SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Project Manager
Project Management Office
Cost Performance Index
Portfolio
2. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Program Management Office
WBS Dictionary
Critical Chain Method
Parametric Estimating
3. A dependent activity that logically comes after another activity in a schedule.
Level of Effort
Quality Management Plan
Successor Activity
Portfolio
4. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Free Float
Control Account
Secondary Risk
Schedule Variance
5. A formal proposal to modify any document - deliverable - or baseline.
Phase Gate
Change Request
Program
Critical Path Method
6. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Scope Baseline
Project Charter
Schedule Baseline
Risk Register
7. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
S-Curve Analysis
Progressive Elaboration
Apportioned Effort
Schedule Compression
8. The description of the project scope - major deliverables - assumptions - and constraints.
Critical Chain Method
Early Start Date
Product Life Cycle
Project Scope Statement
9. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Earned Value Management
Schedule Variance
Progressive Elaboration
Organizational Breakdown Structure
10. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Risk Register
Risk Mitigation
Risk Acceptance
Cost Variance
11. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Control Account
Schedule Model Analysis
Change Control Board
Performing Organization
12. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Variance at Completion
Decision Tree Analysis
Risk Mitigation
Decomposition
13. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Organizational Project Management Maturity
Enterprise Environmental Factors
Risk
Project Schedule
14. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Successor Activity
Risk Management Plan
Schedule Performance Index
Enterprise Environmental Factors
15. A set of conditions that is required to be met before deliverables are accepted.
Critical Path
Acceptance Criteria
Risk Transference
Backward Pass
16. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Human Resource Plan
Portfolio
Schedule Compression
Most Likely Duration
17. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Schedule Model
Lessons Learned
Lag
WBS Dictionary
18. A dependency between two activities - or between an activity and a milestone.
Decomposition
Project Management Plan
Project Calendar
Logical Relationship
19. An event or situation that indicates that a risk is about to occur.
Trigger Condition
Milestone
Portfolio Management
Project Schedule Network Diagram
20. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Earned Value Management
Start-to-Finish
Portfolio Management
Cost Variance
21. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Data Date
Actual Cost
Budget at Completion
Crashing
22. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Corrective Action
Critical Chain Method
Resource Breakdown Structure
Program
23. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Portfolio Balancing
Planned Value
Pessimistic Duration
Portfolio Management
24. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Portfolio Balancing
Resource Calendar
Project Management Plan
Portfolio
25. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Cost Variance
Quality Management Plan
Pessimistic Duration
Project
26. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Risk Register
Schedule Model
Scope Baseline
Change Control
27. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Early Start Date
Summary Activity
Cost Performance Index
Rolling Wave Planning
28. A risk that would have a negative effect on one or more project objectives.
Acceptance Criteria
Project Manager
Threat
Data Date
29. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Pessimistic Duration
Lead
Risk Management Plan
Progressive Elaboration
30. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Human Resource Plan
Cost Management Plan
Progressive Elaboration
Organizational Process Assets
31. The authorized budget assigned to scheduled work.
Quality Management Plan
Planned Value
Critical Path Activity
Change Control
32. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Precedence Diagramming Method
Start-to-Start
Finish-to-Start
Discrete Effort
33. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Late Start Date
WBS Dictionary
Start-to-Start
Lessons Learned
34. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Deliverable
Threat
What-If Sce
Schedule Model Analysis
35. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Most Likely Duration
Critical Path
Project Management
Project Phase
36. The centralized management of one or more portfolios to achieve strategic objectives.
Portfolio Management
Finish-to-Start
Lag
Project Phase
37. Any activity on the critical path in a project schedule.
Variance Analysis
Project Manager
Risk Category
Critical Path Activity
38. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Effort
Project Management Plan
Organizational Breakdown Structure
Successor Activity
39. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Estimate at Completion
Project Manager
Start-to-Finish
Backward Pass
40. An activity that logically comes before a dependent activity in a schedule.
Project Scope Statement
Predecessor Activity
Level of Effort
Scope Creep
41. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Early Start Date
Risk Transference
Program Management
Crashing
42. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Risk Avoidance
Parametric Estimating
Resource Calendar
Project Management
43. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Early Start Date
Estimate at Completion
WBS Dictionary
Project Scope Statement
44. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Start-to-Start
Bottom-up Estimating
Project Management Office
Schedule Baseline
45. A calendar that identifies working days and shifts that are available for scheduled activities.
Resource Breakdown Structure
Risk
Portfolio Balancing
Project Calendar
46. A group of potential causes of risk.
Risk Category
Risk Mitigation
Risk Acceptance
Planned Value
47. The expected cost to finish all the remaining project work.
Estimate to Complete
Planned Value
Organizational Project Management Maturity
Code of Accounts
48. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Organizational Process Assets
Requirements Management Plan
Total Float
Organizational Project Management Maturity
49. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Analogous Estimating
Successor Activity
Schedule Model Analysis
Enterprise Environmental Factors
50. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Project Scope
Acceptance Criteria
Predecessor Activity
Critical Path Method