SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A grid that links product requirements from their origin to the deliverables that satisfy them.
Requirements Traceability Matrix
Progressive Elaboration
Project Manager
Human Resource Plan
2. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Backward Pass
Critical Path Activity
Project Management Plan
Resource Leveling
3. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Apportioned Effort
Requirements Management Plan
Trigger Condition
Performing Organization
4. A group of related schedule activities aggregated and displayed as a single activity.
WBS Dictionary
Summary Activity
Quality Management Plan
Resource Calendar
5. A grid that shows the project resources assigned to each work package.
Project Schedule
Deliverable
Change Control Board
Responsibility Assignment Matrix
6. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Human Resource Plan
Early Finish Date
Procurement Management Plan
Lessons Learned
7. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Acceptance Criteria
Scope Management Plan
Three-Point Estimate
Parametric Estimating
8. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Program
Finish-to-Finish
What-If Sce
Crashing
9. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Organizational Process Assets
Cost Performance Index
Control Account
Project Manager
10. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Project Phase
Product Life Cycle
Performing Organization
Risk Transference
11. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Portfolio Management
Milestone
Project Management Office
Early Finish Date
12. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Baseline
Resource Leveling
Risk Management Plan
Milestone
13. A graphical representation of the logical relationships among the project schedule activities.
Project Schedule Network Diagram
Predecessor Activity
Successor Activity
Project Scope
14. A group of potential causes of risk.
Portfolio Management
To-Complete Performance Index
Human Resource Plan
Risk Category
15. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Procurement Management Plan
Secondary Risk
Program Management
Budget at Completion
16. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Baseline
Decomposition
Risk Breakdown Structure
Schedule Performance Index
17. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Project Phase
Optimistic Duration
Schedule Model Analysis
Enterprise Environmental Factors
18. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Rolling Wave Planning
Project Scope Statement
Change Control
Risk Register
19. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Project Management
Preventive Action
Late Start Date
Cost Performance Index
20. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Risk Mitigation
Successor Activity
Trigger Condition
Responsibility Assignment Matrix
21. The series of phases that a project passes through from its initiation to its closure.
Three-Point Estimate
Project Life Cycle
Corrective Action
Summary Activity
22. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Lag
Variance Analysis
Finish-to-Start
Communication Management Plan
23. A set of conditions that is required to be met before deliverables are accepted.
Acceptance Criteria
Schedule Model Analysis
Three-Point Estimate
Path Convergence
24. An event or situation that indicates that a risk is about to occur.
Most Likely Duration
Crashing
Trigger Condition
Resource Breakdown Structure
25. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Risk Management Plan
Path Divergence
Organizational Process Assets
Effort
26. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Critical Path Activity
Schedule Compression
Risk
Risk Mitigation
27. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Enterprise Environmental Factors
Actual Cost
Phase Gate
Lag
28. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Change Request
Decomposition
Project Scope
Schedule Variance
29. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Level of Effort
Early Finish Date
Late Finish Date
Change Request
30. The sum of all budgets established for the work to be performed.
Project Scope Statement
Budget at Completion
Project Management Plan
Successor Activity
31. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Baseline
Risk Register
Cost Variance
Path Convergence
32. A formal proposal to modify any document - deliverable - or baseline.
Project Management Office
Change Request
Path Convergence
Bottom-up Estimating
33. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Requirements Traceability Matrix
Total Float
Organizational Process Assets
Program Management Office
34. A numbering system used to uniquely identify each component of the work breakdown structure.
Preventive Action
Code of Accounts
Requirement
Baseline
35. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Logical Relationship
Three-Point Estimate
Bottom-up Estimating
Project Calendar
36. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Program Management
Procurement Management Plan
Performing Organization
Lead
37. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Risk Transference
Summary Activity
Project
Early Start Date
38. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Path Divergence
Schedule Management Plan
WBS Dictionary
Acceptance Criteria
39. A document in which the results of risk analysis and risk response planning are recorded.
Lag
Risk Register
Late Start Date
Start-to-Start
40. A relationship in which a schedule activity has more than one predecessor.
Preventive Action
Start-to-Start
Finish-to-Finish
Path Convergence
41. A technique used to shorten the schedule duration without reducing the project scope.
Preventive Action
Earned Value Management
Program Management
Schedule Compression
42. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Parametric Estimating
Performing Organization
S-Curve Analysis
Lead
43. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Project Management
Path Divergence
Actual Cost
Risk Avoidance
44. A distinct - scheduled portion of work performed during the course of a project.
S-Curve Analysis
Budget at Completion
Activity
Risk Breakdown Structure
45. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Start-to-Start
Control Account
Assumption
Project Management
46. A relationship in which a schedule activity has more than one successor.
Predecessor Activity
Risk Register
Late Start Date
Path Divergence
47. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Planned Value
Project Calendar
WBS Dictionary
Portfolio Balancing
48. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Cost Variance
Requirement
Risk Acceptance
Schedule Baseline
49. The realized cost incurred for the work performed on an activity during a specific time period.
Requirements Traceability Matrix
Project
Actual Cost
Crashing
50. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Total Float
Critical Path Activity
Critical Path Method
Start-to-Start