SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Early Start Date
Risk Management Plan
Organizational Process Assets
Schedule Model
2. A technique used to shorten the schedule duration without reducing the project scope.
Acceptance Criteria
Start-to-Finish
Schedule Compression
Level of Effort
3. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Most Likely Duration
Bottom-up Estimating
Late Start Date
Requirement
4. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Performing Organization
Corrective Action
Change Control
Project Charter
5. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Lag
Finish-to-Start
Planned Value
Product Life Cycle
6. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Procurement Management Plan
What-If Sce
Lead
Budget at Completion
7. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Baseline
Resource Leveling
To-Complete Performance Index
Performing Organization
8. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Risk Mitigation
Bottom-up Estimating
Estimate to Complete
Requirements Management Plan
9. A calendar that identifies the working days and shifts upon which each specific resource is available.
Data Date
Resource Calendar
Lead
To-Complete Performance Index
10. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Level of Effort
Summary Activity
Schedule Management Plan
Estimate at Completion
11. A risk that would have a negative effect on one or more project objectives.
Activity
Analogous Estimating
Human Resource Plan
Threat
12. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Start-to-Finish
Procurement Management Plan
Program
Milestone
13. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Cost Performance Index
Portfolio Balancing
Crashing
Percent Complete
14. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Staffing Management Plan
Early Finish Date
Project Management Office
Baseline
15. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Performing Organization
Lag
Resource Breakdown Structure
Finish-to-Start
16. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Most Likely Duration
Schedule Performance Index
Stakeholder
Level of Effort
17. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Optimistic Duration
Control Account
Product Life Cycle
Backward Pass
18. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Apportioned Effort
Cost Management Plan
Communication Management Plan
Opportunity
19. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Data Date
Program Management
Early Finish Date
Scope Management Plan
20. The centralized management of one or more portfolios to achieve strategic objectives.
Portfolio Management
Schedule Baseline
Secondary Risk
Preventive Action
21. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Critical Path Activity
Staffing Management Plan
Critical Path Method
Risk Breakdown Structure
22. An event or situation that indicates that a risk is about to occur.
Cost Management Plan
Project
Trigger Condition
Risk Register
23. A hierarchical representation of resources by category and type.
Trigger Condition
Product Life Cycle
Project Manager
Resource Breakdown Structure
24. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Analogous Estimating
Project Management Office
Control Account
Estimate at Completion
25. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Estimate to Complete
Communication Management Plan
Early Start Date
Risk Acceptance
26. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Change Control System
Change Request
To-Complete Performance Index
Summary Activity
27. The document that describes how the project will be executed - monitored - and controlled.
Performing Organization
Free Float
Project Calendar
Project Management Plan
28. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Trigger Condition
Fast Tracking
Deliverable
Project
29. The realized cost incurred for the work performed on an activity during a specific time period.
Scope Management Plan
Actual Cost
Early Start Date
Predecessor Activity
30. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Threat
Free Float
Cost Variance
Schedule Variance
31. A grid that links product requirements from their origin to the deliverables that satisfy them.
Risk Transference
Early Start Date
Requirements Traceability Matrix
Project Management
32. An activity that logically comes before a dependent activity in a schedule.
Resource Leveling
Predecessor Activity
Discrete Effort
Lead
33. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Program Management Office
Schedule Model
Pessimistic Duration
Budget at Completion
34. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Estimate at Completion
Project Management Plan
Portfolio
Path Convergence
35. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Trigger Condition
Cost Management Plan
Lag
Enterprise Environmental Factors
36. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Responsibility Assignment Matrix
Risk
Quality Management Plan
Early Finish Date
37. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Decision Tree Analysis
Product Life Cycle
Staffing Management Plan
Project Phase
38. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Earned Value Management
Total Float
Change Control System
Precedence Diagramming Method
39. A group of potential causes of risk.
Estimate to Complete
Level of Effort
Risk Category
Planned Value
40. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Requirement
Schedule Model Analysis
Product Life Cycle
Path Convergence
41. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Estimate at Completion
Analogous Estimating
Deliverable
Corrective Action
42. A calendar that identifies working days and shifts that are available for scheduled activities.
Lag
Logical Relationship
Project Calendar
Finish-to-Start
43. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Project Calendar
Start-to-Finish
Bottom-up Estimating
Critical Path
44. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Successor Activity
Late Finish Date
Decomposition
Change Control Board
45. A point in time when the status of the project is recorded.
Variance at Completion
Resource Breakdown Structure
Assumption
Data Date
46. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Change Request
Effort
Performing Organization
Assumption
47. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Assumption
Resource Calendar
Path Divergence
Scope Creep
48. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Staffing Management Plan
Code of Accounts
Portfolio Balancing
Early Start Date
49. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Staffing Management Plan
What-If Sce
Free Float
Apportioned Effort
50. Any activity on the critical path in a project schedule.
Critical Path Activity
Lag
Change Control
Crashing