SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Three-Point Estimate
Project Schedule Network Diagram
Organizational Process Assets
Critical Path Method
2. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Control Account
Change Request
Organizational Project Management Maturity
Actual Cost
3. A document in which the results of risk analysis and risk response planning are recorded.
Risk Register
Quality Management Plan
Three-Point Estimate
Threat
4. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Crashing
To-Complete Performance Index
Corrective Action
Data Date
5. A graphical representation of the logical relationships among the project schedule activities.
Path Convergence
Resource Leveling
Backward Pass
Project Schedule Network Diagram
6. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Lessons Learned
Risk Acceptance
Risk Mitigation
Project Manager
7. A formal proposal to modify any document - deliverable - or baseline.
Change Request
Progressive Elaboration
Cost Variance
Discrete Effort
8. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Start-to-Finish
Bottom-up Estimating
Risk Avoidance
Risk Breakdown Structure
9. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
WBS Dictionary
Finish-to-Finish
Percent Complete
Stakeholder
10. An activity that logically comes before a dependent activity in a schedule.
Trigger Condition
Predecessor Activity
Organizational Breakdown Structure
Portfolio Management
11. A risk that would have a positive effect on one or more project objectives.
Total Float
Most Likely Duration
Communication Management Plan
Opportunity
12. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Analogous Estimating
Late Start Date
Effort
Project Life Cycle
13. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
WBS Dictionary
Critical Path Method
Project Phase
Predecessor Activity
14. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Requirements Management Plan
Start-to-Start
Logical Relationship
Estimate to Complete
15. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
To-Complete Performance Index
Probability and Impact Matrix
Resource Leveling
Portfolio Management
16. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Portfolio Balancing
Constraint
Lag
Critical Path Activity
17. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Schedule Compression
Phase Gate
Apportioned Effort
S-Curve Analysis
18. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Corrective Action
Early Start Date
Organizational Breakdown Structure
Change Control
19. A group of related schedule activities aggregated and displayed as a single activity.
Summary Activity
Project Management Office
Schedule Model Analysis
Lead
20. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Cost Management Plan
Organizational Breakdown Structure
Forward Pass
Summary Activity
21. A hierarchical representation of risks that is organized according to risk categories.
Summary Activity
Risk Breakdown Structure
Resource Calendar
Baseline
22. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Phase Gate
Fast Tracking
Cost Management Plan
Risk Breakdown Structure
23. The series of phases that a project passes through from its initiation to its closure.
Decision Tree Analysis
Data Date
Project Life Cycle
Scope Baseline
24. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Requirements Management Plan
Program Management Office
Estimate to Complete
Risk Category
25. A calendar that identifies the working days and shifts upon which each specific resource is available.
Late Start Date
Resource Calendar
Most Likely Duration
Total Float
26. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Code of Accounts
Baseline
Scope Creep
Project Calendar
27. The description of the project scope - major deliverables - assumptions - and constraints.
Project Scope Statement
Logical Relationship
Late Finish Date
Project Scope
28. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Earned Value Management
Estimate at Completion
Procurement Management Plan
Scope Management Plan
29. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Early Start Date
Trigger Condition
Lead
Scope Baseline
30. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Baseline
Schedule Management Plan
Variance at Completion
Critical Path
31. A calendar that identifies working days and shifts that are available for scheduled activities.
Project Calendar
Variance at Completion
Summary Activity
Deliverable
32. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Organizational Project Management Maturity
Requirements Management Plan
Risk
Critical Path Activity
33. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Project Manager
Three-Point Estimate
Risk Register
Scope Creep
34. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Start-to-Start
Project Calendar
Cost Performance Index
Project Life Cycle
35. The authorized budget assigned to scheduled work.
Planned Value
Risk Avoidance
Cost Management Plan
Late Start Date
36. An intentional activity that realigns the performance of the project work with the project management plan.
Activity
Estimate to Complete
Estimate at Completion
Corrective Action
37. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Start-to-Finish
Change Control Board
Program Management
Late Finish Date
38. A significant point or event in a project - program - or portfolio.
Lessons Learned
Preventive Action
Milestone
Path Divergence
39. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Precedence Diagramming Method
Schedule Management Plan
Start-to-Finish
Defect Repair
40. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Communication Management Plan
Project Schedule
Risk Avoidance
Finish-to-Finish
41. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Parametric Estimating
Most Likely Duration
Change Control System
Code of Accounts
42. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Quality Management Plan
Project Calendar
Variance Analysis
Change Control Board
43. A dependent activity that logically comes after another activity in a schedule.
Successor Activity
Risk Acceptance
Milestone
Late Finish Date
44. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Optimistic Duration
Early Finish Date
Performing Organization
Rolling Wave Planning
45. A limiting factor that affects the execution of a project - program - portfolio - or process.
Rolling Wave Planning
Human Resource Plan
Constraint
Project Calendar
46. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Percent Complete
Corrective Action
Critical Path Method
Planned Value
47. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Product Life Cycle
Project Management
Project Life Cycle
Sponsor
48. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Risk Management Plan
Portfolio Balancing
Staffing Management Plan
Constraint
49. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Deliverable
Control Account
Project Management Plan
Requirements Management Plan
50. The sum of all budgets established for the work to be performed.
Risk
Estimate at Completion
Project Management
Budget at Completion
Sorry!:) No result found.
Can you answer 50 questions in 15 minutes?
Let me suggest you:
Browse all subjects
Browse all tests
Most popular tests
Major Subjects
Tests & Exams
AP
CLEP
DSST
GRE
SAT
GMAT
Certifications
CISSP go to https://www.isc2.org/
PMP
ITIL
RHCE
MCTS
More...
IT Skills
Android Programming
Data Modeling
Objective C Programming
Basic Python Programming
Adobe Illustrator
More...
Business Skills
Advertising Techniques
Business Accounting Basics
Business Strategy
Human Resource Management
Marketing Basics
More...
Soft Skills
Body Language
People Skills
Public Speaking
Persuasion
Job Hunting And Resumes
More...
Vocabulary
GRE Vocab
SAT Vocab
TOEFL Essential Vocab
Basic English Words For All
Global Words You Should Know
Business English
More...
Languages
AP German Vocab
AP Latin Vocab
SAT Subject Test: French
Italian Survival
Norwegian Survival
More...
Engineering
Audio Engineering
Computer Science Engineering
Aerospace Engineering
Chemical Engineering
Structural Engineering
More...
Health Sciences
Basic Nursing Skills
Health Science Language Fundamentals
Veterinary Technology Medical Language
Cardiology
Clinical Surgery
More...
English
Grammar Fundamentals
Literary And Rhetorical Vocab
Elements Of Style Vocab
Introduction To English Major
Complete Advanced Sentences
Literature
Homonyms
More...
Math
Algebra Formulas
Basic Arithmetic: Measurements
Metric Conversions
Geometric Properties
Important Math Facts
Number Sense Vocab
Business Math
More...
Other Major Subjects
Science
Economics
History
Law
Performing-arts
Cooking
Logic & Reasoning
Trivia
Browse all subjects
Browse all tests
Most popular tests