SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Risk Breakdown Structure
Lead
Performing Organization
Project Management Office
2. A relationship in which a schedule activity has more than one successor.
Cost Performance Index
Path Divergence
Risk Mitigation
Requirements Traceability Matrix
3. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Product Life Cycle
Organizational Breakdown Structure
Variance Analysis
Schedule Compression
4. A technique for determining the cause and degree of difference between the baseline and actual performance.
Variance Analysis
Estimate at Completion
Scope Management Plan
Optimistic Duration
5. A hierarchical representation of risks that is organized according to risk categories.
Predecessor Activity
What-If Sce
Risk Breakdown Structure
Schedule Performance Index
6. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Assumption
Lessons Learned
Path Convergence
Resource Breakdown Structure
7. The expected cost to finish all the remaining project work.
Change Control
Free Float
S-Curve Analysis
Estimate to Complete
8. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Activity
Apportioned Effort
Portfolio
Estimate at Completion
9. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Scope Creep
Percent Complete
Lag
Planned Value
10. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Project Management Plan
WBS Dictionary
Cost Performance Index
Enterprise Environmental Factors
11. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Project Schedule Network Diagram
Project Management
Variance at Completion
Quality Management Plan
12. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Project Manager
Most Likely Duration
Risk Breakdown Structure
Analogous Estimating
13. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Stakeholder
Project Scope Statement
Schedule Model Analysis
Risk
14. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Schedule Variance
Most Likely Duration
Analogous Estimating
Program Management Office
15. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Backward Pass
Activity
Project Manager
Human Resource Plan
16. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Responsibility Assignment Matrix
Requirements Management Plan
Risk Avoidance
Schedule Performance Index
17. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Planned Value
Project Phase
Resource Calendar
Activity
18. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Fast Tracking
Logical Relationship
Critical Path
Schedule Baseline
19. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Effort
Risk Acceptance
Early Start Date
Project Management
20. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Project Life Cycle
Estimate to Complete
Precedence Diagramming Method
Program
21. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Earned Value Management
Lead
Estimate at Completion
Staffing Management Plan
22. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Risk
Rolling Wave Planning
Pessimistic Duration
Procurement Management Plan
23. A numbering system used to uniquely identify each component of the work breakdown structure.
Data Date
Code of Accounts
Project
Discrete Effort
24. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Schedule Variance
Organizational Process Assets
Risk Transference
Program Management Office
25. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Fast Tracking
Project Charter
Change Request
Responsibility Assignment Matrix
26. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Scope Baseline
Critical Path
Communication Management Plan
Progressive Elaboration
27. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Level of Effort
Probability and Impact Matrix
Schedule Model Analysis
To-Complete Performance Index
28. A document in which the results of risk analysis and risk response planning are recorded.
Risk Register
Risk Management Plan
Portfolio Management
Project Phase
29. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Three-Point Estimate
Cost Performance Index
Project Calendar
Deliverable
30. The series of phases that a project passes through from its initiation to its closure.
Pessimistic Duration
Project Life Cycle
Start-to-Start
Trigger Condition
31. A calendar that identifies working days and shifts that are available for scheduled activities.
Project
Quality Management Plan
Organizational Process Assets
Project Calendar
32. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Portfolio
Risk Transference
Discrete Effort
Successor Activity
33. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Cost Management Plan
Critical Path Method
Baseline
Optimistic Duration
34. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Lessons Learned
Cost Performance Index
WBS Dictionary
Human Resource Plan
35. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Change Request
WBS Dictionary
Opportunity
Schedule Baseline
36. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Variance at Completion
Staffing Management Plan
Schedule Model Analysis
Change Control Board
37. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Risk Avoidance
Lag
Probability and Impact Matrix
Finish-to-Finish
38. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Decision Tree Analysis
Planned Value
Staffing Management Plan
Risk Avoidance
39. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Lead
Schedule Variance
Quality Management Plan
Risk Register
40. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Apportioned Effort
What-If Sce
Procurement Management Plan
Lead
41. A dependency between two activities - or between an activity and a milestone.
Cost Performance Index
Logical Relationship
Project Manager
Late Start Date
42. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Change Control System
Project Phase
Pessimistic Duration
Phase Gate
43. A limiting factor that affects the execution of a project - program - portfolio - or process.
Constraint
Performing Organization
Milestone
S-Curve Analysis
44. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Rolling Wave Planning
Budget at Completion
Trigger Condition
Performing Organization
45. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Cost Management Plan
Resource Breakdown Structure
Organizational Project Management Maturity
Project Schedule
46. The document that describes how the project will be executed - monitored - and controlled.
Project Management Plan
Schedule Model
Rolling Wave Planning
Project Charter
47. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Communication Management Plan
Finish-to-Start
Data Date
S-Curve Analysis
48. A graphical representation of the logical relationships among the project schedule activities.
Budget at Completion
Project Schedule Network Diagram
Change Control Board
Critical Path
49. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Fast Tracking
Human Resource Plan
Discrete Effort
Critical Path
50. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Acceptance Criteria
Actual Cost
Code of Accounts
Most Likely Duration