risk - or is unable to identify any other suitable response strategy






33. The acquirer of products - services or results for an organization






34. Quantifiable deviation - departure or divergence away from a known baseline or expected value






35. The process of defining and documenting stakeholder needs to meet project objectives






36. Schedule activity that determines when the logical successor activity can begin or end






37. Logical grouping of project management inputs - tools and techniques and outputs. includes initiating processes - planning processes - executing processes - monitoring and controlling processes and closing processes. NOT project phases






38. The process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact






39. An estimating technique that uses the values of parameters - such as scope - cost - budget - and duration or measures of scale such as size - weight - and complexity from a previous similar activity as the basis of estimating the same parameter or me






40. Logical relationship where initiation of work of the successor activity depends on the completion of work of the predecessor activity






41. An approved plan for a project - plus or minus approved changes. it is compared to actual performance to determine if performance is within acceptable variance thresholds. generally refers to the current baseline - but may refer to the original or so






42. Processes concerned with conducting risk management planning - identification - analysis - responses and monitoring and control on a project






43. Hierarchal structure of resources by resource category and resource type used in resource leveling schedules and to develop resource limited schedules and which may be used to identify and analyze project human resource management






44. Calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal. ratio of remaining work to funds remaining






45. Risk response planning technique for a threat that creates changes to the project management plan that are meant to either eliminate the risk or to protect the project objectives from its impact.






46. A documented tabulation of schedule activities that shows the activity description - activity identifier - and a sufficiently detailed scope of work description so project team members understand what work is to be performed






47. Modification that allows an acceleration of the successor activity.






48. The approved estimate for the project or any work breakdown structure component or any schedule activity






49. Graphic display of cumulative costs - labor - hours - percentage of work or other quantities - plotted against time. used to depict planned value - earned value and active costs.






50. The earliest point in time on which the uncompleted portions of a schedule activity can start - based on the schedule network logic - the data date and any schedule constraints.






Can you answer 50 questions in 15 minutes?



Let me suggest you:



Major Subjects



Tests & Exams


AP
CLEP
DSST
GRE
SAT
GMAT

Most popular tests