SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Acceptance Criteria
Resource Leveling
Project
Organizational Breakdown Structure
2. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Critical Path
Responsibility Assignment Matrix
Schedule Variance
Backward Pass
3. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Free Float
Late Finish Date
To-Complete Performance Index
Risk Management Plan
4. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Organizational Breakdown Structure
Scope Baseline
Cost Performance Index
WBS Dictionary
5. A relationship in which a schedule activity has more than one predecessor.
Decomposition
Path Convergence
Parametric Estimating
Critical Path
6. An activity that logically comes before a dependent activity in a schedule.
Predecessor Activity
Schedule Variance
Requirements Management Plan
Rolling Wave Planning
7. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Earned Value
Requirement
Change Control
Defect Repair
8. A group of potential causes of risk.
Product Life Cycle
Code of Accounts
Risk Category
Actual Cost
9. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Project Management Office
What-If Sce
Project Phase
Pessimistic Duration
10. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Schedule Management Plan
Most Likely Duration
Variance Analysis
Responsibility Assignment Matrix
11. A set of conditions that is required to be met before deliverables are accepted.
Acceptance Criteria
Program Management
Trigger Condition
Logical Relationship
12. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Cost Variance
Procurement Management Plan
Organizational Process Assets
Crashing
13. The sum of all budgets established for the work to be performed.
Late Finish Date
Budget at Completion
Scope Management Plan
Estimate to Complete
14. A risk that arises as a direct result of implementing a risk response.
Effort
Secondary Risk
Program Management Office
Assumption
15. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Scope Creep
Product Life Cycle
Progressive Elaboration
Portfolio
16. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Code of Accounts
Budget at Completion
Summary Activity
S-Curve Analysis
17. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Opportunity
Risk Acceptance
Actual Cost
Procurement Management Plan
18. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Risk Management Plan
Risk Category
S-Curve Analysis
Free Float
19. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Free Float
Start-to-Finish
Lead
Defect Repair
20. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Optimistic Duration
Cost Management Plan
Critical Chain Method
Project Management
21. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Project Schedule Network Diagram
Phase Gate
Variance Analysis
Schedule Variance
22. The document that describes how the project will be executed - monitored - and controlled.
Effort
Project Management Plan
Resource Breakdown Structure
Optimistic Duration
23. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Bottom-up Estimating
Late Start Date
Optimistic Duration
Communication Management Plan
24. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Scope Baseline
Lessons Learned
Quality Management Plan
Product Life Cycle
25. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Lessons Learned
Program
Project Schedule
Finish-to-Start
26. A numbering system used to uniquely identify each component of the work breakdown structure.
Scope Management Plan
Discrete Effort
Code of Accounts
Risk Acceptance
27. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Scope Creep
Most Likely Duration
Preventive Action
To-Complete Performance Index
28. A hierarchical representation of resources by category and type.
Portfolio
Opportunity
Resource Breakdown Structure
Risk Acceptance
29. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Variance at Completion
Rolling Wave Planning
Risk Mitigation
Progressive Elaboration
30. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Change Control
Bottom-up Estimating
Sponsor
Probability and Impact Matrix
31. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Requirements Management Plan
Bottom-up Estimating
Project Charter
Effort
32. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Early Start Date
Risk
Stakeholder
Change Control System
33. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Finish-to-Start
Scope Management Plan
Precedence Diagramming Method
Communication Management Plan
34. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Product Life Cycle
Project Charter
Decomposition
Staffing Management Plan
35. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Portfolio
Variance Analysis
Finish-to-Start
Program Management
36. The realized cost incurred for the work performed on an activity during a specific time period.
Bottom-up Estimating
Actual Cost
Lessons Learned
Data Date
37. A dependent activity that logically comes after another activity in a schedule.
Project Management Plan
Requirements Management Plan
What-If Sce
Successor Activity
38. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Quality Management Plan
Start-to-Start
Control Account
Acceptance Criteria
39. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Backward Pass
Requirements Management Plan
WBS Dictionary
Estimate to Complete
40. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Scope Creep
Schedule Performance Index
Early Finish Date
Secondary Risk
41. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Apportioned Effort
Risk Mitigation
Project Schedule
Project Charter
42. The measure of work performed expressed in terms of the budget authorized for that work.
Analogous Estimating
Baseline
Earned Value
Constraint
43. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Risk Register
Bottom-up Estimating
Parametric Estimating
Variance Analysis
44. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Backward Pass
Risk
Decomposition
Project Management Office
45. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Critical Path Method
Schedule Performance Index
Threat
Lag
46. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Path Convergence
Analogous Estimating
Project Phase
Organizational Project Management Maturity
47. A distinct - scheduled portion of work performed during the course of a project.
Activity
Cost Variance
Performing Organization
Portfolio Balancing
48. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Human Resource Plan
Project Scope
Change Control
Quality Management Plan
49. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Successor Activity
Decision Tree Analysis
Risk Register
Project Scope
50. A relationship in which a schedule activity has more than one successor.
Sponsor
Path Divergence
Schedule Performance Index
Optimistic Duration