SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Decision Tree Analysis
Progressive Elaboration
Finish-to-Start
Critical Path
2. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Precedence Diagramming Method
Cost Management Plan
Program Management Office
What-If Sce
3. A risk that arises as a direct result of implementing a risk response.
Secondary Risk
Risk Register
Trigger Condition
Decomposition
4. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Risk Acceptance
Earned Value Management
Estimate at Completion
Deliverable
5. A distinct - scheduled portion of work performed during the course of a project.
Activity
Defect Repair
Path Convergence
Scope Management Plan
6. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Scope Creep
Project Scope
Cost Management Plan
Lessons Learned
7. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Pessimistic Duration
Control Account
What-If Sce
Project Calendar
8. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Scope Baseline
Percent Complete
Cost Variance
Decision Tree Analysis
9. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Critical Path Method
Forward Pass
Cost Performance Index
Resource Leveling
10. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Project Management
Stakeholder
Project Schedule
Preventive Action
11. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Path Divergence
Critical Path
Start-to-Finish
Critical Path Activity
12. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Critical Path Method
Free Float
S-Curve Analysis
Quality Management Plan
13. A risk that would have a positive effect on one or more project objectives.
Project Scope Statement
Risk Management Plan
Opportunity
Lead
14. A risk that would have a negative effect on one or more project objectives.
Critical Chain Method
Threat
Defect Repair
Communication Management Plan
15. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Estimate to Complete
Critical Path Method
Change Control Board
Bottom-up Estimating
16. The document that describes how the project will be executed - monitored - and controlled.
Start-to-Finish
Cost Performance Index
Project Management Plan
Human Resource Plan
17. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Lag
Enterprise Environmental Factors
Risk Breakdown Structure
Portfolio
18. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Preventive Action
Organizational Process Assets
Percent Complete
Three-Point Estimate
19. The expected cost to finish all the remaining project work.
Risk Avoidance
Estimate to Complete
Opportunity
Path Divergence
20. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
What-If Sce
Baseline
Early Start Date
Change Control Board
21. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Data Date
Risk Management Plan
Phase Gate
Risk Acceptance
22. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Decomposition
Pessimistic Duration
Cost Performance Index
Change Control
23. A graphical representation of the logical relationships among the project schedule activities.
Project Schedule Network Diagram
Rolling Wave Planning
Quality Management Plan
Cost Performance Index
24. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Earned Value Management
Forward Pass
Parametric Estimating
Risk Register
25. A hierarchical representation of resources by category and type.
Optimistic Duration
Assumption
Product Life Cycle
Resource Breakdown Structure
26. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Estimate to Complete
Organizational Breakdown Structure
Defect Repair
Data Date
27. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Project
Pessimistic Duration
Risk
Schedule Performance Index
28. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Risk Register
Free Float
Organizational Project Management Maturity
Staffing Management Plan
29. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Variance Analysis
Sponsor
Assumption
Lessons Learned
30. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Project Management Plan
Project Management
Portfolio
Portfolio Management
31. A significant point or event in a project - program - or portfolio.
Secondary Risk
Most Likely Duration
Data Date
Milestone
32. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Defect Repair
Backward Pass
Earned Value
Bottom-up Estimating
33. A grid that links product requirements from their origin to the deliverables that satisfy them.
Precedence Diagramming Method
Portfolio Balancing
Early Finish Date
Requirements Traceability Matrix
34. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Critical Path
Change Control Board
Secondary Risk
Organizational Breakdown Structure
35. Any activity on the critical path in a project schedule.
Assumption
Schedule Performance Index
Preventive Action
Critical Path Activity
36. A grid that shows the project resources assigned to each work package.
Responsibility Assignment Matrix
Probability and Impact Matrix
Requirements Management Plan
Earned Value
37. An intentional activity to modify a nonconforming product or product component.
Critical Path
Schedule Management Plan
Critical Chain Method
Defect Repair
38. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Optimistic Duration
Project Schedule
Scope Management Plan
Estimate to Complete
39. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Sponsor
Risk Acceptance
Project Calendar
Preventive Action
40. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Program Management
Schedule Variance
Control Account
Trigger Condition
41. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Optimistic Duration
Schedule Model
Scope Baseline
Procurement Management Plan
42. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Enterprise Environmental Factors
Product Life Cycle
Scope Creep
Logical Relationship
43. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Project Schedule
Portfolio Management
Performing Organization
Finish-to-Start
44. A relationship in which a schedule activity has more than one successor.
Early Finish Date
Performing Organization
Constraint
Path Divergence
45. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Program
Pessimistic Duration
Project Management Plan
Earned Value Management
46. A calendar that identifies the working days and shifts upon which each specific resource is available.
Responsibility Assignment Matrix
S-Curve Analysis
Resource Calendar
Lead
47. A dependent activity that logically comes after another activity in a schedule.
Path Divergence
Successor Activity
Program Management Office
Earned Value Management
48. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
What-If Sce
Enterprise Environmental Factors
Summary Activity
Risk Mitigation
49. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Finish-to-Start
Cost Variance
Progressive Elaboration
To-Complete Performance Index
50. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Project Life Cycle
Rolling Wave Planning
Threat
Risk Transference