SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Lessons Learned
Fast Tracking
Parametric Estimating
Staffing Management Plan
2. Any activity on the critical path in a project schedule.
Deliverable
Data Date
Critical Path Activity
Milestone
3. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Estimate to Complete
Sponsor
Communication Management Plan
Schedule Variance
4. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Discrete Effort
Risk Management Plan
Schedule Variance
Apportioned Effort
5. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
S-Curve Analysis
Forward Pass
Progressive Elaboration
Project Schedule
6. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Lead
Finish-to-Finish
Gantt Chart
Preventive Action
7. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Project Management
Scope Baseline
Change Request
Gantt Chart
8. A risk that arises as a direct result of implementing a risk response.
Trigger Condition
Secondary Risk
Free Float
Project Scope
9. A relationship in which a schedule activity has more than one predecessor.
Free Float
Cost Performance Index
Variance at Completion
Path Convergence
10. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Staffing Management Plan
Progressive Elaboration
Deliverable
Change Request
11. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Schedule Management Plan
Level of Effort
Schedule Model Analysis
Corrective Action
12. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Activity
Variance Analysis
To-Complete Performance Index
Risk Category
13. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Resource Breakdown Structure
Product Life Cycle
Preventive Action
Critical Path Method
14. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Change Control Board
Trigger Condition
Bottom-up Estimating
Secondary Risk
15. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Opportunity
Backward Pass
Schedule Performance Index
Performing Organization
16. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Project Scope Statement
Schedule Performance Index
Discrete Effort
Communication Management Plan
17. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Project Calendar
Critical Path Activity
Earned Value Management
Gantt Chart
18. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Decomposition
Baseline
Apportioned Effort
Start-to-Finish
19. A graphical representation of the logical relationships among the project schedule activities.
Organizational Breakdown Structure
Lag
Project Schedule Network Diagram
Product Life Cycle
20. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Precedence Diagramming Method
Budget at Completion
Successor Activity
Start-to-Start
21. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Scope Baseline
Decision Tree Analysis
Finish-to-Start
Phase Gate
22. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Responsibility Assignment Matrix
Program
Schedule Baseline
Portfolio
23. An event or situation that indicates that a risk is about to occur.
Risk Register
To-Complete Performance Index
Trigger Condition
Cost Performance Index
24. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Scope Creep
Program
Staffing Management Plan
Effort
25. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Project Phase
Scope Creep
Schedule Management Plan
Project Management
26. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Resource Calendar
Probability and Impact Matrix
Estimate at Completion
Apportioned Effort
27. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Critical Path
Scope Baseline
Risk Mitigation
Total Float
28. A calendar that identifies working days and shifts that are available for scheduled activities.
Change Request
Project Calendar
Responsibility Assignment Matrix
Scope Baseline
29. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Actual Cost
Discrete Effort
Gantt Chart
Deliverable
30. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Constraint
Start-to-Finish
Corrective Action
Scope Management Plan
31. The document that describes how the project will be executed - monitored - and controlled.
Project Schedule
Organizational Project Management Maturity
Project Management Plan
Data Date
32. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Backward Pass
Probability and Impact Matrix
Project Scope
Cost Performance Index
33. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Control Account
Analogous Estimating
Earned Value Management
Preventive Action
34. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Early Start Date
Rolling Wave Planning
Communication Management Plan
Cost Management Plan
35. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Schedule Performance Index
Lessons Learned
Schedule Variance
Change Control
36. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Estimate at Completion
Organizational Project Management Maturity
Enterprise Environmental Factors
Forward Pass
37. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Estimate at Completion
Planned Value
Schedule Management Plan
Critical Path
38. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Critical Chain Method
Finish-to-Finish
Portfolio Balancing
S-Curve Analysis
39. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Free Float
Progressive Elaboration
Start-to-Finish
Schedule Variance
40. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Lag
Project Life Cycle
Start-to-Start
Risk
41. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Bottom-up Estimating
Stakeholder
Finish-to-Finish
Variance at Completion
42. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
WBS Dictionary
Project Phase
Analogous Estimating
Bottom-up Estimating
43. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Program Management Office
Crashing
Probability and Impact Matrix
Finish-to-Finish
44. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Lag
Schedule Variance
Decision Tree Analysis
Human Resource Plan
45. A formal proposal to modify any document - deliverable - or baseline.
Change Request
Risk Transference
Lessons Learned
Project Schedule
46. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Apportioned Effort
Lessons Learned
Project Management Office
Stakeholder
47. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Organizational Project Management Maturity
Project Calendar
Apportioned Effort
Earned Value
48. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Project Management
Scope Management Plan
Scope Baseline
Change Request
49. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Earned Value
Preventive Action
WBS Dictionary
Change Control
50. A significant point or event in a project - program - or portfolio.
Scope Management Plan
Milestone
Organizational Project Management Maturity
Risk Management Plan
Sorry!:) No result found.
Can you answer 50 questions in 15 minutes?
Let me suggest you:
Browse all subjects
Browse all tests
Most popular tests
Major Subjects
Tests & Exams
AP
CLEP
DSST
GRE
SAT
GMAT
Certifications
CISSP go to https://www.isc2.org/
PMP
ITIL
RHCE
MCTS
More...
IT Skills
Android Programming
Data Modeling
Objective C Programming
Basic Python Programming
Adobe Illustrator
More...
Business Skills
Advertising Techniques
Business Accounting Basics
Business Strategy
Human Resource Management
Marketing Basics
More...
Soft Skills
Body Language
People Skills
Public Speaking
Persuasion
Job Hunting And Resumes
More...
Vocabulary
GRE Vocab
SAT Vocab
TOEFL Essential Vocab
Basic English Words For All
Global Words You Should Know
Business English
More...
Languages
AP German Vocab
AP Latin Vocab
SAT Subject Test: French
Italian Survival
Norwegian Survival
More...
Engineering
Audio Engineering
Computer Science Engineering
Aerospace Engineering
Chemical Engineering
Structural Engineering
More...
Health Sciences
Basic Nursing Skills
Health Science Language Fundamentals
Veterinary Technology Medical Language
Cardiology
Clinical Surgery
More...
English
Grammar Fundamentals
Literary And Rhetorical Vocab
Elements Of Style Vocab
Introduction To English Major
Complete Advanced Sentences
Literature
Homonyms
More...
Math
Algebra Formulas
Basic Arithmetic: Measurements
Metric Conversions
Geometric Properties
Important Math Facts
Number Sense Vocab
Business Math
More...
Other Major Subjects
Science
Economics
History
Law
Performing-arts
Cooking
Logic & Reasoning
Trivia
Browse all subjects
Browse all tests
Most popular tests