SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A formal proposal to modify any document - deliverable - or baseline.
Most Likely Duration
Change Request
Opportunity
Resource Calendar
2. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Apportioned Effort
Late Start Date
Discrete Effort
Schedule Variance
3. The authorized budget assigned to scheduled work.
Project Scope Statement
To-Complete Performance Index
Planned Value
Project Management
4. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Change Control Board
Portfolio Balancing
Opportunity
Summary Activity
5. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Risk Transference
Enterprise Environmental Factors
Project Phase
Schedule Variance
6. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Free Float
Percent Complete
Fast Tracking
Program
7. A technique for determining the cause and degree of difference between the baseline and actual performance.
Optimistic Duration
Cost Variance
Variance Analysis
Path Divergence
8. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Project Schedule
Schedule Model Analysis
Critical Path Method
Cost Management Plan
9. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Path Divergence
Portfolio Management
Lead
Scope Creep
10. A hierarchical representation of resources by category and type.
Optimistic Duration
Portfolio
Baseline
Resource Breakdown Structure
11. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Risk Transference
Predecessor Activity
To-Complete Performance Index
Bottom-up Estimating
12. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Variance Analysis
Data Date
Opportunity
Risk
13. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Sponsor
Variance at Completion
Cost Performance Index
Start-to-Start
14. A set of conditions that is required to be met before deliverables are accepted.
Acceptance Criteria
Project Schedule
Schedule Management Plan
Quality Management Plan
15. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Forward Pass
Baseline
Schedule Baseline
Acceptance Criteria
16. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Organizational Project Management Maturity
Corrective Action
Portfolio Management
Assumption
17. A technique used to shorten the schedule duration without reducing the project scope.
Responsibility Assignment Matrix
Decomposition
Logical Relationship
Schedule Compression
18. The measure of work performed expressed in terms of the budget authorized for that work.
Project Schedule Network Diagram
Pessimistic Duration
Enterprise Environmental Factors
Earned Value
19. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Lessons Learned
Gantt Chart
Resource Breakdown Structure
Project Management
20. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Schedule Management Plan
Discrete Effort
Quality Management Plan
Data Date
21. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Threat
Free Float
Portfolio
Assumption
22. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Cost Performance Index
WBS Dictionary
Rolling Wave Planning
Schedule Model Analysis
23. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Program Management Office
Cost Variance
Early Finish Date
Schedule Model
24. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Probability and Impact Matrix
Threat
What-If Sce
Resource Leveling
25. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Logical Relationship
Code of Accounts
Late Finish Date
Estimate at Completion
26. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Schedule Baseline
Schedule Performance Index
Risk Acceptance
Crashing
27. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Gantt Chart
Earned Value Management
Project Scope Statement
Project Life Cycle
28. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Risk Breakdown Structure
Performing Organization
Start-to-Start
Project Charter
29. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Crashing
Path Convergence
Risk Transference
Opportunity
30. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Project Scope Statement
Change Control System
Risk Mitigation
Portfolio Management
31. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Estimate at Completion
Human Resource Plan
Phase Gate
Fast Tracking
32. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Assumption
Change Request
Pessimistic Duration
Level of Effort
33. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Requirements Management Plan
Variance Analysis
Portfolio Management
Phase Gate
34. The realized cost incurred for the work performed on an activity during a specific time period.
Change Control System
Estimate at Completion
Actual Cost
Trigger Condition
35. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Progressive Elaboration
Human Resource Plan
Apportioned Effort
Earned Value
36. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Risk
Rolling Wave Planning
Schedule Baseline
Start-to-Start
37. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Parametric Estimating
Control Account
Risk Acceptance
Finish-to-Start
38. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Organizational Process Assets
Secondary Risk
Risk Mitigation
Risk Breakdown Structure
39. A significant point or event in a project - program - or portfolio.
To-Complete Performance Index
Activity
Early Start Date
Milestone
40. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Project Management
Enterprise Environmental Factors
Acceptance Criteria
Predecessor Activity
41. A distinct - scheduled portion of work performed during the course of a project.
Critical Chain Method
Activity
Start-to-Finish
Program Management Office
42. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Enterprise Environmental Factors
Acceptance Criteria
Late Finish Date
Program
43. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Activity
Organizational Breakdown Structure
Late Finish Date
Project Calendar
44. A point in time when the status of the project is recorded.
Decision Tree Analysis
Critical Path
Data Date
Forward Pass
45. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Estimate at Completion
Risk Register
Schedule Performance Index
Performing Organization
46. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Requirements Traceability Matrix
Early Finish Date
Lessons Learned
Milestone
47. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Baseline
Critical Path
Opportunity
Defect Repair
48. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Code of Accounts
Responsibility Assignment Matrix
Effort
Organizational Project Management Maturity
49. A limiting factor that affects the execution of a project - program - portfolio - or process.
Risk Management Plan
Constraint
Change Request
Late Start Date
50. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Program
Project Scope Statement
Project Management
Predecessor Activity