SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Summary Activity
Level of Effort
Risk Mitigation
Baseline
2. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Probability and Impact Matrix
Stakeholder
Risk Register
Product Life Cycle
3. A risk that would have a negative effect on one or more project objectives.
Threat
Summary Activity
Parametric Estimating
Lag
4. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Project Charter
S-Curve Analysis
Crashing
Start-to-Finish
5. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Finish-to-Start
What-If Sce
Project Manager
Total Float
6. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Discrete Effort
Path Divergence
Program Management
Estimate at Completion
7. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Program
Project
Forward Pass
Preventive Action
8. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Change Control Board
Project Life Cycle
Quality Management Plan
Schedule Baseline
9. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Most Likely Duration
Schedule Baseline
Portfolio Management
Budget at Completion
10. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Project Schedule
Activity
Earned Value Management
Project Management
11. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Analogous Estimating
Quality Management Plan
Risk Register
Resource Calendar
12. An event or situation that indicates that a risk is about to occur.
Trigger Condition
Decomposition
Quality Management Plan
Probability and Impact Matrix
13. A document in which the results of risk analysis and risk response planning are recorded.
Threat
Responsibility Assignment Matrix
Schedule Model Analysis
Risk Register
14. The sum of all budgets established for the work to be performed.
Budget at Completion
Communication Management Plan
Rolling Wave Planning
Secondary Risk
15. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Data Date
Percent Complete
Parametric Estimating
Schedule Model Analysis
16. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Procurement Management Plan
Portfolio Balancing
Performing Organization
Project Schedule Network Diagram
17. The authorized budget assigned to scheduled work.
Planned Value
Earned Value Management
Predecessor Activity
Risk Acceptance
18. A formal proposal to modify any document - deliverable - or baseline.
Activity
Early Start Date
Change Request
Critical Path Method
19. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Schedule Compression
Schedule Variance
Project Schedule Network Diagram
Optimistic Duration
20. A point in time when the status of the project is recorded.
Data Date
Project Manager
Project Management Plan
Planned Value
21. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Rolling Wave Planning
Baseline
Earned Value Management
Gantt Chart
22. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Three-Point Estimate
Estimate at Completion
Critical Path
Scope Creep
23. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Enterprise Environmental Factors
Data Date
Three-Point Estimate
Preventive Action
24. A grid that links product requirements from their origin to the deliverables that satisfy them.
Requirements Traceability Matrix
Path Divergence
Total Float
Requirements Management Plan
25. A limiting factor that affects the execution of a project - program - portfolio - or process.
Crashing
Risk Avoidance
Corrective Action
Constraint
26. Any activity on the critical path in a project schedule.
What-If Sce
Cost Variance
Project
Critical Path Activity
27. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Critical Path
Early Start Date
Preventive Action
Most Likely Duration
28. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Actual Cost
Enterprise Environmental Factors
Cost Variance
Resource Leveling
29. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Quality Management Plan
Critical Path
Progressive Elaboration
Backward Pass
30. A significant point or event in a project - program - or portfolio.
Milestone
Critical Chain Method
Critical Path Activity
Defect Repair
31. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Phase Gate
To-Complete Performance Index
Probability and Impact Matrix
Requirement
32. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Schedule Baseline
Finish-to-Start
Schedule Management Plan
Apportioned Effort
33. An intentional activity that realigns the performance of the project work with the project management plan.
Rolling Wave Planning
Corrective Action
Requirements Traceability Matrix
Portfolio Management
34. A numbering system used to uniquely identify each component of the work breakdown structure.
Schedule Management Plan
Code of Accounts
Bottom-up Estimating
Project Schedule
35. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Critical Path
WBS Dictionary
Risk Avoidance
Risk Acceptance
36. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Program Management Office
What-If Sce
Decision Tree Analysis
Trigger Condition
37. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Threat
Bottom-up Estimating
Defect Repair
Late Start Date
38. A temporary endeavor undertaken to create a unique product - service - or result.
Critical Path Method
Rolling Wave Planning
Resource Leveling
Project
39. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Three-Point Estimate
Level of Effort
Risk Avoidance
Effort
40. A dependent activity that logically comes after another activity in a schedule.
Estimate to Complete
Successor Activity
Probability and Impact Matrix
Risk Transference
41. An intentional activity to modify a nonconforming product or product component.
Defect Repair
Logical Relationship
Rolling Wave Planning
Portfolio Balancing
42. The work performed to deliver a product - service - or result with the specified features and functions.
Project Scope
Defect Repair
Summary Activity
Requirements Management Plan
43. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Probability and Impact Matrix
Human Resource Plan
Critical Path
Lead
44. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Variance Analysis
WBS Dictionary
Critical Path Method
Constraint
45. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Backward Pass
Critical Path
Decomposition
Variance at Completion
46. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Schedule Model
Project Manager
Path Convergence
Program
47. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Risk Transference
Parametric Estimating
Project Charter
Logical Relationship
48. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Procurement Management Plan
Scope Management Plan
Resource Leveling
To-Complete Performance Index
49. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Critical Chain Method
Program Management
Resource Leveling
Path Divergence
50. A technique for determining the cause and degree of difference between the baseline and actual performance.
Acceptance Criteria
Requirements Traceability Matrix
Variance Analysis
Summary Activity