SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Performing Organization
Early Finish Date
WBS Dictionary
Control Account
2. A dependency between two activities - or between an activity and a milestone.
Preventive Action
Logical Relationship
Pessimistic Duration
Lessons Learned
3. A significant point or event in a project - program - or portfolio.
Project Management Office
Milestone
Total Float
Performing Organization
4. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Logical Relationship
Program Management
Project Scope
Decomposition
5. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Effort
Change Request
Schedule Model Analysis
Late Finish Date
6. A relationship in which a schedule activity has more than one successor.
Stakeholder
Change Control System
Path Divergence
Finish-to-Finish
7. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Project Management Office
Portfolio Management
Parametric Estimating
Decision Tree Analysis
8. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Late Finish Date
Percent Complete
Defect Repair
Responsibility Assignment Matrix
9. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Control Account
Program
Most Likely Duration
Cost Variance
10. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Three-Point Estimate
Start-to-Finish
Program
Effort
11. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Percent Complete
Requirements Management Plan
Budget at Completion
Sponsor
12. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Project
Predecessor Activity
Preventive Action
Project Schedule
13. An activity that logically comes before a dependent activity in a schedule.
Resource Calendar
Schedule Compression
Three-Point Estimate
Predecessor Activity
14. The work performed to deliver a product - service - or result with the specified features and functions.
Cost Performance Index
Project Scope
To-Complete Performance Index
Decomposition
15. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Enterprise Environmental Factors
Quality Management Plan
Total Float
Forward Pass
16. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Risk Transference
Probability and Impact Matrix
Precedence Diagramming Method
Organizational Project Management Maturity
17. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Precedence Diagramming Method
Enterprise Environmental Factors
Acceptance Criteria
Corrective Action
18. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Sponsor
Requirement
Control Account
Program Management Office
19. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Risk Acceptance
Probability and Impact Matrix
Project Calendar
Summary Activity
20. A grid that shows the project resources assigned to each work package.
Phase Gate
Defect Repair
Portfolio Management
Responsibility Assignment Matrix
21. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Project Phase
Actual Cost
Trigger Condition
Project
22. The centralized management of one or more portfolios to achieve strategic objectives.
Logical Relationship
Communication Management Plan
Portfolio Management
Optimistic Duration
23. The sum of all budgets established for the work to be performed.
Budget at Completion
Milestone
Effort
Project Manager
24. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Path Divergence
Requirement
Responsibility Assignment Matrix
Critical Path Method
25. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Gantt Chart
Resource Leveling
Quality Management Plan
Requirements Traceability Matrix
26. A risk that would have a positive effect on one or more project objectives.
Pessimistic Duration
Responsibility Assignment Matrix
Risk Category
Opportunity
27. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Threat
Organizational Process Assets
Schedule Baseline
Early Finish Date
28. A graphical representation of the logical relationships among the project schedule activities.
Threat
Most Likely Duration
Project Schedule Network Diagram
Project Phase
29. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Secondary Risk
Portfolio Balancing
Procurement Management Plan
Scope Baseline
30. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
What-If Sce
Budget at Completion
Enterprise Environmental Factors
Earned Value Management
31. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Lead
Total Float
Organizational Breakdown Structure
Level of Effort
32. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Product Life Cycle
Gantt Chart
Project Life Cycle
Scope Creep
33. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Resource Leveling
Project Management
Earned Value
Path Convergence
34. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Optimistic Duration
Portfolio Balancing
Apportioned Effort
Portfolio
35. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Threat
Finish-to-Start
Late Finish Date
Project Manager
36. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Summary Activity
Analogous Estimating
Resource Leveling
Optimistic Duration
37. A technique for determining the cause and degree of difference between the baseline and actual performance.
Most Likely Duration
Product Life Cycle
What-If Sce
Variance Analysis
38. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Decision Tree Analysis
Cost Performance Index
Path Divergence
Path Convergence
39. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Change Control Board
Schedule Compression
Risk Acceptance
Cost Variance
40. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Probability and Impact Matrix
Schedule Model
Cost Performance Index
Lag
41. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Start-to-Start
Critical Path
Risk Mitigation
Constraint
42. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Organizational Breakdown Structure
Rolling Wave Planning
Resource Breakdown Structure
Discrete Effort
43. A relationship in which a schedule activity has more than one predecessor.
Path Convergence
Critical Path Activity
Apportioned Effort
Decision Tree Analysis
44. The realized cost incurred for the work performed on an activity during a specific time period.
Budget at Completion
To-Complete Performance Index
Finish-to-Finish
Actual Cost
45. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Project Schedule
Control Account
Change Request
Risk Avoidance
46. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Percent Complete
Project Manager
Human Resource Plan
Risk Register
47. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Project Management Plan
Most Likely Duration
Corrective Action
Cost Management Plan
48. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Critical Path Method
Procurement Management Plan
Project Charter
Cost Performance Index
49. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Corrective Action
Effort
Project Phase
Backward Pass
50. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Finish-to-Finish
Product Life Cycle
Decision Tree Analysis
Schedule Model Analysis
Sorry!:) No result found.
Can you answer 50 questions in 15 minutes?
Let me suggest you:
Browse all subjects
Browse all tests
Most popular tests
Major Subjects
Tests & Exams
AP
CLEP
DSST
GRE
SAT
GMAT
Certifications
CISSP go to https://www.isc2.org/
PMP
ITIL
RHCE
MCTS
More...
IT Skills
Android Programming
Data Modeling
Objective C Programming
Basic Python Programming
Adobe Illustrator
More...
Business Skills
Advertising Techniques
Business Accounting Basics
Business Strategy
Human Resource Management
Marketing Basics
More...
Soft Skills
Body Language
People Skills
Public Speaking
Persuasion
Job Hunting And Resumes
More...
Vocabulary
GRE Vocab
SAT Vocab
TOEFL Essential Vocab
Basic English Words For All
Global Words You Should Know
Business English
More...
Languages
AP German Vocab
AP Latin Vocab
SAT Subject Test: French
Italian Survival
Norwegian Survival
More...
Engineering
Audio Engineering
Computer Science Engineering
Aerospace Engineering
Chemical Engineering
Structural Engineering
More...
Health Sciences
Basic Nursing Skills
Health Science Language Fundamentals
Veterinary Technology Medical Language
Cardiology
Clinical Surgery
More...
English
Grammar Fundamentals
Literary And Rhetorical Vocab
Elements Of Style Vocab
Introduction To English Major
Complete Advanced Sentences
Literature
Homonyms
More...
Math
Algebra Formulas
Basic Arithmetic: Measurements
Metric Conversions
Geometric Properties
Important Math Facts
Number Sense Vocab
Business Math
More...
Other Major Subjects
Science
Economics
History
Law
Performing-arts
Cooking
Logic & Reasoning
Trivia
Browse all subjects
Browse all tests
Most popular tests