SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An event or situation that indicates that a risk is about to occur.
Three-Point Estimate
Risk Avoidance
Corrective Action
Trigger Condition
2. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Three-Point Estimate
Risk
Responsibility Assignment Matrix
Earned Value
3. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Scope Baseline
Level of Effort
Assumption
Deliverable
4. A numbering system used to uniquely identify each component of the work breakdown structure.
Code of Accounts
Schedule Management Plan
Most Likely Duration
Start-to-Finish
5. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Change Control
Requirements Management Plan
Activity
Variance Analysis
6. An intentional activity that realigns the performance of the project work with the project management plan.
Finish-to-Start
Deliverable
Corrective Action
Stakeholder
7. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Performing Organization
Assumption
Critical Path Activity
Lessons Learned
8. A grid that shows the project resources assigned to each work package.
Start-to-Start
Responsibility Assignment Matrix
Portfolio Management
Schedule Model
9. A temporary endeavor undertaken to create a unique product - service - or result.
Summary Activity
Project
Early Start Date
Schedule Performance Index
10. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Decomposition
Program Management
Phase Gate
Sponsor
11. A hierarchical representation of risks that is organized according to risk categories.
Change Request
Actual Cost
Critical Path Method
Risk Breakdown Structure
12. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Scope Creep
Preventive Action
WBS Dictionary
Backward Pass
13. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Percent Complete
Critical Path Activity
Decision Tree Analysis
Precedence Diagramming Method
14. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Project
Procurement Management Plan
Performing Organization
Progressive Elaboration
15. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Risk Acceptance
Risk Management Plan
Estimate to Complete
Variance at Completion
16. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Project Management
Scope Baseline
Crashing
Forward Pass
17. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Actual Cost
Quality Management Plan
Project
Schedule Model
18. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Staffing Management Plan
Communication Management Plan
Path Convergence
Scope Baseline
19. A technique used to shorten the schedule duration without reducing the project scope.
Program Management Office
Risk Mitigation
Forward Pass
Schedule Compression
20. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Gantt Chart
Three-Point Estimate
Parametric Estimating
Precedence Diagramming Method
21. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Scope Creep
Project Management
Critical Path
Organizational Breakdown Structure
22. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Schedule Baseline
Resource Calendar
Finish-to-Finish
Schedule Management Plan
23. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Predecessor Activity
Crashing
Project Life Cycle
Risk
24. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Data Date
Critical Path Method
Phase Gate
Project Charter
25. The document that describes how the project will be executed - monitored - and controlled.
Opportunity
Bottom-up Estimating
Schedule Performance Index
Project Management Plan
26. A group of related schedule activities aggregated and displayed as a single activity.
Variance Analysis
Milestone
Program
Summary Activity
27. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Variance at Completion
Path Convergence
What-If Sce
Pessimistic Duration
28. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Trigger Condition
Lessons Learned
Apportioned Effort
Early Start Date
29. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Path Convergence
Actual Cost
Critical Chain Method
Percent Complete
30. A calendar that identifies the working days and shifts upon which each specific resource is available.
Schedule Model
Program
Gantt Chart
Resource Calendar
31. The realized cost incurred for the work performed on an activity during a specific time period.
Risk Register
Actual Cost
Secondary Risk
Resource Leveling
32. A significant point or event in a project - program - or portfolio.
Bottom-up Estimating
Cost Variance
Free Float
Milestone
33. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Schedule Management Plan
Constraint
Start-to-Finish
Discrete Effort
34. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Bottom-up Estimating
Project Management
Early Finish Date
Portfolio Balancing
35. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Scope Creep
Project Manager
Progressive Elaboration
Backward Pass
36. The work performed to deliver a product - service - or result with the specified features and functions.
Change Control Board
Project Scope
Rolling Wave Planning
Project Charter
37. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Probability and Impact Matrix
Fast Tracking
What-If Sce
Crashing
38. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Parametric Estimating
Communication Management Plan
Requirement
Schedule Performance Index
39. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Schedule Baseline
Milestone
Discrete Effort
Project Phase
40. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
WBS Dictionary
Progressive Elaboration
Defect Repair
Crashing
41. A risk that would have a positive effect on one or more project objectives.
Start-to-Start
Early Start Date
Path Divergence
Opportunity
42. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Corrective Action
Late Finish Date
Schedule Variance
Schedule Performance Index
43. A grid that links product requirements from their origin to the deliverables that satisfy them.
Requirement
Project Manager
Parametric Estimating
Requirements Traceability Matrix
44. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Percent Complete
Progressive Elaboration
Cost Management Plan
Lag
45. A relationship in which a schedule activity has more than one predecessor.
Scope Creep
Path Convergence
Human Resource Plan
Risk
46. The sum of all budgets established for the work to be performed.
Late Finish Date
Budget at Completion
Lessons Learned
Risk
47. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Schedule Variance
Logical Relationship
Sponsor
Effort
48. A relationship in which a schedule activity has more than one successor.
Risk Mitigation
Baseline
Path Divergence
Staffing Management Plan
49. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Risk Avoidance
Acceptance Criteria
Critical Path Activity
Successor Activity
50. The centralized management of one or more portfolios to achieve strategic objectives.
Effort
Project Manager
Risk
Portfolio Management