SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Project Charter
Stakeholder
Finish-to-Start
Risk Category
2. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Apportioned Effort
Planned Value
Performing Organization
Data Date
3. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Scope Baseline
Project Manager
Predecessor Activity
Decomposition
4. A graphical representation of the logical relationships among the project schedule activities.
Finish-to-Finish
Decomposition
Project Schedule Network Diagram
Cost Performance Index
5. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Phase Gate
Project Life Cycle
Probability and Impact Matrix
Program Management
6. A group of potential causes of risk.
Late Start Date
Stakeholder
Lead
Risk Category
7. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Change Control System
Risk
Path Divergence
Three-Point Estimate
8. A grid that links product requirements from their origin to the deliverables that satisfy them.
Rolling Wave Planning
Pessimistic Duration
Stakeholder
Requirements Traceability Matrix
9. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Sponsor
Schedule Baseline
Requirements Management Plan
Assumption
10. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Portfolio Balancing
Performing Organization
Portfolio Management
Staffing Management Plan
11. A grid that shows the project resources assigned to each work package.
Organizational Breakdown Structure
Crashing
Responsibility Assignment Matrix
Portfolio Management
12. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Late Start Date
Requirement
Crashing
WBS Dictionary
13. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Bottom-up Estimating
Level of Effort
Organizational Breakdown Structure
Backward Pass
14. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Resource Breakdown Structure
Critical Path
Decision Tree Analysis
Communication Management Plan
15. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Lessons Learned
Stakeholder
Rolling Wave Planning
Fast Tracking
16. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Data Date
Risk
Free Float
Portfolio Management
17. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Requirement
Product Life Cycle
Portfolio
Change Request
18. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Most Likely Duration
Control Account
Rolling Wave Planning
Gantt Chart
19. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Analogous Estimating
Change Control Board
Earned Value Management
Secondary Risk
20. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Three-Point Estimate
S-Curve Analysis
Human Resource Plan
To-Complete Performance Index
21. A dependent activity that logically comes after another activity in a schedule.
Successor Activity
Budget at Completion
Scope Creep
Performing Organization
22. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Free Float
Predecessor Activity
Estimate to Complete
Change Control Board
23. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Human Resource Plan
Organizational Breakdown Structure
Project
Portfolio
24. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Lessons Learned
Path Convergence
Level of Effort
Forward Pass
25. A technique for determining the cause and degree of difference between the baseline and actual performance.
Change Control
Path Convergence
Variance Analysis
Lag
26. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Decision Tree Analysis
Crashing
Risk Management Plan
Schedule Variance
27. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Analogous Estimating
Percent Complete
Control Account
Stakeholder
28. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
S-Curve Analysis
Baseline
Project Management Office
Risk Mitigation
29. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Project Management
Requirements Management Plan
Project Calendar
Level of Effort
30. A dependency between two activities - or between an activity and a milestone.
Logical Relationship
Risk Register
Scope Creep
Milestone
31. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Percent Complete
Risk Transference
Critical Chain Method
Project Schedule
32. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Project Manager
Risk Category
Program Management Office
Risk Register
33. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Change Control
Schedule Performance Index
Constraint
Requirement
34. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Pessimistic Duration
Cost Performance Index
Risk Acceptance
Most Likely Duration
35. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Discrete Effort
Resource Calendar
Phase Gate
Scope Creep
36. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Activity
Product Life Cycle
Schedule Model
Control Account
37. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Program Management Office
Quality Management Plan
Path Convergence
What-If Sce
38. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Rolling Wave Planning
Critical Path
Change Control
Early Start Date
39. A set of conditions that is required to be met before deliverables are accepted.
Start-to-Start
Acceptance Criteria
Critical Path Method
Organizational Project Management Maturity
40. A risk that would have a negative effect on one or more project objectives.
Parametric Estimating
Threat
Level of Effort
Project Schedule Network Diagram
41. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Constraint
Most Likely Duration
Project Phase
Bottom-up Estimating
42. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Probability and Impact Matrix
Schedule Baseline
Late Start Date
Human Resource Plan
43. The sum of all budgets established for the work to be performed.
Budget at Completion
Late Start Date
Schedule Baseline
Cost Performance Index
44. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Optimistic Duration
Cost Variance
Data Date
Resource Breakdown Structure
45. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Resource Calendar
Product Life Cycle
Acceptance Criteria
Procurement Management Plan
46. An activity that logically comes before a dependent activity in a schedule.
Code of Accounts
Organizational Breakdown Structure
Predecessor Activity
Secondary Risk
47. The document that describes how the project will be executed - monitored - and controlled.
Project Management Plan
Risk Breakdown Structure
Analogous Estimating
Requirements Traceability Matrix
48. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Schedule Management Plan
Lag
Risk Category
Three-Point Estimate
49. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Precedence Diagramming Method
Level of Effort
Portfolio
Free Float
50. A technique used to shorten the schedule duration without reducing the project scope.
Schedule Management Plan
Requirement
Schedule Compression
Human Resource Plan