SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A hierarchical representation of risks that is organized according to risk categories.
Portfolio
Earned Value Management
Risk Breakdown Structure
Lessons Learned
2. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Schedule Baseline
Backward Pass
Project Manager
Change Control Board
3. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Human Resource Plan
Activity
Milestone
Three-Point Estimate
4. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Change Request
Trigger Condition
Risk Mitigation
Progressive Elaboration
5. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Performing Organization
Project Management Plan
Path Convergence
Bottom-up Estimating
6. A document in which the results of risk analysis and risk response planning are recorded.
Requirements Traceability Matrix
Risk Register
Organizational Breakdown Structure
Opportunity
7. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Percent Complete
Activity
Probability and Impact Matrix
Scope Baseline
8. A dependency between two activities - or between an activity and a milestone.
Decomposition
Budget at Completion
Schedule Model
Logical Relationship
9. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Scope Baseline
Schedule Model Analysis
Trigger Condition
Start-to-Finish
10. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Path Divergence
Risk Mitigation
Phase Gate
S-Curve Analysis
11. The description of the project scope - major deliverables - assumptions - and constraints.
Project Schedule Network Diagram
Requirement
Critical Path Activity
Project Scope Statement
12. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Forward Pass
Rolling Wave Planning
Logical Relationship
Three-Point Estimate
13. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Trigger Condition
Free Float
Actual Cost
Defect Repair
14. A risk that would have a positive effect on one or more project objectives.
Decision Tree Analysis
Apportioned Effort
Opportunity
Assumption
15. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Organizational Process Assets
Finish-to-Start
Risk Management Plan
Risk Transference
16. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Organizational Project Management Maturity
Optimistic Duration
Program Management
Procurement Management Plan
17. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Cost Performance Index
Project Management Office
Schedule Management Plan
Level of Effort
18. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Deliverable
Staffing Management Plan
Progressive Elaboration
Bottom-up Estimating
19. A group of potential causes of risk.
Cost Performance Index
Percent Complete
Risk Category
Probability and Impact Matrix
20. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Change Control System
Project Life Cycle
Product Life Cycle
Estimate to Complete
21. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Schedule Model Analysis
Risk Transference
Three-Point Estimate
Organizational Breakdown Structure
22. The work performed to deliver a product - service - or result with the specified features and functions.
Three-Point Estimate
Project Scope
Project Management Office
Enterprise Environmental Factors
23. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Organizational Breakdown Structure
Gantt Chart
Portfolio Balancing
Earned Value Management
24. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Estimate at Completion
S-Curve Analysis
Preventive Action
Sponsor
25. The document that describes how the project will be executed - monitored - and controlled.
Project Management Plan
Program
Staffing Management Plan
Budget at Completion
26. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Risk Acceptance
Finish-to-Finish
Decomposition
Risk Management Plan
27. An activity that logically comes before a dependent activity in a schedule.
Risk Category
Estimate at Completion
Predecessor Activity
Organizational Breakdown Structure
28. A relationship in which a schedule activity has more than one predecessor.
Human Resource Plan
Communication Management Plan
Project Phase
Path Convergence
29. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
WBS Dictionary
Late Start Date
Successor Activity
To-Complete Performance Index
30. A relationship in which a schedule activity has more than one successor.
Finish-to-Finish
Path Convergence
Project Charter
Path Divergence
31. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Three-Point Estimate
Bottom-up Estimating
Staffing Management Plan
Gantt Chart
32. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Control Account
Lessons Learned
Requirements Traceability Matrix
Risk
33. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Planned Value
Change Control System
Backward Pass
Scope Baseline
34. The sum of all budgets established for the work to be performed.
Risk Transference
Threat
Deliverable
Budget at Completion
35. A calendar that identifies the working days and shifts upon which each specific resource is available.
Resource Calendar
WBS Dictionary
Scope Management Plan
Project Schedule
36. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Pessimistic Duration
Critical Path Activity
Lessons Learned
Procurement Management Plan
37. A hierarchical representation of resources by category and type.
Resource Breakdown Structure
Free Float
Variance at Completion
Progressive Elaboration
38. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
What-If Sce
Portfolio Management
Risk Management Plan
Schedule Model
39. A technique for determining the cause and degree of difference between the baseline and actual performance.
Project Calendar
Variance Analysis
Risk Management Plan
Progressive Elaboration
40. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Constraint
Requirement
Program Management Office
Scope Management Plan
41. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Probability and Impact Matrix
Program Management Office
Opportunity
Budget at Completion
42. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
What-If Sce
Procurement Management Plan
Change Control Board
Human Resource Plan
43. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Program Management
Procurement Management Plan
Path Convergence
Defect Repair
44. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Sponsor
Resource Calendar
Risk Transference
Cost Management Plan
45. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Schedule Model Analysis
Procurement Management Plan
Critical Path
Predecessor Activity
46. A formal proposal to modify any document - deliverable - or baseline.
Project Life Cycle
Change Request
Early Finish Date
Risk Mitigation
47. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Percent Complete
Schedule Model
Late Finish Date
Start-to-Start
48. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Schedule Management Plan
Most Likely Duration
Apportioned Effort
Late Finish Date
49. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Scope Creep
Budget at Completion
Analogous Estimating
Responsibility Assignment Matrix
50. A limiting factor that affects the execution of a project - program - portfolio - or process.
Rolling Wave Planning
Staffing Management Plan
To-Complete Performance Index
Constraint