SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Critical Path Activity
S-Curve Analysis
Optimistic Duration
Schedule Performance Index
2. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Crashing
Variance Analysis
Variance at Completion
Predecessor Activity
3. A numbering system used to uniquely identify each component of the work breakdown structure.
Rolling Wave Planning
Successor Activity
Code of Accounts
Schedule Variance
4. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Scope Creep
WBS Dictionary
Cost Variance
Lessons Learned
5. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Resource Leveling
Discrete Effort
Three-Point Estimate
Stakeholder
6. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Organizational Process Assets
Assumption
Product Life Cycle
Path Convergence
7. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Project Scope Statement
Gantt Chart
Procurement Management Plan
Pessimistic Duration
8. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Bottom-up Estimating
Performing Organization
Lag
Earned Value Management
9. The description of the project scope - major deliverables - assumptions - and constraints.
Change Control
Requirement
Risk Avoidance
Project Scope Statement
10. A significant point or event in a project - program - or portfolio.
Scope Baseline
Product Life Cycle
Forward Pass
Milestone
11. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Deliverable
Quality Management Plan
To-Complete Performance Index
Constraint
12. A point in time when the status of the project is recorded.
Data Date
Early Start Date
Lag
Project Management Office
13. The document that describes how the project will be executed - monitored - and controlled.
Organizational Project Management Maturity
Project Management Plan
Scope Baseline
Early Finish Date
14. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Risk Mitigation
Parametric Estimating
Lead
S-Curve Analysis
15. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Total Float
Project Management Office
Resource Breakdown Structure
Budget at Completion
16. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Planned Value
Project Schedule
Procurement Management Plan
S-Curve Analysis
17. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Opportunity
Decision Tree Analysis
Precedence Diagramming Method
Parametric Estimating
18. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Project Management
Total Float
Change Control System
Discrete Effort
19. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Project Schedule
Performing Organization
Schedule Compression
Scope Baseline
20. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Schedule Performance Index
Responsibility Assignment Matrix
Free Float
Project Scope Statement
21. The centralized management of one or more portfolios to achieve strategic objectives.
Activity
Earned Value
Portfolio Management
Probability and Impact Matrix
22. An intentional activity to modify a nonconforming product or product component.
Start-to-Start
Predecessor Activity
Defect Repair
Schedule Management Plan
23. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Risk Register
Scope Baseline
Finish-to-Start
Threat
24. A group of potential causes of risk.
Optimistic Duration
Risk Category
Communication Management Plan
Progressive Elaboration
25. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Critical Chain Method
Procurement Management Plan
Schedule Compression
Start-to-Finish
26. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Opportunity
Effort
Corrective Action
Actual Cost
27. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Enterprise Environmental Factors
Communication Management Plan
Requirement
Precedence Diagramming Method
28. A set of conditions that is required to be met before deliverables are accepted.
Change Request
Acceptance Criteria
Threat
Program Management
29. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Opportunity
Control Account
Portfolio Balancing
Schedule Compression
30. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Enterprise Environmental Factors
Summary Activity
Performing Organization
Organizational Breakdown Structure
31. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Actual Cost
Risk Avoidance
Start-to-Finish
Program Management Office
32. An event or situation that indicates that a risk is about to occur.
Variance at Completion
Trigger Condition
Phase Gate
Resource Breakdown Structure
33. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Risk Acceptance
Three-Point Estimate
Progressive Elaboration
Estimate to Complete
34. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Organizational Breakdown Structure
Organizational Process Assets
Percent Complete
Change Control System
35. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Program
Data Date
Analogous Estimating
Requirement
36. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Lag
Resource Calendar
Fast Tracking
Finish-to-Start
37. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Risk Management Plan
Earned Value Management
Project Manager
Finish-to-Finish
38. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Requirements Management Plan
Start-to-Finish
Sponsor
Resource Leveling
39. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Finish-to-Start
Project Scope
Summary Activity
Product Life Cycle
40. The measure of work performed expressed in terms of the budget authorized for that work.
Actual Cost
WBS Dictionary
Total Float
Earned Value
41. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Product Life Cycle
Path Divergence
Threat
Decomposition
42. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Program
Resource Leveling
Stakeholder
Change Control System
43. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Preventive Action
Portfolio
Portfolio Management
Three-Point Estimate
44. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Enterprise Environmental Factors
Critical Chain Method
Deliverable
Resource Calendar
45. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Quality Management Plan
Baseline
Acceptance Criteria
Late Start Date
46. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Risk Breakdown Structure
Program Management
Percent Complete
Level of Effort
47. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Communication Management Plan
Change Control
Secondary Risk
Critical Path Method
48. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Risk Mitigation
Scope Management Plan
Three-Point Estimate
Lag
49. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Early Start Date
Project Scope
Pessimistic Duration
Preventive Action
50. Any activity on the critical path in a project schedule.
Crashing
Project Life Cycle
Critical Path Activity
Actual Cost