SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A calendar that identifies the working days and shifts upon which each specific resource is available.
Schedule Compression
Backward Pass
Risk Register
Resource Calendar
2. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Rolling Wave Planning
Start-to-Start
S-Curve Analysis
Crashing
3. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Risk
S-Curve Analysis
Organizational Project Management Maturity
Schedule Baseline
4. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Level of Effort
Project Manager
Critical Path Activity
Gantt Chart
5. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
To-Complete Performance Index
Enterprise Environmental Factors
Project Schedule
Decision Tree Analysis
6. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Rolling Wave Planning
Preventive Action
Lessons Learned
Budget at Completion
7. A temporary endeavor undertaken to create a unique product - service - or result.
Path Divergence
Project
Program Management Office
Gantt Chart
8. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Variance at Completion
Requirements Traceability Matrix
Scope Management Plan
Gantt Chart
9. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Acceptance Criteria
What-If Sce
Baseline
Early Start Date
10. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Stakeholder
Project Management Office
Performing Organization
Change Control
11. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Program Management
Cost Variance
Project Scope
Critical Path
12. The realized cost incurred for the work performed on an activity during a specific time period.
Preventive Action
Actual Cost
Project Calendar
Start-to-Finish
13. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Schedule Baseline
Crashing
Schedule Variance
Risk
14. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Schedule Variance
Defect Repair
Planned Value
Program
15. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Risk Management Plan
Gantt Chart
Resource Leveling
Cost Variance
16. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Risk Acceptance
To-Complete Performance Index
Assumption
Scope Management Plan
17. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Project Scope
Change Control Board
Variance Analysis
WBS Dictionary
18. A formal proposal to modify any document - deliverable - or baseline.
Project Management
Stakeholder
Lag
Change Request
19. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Requirement
Forward Pass
Resource Breakdown Structure
Risk Avoidance
20. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Finish-to-Finish
Estimate at Completion
Project Manager
Portfolio
21. A hierarchical representation of resources by category and type.
Critical Chain Method
Estimate to Complete
Quality Management Plan
Resource Breakdown Structure
22. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Cost Performance Index
Procurement Management Plan
Risk Transference
Deliverable
23. An intentional activity to modify a nonconforming product or product component.
Organizational Project Management Maturity
Defect Repair
Deliverable
Gantt Chart
24. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
What-If Sce
Activity
Early Finish Date
Schedule Model Analysis
25. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Organizational Process Assets
Risk Transference
Project Scope Statement
Enterprise Environmental Factors
26. A significant point or event in a project - program - or portfolio.
Schedule Compression
Constraint
Start-to-Start
Milestone
27. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Percent Complete
Budget at Completion
Early Finish Date
Free Float
28. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Requirements Management Plan
Logical Relationship
Schedule Model Analysis
Project Management Plan
29. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Early Finish Date
Deliverable
Risk Avoidance
Total Float
30. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Assumption
S-Curve Analysis
Progressive Elaboration
Change Control Board
31. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Quality Management Plan
Project Management
Program
Project Calendar
32. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Finish-to-Finish
Fast Tracking
Project Schedule Network Diagram
Earned Value
33. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Activity
Lead
Risk Register
Earned Value Management
34. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Schedule Compression
Opportunity
Critical Path Method
Scope Baseline
35. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Finish-to-Finish
Control Account
Risk Management Plan
Requirements Traceability Matrix
36. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Schedule Performance Index
Scope Management Plan
Path Convergence
Optimistic Duration
37. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Activity
Project Management Office
To-Complete Performance Index
Earned Value
38. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Estimate to Complete
Finish-to-Start
Project Calendar
Probability and Impact Matrix
39. A technique for determining the cause and degree of difference between the baseline and actual performance.
Activity
Control Account
Variance Analysis
Project Life Cycle
40. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Change Control System
Pessimistic Duration
Portfolio
Predecessor Activity
41. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Project Management Office
Portfolio Balancing
Level of Effort
Enterprise Environmental Factors
42. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Program
Earned Value Management
Estimate at Completion
Start-to-Start
43. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Organizational Project Management Maturity
Critical Path Method
Schedule Model Analysis
Change Control System
44. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Assumption
Late Start Date
Defect Repair
Start-to-Finish
45. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Project Charter
What-If Sce
Baseline
Progressive Elaboration
46. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Pessimistic Duration
Organizational Process Assets
Threat
Variance Analysis
47. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Lead
Critical Path Activity
Decision Tree Analysis
Finish-to-Start
48. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Scope Management Plan
Procurement Management Plan
Logical Relationship
Rolling Wave Planning
49. A distinct - scheduled portion of work performed during the course of a project.
Activity
Project Management Plan
Late Finish Date
Scope Management Plan
50. A risk that arises as a direct result of implementing a risk response.
Early Finish Date
Organizational Process Assets
Secondary Risk
Project Manager