SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Risk Avoidance
Lead
Enterprise Environmental Factors
Activity
2. A point in time when the status of the project is recorded.
Budget at Completion
Requirement
Trigger Condition
Data Date
3. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Total Float
Quality Management Plan
Cost Variance
Project Management Plan
4. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Risk Register
Path Convergence
Control Account
Late Finish Date
5. An activity that logically comes before a dependent activity in a schedule.
Predecessor Activity
Start-to-Finish
Precedence Diagramming Method
Estimate to Complete
6. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Project Scope
Start-to-Finish
Most Likely Duration
Progressive Elaboration
7. A group of related schedule activities aggregated and displayed as a single activity.
Control Account
Actual Cost
Summary Activity
Portfolio Management
8. A calendar that identifies the working days and shifts upon which each specific resource is available.
What-If Sce
Bottom-up Estimating
Resource Calendar
Project Life Cycle
9. A risk that would have a positive effect on one or more project objectives.
Opportunity
Estimate at Completion
Phase Gate
Forward Pass
10. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Risk Avoidance
Program Management Office
Progressive Elaboration
Change Control
11. A graphical representation of the logical relationships among the project schedule activities.
Sponsor
Threat
Project Schedule Network Diagram
Start-to-Finish
12. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Secondary Risk
Risk Avoidance
Schedule Model
Early Start Date
13. A numbering system used to uniquely identify each component of the work breakdown structure.
Project Management Office
Variance at Completion
Code of Accounts
Constraint
14. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Requirements Traceability Matrix
Three-Point Estimate
Product Life Cycle
Project Phase
15. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Start-to-Finish
Scope Baseline
Portfolio Balancing
Organizational Process Assets
16. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Free Float
Change Control
Decision Tree Analysis
Program Management Office
17. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Fast Tracking
Percent Complete
Discrete Effort
Lead
18. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Start-to-Finish
Variance Analysis
Project Scope
Rolling Wave Planning
19. A temporary endeavor undertaken to create a unique product - service - or result.
Project
Finish-to-Start
Free Float
Path Convergence
20. The document that describes how the project will be executed - monitored - and controlled.
Project Management Plan
Constraint
Most Likely Duration
Requirements Traceability Matrix
21. The work performed to deliver a product - service - or result with the specified features and functions.
Program Management Office
Project Scope
Schedule Model
Start-to-Finish
22. The authorized budget assigned to scheduled work.
Total Float
Variance at Completion
Risk Register
Planned Value
23. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Total Float
Baseline
Deliverable
Stakeholder
24. A risk that arises as a direct result of implementing a risk response.
Secondary Risk
Early Finish Date
Acceptance Criteria
Schedule Baseline
25. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Analogous Estimating
Predecessor Activity
Communication Management Plan
Lead
26. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Three-Point Estimate
Apportioned Effort
Lessons Learned
Critical Path
27. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Analogous Estimating
Logical Relationship
Effort
Program
28. A hierarchical representation of risks that is organized according to risk categories.
Risk Breakdown Structure
Acceptance Criteria
Actual Cost
Organizational Project Management Maturity
29. A risk that would have a negative effect on one or more project objectives.
Analogous Estimating
Cost Variance
Acceptance Criteria
Threat
30. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Performing Organization
Crashing
Quality Management Plan
To-Complete Performance Index
31. An intentional activity to modify a nonconforming product or product component.
Defect Repair
Percent Complete
To-Complete Performance Index
Preventive Action
32. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Portfolio Balancing
Organizational Breakdown Structure
Schedule Compression
Finish-to-Start
33. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Lag
Decomposition
Project Manager
Cost Performance Index
34. A grid that shows the project resources assigned to each work package.
Baseline
Responsibility Assignment Matrix
Analogous Estimating
Critical Path Method
35. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Control Account
Decision Tree Analysis
Assumption
Communication Management Plan
36. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Schedule Management Plan
Percent Complete
Program
Organizational Process Assets
37. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Early Finish Date
Variance at Completion
Organizational Breakdown Structure
Logical Relationship
38. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Product Life Cycle
Most Likely Duration
Enterprise Environmental Factors
Cost Performance Index
39. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Baseline
Schedule Model Analysis
Resource Leveling
Organizational Process Assets
40. An event or situation that indicates that a risk is about to occur.
Predecessor Activity
Total Float
Trigger Condition
Gantt Chart
41. A formal proposal to modify any document - deliverable - or baseline.
Change Control System
S-Curve Analysis
Change Request
Constraint
42. A document in which the results of risk analysis and risk response planning are recorded.
Risk Register
Apportioned Effort
Three-Point Estimate
Optimistic Duration
43. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Scope Creep
Human Resource Plan
Planned Value
Program Management Office
44. A dependency between two activities - or between an activity and a milestone.
Logical Relationship
Start-to-Start
Resource Leveling
Late Start Date
45. A dependent activity that logically comes after another activity in a schedule.
Portfolio Balancing
Preventive Action
Successor Activity
Change Control System
46. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Portfolio
WBS Dictionary
Requirements Traceability Matrix
Schedule Baseline
47. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Schedule Model Analysis
Change Control Board
Program Management Office
Organizational Process Assets
48. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Decision Tree Analysis
Project Phase
Start-to-Finish
Optimistic Duration
49. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Cost Performance Index
Logical Relationship
Risk Category
Earned Value Management
50. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Project Schedule
Change Control Board
Path Convergence
Deliverable
Sorry!:) No result found.
Can you answer 50 questions in 15 minutes?
Let me suggest you:
Browse all subjects
Browse all tests
Most popular tests
Major Subjects
Tests & Exams
AP
CLEP
DSST
GRE
SAT
GMAT
Certifications
CISSP go to https://www.isc2.org/
PMP
ITIL
RHCE
MCTS
More...
IT Skills
Android Programming
Data Modeling
Objective C Programming
Basic Python Programming
Adobe Illustrator
More...
Business Skills
Advertising Techniques
Business Accounting Basics
Business Strategy
Human Resource Management
Marketing Basics
More...
Soft Skills
Body Language
People Skills
Public Speaking
Persuasion
Job Hunting And Resumes
More...
Vocabulary
GRE Vocab
SAT Vocab
TOEFL Essential Vocab
Basic English Words For All
Global Words You Should Know
Business English
More...
Languages
AP German Vocab
AP Latin Vocab
SAT Subject Test: French
Italian Survival
Norwegian Survival
More...
Engineering
Audio Engineering
Computer Science Engineering
Aerospace Engineering
Chemical Engineering
Structural Engineering
More...
Health Sciences
Basic Nursing Skills
Health Science Language Fundamentals
Veterinary Technology Medical Language
Cardiology
Clinical Surgery
More...
English
Grammar Fundamentals
Literary And Rhetorical Vocab
Elements Of Style Vocab
Introduction To English Major
Complete Advanced Sentences
Literature
Homonyms
More...
Math
Algebra Formulas
Basic Arithmetic: Measurements
Metric Conversions
Geometric Properties
Important Math Facts
Number Sense Vocab
Business Math
More...
Other Major Subjects
Science
Economics
History
Law
Performing-arts
Cooking
Logic & Reasoning
Trivia
Browse all subjects
Browse all tests
Most popular tests