SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Defect Repair
Forward Pass
Risk Acceptance
Threat
2. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Summary Activity
Portfolio
Scope Creep
Variance Analysis
3. A group of related schedule activities aggregated and displayed as a single activity.
Summary Activity
Finish-to-Start
Rolling Wave Planning
Late Finish Date
4. A calendar that identifies working days and shifts that are available for scheduled activities.
Three-Point Estimate
Portfolio
Project Calendar
Organizational Breakdown Structure
5. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Scope Management Plan
Project Calendar
Early Start Date
Resource Breakdown Structure
6. The measure of work performed expressed in terms of the budget authorized for that work.
Earned Value
Acceptance Criteria
Staffing Management Plan
Progressive Elaboration
7. A temporary endeavor undertaken to create a unique product - service - or result.
Variance at Completion
Project
Phase Gate
Project Management Office
8. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Program Management
Risk Management Plan
Early Finish Date
Constraint
9. A group of potential causes of risk.
Budget at Completion
Deliverable
Risk Category
Program Management Office
10. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Lag
Scope Creep
Project
Path Convergence
11. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Discrete Effort
Analogous Estimating
Effort
Summary Activity
12. A risk that would have a negative effect on one or more project objectives.
Analogous Estimating
Product Life Cycle
Threat
Total Float
13. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Predecessor Activity
Early Start Date
Progressive Elaboration
Preventive Action
14. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Optimistic Duration
Critical Path Activity
Preventive Action
Analogous Estimating
15. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Enterprise Environmental Factors
Earned Value Management
Acceptance Criteria
Program
16. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Backward Pass
Enterprise Environmental Factors
Schedule Model Analysis
Fast Tracking
17. The work performed to deliver a product - service - or result with the specified features and functions.
Critical Chain Method
Backward Pass
Project Scope
Resource Leveling
18. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Gantt Chart
Successor Activity
Parametric Estimating
Lead
19. The realized cost incurred for the work performed on an activity during a specific time period.
Opportunity
Actual Cost
Defect Repair
Requirement
20. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Enterprise Environmental Factors
Requirements Traceability Matrix
Project Management
Planned Value
21. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Change Control Board
Project Management Plan
Pessimistic Duration
Requirements Management Plan
22. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Apportioned Effort
What-If Sce
Finish-to-Finish
Crashing
23. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Portfolio Balancing
To-Complete Performance Index
Milestone
Summary Activity
24. Any activity on the critical path in a project schedule.
Critical Path Activity
Earned Value Management
Risk Management Plan
Procurement Management Plan
25. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Level of Effort
Cost Variance
Organizational Breakdown Structure
Resource Leveling
26. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Project Calendar
Risk Transference
Portfolio Balancing
Product Life Cycle
27. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Late Finish Date
Human Resource Plan
Stakeholder
Secondary Risk
28. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Probability and Impact Matrix
Change Control
Cost Management Plan
Schedule Model Analysis
29. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Scope Management Plan
Cost Management Plan
Acceptance Criteria
Lessons Learned
30. A point in time when the status of the project is recorded.
Project Schedule Network Diagram
Program Management Office
Free Float
Data Date
31. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Total Float
Schedule Variance
Estimate to Complete
Change Request
32. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Communication Management Plan
Discrete Effort
Risk Mitigation
Project
33. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Portfolio Balancing
Crashing
Percent Complete
Scope Baseline
34. An event or situation that indicates that a risk is about to occur.
Early Start Date
Trigger Condition
Phase Gate
Risk Category
35. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Backward Pass
Change Control Board
Assumption
Opportunity
36. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Risk Acceptance
Project Management Office
Pessimistic Duration
Optimistic Duration
37. A relationship in which a schedule activity has more than one successor.
Code of Accounts
Schedule Baseline
Path Divergence
Start-to-Start
38. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Portfolio
Project Life Cycle
Change Control System
Program Management
39. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Total Float
Project Phase
Risk Mitigation
Critical Chain Method
40. A risk that would have a positive effect on one or more project objectives.
Decomposition
Critical Path Activity
Opportunity
Code of Accounts
41. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Risk Breakdown Structure
Risk
Precedence Diagramming Method
Pessimistic Duration
42. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Cost Management Plan
Project Charter
Start-to-Start
Start-to-Finish
43. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Project Schedule
Scope Baseline
Effort
Product Life Cycle
44. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Opportunity
Program Management
Requirement
Baseline
45. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Effort
Variance at Completion
Activity
Change Control Board
46. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Control Account
Organizational Breakdown Structure
Milestone
Stakeholder
47. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
S-Curve Analysis
Stakeholder
Three-Point Estimate
Control Account
48. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Portfolio Balancing
Baseline
Lessons Learned
Cost Variance
49. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Assumption
Resource Breakdown Structure
Responsibility Assignment Matrix
Schedule Model Analysis
50. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Discrete Effort
Cost Variance
Actual Cost
Project Phase