SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Schedule Performance Index
Project Scope Statement
Earned Value
Critical Chain Method
2. A distinct - scheduled portion of work performed during the course of a project.
Schedule Model Analysis
Path Divergence
Activity
Risk Mitigation
3. A set of conditions that is required to be met before deliverables are accepted.
Organizational Breakdown Structure
Acceptance Criteria
Project Life Cycle
Organizational Process Assets
4. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Project Management
Sponsor
Risk
Organizational Process Assets
5. The realized cost incurred for the work performed on an activity during a specific time period.
Optimistic Duration
Scope Baseline
Control Account
Actual Cost
6. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Path Convergence
Progressive Elaboration
Early Start Date
Project Schedule
7. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Three-Point Estimate
Portfolio
Schedule Baseline
Budget at Completion
8. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Resource Calendar
Secondary Risk
Critical Path
Scope Management Plan
9. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Pessimistic Duration
Parametric Estimating
Discrete Effort
Defect Repair
10. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Portfolio
Baseline
Deliverable
Analogous Estimating
11. An intentional activity to modify a nonconforming product or product component.
Project
Critical Chain Method
Path Divergence
Defect Repair
12. A risk that would have a negative effect on one or more project objectives.
Estimate to Complete
Secondary Risk
Threat
Deliverable
13. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Defect Repair
Optimistic Duration
Procurement Management Plan
Project Schedule
14. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Rolling Wave Planning
Change Control System
Enterprise Environmental Factors
Optimistic Duration
15. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Path Convergence
Finish-to-Start
Product Life Cycle
Human Resource Plan
16. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Rolling Wave Planning
Gantt Chart
Change Request
Late Finish Date
17. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Change Request
Project Manager
Backward Pass
Risk Management Plan
18. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Optimistic Duration
Change Control System
Gantt Chart
Progressive Elaboration
19. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Risk
Data Date
Analogous Estimating
Lessons Learned
20. A limiting factor that affects the execution of a project - program - portfolio - or process.
Discrete Effort
Constraint
Start-to-Start
Total Float
21. The description of the project scope - major deliverables - assumptions - and constraints.
Schedule Model Analysis
Planned Value
Project Scope Statement
Project Calendar
22. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Earned Value Management
Schedule Baseline
Scope Baseline
Program Management Office
23. A calendar that identifies working days and shifts that are available for scheduled activities.
Cost Management Plan
Critical Chain Method
Project Calendar
Product Life Cycle
24. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Finish-to-Finish
Risk Management Plan
Performing Organization
Project Management Plan
25. A significant point or event in a project - program - or portfolio.
Project Management Office
Milestone
Requirement
Schedule Performance Index
26. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Bottom-up Estimating
WBS Dictionary
Earned Value
Change Control
27. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Risk Register
Apportioned Effort
Predecessor Activity
Effort
28. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Project Scope Statement
Project Management Office
Organizational Breakdown Structure
Procurement Management Plan
29. A calendar that identifies the working days and shifts upon which each specific resource is available.
Schedule Model Analysis
What-If Sce
Predecessor Activity
Resource Calendar
30. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Risk Acceptance
Backward Pass
Earned Value
Quality Management Plan
31. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Schedule Performance Index
Program Management Office
Project Calendar
Free Float
32. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Critical Path Method
Apportioned Effort
Quality Management Plan
Most Likely Duration
33. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Change Control
Parametric Estimating
Percent Complete
Lag
34. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Variance at Completion
Finish-to-Start
Project Manager
Budget at Completion
35. A hierarchical representation of risks that is organized according to risk categories.
Logical Relationship
Schedule Baseline
Phase Gate
Risk Breakdown Structure
36. A dependent activity that logically comes after another activity in a schedule.
Successor Activity
Apportioned Effort
Estimate to Complete
Risk Breakdown Structure
37. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Apportioned Effort
Sponsor
Schedule Management Plan
Schedule Model
38. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Actual Cost
Risk Mitigation
Path Divergence
Schedule Management Plan
39. The centralized management of one or more portfolios to achieve strategic objectives.
Portfolio Management
Estimate to Complete
Portfolio
Trigger Condition
40. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Change Control Board
Pessimistic Duration
Change Request
Fast Tracking
41. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Risk Register
Decomposition
Portfolio Balancing
Early Start Date
42. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Finish-to-Start
Enterprise Environmental Factors
Project Management Office
Variance Analysis
43. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Analogous Estimating
Resource Calendar
Communication Management Plan
Start-to-Finish
44. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Bottom-up Estimating
Budget at Completion
Lag
Level of Effort
45. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Requirements Management Plan
Assumption
Estimate at Completion
Responsibility Assignment Matrix
46. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Free Float
Baseline
Three-Point Estimate
Procurement Management Plan
47. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Late Start Date
Baseline
Percent Complete
Lessons Learned
48. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Percent Complete
Cost Variance
Decomposition
Risk Breakdown Structure
49. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Responsibility Assignment Matrix
Staffing Management Plan
WBS Dictionary
Requirement
50. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Fast Tracking
Risk Category
Lead
Control Account