SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Estimate at Completion
Start-to-Start
Secondary Risk
Risk Transference
2. A temporary endeavor undertaken to create a unique product - service - or result.
Risk Avoidance
Risk
Portfolio Management
Project
3. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Analogous Estimating
Critical Chain Method
Cost Performance Index
Most Likely Duration
4. A relationship in which a schedule activity has more than one successor.
Project
Procurement Management Plan
Performing Organization
Path Divergence
5. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Quality Management Plan
Threat
Constraint
Three-Point Estimate
6. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Deliverable
Risk Mitigation
Lead
Parametric Estimating
7. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Effort
Risk Register
Project Scope Statement
Earned Value Management
8. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Early Finish Date
Progressive Elaboration
Risk Category
Organizational Project Management Maturity
9. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Change Control System
Variance Analysis
Most Likely Duration
Deliverable
10. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Apportioned Effort
Organizational Breakdown Structure
Responsibility Assignment Matrix
Threat
11. A technique for determining the cause and degree of difference between the baseline and actual performance.
Critical Path Method
Finish-to-Start
Variance Analysis
S-Curve Analysis
12. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Late Start Date
Start-to-Finish
Decomposition
Organizational Breakdown Structure
13. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Risk Management Plan
Gantt Chart
Project
Schedule Performance Index
14. A technique used to shorten the schedule duration without reducing the project scope.
Secondary Risk
Schedule Compression
Change Control Board
Schedule Model Analysis
15. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Scope Baseline
Project Phase
Logical Relationship
What-If Sce
16. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Scope Management Plan
Schedule Performance Index
Project Life Cycle
Procurement Management Plan
17. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Start-to-Start
Program Management Office
Analogous Estimating
Free Float
18. A distinct - scheduled portion of work performed during the course of a project.
Schedule Management Plan
Activity
Lag
Lessons Learned
19. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Early Finish Date
Project Life Cycle
Schedule Baseline
Communication Management Plan
20. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Fast Tracking
Phase Gate
Preventive Action
Defect Repair
21. A hierarchical representation of risks that is organized according to risk categories.
Path Divergence
Performing Organization
Risk Breakdown Structure
Percent Complete
22. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Backward Pass
Requirement
Risk Breakdown Structure
Variance Analysis
23. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Free Float
Resource Calendar
Project Manager
Scope Baseline
24. A grid that links product requirements from their origin to the deliverables that satisfy them.
Lessons Learned
WBS Dictionary
Program Management Office
Requirements Traceability Matrix
25. An event or situation that indicates that a risk is about to occur.
Trigger Condition
Enterprise Environmental Factors
Sponsor
Free Float
26. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Project Management Office
Project Scope Statement
Path Divergence
To-Complete Performance Index
27. A significant point or event in a project - program - or portfolio.
Milestone
Project Phase
Resource Breakdown Structure
Scope Management Plan
28. A relationship in which a schedule activity has more than one predecessor.
Path Convergence
Project Management
Discrete Effort
Parametric Estimating
29. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Project
Critical Path Method
Level of Effort
Rolling Wave Planning
30. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Human Resource Plan
Schedule Variance
Phase Gate
Crashing
31. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Late Start Date
Late Finish Date
Acceptance Criteria
Schedule Performance Index
32. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Project Schedule
Actual Cost
Project Charter
Enterprise Environmental Factors
33. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Change Control Board
Organizational Project Management Maturity
Bottom-up Estimating
Cost Variance
34. A graphical representation of the logical relationships among the project schedule activities.
Project Manager
Project Schedule Network Diagram
Start-to-Start
Project Scope
35. The work performed to deliver a product - service - or result with the specified features and functions.
Project Schedule Network Diagram
Project Scope
Code of Accounts
Requirement
36. The expected cost to finish all the remaining project work.
Threat
Successor Activity
Estimate to Complete
Cost Performance Index
37. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Start-to-Start
Earned Value
Trigger Condition
Risk Transference
38. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Threat
Analogous Estimating
S-Curve Analysis
Critical Path
39. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Critical Chain Method
To-Complete Performance Index
Cost Management Plan
Risk Transference
40. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Schedule Performance Index
Cost Management Plan
Lessons Learned
Risk Category
41. A dependent activity that logically comes after another activity in a schedule.
Baseline
Trigger Condition
Successor Activity
Schedule Baseline
42. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Lead
Control Account
Schedule Model
Project Management Office
43. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Procurement Management Plan
Start-to-Start
Product Life Cycle
Change Control
44. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Acceptance Criteria
Project Manager
Scope Management Plan
Preventive Action
45. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Secondary Risk
Schedule Variance
Baseline
Resource Leveling
46. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Variance Analysis
Analogous Estimating
Portfolio
Actual Cost
47. The measure of work performed expressed in terms of the budget authorized for that work.
Opportunity
Program Management
Risk
Earned Value
48. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Budget at Completion
Fast Tracking
Scope Baseline
Gantt Chart
49. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Estimate to Complete
Cost Management Plan
Control Account
Schedule Variance
50. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Change Request
Gantt Chart
Assumption
Organizational Process Assets