SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
WBS Dictionary
Activity
Rolling Wave Planning
Schedule Model Analysis
2. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Analogous Estimating
Critical Path Method
Control Account
Schedule Management Plan
3. An activity that logically comes before a dependent activity in a schedule.
Project Management
Human Resource Plan
Secondary Risk
Predecessor Activity
4. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Control Account
Critical Path
Total Float
Portfolio
5. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Portfolio Balancing
Level of Effort
Probability and Impact Matrix
Project Charter
6. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Summary Activity
Sponsor
Parametric Estimating
Preventive Action
7. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Total Float
Resource Breakdown Structure
Critical Chain Method
Risk
8. A technique for determining the cause and degree of difference between the baseline and actual performance.
Program Management Office
Variance Analysis
Portfolio Management
WBS Dictionary
9. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Cost Variance
Decomposition
Progressive Elaboration
Resource Leveling
10. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Requirements Management Plan
Stakeholder
Pessimistic Duration
Estimate at Completion
11. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Decision Tree Analysis
Risk
Baseline
Organizational Breakdown Structure
12. A risk that would have a negative effect on one or more project objectives.
Change Control Board
Risk Category
Threat
Variance Analysis
13. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Preventive Action
Product Life Cycle
Gantt Chart
Communication Management Plan
14. A dependency between two activities - or between an activity and a milestone.
Project Management Plan
Variance at Completion
Logical Relationship
Gantt Chart
15. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Effort
Late Start Date
Scope Baseline
Variance at Completion
16. The centralized management of one or more portfolios to achieve strategic objectives.
Project Manager
Portfolio Management
Change Control Board
Change Control
17. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Project Phase
Precedence Diagramming Method
Free Float
Program Management Office
18. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Lag
Assumption
Cost Variance
Procurement Management Plan
19. A limiting factor that affects the execution of a project - program - portfolio - or process.
Control Account
Risk Category
Constraint
Decomposition
20. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Project Life Cycle
Project Manager
Project Management Plan
Opportunity
21. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Change Control Board
Project
Cost Variance
Program Management Office
22. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Finish-to-Finish
Most Likely Duration
Communication Management Plan
Human Resource Plan
23. The measure of work performed expressed in terms of the budget authorized for that work.
Early Finish Date
Earned Value
Project Management
Cost Performance Index
24. A relationship in which a schedule activity has more than one successor.
Path Divergence
Analogous Estimating
Change Control
Logical Relationship
25. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Lag
Optimistic Duration
Scope Creep
Change Control System
26. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Baseline
Start-to-Finish
Path Convergence
Early Finish Date
27. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Budget at Completion
Project Charter
Organizational Process Assets
Cost Performance Index
28. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Threat
Project Management Plan
Stakeholder
Gantt Chart
29. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Resource Leveling
Three-Point Estimate
Start-to-Finish
What-If Sce
30. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Staffing Management Plan
Deliverable
Milestone
Project Life Cycle
31. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Communication Management Plan
Project Calendar
Assumption
Backward Pass
32. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Schedule Performance Index
Project Scope Statement
Schedule Model Analysis
Requirement
33. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Change Control Board
Secondary Risk
Critical Path
Code of Accounts
34. A calendar that identifies the working days and shifts upon which each specific resource is available.
Resource Calendar
Effort
Early Finish Date
Resource Leveling
35. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Program
Lead
Level of Effort
Phase Gate
36. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Organizational Project Management Maturity
Critical Path Method
Milestone
Portfolio
37. A numbering system used to uniquely identify each component of the work breakdown structure.
Corrective Action
Fast Tracking
Schedule Baseline
Code of Accounts
38. A temporary endeavor undertaken to create a unique product - service - or result.
Project
Late Start Date
Schedule Baseline
Scope Baseline
39. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Probability and Impact Matrix
Variance Analysis
Responsibility Assignment Matrix
Project Management Office
40. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Total Float
Project Phase
Program Management Office
Threat
41. A document in which the results of risk analysis and risk response planning are recorded.
Most Likely Duration
Risk Register
Portfolio Balancing
Human Resource Plan
42. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Percent Complete
Precedence Diagramming Method
Scope Creep
What-If Sce
43. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Secondary Risk
Summary Activity
Scope Creep
Staffing Management Plan
44. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Project Phase
Finish-to-Start
Late Start Date
Critical Path Method
45. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
WBS Dictionary
Activity
Assumption
Rolling Wave Planning
46. A risk that arises as a direct result of implementing a risk response.
Schedule Performance Index
Program Management
Change Control System
Secondary Risk
47. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Performing Organization
Project Life Cycle
Discrete Effort
Schedule Management Plan
48. A formal proposal to modify any document - deliverable - or baseline.
Deliverable
Change Request
Risk Breakdown Structure
Optimistic Duration
49. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Percent Complete
Critical Path Method
Phase Gate
Apportioned Effort
50. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Effort
Path Divergence
Organizational Breakdown Structure
Phase Gate