SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The realized cost incurred for the work performed on an activity during a specific time period.
Path Divergence
Actual Cost
Control Account
Total Float
2. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Summary Activity
Schedule Baseline
Start-to-Start
Schedule Management Plan
3. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Code of Accounts
Portfolio Management
Bottom-up Estimating
Risk Management Plan
4. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Critical Path Activity
Quality Management Plan
Project Charter
Deliverable
5. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Planned Value
Portfolio Management
Organizational Project Management Maturity
Baseline
6. A risk that arises as a direct result of implementing a risk response.
Path Convergence
Path Divergence
Secondary Risk
Discrete Effort
7. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Critical Path Method
Change Control
Requirements Management Plan
Program Management Office
8. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Risk Management Plan
Organizational Process Assets
Free Float
Change Control
9. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Enterprise Environmental Factors
Summary Activity
Requirement
Milestone
10. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Project Management
Change Control
Project Schedule Network Diagram
Scope Baseline
11. A relationship in which a schedule activity has more than one successor.
S-Curve Analysis
Path Divergence
Successor Activity
Finish-to-Start
12. A limiting factor that affects the execution of a project - program - portfolio - or process.
Phase Gate
Progressive Elaboration
Project Life Cycle
Constraint
13. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Schedule Model
Project Phase
Staffing Management Plan
Apportioned Effort
14. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Change Control Board
Backward Pass
Quality Management Plan
Pessimistic Duration
15. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Risk Mitigation
Schedule Performance Index
Schedule Baseline
Path Divergence
16. A risk that would have a negative effect on one or more project objectives.
Crashing
Threat
Enterprise Environmental Factors
Project Management
17. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Three-Point Estimate
Cost Performance Index
Risk Mitigation
Late Start Date
18. The centralized management of one or more portfolios to achieve strategic objectives.
Portfolio Management
Early Finish Date
Three-Point Estimate
Requirements Management Plan
19. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Procurement Management Plan
Resource Breakdown Structure
Risk Management Plan
Forward Pass
20. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Critical Path Activity
Critical Path Method
Cost Management Plan
Budget at Completion
21. A relationship in which a schedule activity has more than one predecessor.
Path Convergence
Secondary Risk
Late Finish Date
Lead
22. A graphical representation of the logical relationships among the project schedule activities.
Total Float
Preventive Action
Project Schedule Network Diagram
Risk Breakdown Structure
23. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Finish-to-Start
Secondary Risk
Schedule Model Analysis
Critical Chain Method
24. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Critical Path Activity
Human Resource Plan
Pessimistic Duration
Schedule Performance Index
25. A formal proposal to modify any document - deliverable - or baseline.
Change Request
Risk Management Plan
Program
Pessimistic Duration
26. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Responsibility Assignment Matrix
Effort
Lessons Learned
Project Schedule
27. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Risk Acceptance
Early Start Date
Estimate at Completion
Parametric Estimating
28. Any activity on the critical path in a project schedule.
Critical Path Activity
Product Life Cycle
Rolling Wave Planning
Estimate to Complete
29. The document that describes how the project will be executed - monitored - and controlled.
Precedence Diagramming Method
Estimate at Completion
Project Management Plan
Resource Calendar
30. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Pessimistic Duration
Resource Leveling
Three-Point Estimate
Change Control System
31. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Start-to-Start
Forward Pass
Schedule Baseline
Optimistic Duration
32. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Successor Activity
Rolling Wave Planning
Most Likely Duration
Milestone
33. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Change Control System
Program
Forward Pass
To-Complete Performance Index
34. A risk that would have a positive effect on one or more project objectives.
Lag
Opportunity
Project
Risk Mitigation
35. A technique for determining the cause and degree of difference between the baseline and actual performance.
Resource Breakdown Structure
Variance Analysis
Discrete Effort
Start-to-Start
36. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Project Phase
Lessons Learned
Progressive Elaboration
Decomposition
37. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Critical Chain Method
Parametric Estimating
Project Schedule Network Diagram
Stakeholder
38. A point in time when the status of the project is recorded.
Critical Chain Method
Schedule Variance
Data Date
Change Control Board
39. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Project Charter
Program Management Office
Successor Activity
WBS Dictionary
40. An activity that logically comes before a dependent activity in a schedule.
Effort
Code of Accounts
Predecessor Activity
Phase Gate
41. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Program
Project Calendar
Organizational Breakdown Structure
Crashing
42. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Analogous Estimating
Scope Management Plan
Path Convergence
Risk
43. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Successor Activity
Trigger Condition
Risk Mitigation
Precedence Diagramming Method
44. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Risk Avoidance
Staffing Management Plan
Project Schedule
Communication Management Plan
45. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Finish-to-Start
Schedule Performance Index
Risk Management Plan
Late Start Date
46. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Fast Tracking
Decision Tree Analysis
Project Phase
Change Control Board
47. The series of phases that a project passes through from its initiation to its closure.
To-Complete Performance Index
Project Life Cycle
Parametric Estimating
Project Management Office
48. A grid that shows the project resources assigned to each work package.
Responsibility Assignment Matrix
What-If Sce
Finish-to-Start
Project Scope
49. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Project Schedule
Sponsor
Start-to-Finish
Product Life Cycle
50. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Rolling Wave Planning
Program
Probability and Impact Matrix
Cost Performance Index