SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Late Finish Date
Fast Tracking
Sponsor
Portfolio Management
2. A grid that shows the project resources assigned to each work package.
Organizational Process Assets
Responsibility Assignment Matrix
Program
Apportioned Effort
3. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Activity
Variance at Completion
Summary Activity
WBS Dictionary
4. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Staffing Management Plan
Program
Actual Cost
Secondary Risk
5. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Project Schedule Network Diagram
Risk
Defect Repair
Procurement Management Plan
6. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Apportioned Effort
Optimistic Duration
Cost Variance
Scope Management Plan
7. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Procurement Management Plan
Decomposition
Performing Organization
Organizational Breakdown Structure
8. The series of phases that a project passes through from its initiation to its closure.
Late Finish Date
Analogous Estimating
Probability and Impact Matrix
Project Life Cycle
9. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Lead
Change Control System
Change Control Board
Schedule Performance Index
10. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Pessimistic Duration
Critical Path Method
Path Divergence
Project Management Plan
11. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Code of Accounts
Corrective Action
Variance Analysis
Control Account
12. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Secondary Risk
Lead
Late Start Date
Resource Leveling
13. A set of conditions that is required to be met before deliverables are accepted.
WBS Dictionary
Crashing
Acceptance Criteria
Risk Acceptance
14. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Critical Path Method
Change Control Board
Organizational Project Management Maturity
Schedule Model
15. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
S-Curve Analysis
Schedule Management Plan
Lag
Analogous Estimating
16. A group of related schedule activities aggregated and displayed as a single activity.
Responsibility Assignment Matrix
Start-to-Finish
Summary Activity
Total Float
17. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Decomposition
Gantt Chart
Planned Value
Discrete Effort
18. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Backward Pass
Discrete Effort
Corrective Action
Project Phase
19. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Critical Path
Baseline
Three-Point Estimate
Project Charter
20. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Risk Management Plan
Enterprise Environmental Factors
Logical Relationship
Communication Management Plan
21. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Secondary Risk
Start-to-Finish
Decomposition
Project Charter
22. The measure of work performed expressed in terms of the budget authorized for that work.
Lag
Decomposition
Earned Value
Analogous Estimating
23. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Progressive Elaboration
Responsibility Assignment Matrix
Schedule Management Plan
Late Finish Date
24. A dependency between two activities - or between an activity and a milestone.
Phase Gate
Progressive Elaboration
Logical Relationship
Portfolio
25. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Human Resource Plan
Scope Baseline
Procurement Management Plan
Project Calendar
26. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Milestone
Lag
Apportioned Effort
Change Control Board
27. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Total Float
Earned Value
Rolling Wave Planning
Schedule Model Analysis
28. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Control Account
Decision Tree Analysis
Forward Pass
Lessons Learned
29. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Early Finish Date
Project Calendar
Resource Calendar
Program
30. A calendar that identifies working days and shifts that are available for scheduled activities.
Fast Tracking
Project Calendar
Summary Activity
Scope Baseline
31. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Start-to-Finish
Precedence Diagramming Method
Planned Value
Earned Value Management
32. An intentional activity that realigns the performance of the project work with the project management plan.
Corrective Action
Opportunity
Variance at Completion
Project Management Plan
33. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
To-Complete Performance Index
Program Management Office
Data Date
Successor Activity
34. A technique for determining the cause and degree of difference between the baseline and actual performance.
Variance Analysis
Apportioned Effort
Precedence Diagramming Method
Organizational Process Assets
35. A technique used to shorten the schedule duration without reducing the project scope.
Portfolio Balancing
Gantt Chart
Trigger Condition
Schedule Compression
36. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Project
Risk Category
Early Finish Date
Apportioned Effort
37. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Schedule Variance
Project Phase
Schedule Model Analysis
Phase Gate
38. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Parametric Estimating
Sponsor
Change Request
Preventive Action
39. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Schedule Baseline
Risk Register
Cost Performance Index
Sponsor
40. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Enterprise Environmental Factors
Project Management Office
Percent Complete
Data Date
41. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Schedule Management Plan
Risk Management Plan
Lessons Learned
Early Start Date
42. A document in which the results of risk analysis and risk response planning are recorded.
Bottom-up Estimating
Successor Activity
Risk Register
Risk Management Plan
43. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Three-Point Estimate
What-If Sce
Portfolio Balancing
Risk Breakdown Structure
44. A grid that links product requirements from their origin to the deliverables that satisfy them.
Constraint
Control Account
Requirements Traceability Matrix
Optimistic Duration
45. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Code of Accounts
Estimate at Completion
Precedence Diagramming Method
Organizational Process Assets
46. Any activity on the critical path in a project schedule.
Critical Path Activity
What-If Sce
S-Curve Analysis
Sponsor
47. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Change Request
Risk
Scope Baseline
Pessimistic Duration
48. A temporary endeavor undertaken to create a unique product - service - or result.
Portfolio
Project
Path Convergence
Code of Accounts
49. An intentional activity to modify a nonconforming product or product component.
Defect Repair
Logical Relationship
Path Convergence
Project Life Cycle
50. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Gantt Chart
Project Charter
Sponsor
Project Manager