SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Risk Avoidance
Cost Variance
Threat
Communication Management Plan
2. The realized cost incurred for the work performed on an activity during a specific time period.
Level of Effort
Actual Cost
Discrete Effort
Analogous Estimating
3. A risk that would have a negative effect on one or more project objectives.
Risk Breakdown Structure
Path Divergence
Secondary Risk
Threat
4. A formal proposal to modify any document - deliverable - or baseline.
Start-to-Start
S-Curve Analysis
Change Request
Acceptance Criteria
5. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Performing Organization
Logical Relationship
Responsibility Assignment Matrix
Project Schedule
6. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Cost Management Plan
Decision Tree Analysis
Cost Performance Index
Backward Pass
7. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Budget at Completion
Project Life Cycle
Project Charter
Project Scope
8. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Finish-to-Start
Most Likely Duration
Fast Tracking
Late Finish Date
9. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Early Start Date
Budget at Completion
Organizational Process Assets
Requirements Traceability Matrix
10. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Requirements Traceability Matrix
Scope Management Plan
Late Finish Date
Risk Acceptance
11. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Procurement Management Plan
Requirements Management Plan
Project Scope Statement
Analogous Estimating
12. A relationship in which a schedule activity has more than one predecessor.
Resource Leveling
Quality Management Plan
Path Convergence
Defect Repair
13. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Estimate at Completion
Cost Management Plan
Earned Value
Apportioned Effort
14. A risk that arises as a direct result of implementing a risk response.
Change Control System
Project Management Office
Secondary Risk
S-Curve Analysis
15. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Project Calendar
Project Phase
Start-to-Start
Risk
16. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Portfolio
Estimate at Completion
Product Life Cycle
Quality Management Plan
17. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Risk Acceptance
Late Finish Date
Most Likely Duration
Schedule Baseline
18. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Critical Path Activity
Variance at Completion
Earned Value Management
Apportioned Effort
19. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Schedule Performance Index
Estimate at Completion
Schedule Compression
Gantt Chart
20. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Schedule Model Analysis
Constraint
Late Start Date
Early Finish Date
21. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Schedule Model Analysis
Change Control System
Critical Chain Method
Project Management
22. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Risk Mitigation
Lessons Learned
Schedule Model
Critical Chain Method
23. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Baseline
Estimate at Completion
Schedule Performance Index
Critical Path
24. A relationship in which a schedule activity has more than one successor.
Free Float
Scope Baseline
Path Divergence
Project Phase
25. The document that describes how the project will be executed - monitored - and controlled.
Trigger Condition
Project Management Plan
Corrective Action
Schedule Variance
26. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Deliverable
Procurement Management Plan
Lessons Learned
Trigger Condition
27. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Critical Path Activity
Discrete Effort
Enterprise Environmental Factors
Corrective Action
28. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Stakeholder
Responsibility Assignment Matrix
Finish-to-Finish
Schedule Performance Index
29. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Quality Management Plan
Trigger Condition
Deliverable
Late Start Date
30. A temporary endeavor undertaken to create a unique product - service - or result.
Portfolio
Change Control Board
Project
Level of Effort
31. The series of phases that a project passes through from its initiation to its closure.
Project Schedule Network Diagram
Three-Point Estimate
Responsibility Assignment Matrix
Project Life Cycle
32. The authorized budget assigned to scheduled work.
Planned Value
Variance at Completion
Product Life Cycle
What-If Sce
33. The description of the project scope - major deliverables - assumptions - and constraints.
Earned Value
Backward Pass
Lessons Learned
Project Scope Statement
34. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Change Control
Estimate at Completion
Opportunity
Schedule Compression
35. A group of potential causes of risk.
Three-Point Estimate
Risk Category
Risk Transference
Product Life Cycle
36. A risk that would have a positive effect on one or more project objectives.
Opportunity
Portfolio Balancing
Project Calendar
Project Phase
37. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Phase Gate
Logical Relationship
Rolling Wave Planning
Trigger Condition
38. A hierarchical representation of resources by category and type.
Path Divergence
Risk Management Plan
Predecessor Activity
Resource Breakdown Structure
39. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Requirements Management Plan
Cost Performance Index
Rolling Wave Planning
Lag
40. An intentional activity to modify a nonconforming product or product component.
Defect Repair
Program
Risk Breakdown Structure
Organizational Process Assets
41. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Organizational Project Management Maturity
Parametric Estimating
Level of Effort
Discrete Effort
42. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Percent Complete
Cost Variance
Late Finish Date
What-If Sce
43. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Scope Baseline
Baseline
Cost Performance Index
Portfolio
44. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Percent Complete
Project Schedule Network Diagram
Communication Management Plan
Portfolio
45. A calendar that identifies working days and shifts that are available for scheduled activities.
Portfolio Balancing
Project Calendar
Probability and Impact Matrix
Critical Chain Method
46. A graphical representation of the logical relationships among the project schedule activities.
Requirement
Project Schedule Network Diagram
What-If Sce
Cost Variance
47. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Schedule Variance
Variance at Completion
Earned Value Management
Lag
48. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Resource Leveling
Phase Gate
Portfolio Balancing
What-If Sce
49. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Communication Management Plan
Finish-to-Start
Late Finish Date
Change Request
50. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Finish-to-Start
Stakeholder
Level of Effort
Three-Point Estimate