SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Data Date
Requirement
Performing Organization
Human Resource Plan
2. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Parametric Estimating
Baseline
Schedule Baseline
Project Charter
3. The expected cost to finish all the remaining project work.
Late Start Date
Estimate to Complete
Rolling Wave Planning
Pessimistic Duration
4. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Resource Breakdown Structure
Program
Secondary Risk
Lead
5. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Performing Organization
Fast Tracking
Change Control
Rolling Wave Planning
6. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Precedence Diagramming Method
Stakeholder
Human Resource Plan
Project Management Office
7. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Start-to-Start
Actual Cost
Threat
Project Charter
8. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Start-to-Finish
Resource Leveling
Communication Management Plan
Predecessor Activity
9. A hierarchical representation of resources by category and type.
Program
Budget at Completion
Schedule Management Plan
Resource Breakdown Structure
10. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Percent Complete
Baseline
Assumption
Analogous Estimating
11. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Variance Analysis
Risk
Baseline
Data Date
12. A relationship in which a schedule activity has more than one predecessor.
Project Manager
Path Convergence
Schedule Model
Project Management Office
13. A dependency between two activities - or between an activity and a milestone.
Start-to-Start
Code of Accounts
Project Life Cycle
Logical Relationship
14. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Threat
Fast Tracking
Requirement
Early Start Date
15. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Finish-to-Finish
Variance at Completion
Critical Path Activity
Data Date
16. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Requirement
Resource Leveling
Three-Point Estimate
Enterprise Environmental Factors
17. A risk that would have a positive effect on one or more project objectives.
Lag
Schedule Compression
Opportunity
Scope Baseline
18. A temporary endeavor undertaken to create a unique product - service - or result.
Project
Defect Repair
Critical Path Method
Actual Cost
19. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Finish-to-Finish
Product Life Cycle
Project Manager
Early Start Date
20. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Free Float
Lag
Activity
Project Schedule Network Diagram
21. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Preventive Action
Project Charter
Change Control System
Cost Management Plan
22. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Trigger Condition
Estimate at Completion
Sponsor
Decision Tree Analysis
23. An intentional activity that realigns the performance of the project work with the project management plan.
Corrective Action
Discrete Effort
Crashing
Risk Breakdown Structure
24. A grid that shows the project resources assigned to each work package.
Program Management Office
Risk Transference
Responsibility Assignment Matrix
Most Likely Duration
25. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Planned Value
Deliverable
Rolling Wave Planning
Early Finish Date
26. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Project Phase
Risk Avoidance
Change Control System
Scope Creep
27. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Risk Mitigation
Actual Cost
Critical Chain Method
Parametric Estimating
28. The work performed to deliver a product - service - or result with the specified features and functions.
WBS Dictionary
Backward Pass
Project Scope
Forward Pass
29. A numbering system used to uniquely identify each component of the work breakdown structure.
Estimate at Completion
Risk
Logical Relationship
Code of Accounts
30. A relationship in which a schedule activity has more than one successor.
Path Divergence
Project Schedule
Successor Activity
Risk Category
31. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Progressive Elaboration
Summary Activity
Trigger Condition
Risk Transference
32. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Cost Performance Index
Deliverable
Early Finish Date
Risk Mitigation
33. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Enterprise Environmental Factors
Cost Performance Index
Crashing
Schedule Model
34. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Optimistic Duration
Threat
Crashing
Risk Register
35. The document that describes how the project will be executed - monitored - and controlled.
Requirement
Apportioned Effort
Project Management Plan
Cost Management Plan
36. A group of potential causes of risk.
Optimistic Duration
Parametric Estimating
Risk Category
Planned Value
37. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Discrete Effort
Risk Acceptance
Fast Tracking
Human Resource Plan
38. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Corrective Action
Stakeholder
Finish-to-Finish
Logical Relationship
39. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Estimate to Complete
Risk Management Plan
Finish-to-Start
Project Management Office
40. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Path Divergence
Acceptance Criteria
Schedule Baseline
Earned Value Management
41. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Summary Activity
Project Management
Effort
Lag
42. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Project Manager
Start-to-Start
Preventive Action
Risk Avoidance
43. The realized cost incurred for the work performed on an activity during a specific time period.
Decomposition
Control Account
Backward Pass
Actual Cost
44. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Portfolio
Sponsor
Decision Tree Analysis
Bottom-up Estimating
45. A formal proposal to modify any document - deliverable - or baseline.
Fast Tracking
Change Request
Baseline
Requirement
46. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Risk Register
Successor Activity
Variance at Completion
Risk
47. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Program Management
Phase Gate
Critical Path Method
Schedule Model
48. A significant point or event in a project - program - or portfolio.
Activity
Milestone
Earned Value
Scope Baseline
49. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Variance at Completion
Schedule Model Analysis
Portfolio Management
Late Finish Date
50. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Start-to-Start
Program Management Office
Project Life Cycle
Constraint