SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
WBS Dictionary
Critical Path Activity
Lessons Learned
Estimate at Completion
2. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Lessons Learned
Organizational Project Management Maturity
Forward Pass
Estimate to Complete
3. A technique for determining the cause and degree of difference between the baseline and actual performance.
Bottom-up Estimating
Planned Value
Free Float
Variance Analysis
4. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Corrective Action
Risk Mitigation
Project Phase
Crashing
5. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Change Control Board
Cost Variance
Lead
Program Management Office
6. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Assumption
Data Date
Path Convergence
Product Life Cycle
7. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Performing Organization
Deliverable
Organizational Breakdown Structure
Risk Register
8. A hierarchical representation of resources by category and type.
Project Phase
Change Control Board
Late Start Date
Resource Breakdown Structure
9. A numbering system used to uniquely identify each component of the work breakdown structure.
Risk Breakdown Structure
Organizational Process Assets
Data Date
Code of Accounts
10. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Resource Breakdown Structure
Logical Relationship
Project Schedule
Analogous Estimating
11. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Sponsor
WBS Dictionary
Program
Risk Acceptance
12. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
To-Complete Performance Index
Risk Register
Program Management Office
Finish-to-Finish
13. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Fast Tracking
Code of Accounts
Critical Path Method
Activity
14. The document that describes how the project will be executed - monitored - and controlled.
Project Management Plan
Critical Chain Method
Pessimistic Duration
Rolling Wave Planning
15. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Secondary Risk
Organizational Project Management Maturity
Cost Variance
Program
16. A group of potential causes of risk.
Successor Activity
Change Control System
Acceptance Criteria
Risk Category
17. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Risk Transference
Three-Point Estimate
Project Manager
Most Likely Duration
18. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Critical Path Method
Control Account
Quality Management Plan
Parametric Estimating
19. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Probability and Impact Matrix
Organizational Project Management Maturity
Control Account
Organizational Breakdown Structure
20. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Organizational Project Management Maturity
Risk Avoidance
Precedence Diagramming Method
Pessimistic Duration
21. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Performing Organization
Forward Pass
Organizational Process Assets
Requirements Traceability Matrix
22. A group of related schedule activities aggregated and displayed as a single activity.
Summary Activity
Cost Variance
Organizational Process Assets
Risk Transference
23. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Schedule Model Analysis
Fast Tracking
Risk Mitigation
Assumption
24. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Earned Value Management
Performing Organization
Lessons Learned
Preventive Action
25. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Decision Tree Analysis
Risk Avoidance
Baseline
Logical Relationship
26. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Path Convergence
Schedule Management Plan
Start-to-Finish
Trigger Condition
27. An intentional activity that realigns the performance of the project work with the project management plan.
Corrective Action
Forward Pass
Program
Control Account
28. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Human Resource Plan
Portfolio Balancing
Stakeholder
Corrective Action
29. The sum of all budgets established for the work to be performed.
Analogous Estimating
Risk
Budget at Completion
Risk Acceptance
30. The measure of work performed expressed in terms of the budget authorized for that work.
Project
Deliverable
Budget at Completion
Earned Value
31. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Requirements Traceability Matrix
Change Control
Percent Complete
Scope Creep
32. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Early Finish Date
Lessons Learned
Staffing Management Plan
Project Management Plan
33. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Three-Point Estimate
Finish-to-Start
Risk Mitigation
Portfolio Balancing
34. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Lessons Learned
Decomposition
Planned Value
Late Start Date
35. The centralized management of one or more portfolios to achieve strategic objectives.
Estimate to Complete
Estimate at Completion
Portfolio Management
Enterprise Environmental Factors
36. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Risk Management Plan
Product Life Cycle
Effort
Baseline
37. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Level of Effort
Corrective Action
Project Manager
Schedule Compression
38. A distinct - scheduled portion of work performed during the course of a project.
Procurement Management Plan
Analogous Estimating
Activity
Program
39. The work performed to deliver a product - service - or result with the specified features and functions.
Predecessor Activity
Project Scope
Project Calendar
Early Finish Date
40. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Risk
Project Phase
Trigger Condition
Late Finish Date
41. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Risk Mitigation
Crashing
Early Finish Date
Sponsor
42. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Discrete Effort
Forward Pass
Summary Activity
What-If Sce
43. A grid that links product requirements from their origin to the deliverables that satisfy them.
Product Life Cycle
Variance at Completion
Requirements Traceability Matrix
Effort
44. A hierarchical representation of risks that is organized according to risk categories.
Optimistic Duration
Risk Breakdown Structure
Cost Performance Index
Lead
45. A risk that would have a negative effect on one or more project objectives.
Schedule Baseline
Threat
Project Calendar
Requirement
46. A calendar that identifies the working days and shifts upon which each specific resource is available.
Planned Value
Risk Acceptance
Project Charter
Resource Calendar
47. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Project Schedule Network Diagram
Preventive Action
Start-to-Start
Progressive Elaboration
48. A significant point or event in a project - program - or portfolio.
Milestone
Stakeholder
Crashing
Baseline
49. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Parametric Estimating
Early Start Date
Risk Mitigation
Project Schedule
50. A technique used to shorten the schedule duration without reducing the project scope.
Responsibility Assignment Matrix
Schedule Compression
Cost Performance Index
Risk Mitigation