SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Project Management Plan
Project Calendar
Level of Effort
Performing Organization
2. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Organizational Project Management Maturity
Risk Register
Control Account
Total Float
3. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Trigger Condition
Late Start Date
Crashing
Gantt Chart
4. Any activity on the critical path in a project schedule.
Enterprise Environmental Factors
Variance Analysis
Data Date
Critical Path Activity
5. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Cost Variance
Decomposition
Optimistic Duration
Communication Management Plan
6. A risk that would have a negative effect on one or more project objectives.
Free Float
Enterprise Environmental Factors
Threat
Start-to-Start
7. A temporary endeavor undertaken to create a unique product - service - or result.
Project Scope Statement
Preventive Action
Crashing
Project
8. A technique used to shorten the schedule duration without reducing the project scope.
Resource Leveling
Schedule Compression
Project Management Office
Stakeholder
9. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Product Life Cycle
Responsibility Assignment Matrix
Project Schedule Network Diagram
Cost Variance
10. A relationship in which a schedule activity has more than one predecessor.
Path Divergence
Path Convergence
Successor Activity
Discrete Effort
11. A set of conditions that is required to be met before deliverables are accepted.
Staffing Management Plan
Acceptance Criteria
Project Management
Cost Variance
12. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Requirements Management Plan
Portfolio Management
Risk Category
Backward Pass
13. A dependent activity that logically comes after another activity in a schedule.
Discrete Effort
Successor Activity
Scope Creep
Finish-to-Start
14. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Estimate to Complete
Organizational Breakdown Structure
Risk Register
Lessons Learned
15. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Project Management Office
Staffing Management Plan
Human Resource Plan
Critical Chain Method
16. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Cost Management Plan
Resource Leveling
Change Control System
Project Schedule
17. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Scope Baseline
Change Control Board
Project Life Cycle
Resource Breakdown Structure
18. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
What-If Sce
Change Request
Quality Management Plan
Budget at Completion
19. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
S-Curve Analysis
Portfolio Balancing
Responsibility Assignment Matrix
Control Account
20. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Percent Complete
Project Management
Procurement Management Plan
Change Request
21. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Portfolio
Risk Breakdown Structure
Preventive Action
Crashing
22. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Project Management
Critical Path
Organizational Project Management Maturity
Performing Organization
23. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Critical Chain Method
Risk Acceptance
Lead
Pessimistic Duration
24. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Portfolio Balancing
What-If Sce
Estimate at Completion
Organizational Project Management Maturity
25. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Cost Management Plan
Schedule Variance
Summary Activity
Resource Calendar
26. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Rolling Wave Planning
Risk Avoidance
Enterprise Environmental Factors
Milestone
27. An activity that logically comes before a dependent activity in a schedule.
Budget at Completion
Predecessor Activity
Crashing
Project Life Cycle
28. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Lessons Learned
Three-Point Estimate
Project Schedule Network Diagram
Organizational Breakdown Structure
29. An intentional activity that realigns the performance of the project work with the project management plan.
Corrective Action
Preventive Action
Requirements Management Plan
Lessons Learned
30. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Secondary Risk
Finish-to-Start
Resource Calendar
Apportioned Effort
31. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Earned Value
Program Management
Responsibility Assignment Matrix
Predecessor Activity
32. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
To-Complete Performance Index
Scope Management Plan
Lessons Learned
Project Management
33. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Acceptance Criteria
Finish-to-Finish
Precedence Diagramming Method
WBS Dictionary
34. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Early Start Date
S-Curve Analysis
Three-Point Estimate
Schedule Model
35. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Risk
Program Management
Level of Effort
Change Control System
36. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
To-Complete Performance Index
Enterprise Environmental Factors
Critical Path Activity
Three-Point Estimate
37. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Risk Register
Path Divergence
Progressive Elaboration
Discrete Effort
38. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Schedule Model Analysis
Baseline
Critical Path
Cost Management Plan
39. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Free Float
Risk Mitigation
Earned Value
To-Complete Performance Index
40. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Estimate at Completion
Risk
Change Request
Variance Analysis
41. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Critical Path
Three-Point Estimate
Risk Management Plan
Project Management Office
42. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
To-Complete Performance Index
Risk Mitigation
What-If Sce
Control Account
43. An intentional activity to modify a nonconforming product or product component.
Schedule Baseline
Staffing Management Plan
Defect Repair
Change Control Board
44. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Project Calendar
Predecessor Activity
Critical Path Method
Variance at Completion
45. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Trigger Condition
Analogous Estimating
Late Finish Date
Apportioned Effort
46. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Backward Pass
WBS Dictionary
Project
Requirements Management Plan
47. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Probability and Impact Matrix
Cost Management Plan
Defect Repair
Risk Acceptance
48. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Fast Tracking
Scope Baseline
Phase Gate
Enterprise Environmental Factors
49. The description of the project scope - major deliverables - assumptions - and constraints.
Free Float
Project Scope Statement
Risk Mitigation
Communication Management Plan
50. A calendar that identifies working days and shifts that are available for scheduled activities.
Trigger Condition
Project Calendar
Data Date
Critical Path Activity
Sorry!:) No result found.
Can you answer 50 questions in 15 minutes?
Let me suggest you:
Browse all subjects
Browse all tests
Most popular tests
Major Subjects
Tests & Exams
AP
CLEP
DSST
GRE
SAT
GMAT
Certifications
CISSP go to https://www.isc2.org/
PMP
ITIL
RHCE
MCTS
More...
IT Skills
Android Programming
Data Modeling
Objective C Programming
Basic Python Programming
Adobe Illustrator
More...
Business Skills
Advertising Techniques
Business Accounting Basics
Business Strategy
Human Resource Management
Marketing Basics
More...
Soft Skills
Body Language
People Skills
Public Speaking
Persuasion
Job Hunting And Resumes
More...
Vocabulary
GRE Vocab
SAT Vocab
TOEFL Essential Vocab
Basic English Words For All
Global Words You Should Know
Business English
More...
Languages
AP German Vocab
AP Latin Vocab
SAT Subject Test: French
Italian Survival
Norwegian Survival
More...
Engineering
Audio Engineering
Computer Science Engineering
Aerospace Engineering
Chemical Engineering
Structural Engineering
More...
Health Sciences
Basic Nursing Skills
Health Science Language Fundamentals
Veterinary Technology Medical Language
Cardiology
Clinical Surgery
More...
English
Grammar Fundamentals
Literary And Rhetorical Vocab
Elements Of Style Vocab
Introduction To English Major
Complete Advanced Sentences
Literature
Homonyms
More...
Math
Algebra Formulas
Basic Arithmetic: Measurements
Metric Conversions
Geometric Properties
Important Math Facts
Number Sense Vocab
Business Math
More...
Other Major Subjects
Science
Economics
History
Law
Performing-arts
Cooking
Logic & Reasoning
Trivia
Browse all subjects
Browse all tests
Most popular tests