SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Corrective Action
Organizational Process Assets
Preventive Action
Risk
2. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Organizational Project Management Maturity
Project Schedule Network Diagram
Organizational Process Assets
Crashing
3. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Portfolio Balancing
Forward Pass
Discrete Effort
Backward Pass
4. A group of related schedule activities aggregated and displayed as a single activity.
Schedule Model
Summary Activity
Predecessor Activity
Successor Activity
5. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Change Request
Variance at Completion
WBS Dictionary
Procurement Management Plan
6. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Critical Path Method
Schedule Model
Variance at Completion
Project
7. A risk that would have a negative effect on one or more project objectives.
Finish-to-Finish
Threat
Portfolio Balancing
Project Charter
8. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Discrete Effort
Cost Management Plan
Code of Accounts
Resource Leveling
9. A distinct - scheduled portion of work performed during the course of a project.
Early Start Date
Activity
Trigger Condition
Estimate to Complete
10. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Critical Chain Method
Risk Management Plan
Requirements Management Plan
Pessimistic Duration
11. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Risk
Stakeholder
Sponsor
Portfolio
12. A relationship in which a schedule activity has more than one successor.
Performing Organization
Early Finish Date
Percent Complete
Path Divergence
13. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Staffing Management Plan
Forward Pass
Risk Register
Effort
14. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Scope Creep
Baseline
Three-Point Estimate
Fast Tracking
15. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Performing Organization
Crashing
Schedule Performance Index
Level of Effort
16. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Procurement Management Plan
Milestone
Scope Baseline
Critical Chain Method
17. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Project Schedule
Finish-to-Finish
WBS Dictionary
Most Likely Duration
18. A technique used to shorten the schedule duration without reducing the project scope.
Schedule Compression
Lessons Learned
Project Management Plan
Organizational Project Management Maturity
19. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Preventive Action
Communication Management Plan
Forward Pass
Project Calendar
20. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Parametric Estimating
Project Schedule Network Diagram
Schedule Baseline
Late Finish Date
21. A dependency between two activities - or between an activity and a milestone.
Start-to-Finish
Predecessor Activity
Forward Pass
Logical Relationship
22. The realized cost incurred for the work performed on an activity during a specific time period.
Critical Path Method
Finish-to-Finish
Actual Cost
Optimistic Duration
23. A numbering system used to uniquely identify each component of the work breakdown structure.
Program Management
Probability and Impact Matrix
Optimistic Duration
Code of Accounts
24. The sum of all budgets established for the work to be performed.
Risk Category
Budget at Completion
Schedule Variance
Variance at Completion
25. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Total Float
Project Manager
Lag
Risk Category
26. A hierarchical representation of risks that is organized according to risk categories.
Optimistic Duration
Lag
Earned Value Management
Risk Breakdown Structure
27. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Discrete Effort
WBS Dictionary
Analogous Estimating
Corrective Action
28. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Forward Pass
Backward Pass
Progressive Elaboration
Decomposition
29. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Risk Breakdown Structure
Budget at Completion
Resource Leveling
Cost Variance
30. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Communication Management Plan
Threat
Early Finish Date
Data Date
31. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Earned Value
Critical Path
Predecessor Activity
Project Life Cycle
32. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Project Charter
Finish-to-Finish
Lag
Cost Management Plan
33. A calendar that identifies the working days and shifts upon which each specific resource is available.
Resource Calendar
Late Start Date
Organizational Project Management Maturity
Communication Management Plan
34. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Effort
Schedule Management Plan
Program Management Office
Lead
35. A calendar that identifies working days and shifts that are available for scheduled activities.
Project Management Office
Project Calendar
Program
Precedence Diagramming Method
36. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
What-If Sce
Performing Organization
Staffing Management Plan
Resource Calendar
37. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Critical Path Activity
Schedule Model Analysis
Milestone
Schedule Variance
38. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Opportunity
Risk Register
Free Float
Program
39. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Stakeholder
Forward Pass
Risk Transference
S-Curve Analysis
40. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Change Request
Product Life Cycle
Program Management
Lead
41. A group of potential causes of risk.
Change Request
Risk Category
Resource Breakdown Structure
Parametric Estimating
42. A limiting factor that affects the execution of a project - program - portfolio - or process.
Cost Performance Index
Constraint
Risk Category
Gantt Chart
43. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Human Resource Plan
Estimate to Complete
Percent Complete
Portfolio
44. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Risk Mitigation
Schedule Management Plan
Cost Performance Index
Predecessor Activity
45. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Optimistic Duration
Project Phase
Organizational Process Assets
Portfolio Balancing
46. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Planned Value
Project Calendar
Cost Performance Index
Project Management Office
47. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Activity
Lead
Change Control Board
Critical Chain Method
48. A dependent activity that logically comes after another activity in a schedule.
Precedence Diagramming Method
Predecessor Activity
Requirements Traceability Matrix
Successor Activity
49. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Portfolio
Critical Path
S-Curve Analysis
Scope Management Plan
50. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Critical Path Method
Requirements Traceability Matrix
Optimistic Duration
Program Management