SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Level of Effort
Variance Analysis
Progressive Elaboration
Preventive Action
2. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Progressive Elaboration
Critical Path Method
Free Float
Portfolio Management
3. An intentional activity that realigns the performance of the project work with the project management plan.
Project Calendar
Percent Complete
Corrective Action
Critical Path Activity
4. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Early Finish Date
Program
Corrective Action
Planned Value
5. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Variance Analysis
Project Management
Risk
Project Scope
6. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Change Control Board
Estimate to Complete
Crashing
Performing Organization
7. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Quality Management Plan
Gantt Chart
Schedule Baseline
Variance at Completion
8. A risk that would have a positive effect on one or more project objectives.
Change Control
Opportunity
Control Account
Organizational Project Management Maturity
9. A distinct - scheduled portion of work performed during the course of a project.
Project Management Office
Activity
Pessimistic Duration
Project Charter
10. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Portfolio Management
Staffing Management Plan
Crashing
Effort
11. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Organizational Breakdown Structure
Analogous Estimating
Phase Gate
Product Life Cycle
12. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Estimate at Completion
Control Account
Three-Point Estimate
Assumption
13. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Change Control
Change Request
Most Likely Duration
Risk Management Plan
14. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Precedence Diagramming Method
Logical Relationship
Responsibility Assignment Matrix
Schedule Management Plan
15. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Portfolio Balancing
Critical Path
Risk Mitigation
Change Control
16. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Start-to-Finish
Variance Analysis
Program Management
Constraint
17. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Cost Management Plan
Enterprise Environmental Factors
Project
Cost Variance
18. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Project Management Plan
Preventive Action
S-Curve Analysis
Early Start Date
19. A calendar that identifies working days and shifts that are available for scheduled activities.
Gantt Chart
Project Calendar
Requirements Traceability Matrix
Path Divergence
20. The measure of work performed expressed in terms of the budget authorized for that work.
Data Date
Cost Management Plan
Earned Value
Logical Relationship
21. An intentional activity to modify a nonconforming product or product component.
Gantt Chart
Schedule Model Analysis
Defect Repair
Summary Activity
22. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Change Request
Variance at Completion
Data Date
WBS Dictionary
23. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Risk Mitigation
Decomposition
Portfolio
Corrective Action
24. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Gantt Chart
Program
Data Date
Opportunity
25. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Responsibility Assignment Matrix
Change Control Board
Path Divergence
Project Management
26. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Change Request
Deliverable
Most Likely Duration
Project Schedule
27. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Schedule Variance
Project Scope Statement
Three-Point Estimate
Project Charter
28. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Quality Management Plan
Start-to-Start
Optimistic Duration
Resource Calendar
29. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Requirements Management Plan
Risk Avoidance
Milestone
Planned Value
30. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Code of Accounts
Path Convergence
Most Likely Duration
Schedule Model Analysis
31. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Constraint
Early Finish Date
Earned Value Management
Progressive Elaboration
32. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Staffing Management Plan
Late Finish Date
Stakeholder
Late Start Date
33. The work performed to deliver a product - service - or result with the specified features and functions.
Code of Accounts
Decomposition
Most Likely Duration
Project Scope
34. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Deliverable
Early Start Date
Secondary Risk
Portfolio Balancing
35. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Resource Calendar
Baseline
Schedule Model
Project
36. A risk that arises as a direct result of implementing a risk response.
Schedule Performance Index
Acceptance Criteria
Secondary Risk
Earned Value Management
37. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Lead
Risk Avoidance
Portfolio
Performing Organization
38. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Schedule Model Analysis
Level of Effort
Change Control
Organizational Breakdown Structure
39. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Estimate at Completion
Estimate to Complete
Risk Transference
Code of Accounts
40. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Change Control Board
Late Start Date
Schedule Variance
Backward Pass
41. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Optimistic Duration
Deliverable
Project
Backward Pass
42. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Lessons Learned
Critical Path Method
Project Management
Preventive Action
43. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Project Life Cycle
What-If Sce
Scope Baseline
Project Management Plan
44. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Change Control System
Schedule Management Plan
Forward Pass
Decision Tree Analysis
45. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Risk Avoidance
Trigger Condition
Level of Effort
Portfolio Balancing
46. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Portfolio Management
Finish-to-Start
Progressive Elaboration
Precedence Diagramming Method
47. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Risk Acceptance
Sponsor
Lead
Level of Effort
48. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Project Calendar
Three-Point Estimate
Risk Acceptance
Procurement Management Plan
49. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Baseline
Resource Breakdown Structure
Logical Relationship
Critical Chain Method
50. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Cost Performance Index
Project Scope
Organizational Breakdown Structure
Critical Chain Method
Sorry!:) No result found.
Can you answer 50 questions in 15 minutes?
Let me suggest you:
Browse all subjects
Browse all tests
Most popular tests
Major Subjects
Tests & Exams
AP
CLEP
DSST
GRE
SAT
GMAT
Certifications
CISSP go to https://www.isc2.org/
PMP
ITIL
RHCE
MCTS
More...
IT Skills
Android Programming
Data Modeling
Objective C Programming
Basic Python Programming
Adobe Illustrator
More...
Business Skills
Advertising Techniques
Business Accounting Basics
Business Strategy
Human Resource Management
Marketing Basics
More...
Soft Skills
Body Language
People Skills
Public Speaking
Persuasion
Job Hunting And Resumes
More...
Vocabulary
GRE Vocab
SAT Vocab
TOEFL Essential Vocab
Basic English Words For All
Global Words You Should Know
Business English
More...
Languages
AP German Vocab
AP Latin Vocab
SAT Subject Test: French
Italian Survival
Norwegian Survival
More...
Engineering
Audio Engineering
Computer Science Engineering
Aerospace Engineering
Chemical Engineering
Structural Engineering
More...
Health Sciences
Basic Nursing Skills
Health Science Language Fundamentals
Veterinary Technology Medical Language
Cardiology
Clinical Surgery
More...
English
Grammar Fundamentals
Literary And Rhetorical Vocab
Elements Of Style Vocab
Introduction To English Major
Complete Advanced Sentences
Literature
Homonyms
More...
Math
Algebra Formulas
Basic Arithmetic: Measurements
Metric Conversions
Geometric Properties
Important Math Facts
Number Sense Vocab
Business Math
More...
Other Major Subjects
Science
Economics
History
Law
Performing-arts
Cooking
Logic & Reasoning
Trivia
Browse all subjects
Browse all tests
Most popular tests