SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A distinct - scheduled portion of work performed during the course of a project.
Requirements Traceability Matrix
Risk Acceptance
Logical Relationship
Activity
2. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Risk Avoidance
Rolling Wave Planning
Enterprise Environmental Factors
Change Control Board
3. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Communication Management Plan
Probability and Impact Matrix
Estimate at Completion
Code of Accounts
4. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Requirements Management Plan
Cost Performance Index
Late Start Date
Scope Management Plan
5. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Risk Management Plan
Discrete Effort
Summary Activity
Forward Pass
6. A risk that would have a positive effect on one or more project objectives.
Variance at Completion
Opportunity
Risk
Risk Management Plan
7. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Early Finish Date
Risk Breakdown Structure
Free Float
S-Curve Analysis
8. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Deliverable
Constraint
Discrete Effort
Resource Calendar
9. A document in which the results of risk analysis and risk response planning are recorded.
Risk Register
Schedule Compression
Preventive Action
S-Curve Analysis
10. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Optimistic Duration
Opportunity
Risk Category
Project
11. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Cost Management Plan
Schedule Management Plan
What-If Sce
Enterprise Environmental Factors
12. A dependent activity that logically comes after another activity in a schedule.
Portfolio Management
Preventive Action
Successor Activity
Late Start Date
13. An intentional activity to modify a nonconforming product or product component.
Project Management Office
Defect Repair
Parametric Estimating
Assumption
14. A hierarchical representation of risks that is organized according to risk categories.
Logical Relationship
Risk Breakdown Structure
Analogous Estimating
What-If Sce
15. A set of conditions that is required to be met before deliverables are accepted.
Resource Breakdown Structure
Backward Pass
Organizational Breakdown Structure
Acceptance Criteria
16. A grid that shows the project resources assigned to each work package.
Backward Pass
Corrective Action
Actual Cost
Responsibility Assignment Matrix
17. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Project Life Cycle
Organizational Project Management Maturity
Early Finish Date
Risk Acceptance
18. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Project Management Plan
Estimate to Complete
Early Start Date
Schedule Model
19. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Probability and Impact Matrix
Sponsor
Project Manager
Project Scope Statement
20. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Corrective Action
Path Divergence
Quality Management Plan
Project Manager
21. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Total Float
Early Finish Date
Risk Transference
Cost Variance
22. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Path Convergence
Late Finish Date
Critical Chain Method
Decision Tree Analysis
23. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Performing Organization
Earned Value Management
Resource Breakdown Structure
Planned Value
24. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Organizational Breakdown Structure
Cost Performance Index
Stakeholder
Human Resource Plan
25. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Procurement Management Plan
Project Manager
Precedence Diagramming Method
Most Likely Duration
26. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Requirements Management Plan
Early Finish Date
Trigger Condition
Earned Value Management
27. A point in time when the status of the project is recorded.
Fast Tracking
Data Date
Cost Variance
Project Life Cycle
28. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Critical Path Method
Pessimistic Duration
Change Control System
Optimistic Duration
29. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Finish-to-Finish
Project Scope
S-Curve Analysis
Portfolio Balancing
30. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Critical Path Activity
Program Management Office
Gantt Chart
Schedule Performance Index
31. A calendar that identifies working days and shifts that are available for scheduled activities.
Risk Mitigation
Project Calendar
Pessimistic Duration
Risk Breakdown Structure
32. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Project Calendar
Apportioned Effort
Secondary Risk
Risk Transference
33. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Project Scope Statement
Organizational Breakdown Structure
Portfolio
Staffing Management Plan
34. The expected cost to finish all the remaining project work.
Risk Mitigation
Lag
Risk Category
Estimate to Complete
35. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Portfolio
What-If Sce
Pessimistic Duration
Decision Tree Analysis
36. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Lag
Scope Baseline
Acceptance Criteria
Schedule Variance
37. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Bottom-up Estimating
Project Management Office
Decision Tree Analysis
Discrete Effort
38. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Organizational Breakdown Structure
Variance Analysis
Change Control System
Critical Path
39. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Schedule Performance Index
Deliverable
To-Complete Performance Index
Organizational Project Management Maturity
40. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Apportioned Effort
Quality Management Plan
Backward Pass
Trigger Condition
41. The series of phases that a project passes through from its initiation to its closure.
Cost Variance
Project Life Cycle
Optimistic Duration
Estimate to Complete
42. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Scope Baseline
Stakeholder
Late Start Date
Analogous Estimating
43. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Scope Creep
Earned Value
Earned Value Management
Sponsor
44. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Schedule Performance Index
Trigger Condition
WBS Dictionary
Change Control Board
45. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Precedence Diagramming Method
Optimistic Duration
Preventive Action
Cost Performance Index
46. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Lag
Enterprise Environmental Factors
Bottom-up Estimating
Level of Effort
47. The sum of all budgets established for the work to be performed.
Corrective Action
Project
Late Finish Date
Budget at Completion
48. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Communication Management Plan
Organizational Process Assets
Risk Acceptance
Finish-to-Start
49. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Summary Activity
Schedule Variance
Estimate at Completion
Total Float
50. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Staffing Management Plan
Variance at Completion
Rolling Wave Planning
Product Life Cycle