SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A hierarchical representation of resources by category and type.
Risk Management Plan
Resource Breakdown Structure
Earned Value Management
Risk Avoidance
2. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Lag
Early Start Date
Performing Organization
Change Request
3. A calendar that identifies the working days and shifts upon which each specific resource is available.
Acceptance Criteria
Crashing
Project
Resource Calendar
4. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Project
Scope Management Plan
Cost Variance
Risk Mitigation
5. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Fast Tracking
Stakeholder
Risk
Schedule Performance Index
6. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Project Scope
Project Management Plan
Critical Chain Method
Risk Transference
7. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Backward Pass
Risk Breakdown Structure
Sponsor
Schedule Performance Index
8. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Stakeholder
Critical Chain Method
Defect Repair
Finish-to-Start
9. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Late Finish Date
Risk Register
Optimistic Duration
Analogous Estimating
10. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Schedule Baseline
Risk Mitigation
Apportioned Effort
Acceptance Criteria
11. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Level of Effort
Late Finish Date
Preventive Action
Total Float
12. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Analogous Estimating
Performing Organization
Parametric Estimating
Program Management Office
13. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Variance Analysis
Resource Breakdown Structure
Control Account
Schedule Management Plan
14. Any activity on the critical path in a project schedule.
Requirements Management Plan
Project Schedule
Critical Path Activity
Staffing Management Plan
15. A calendar that identifies working days and shifts that are available for scheduled activities.
Planned Value
Probability and Impact Matrix
Project Calendar
Procurement Management Plan
16. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Probability and Impact Matrix
Schedule Model Analysis
Schedule Model
Resource Calendar
17. A group of related schedule activities aggregated and displayed as a single activity.
Free Float
Portfolio Balancing
Summary Activity
Path Convergence
18. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Portfolio Balancing
Schedule Performance Index
Activity
Risk Management Plan
19. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Risk
Apportioned Effort
Lag
Estimate at Completion
20. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Enterprise Environmental Factors
Resource Calendar
Risk
S-Curve Analysis
21. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Critical Chain Method
Acceptance Criteria
Procurement Management Plan
Project Calendar
22. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Early Start Date
Earned Value Management
Responsibility Assignment Matrix
Project Manager
23. A set of conditions that is required to be met before deliverables are accepted.
Project Phase
Cost Variance
Acceptance Criteria
Finish-to-Start
24. A hierarchical representation of risks that is organized according to risk categories.
Risk Breakdown Structure
Staffing Management Plan
Opportunity
Human Resource Plan
25. The work performed to deliver a product - service - or result with the specified features and functions.
Cost Variance
Project Scope
Earned Value
Start-to-Start
26. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Risk Transference
Finish-to-Start
Requirements Management Plan
Late Start Date
27. The sum of all budgets established for the work to be performed.
Risk
Portfolio
Schedule Variance
Budget at Completion
28. The description of the project scope - major deliverables - assumptions - and constraints.
Schedule Variance
Resource Leveling
Precedence Diagramming Method
Project Scope Statement
29. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Scope Creep
Early Start Date
Risk Category
Program
30. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Program Management
Organizational Breakdown Structure
Actual Cost
Risk Avoidance
31. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Start-to-Start
Change Control
Rolling Wave Planning
Resource Leveling
32. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Code of Accounts
Late Finish Date
Variance at Completion
Risk Breakdown Structure
33. A point in time when the status of the project is recorded.
Free Float
Budget at Completion
Data Date
Phase Gate
34. A graphical representation of the logical relationships among the project schedule activities.
Lag
Secondary Risk
Project Schedule Network Diagram
Early Start Date
35. A risk that would have a positive effect on one or more project objectives.
Cost Performance Index
Opportunity
Logical Relationship
Risk Management Plan
36. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Cost Variance
Late Start Date
Schedule Model Analysis
Early Finish Date
37. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Responsibility Assignment Matrix
Risk Mitigation
Probability and Impact Matrix
Organizational Project Management Maturity
38. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Risk
Most Likely Duration
Constraint
Bottom-up Estimating
39. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Parametric Estimating
Quality Management Plan
Start-to-Finish
Lessons Learned
40. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Estimate to Complete
Communication Management Plan
Optimistic Duration
Total Float
41. A group of potential causes of risk.
Risk Category
Constraint
Data Date
Start-to-Finish
42. A risk that arises as a direct result of implementing a risk response.
Estimate at Completion
Secondary Risk
Responsibility Assignment Matrix
Parametric Estimating
43. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Schedule Model Analysis
Opportunity
Early Start Date
Critical Chain Method
44. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Cost Management Plan
Trigger Condition
Stakeholder
Critical Path
45. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Risk Management Plan
Start-to-Finish
Risk Transference
S-Curve Analysis
46. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Secondary Risk
Rolling Wave Planning
Crashing
Preventive Action
47. A temporary endeavor undertaken to create a unique product - service - or result.
Summary Activity
Project
Resource Breakdown Structure
Milestone
48. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Critical Path Method
Change Control System
Finish-to-Finish
Lead
49. The expected cost to finish all the remaining project work.
Risk
Responsibility Assignment Matrix
Estimate to Complete
Risk Mitigation
50. The realized cost incurred for the work performed on an activity during a specific time period.
Actual Cost
Precedence Diagramming Method
Project Schedule Network Diagram
Estimate at Completion