SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A hierarchical representation of risks that is organized according to risk categories.
Performing Organization
Critical Path Method
Summary Activity
Risk Breakdown Structure
2. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Phase Gate
Communication Management Plan
Schedule Performance Index
Risk
3. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Program Management Office
Project Management
Bottom-up Estimating
Scope Baseline
4. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Discrete Effort
Late Finish Date
Critical Path Activity
Project Manager
5. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Data Date
Preventive Action
Requirement
Opportunity
6. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Data Date
Change Control Board
Portfolio Balancing
Project Calendar
7. A dependency between two activities - or between an activity and a milestone.
Program Management
Logical Relationship
Earned Value
Project Management Plan
8. The authorized budget assigned to scheduled work.
WBS Dictionary
Variance Analysis
Planned Value
Quality Management Plan
9. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Earned Value Management
Cost Performance Index
Lessons Learned
Schedule Compression
10. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Late Start Date
Estimate at Completion
Resource Leveling
Risk Avoidance
11. The description of the project scope - major deliverables - assumptions - and constraints.
Scope Baseline
Pessimistic Duration
Earned Value
Project Scope Statement
12. A limiting factor that affects the execution of a project - program - portfolio - or process.
Summary Activity
Activity
Constraint
Opportunity
13. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Fast Tracking
Start-to-Finish
Analogous Estimating
Risk Transference
14. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Summary Activity
Project Schedule
Organizational Process Assets
Schedule Variance
15. A formal proposal to modify any document - deliverable - or baseline.
Cost Performance Index
Successor Activity
Resource Breakdown Structure
Change Request
16. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Most Likely Duration
Schedule Variance
Human Resource Plan
Resource Calendar
17. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Gantt Chart
Path Divergence
Critical Path
Product Life Cycle
18. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
S-Curve Analysis
Probability and Impact Matrix
Late Start Date
Risk Transference
19. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Logical Relationship
Project Management Office
Project Schedule Network Diagram
To-Complete Performance Index
20. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Estimate at Completion
Project Charter
Probability and Impact Matrix
Schedule Baseline
21. A group of potential causes of risk.
Risk Category
Schedule Variance
Lag
Risk
22. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Budget at Completion
WBS Dictionary
Stakeholder
Requirements Management Plan
23. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Early Start Date
Estimate at Completion
Quality Management Plan
Decomposition
24. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Percent Complete
Critical Chain Method
Change Control
Fast Tracking
25. A hierarchical representation of resources by category and type.
Resource Breakdown Structure
Activity
Project Calendar
Program
26. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
S-Curve Analysis
Schedule Model Analysis
Organizational Project Management Maturity
What-If Sce
27. Any activity on the critical path in a project schedule.
Risk Register
Critical Path Activity
Change Control
Analogous Estimating
28. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Stakeholder
Performing Organization
Trigger Condition
Budget at Completion
29. A point in time when the status of the project is recorded.
Cost Performance Index
Schedule Baseline
Data Date
Risk Transference
30. The realized cost incurred for the work performed on an activity during a specific time period.
Project Manager
Actual Cost
Change Control
Communication Management Plan
31. A risk that arises as a direct result of implementing a risk response.
Project Schedule Network Diagram
Secondary Risk
Logical Relationship
Risk Transference
32. A relationship in which a schedule activity has more than one successor.
Project Schedule
Free Float
Portfolio Balancing
Path Divergence
33. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Early Start Date
Level of Effort
Risk Breakdown Structure
Program Management Office
34. A calendar that identifies working days and shifts that are available for scheduled activities.
Project Calendar
Milestone
Most Likely Duration
Actual Cost
35. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
To-Complete Performance Index
Performing Organization
Successor Activity
Estimate at Completion
36. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Project Phase
Estimate to Complete
Three-Point Estimate
Project Life Cycle
37. A dependent activity that logically comes after another activity in a schedule.
Successor Activity
Path Convergence
S-Curve Analysis
Decomposition
38. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Enterprise Environmental Factors
Total Float
Risk Avoidance
Program
39. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Resource Leveling
Change Control System
Total Float
Project Charter
40. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Activity
Portfolio
Effort
Cost Performance Index
41. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Organizational Process Assets
Estimate at Completion
Path Divergence
Constraint
42. A calendar that identifies the working days and shifts upon which each specific resource is available.
Change Request
Resource Calendar
Risk Breakdown Structure
Milestone
43. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Risk Avoidance
Project Management Office
Scope Management Plan
Parametric Estimating
44. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Analogous Estimating
Most Likely Duration
Path Divergence
Procurement Management Plan
45. A relationship in which a schedule activity has more than one predecessor.
Path Convergence
Discrete Effort
Logical Relationship
Project Scope Statement
46. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Start-to-Finish
Summary Activity
Risk Acceptance
Scope Creep
47. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Quality Management Plan
Path Convergence
Data Date
Discrete Effort
48. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Probability and Impact Matrix
Actual Cost
Bottom-up Estimating
Organizational Process Assets
49. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Estimate to Complete
Decision Tree Analysis
Cost Performance Index
Gantt Chart
50. The expected cost to finish all the remaining project work.
Estimate to Complete
Schedule Model
Critical Path
Schedule Performance Index