SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Critical Path Activity
Requirement
Schedule Model Analysis
Project Charter
2. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Risk Management Plan
Risk Acceptance
Decomposition
Preventive Action
3. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Acceptance Criteria
To-Complete Performance Index
Optimistic Duration
Project
4. A hierarchical representation of risks that is organized according to risk categories.
Schedule Baseline
Control Account
Assumption
Risk Breakdown Structure
5. A relationship in which a schedule activity has more than one predecessor.
Change Control
WBS Dictionary
Path Convergence
Estimate to Complete
6. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Earned Value
Schedule Variance
Decision Tree Analysis
What-If Sce
7. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
S-Curve Analysis
Risk Acceptance
Variance at Completion
Schedule Management Plan
8. Any activity on the critical path in a project schedule.
Critical Path Activity
Progressive Elaboration
WBS Dictionary
Resource Calendar
9. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Project Schedule
Critical Path Activity
Estimate at Completion
WBS Dictionary
10. The series of phases that a project passes through from its initiation to its closure.
Opportunity
Portfolio Management
Preventive Action
Project Life Cycle
11. A graphical representation of the logical relationships among the project schedule activities.
Estimate at Completion
Project Schedule Network Diagram
Apportioned Effort
Gantt Chart
12. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Start-to-Start
Scope Creep
Cost Management Plan
Lead
13. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Gantt Chart
Lag
Human Resource Plan
Program
14. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Quality Management Plan
Decision Tree Analysis
Critical Path Activity
Change Control System
15. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Staffing Management Plan
Opportunity
Project Management
Project Life Cycle
16. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Start-to-Finish
Baseline
Earned Value
Earned Value Management
17. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Schedule Compression
Percent Complete
Free Float
Predecessor Activity
18. A set of conditions that is required to be met before deliverables are accepted.
Control Account
Program
Percent Complete
Acceptance Criteria
19. A grid that links product requirements from their origin to the deliverables that satisfy them.
Requirements Traceability Matrix
Program
Total Float
Bottom-up Estimating
20. A group of related schedule activities aggregated and displayed as a single activity.
Project Schedule Network Diagram
Critical Path Method
Percent Complete
Summary Activity
21. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Effort
Requirements Traceability Matrix
Human Resource Plan
Deliverable
22. A risk that would have a negative effect on one or more project objectives.
Analogous Estimating
Milestone
S-Curve Analysis
Threat
23. The authorized budget assigned to scheduled work.
Scope Creep
Change Control
Planned Value
Precedence Diagramming Method
24. A distinct - scheduled portion of work performed during the course of a project.
Requirements Traceability Matrix
Gantt Chart
Activity
Portfolio
25. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Project Management Office
Change Control System
Risk Register
Critical Path Activity
26. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Schedule Management Plan
Portfolio
Quality Management Plan
Summary Activity
27. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Project Schedule Network Diagram
Baseline
Apportioned Effort
Optimistic Duration
28. A dependent activity that logically comes after another activity in a schedule.
Successor Activity
Requirement
Bottom-up Estimating
Scope Management Plan
29. A point in time when the status of the project is recorded.
Level of Effort
Responsibility Assignment Matrix
Data Date
Parametric Estimating
30. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Project Manager
Schedule Model
Earned Value
Early Start Date
31. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Portfolio Balancing
Schedule Model
Organizational Process Assets
Crashing
32. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Communication Management Plan
Project Schedule
Analogous Estimating
Defect Repair
33. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Free Float
Estimate at Completion
Earned Value Management
Crashing
34. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Late Start Date
Decision Tree Analysis
Project Charter
Earned Value
35. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Variance Analysis
Scope Creep
Start-to-Finish
Backward Pass
36. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Risk Avoidance
Schedule Model
Variance Analysis
Schedule Compression
37. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Start-to-Finish
Variance at Completion
Cost Management Plan
Human Resource Plan
38. A relationship in which a schedule activity has more than one successor.
Sponsor
Path Divergence
Pessimistic Duration
Schedule Model
39. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Program
Three-Point Estimate
Requirements Management Plan
Portfolio Balancing
40. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Discrete Effort
Risk Avoidance
Change Request
WBS Dictionary
41. A formal proposal to modify any document - deliverable - or baseline.
Lag
Communication Management Plan
Change Request
Change Control
42. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Secondary Risk
Critical Path Activity
Three-Point Estimate
Schedule Variance
43. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Decision Tree Analysis
Corrective Action
Critical Path Method
Change Request
44. The sum of all budgets established for the work to be performed.
Finish-to-Finish
Budget at Completion
Risk Category
Risk Avoidance
45. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
To-Complete Performance Index
Performing Organization
Variance at Completion
Risk
46. The centralized management of one or more portfolios to achieve strategic objectives.
Human Resource Plan
To-Complete Performance Index
Portfolio Management
Predecessor Activity
47. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Most Likely Duration
Gantt Chart
Risk Mitigation
Schedule Variance
48. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Schedule Performance Index
Organizational Project Management Maturity
Risk Breakdown Structure
Constraint
49. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Requirements Traceability Matrix
Requirement
Organizational Project Management Maturity
Probability and Impact Matrix
50. A temporary endeavor undertaken to create a unique product - service - or result.
Code of Accounts
Change Control System
Assumption
Project