SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Estimate to Complete
Change Control System
Preventive Action
Critical Path
2. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Project Phase
Bottom-up Estimating
Performing Organization
Probability and Impact Matrix
3. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Risk Mitigation
Cost Variance
Lessons Learned
Risk Breakdown Structure
4. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Decomposition
Sponsor
Lead
Risk Transference
5. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Organizational Breakdown Structure
Earned Value Management
Project Scope Statement
Staffing Management Plan
6. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Late Start Date
Percent Complete
Requirements Management Plan
Start-to-Finish
7. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Decision Tree Analysis
Project Schedule
Budget at Completion
Planned Value
8. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
WBS Dictionary
Procurement Management Plan
Gantt Chart
Constraint
9. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
What-If Sce
Start-to-Finish
Fast Tracking
Scope Creep
10. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Change Request
Deliverable
Probability and Impact Matrix
To-Complete Performance Index
11. A grid that links product requirements from their origin to the deliverables that satisfy them.
Optimistic Duration
Portfolio Management
Critical Chain Method
Requirements Traceability Matrix
12. The sum of all budgets established for the work to be performed.
Project Schedule Network Diagram
Lessons Learned
Budget at Completion
Enterprise Environmental Factors
13. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Project Charter
Schedule Variance
Enterprise Environmental Factors
Discrete Effort
14. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Percent Complete
Risk Transference
Acceptance Criteria
Project Charter
15. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Portfolio
Risk Register
Fast Tracking
Scope Management Plan
16. A formal proposal to modify any document - deliverable - or baseline.
Change Request
Change Control
Analogous Estimating
Critical Path Activity
17. A dependent activity that logically comes after another activity in a schedule.
Communication Management Plan
Successor Activity
Schedule Variance
Requirements Management Plan
18. A group of potential causes of risk.
Risk Category
Risk Transference
Acceptance Criteria
Change Control System
19. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Crashing
Scope Baseline
Change Control
Backward Pass
20. A significant point or event in a project - program - or portfolio.
Lead
Milestone
Risk Acceptance
What-If Sce
21. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Precedence Diagramming Method
Earned Value
Early Finish Date
Program Management
22. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Program Management Office
Baseline
Earned Value
Late Finish Date
23. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Late Start Date
Project Management
Progressive Elaboration
Bottom-up Estimating
24. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Risk Acceptance
Scope Baseline
Schedule Management Plan
Project Scope Statement
25. A set of conditions that is required to be met before deliverables are accepted.
Path Divergence
Phase Gate
Acceptance Criteria
Parametric Estimating
26. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Crashing
Late Finish Date
Percent Complete
Estimate to Complete
27. A risk that would have a negative effect on one or more project objectives.
Threat
Portfolio Management
Variance Analysis
Analogous Estimating
28. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Project Charter
Program Management Office
Program Management
Change Control
29. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Lag
Schedule Management Plan
Scope Creep
Percent Complete
30. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Communication Management Plan
Three-Point Estimate
Early Finish Date
Phase Gate
31. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Project Management Plan
Critical Path Activity
Apportioned Effort
Estimate to Complete
32. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Sponsor
Path Convergence
Percent Complete
Estimate to Complete
33. The realized cost incurred for the work performed on an activity during a specific time period.
Earned Value
Actual Cost
Planned Value
Most Likely Duration
34. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Schedule Model Analysis
Stakeholder
Risk Management Plan
Risk Acceptance
35. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Project Charter
Late Finish Date
Analogous Estimating
Actual Cost
36. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Risk Avoidance
Control Account
Trigger Condition
Schedule Baseline
37. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Deliverable
Risk Category
Early Start Date
Total Float
38. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Crashing
Constraint
Start-to-Start
Change Request
39. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Schedule Model Analysis
Requirement
Risk Register
Finish-to-Finish
40. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Procurement Management Plan
WBS Dictionary
Threat
Staffing Management Plan
41. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Schedule Compression
Earned Value Management
Scope Creep
Change Control Board
42. The expected cost to finish all the remaining project work.
Estimate to Complete
Finish-to-Start
Enterprise Environmental Factors
Organizational Process Assets
43. A calendar that identifies working days and shifts that are available for scheduled activities.
Predecessor Activity
Cost Performance Index
Project Calendar
Requirements Management Plan
44. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Cost Management Plan
Three-Point Estimate
Risk Transference
Finish-to-Start
45. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Decomposition
Performing Organization
Risk
Preventive Action
46. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Phase Gate
Lessons Learned
Trigger Condition
Probability and Impact Matrix
47. A limiting factor that affects the execution of a project - program - portfolio - or process.
Effort
Constraint
Summary Activity
Project Charter
48. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Project Scope Statement
Project Manager
Schedule Baseline
Portfolio Balancing
49. The description of the project scope - major deliverables - assumptions - and constraints.
Project Scope Statement
Estimate at Completion
Cost Variance
Risk
50. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Crashing
Scope Management Plan
Opportunity
Risk Acceptance