SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A hierarchical representation of risks that is organized according to risk categories.
Risk Breakdown Structure
Opportunity
Analogous Estimating
Schedule Model Analysis
2. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Start-to-Finish
Requirements Management Plan
Decomposition
Risk Transference
3. The realized cost incurred for the work performed on an activity during a specific time period.
Actual Cost
Portfolio
Optimistic Duration
Decomposition
4. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Successor Activity
What-If Sce
Requirement
Code of Accounts
5. A relationship in which a schedule activity has more than one successor.
Preventive Action
Secondary Risk
Path Divergence
Resource Calendar
6. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Late Start Date
Scope Creep
Product Life Cycle
Pessimistic Duration
7. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Sponsor
Project Schedule Network Diagram
Phase Gate
Path Convergence
8. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Schedule Management Plan
Variance Analysis
Risk Transference
Cost Management Plan
9. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Scope Baseline
Predecessor Activity
Risk Avoidance
Project Charter
10. A document in which the results of risk analysis and risk response planning are recorded.
Portfolio
Risk Register
Corrective Action
Responsibility Assignment Matrix
11. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Resource Leveling
Critical Path
Decision Tree Analysis
Scope Baseline
12. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Change Control System
Project Life Cycle
S-Curve Analysis
Optimistic Duration
13. A group of related schedule activities aggregated and displayed as a single activity.
Backward Pass
Summary Activity
Pessimistic Duration
Project Scope
14. The sum of all budgets established for the work to be performed.
Level of Effort
Project Management
Budget at Completion
Successor Activity
15. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Responsibility Assignment Matrix
Defect Repair
Enterprise Environmental Factors
Schedule Model Analysis
16. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Actual Cost
Phase Gate
Requirements Traceability Matrix
Code of Accounts
17. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Start-to-Start
Estimate at Completion
Threat
Procurement Management Plan
18. The document that describes how the project will be executed - monitored - and controlled.
Project Management Plan
Level of Effort
Resource Calendar
Lag
19. A risk that would have a negative effect on one or more project objectives.
Threat
Finish-to-Finish
Phase Gate
Risk Register
20. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Early Finish Date
What-If Sce
Change Control
Decomposition
21. An event or situation that indicates that a risk is about to occur.
Free Float
Discrete Effort
Analogous Estimating
Trigger Condition
22. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Start-to-Finish
Resource Calendar
What-If Sce
Project Manager
23. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Lessons Learned
Project Charter
Earned Value Management
Start-to-Finish
24. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Portfolio Balancing
Schedule Model
Stakeholder
Preventive Action
25. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Trigger Condition
Phase Gate
Risk Transference
Risk Register
26. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Procurement Management Plan
Stakeholder
Assumption
Analogous Estimating
27. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Percent Complete
Project Scope
Project Charter
Rolling Wave Planning
28. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Estimate to Complete
Baseline
Opportunity
Schedule Management Plan
29. A grid that shows the project resources assigned to each work package.
Summary Activity
Responsibility Assignment Matrix
Requirement
Communication Management Plan
30. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Estimate at Completion
Optimistic Duration
Decomposition
Scope Management Plan
31. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Risk Breakdown Structure
Organizational Breakdown Structure
Trigger Condition
Portfolio Balancing
32. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Risk Register
Lessons Learned
Schedule Model
Project Schedule
33. A set of conditions that is required to be met before deliverables are accepted.
Portfolio Balancing
Acceptance Criteria
Risk Breakdown Structure
Change Control Board
34. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Schedule Baseline
Start-to-Start
Variance at Completion
Cost Variance
35. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Baseline
Change Request
Quality Management Plan
Risk Breakdown Structure
36. A limiting factor that affects the execution of a project - program - portfolio - or process.
Constraint
Project Calendar
Assumption
Variance at Completion
37. A graphical representation of the logical relationships among the project schedule activities.
Probability and Impact Matrix
Change Control Board
Project Schedule Network Diagram
Path Divergence
38. The measure of work performed expressed in terms of the budget authorized for that work.
Project Management Office
Earned Value
Risk Mitigation
Critical Path
39. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Enterprise Environmental Factors
Requirements Management Plan
Control Account
Project Management Office
40. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
To-Complete Performance Index
Trigger Condition
Discrete Effort
Risk Management Plan
41. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Portfolio
Program Management
Human Resource Plan
Constraint
42. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Crashing
Cost Variance
Analogous Estimating
Project Scope Statement
43. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Early Finish Date
Risk Acceptance
Risk Transference
Portfolio
44. A technique used to shorten the schedule duration without reducing the project scope.
Critical Chain Method
Schedule Compression
Milestone
Estimate at Completion
45. The authorized budget assigned to scheduled work.
Portfolio
Risk Register
Planned Value
Communication Management Plan
46. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Resource Leveling
Threat
Risk Transference
Deliverable
47. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Defect Repair
Corrective Action
Three-Point Estimate
Optimistic Duration
48. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Threat
Critical Chain Method
Sponsor
Project Schedule Network Diagram
49. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Lessons Learned
Precedence Diagramming Method
Forward Pass
Bottom-up Estimating
50. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Project Phase
Resource Calendar
Late Start Date
Defect Repair