SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Milestone
Deliverable
Secondary Risk
Apportioned Effort
2. A risk that would have a negative effect on one or more project objectives.
Successor Activity
Corrective Action
Start-to-Finish
Threat
3. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Assumption
Performing Organization
Deliverable
Staffing Management Plan
4. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Organizational Project Management Maturity
Three-Point Estimate
Assumption
Fast Tracking
5. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Defect Repair
WBS Dictionary
Product Life Cycle
Decomposition
6. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Project Schedule
Program Management Office
Constraint
Program Management
7. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Decision Tree Analysis
Budget at Completion
Early Start Date
Activity
8. A graphical representation of the logical relationships among the project schedule activities.
Project Schedule Network Diagram
Logical Relationship
Risk Management Plan
Resource Leveling
9. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Secondary Risk
Cost Performance Index
Risk Breakdown Structure
Finish-to-Finish
10. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Change Control Board
Project Schedule Network Diagram
Crashing
Start-to-Finish
11. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Cost Performance Index
Organizational Project Management Maturity
Project Charter
Estimate at Completion
12. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
WBS Dictionary
Gantt Chart
Free Float
Change Control Board
13. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Precedence Diagramming Method
Deliverable
Bottom-up Estimating
Requirement
14. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Cost Performance Index
Phase Gate
Finish-to-Finish
Stakeholder
15. A hierarchical representation of risks that is organized according to risk categories.
Logical Relationship
Risk Breakdown Structure
Communication Management Plan
Risk Register
16. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Project Management
Phase Gate
Budget at Completion
Risk Management Plan
17. A risk that would have a positive effect on one or more project objectives.
Estimate to Complete
Risk Register
Opportunity
Planned Value
18. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Project Phase
Requirement
Discrete Effort
Level of Effort
19. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Control Account
Backward Pass
Variance at Completion
Free Float
20. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Successor Activity
Earned Value
Project Management Office
Requirements Management Plan
21. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Preventive Action
Fast Tracking
Corrective Action
Gantt Chart
22. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Start-to-Start
Actual Cost
Milestone
Variance at Completion
23. A dependent activity that logically comes after another activity in a schedule.
Change Request
Successor Activity
Early Finish Date
Stakeholder
24. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Project Schedule
Start-to-Start
Project
Project Phase
25. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Planned Value
Successor Activity
Optimistic Duration
Project Charter
26. A numbering system used to uniquely identify each component of the work breakdown structure.
Risk
Code of Accounts
Project Management Plan
Milestone
27. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Schedule Model
Requirement
Backward Pass
Cost Variance
28. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Three-Point Estimate
Project Management
Data Date
Risk Transference
29. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Performing Organization
Organizational Project Management Maturity
Requirement
Backward Pass
30. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Communication Management Plan
Requirement
Estimate to Complete
Portfolio Balancing
31. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Schedule Model
Summary Activity
Cost Variance
S-Curve Analysis
32. A grid that shows the project resources assigned to each work package.
Actual Cost
Risk Avoidance
Stakeholder
Responsibility Assignment Matrix
33. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Early Finish Date
Critical Path Activity
Level of Effort
Program
34. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Pessimistic Duration
Assumption
Schedule Compression
Phase Gate
35. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Quality Management Plan
Project Schedule Network Diagram
Level of Effort
Procurement Management Plan
36. A relationship in which a schedule activity has more than one predecessor.
Code of Accounts
Lead
Path Convergence
Defect Repair
37. An intentional activity that realigns the performance of the project work with the project management plan.
Project Management Plan
Corrective Action
Milestone
Change Control Board
38. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Finish-to-Start
Opportunity
Project
Decomposition
39. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Change Control System
Percent Complete
Most Likely Duration
Analogous Estimating
40. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Probability and Impact Matrix
Scope Baseline
Forward Pass
Free Float
41. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Risk
Project Charter
Risk Mitigation
Actual Cost
42. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Rolling Wave Planning
Milestone
Requirement
Schedule Baseline
43. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Change Control
Fast Tracking
Lag
Probability and Impact Matrix
44. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Probability and Impact Matrix
Project Management Office
Variance Analysis
Risk
45. A group of related schedule activities aggregated and displayed as a single activity.
Summary Activity
Cost Management Plan
Human Resource Plan
Free Float
46. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Risk Category
Earned Value
Critical Path Method
Percent Complete
47. A technique used to shorten the schedule duration without reducing the project scope.
Start-to-Finish
Early Start Date
Assumption
Schedule Compression
48. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Finish-to-Finish
Critical Path Method
Apportioned Effort
Project Life Cycle
49. A dependency between two activities - or between an activity and a milestone.
Parametric Estimating
Resource Calendar
Logical Relationship
Schedule Performance Index
50. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Budget at Completion
Change Control System
Project Manager
Cost Management Plan