SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Critical Path Activity
Rolling Wave Planning
Backward Pass
Requirements Traceability Matrix
2. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Schedule Model
Percent Complete
Three-Point Estimate
Parametric Estimating
3. An event or situation that indicates that a risk is about to occur.
Trigger Condition
Control Account
Progressive Elaboration
Staffing Management Plan
4. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Acceptance Criteria
Lessons Learned
Free Float
Organizational Process Assets
5. A dependent activity that logically comes after another activity in a schedule.
Successor Activity
Acceptance Criteria
Baseline
Program
6. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Three-Point Estimate
Requirements Traceability Matrix
Optimistic Duration
Schedule Variance
7. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Corrective Action
Project Management
Baseline
Quality Management Plan
8. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Project Schedule
Crashing
Threat
Program
9. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
WBS Dictionary
Resource Leveling
Early Start Date
Schedule Variance
10. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Bottom-up Estimating
Risk Acceptance
Critical Path
Variance Analysis
11. A hierarchical representation of risks that is organized according to risk categories.
Risk Breakdown Structure
Requirement
Risk Transference
Organizational Breakdown Structure
12. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Start-to-Finish
Cost Variance
Gantt Chart
Precedence Diagramming Method
13. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Late Finish Date
Requirements Management Plan
Preventive Action
Baseline
14. An activity that logically comes before a dependent activity in a schedule.
Quality Management Plan
Probability and Impact Matrix
Predecessor Activity
Logical Relationship
15. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Risk Acceptance
Performing Organization
Fast Tracking
What-If Sce
16. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Variance at Completion
Procurement Management Plan
Risk Avoidance
Schedule Baseline
17. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Organizational Project Management Maturity
Requirements Management Plan
Bottom-up Estimating
Data Date
18. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Project Management Plan
Schedule Variance
Resource Leveling
Decomposition
19. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Schedule Management Plan
Control Account
Enterprise Environmental Factors
Project Management
20. A calendar that identifies the working days and shifts upon which each specific resource is available.
Resource Calendar
Control Account
Percent Complete
Change Control System
21. The realized cost incurred for the work performed on an activity during a specific time period.
Schedule Model
Risk Acceptance
S-Curve Analysis
Actual Cost
22. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Resource Leveling
Trigger Condition
Risk Acceptance
Effort
23. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Scope Creep
Risk Breakdown Structure
Enterprise Environmental Factors
Progressive Elaboration
24. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Deliverable
Risk Mitigation
Level of Effort
Preventive Action
25. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Discrete Effort
Program Management Office
What-If Sce
Control Account
26. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Early Finish Date
Project Scope Statement
Change Control Board
Schedule Model
27. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Critical Path Activity
Successor Activity
Organizational Breakdown Structure
Cost Management Plan
28. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Scope Management Plan
Late Start Date
Scope Creep
Cost Variance
29. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Project Manager
Requirements Management Plan
Late Finish Date
Analogous Estimating
30. A risk that would have a positive effect on one or more project objectives.
Procurement Management Plan
Apportioned Effort
Opportunity
Project Life Cycle
31. A grid that shows the project resources assigned to each work package.
Progressive Elaboration
Human Resource Plan
Milestone
Responsibility Assignment Matrix
32. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Scope Management Plan
Baseline
Project Management
Preventive Action
33. A risk that would have a negative effect on one or more project objectives.
Forward Pass
Threat
Late Finish Date
Schedule Variance
34. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Change Control
Critical Path Activity
Parametric Estimating
Budget at Completion
35. A hierarchical representation of resources by category and type.
Schedule Baseline
Project
Preventive Action
Resource Breakdown Structure
36. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Decision Tree Analysis
Parametric Estimating
Project Management Plan
Early Start Date
37. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Finish-to-Finish
Lessons Learned
Risk Category
Portfolio Balancing
38. A technique used to shorten the schedule duration without reducing the project scope.
Earned Value
Scope Baseline
Schedule Compression
Rolling Wave Planning
39. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Organizational Process Assets
Human Resource Plan
Project Management Plan
Schedule Baseline
40. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Finish-to-Start
Successor Activity
Human Resource Plan
Crashing
41. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Organizational Breakdown Structure
Schedule Performance Index
Apportioned Effort
Portfolio Balancing
42. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Project Life Cycle
Performing Organization
Risk Avoidance
Data Date
43. The document that describes how the project will be executed - monitored - and controlled.
Schedule Model Analysis
Project Management Plan
Schedule Variance
Pessimistic Duration
44. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Finish-to-Start
Apportioned Effort
Finish-to-Finish
Early Finish Date
45. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Scope Creep
Decision Tree Analysis
What-If Sce
Effort
46. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Early Finish Date
Project Calendar
Defect Repair
Schedule Variance
47. An intentional activity to modify a nonconforming product or product component.
Defect Repair
Free Float
Control Account
Risk Category
48. A relationship in which a schedule activity has more than one predecessor.
Discrete Effort
Path Convergence
Budget at Completion
Enterprise Environmental Factors
49. A document in which the results of risk analysis and risk response planning are recorded.
Early Finish Date
Risk Register
Secondary Risk
Critical Path
50. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Corrective Action
Progressive Elaboration
Enterprise Environmental Factors
Project Life Cycle
Sorry!:) No result found.
Can you answer 50 questions in 15 minutes?
Let me suggest you:
Browse all subjects
Browse all tests
Most popular tests
Major Subjects
Tests & Exams
AP
CLEP
DSST
GRE
SAT
GMAT
Certifications
CISSP go to https://www.isc2.org/
PMP
ITIL
RHCE
MCTS
More...
IT Skills
Android Programming
Data Modeling
Objective C Programming
Basic Python Programming
Adobe Illustrator
More...
Business Skills
Advertising Techniques
Business Accounting Basics
Business Strategy
Human Resource Management
Marketing Basics
More...
Soft Skills
Body Language
People Skills
Public Speaking
Persuasion
Job Hunting And Resumes
More...
Vocabulary
GRE Vocab
SAT Vocab
TOEFL Essential Vocab
Basic English Words For All
Global Words You Should Know
Business English
More...
Languages
AP German Vocab
AP Latin Vocab
SAT Subject Test: French
Italian Survival
Norwegian Survival
More...
Engineering
Audio Engineering
Computer Science Engineering
Aerospace Engineering
Chemical Engineering
Structural Engineering
More...
Health Sciences
Basic Nursing Skills
Health Science Language Fundamentals
Veterinary Technology Medical Language
Cardiology
Clinical Surgery
More...
English
Grammar Fundamentals
Literary And Rhetorical Vocab
Elements Of Style Vocab
Introduction To English Major
Complete Advanced Sentences
Literature
Homonyms
More...
Math
Algebra Formulas
Basic Arithmetic: Measurements
Metric Conversions
Geometric Properties
Important Math Facts
Number Sense Vocab
Business Math
More...
Other Major Subjects
Science
Economics
History
Law
Performing-arts
Cooking
Logic & Reasoning
Trivia
Browse all subjects
Browse all tests
Most popular tests