SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Change Control System
Lead
Early Finish Date
Project Life Cycle
2. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Parametric Estimating
Early Start Date
Finish-to-Start
Predecessor Activity
3. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Control Account
Project Scope Statement
Late Start Date
Critical Path Method
4. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Three-Point Estimate
Responsibility Assignment Matrix
Activity
Program
5. A dependency between two activities - or between an activity and a milestone.
Logical Relationship
Successor Activity
Project Scope
Schedule Management Plan
6. The expected cost to finish all the remaining project work.
Lag
Critical Chain Method
Estimate to Complete
Earned Value
7. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Human Resource Plan
Organizational Process Assets
Forward Pass
Gantt Chart
8. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
S-Curve Analysis
Organizational Project Management Maturity
Preventive Action
Analogous Estimating
9. A relationship in which a schedule activity has more than one predecessor.
Sponsor
Schedule Variance
Path Convergence
Estimate to Complete
10. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Critical Path
Start-to-Finish
Scope Management Plan
Precedence Diagramming Method
11. A calendar that identifies working days and shifts that are available for scheduled activities.
Cost Variance
Project Calendar
Deliverable
Critical Path Activity
12. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Discrete Effort
Portfolio Management
Schedule Performance Index
Effort
13. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Risk Avoidance
Quality Management Plan
Risk Acceptance
Project Phase
14. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Critical Path
Procurement Management Plan
Variance Analysis
Project Calendar
15. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Risk Acceptance
Scope Management Plan
Precedence Diagramming Method
Early Finish Date
16. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Organizational Project Management Maturity
Resource Leveling
Rolling Wave Planning
Analogous Estimating
17. A technique used to shorten the schedule duration without reducing the project scope.
Path Convergence
Schedule Compression
Cost Variance
Communication Management Plan
18. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Portfolio Balancing
Risk Register
Early Finish Date
Decomposition
19. A document in which the results of risk analysis and risk response planning are recorded.
Resource Calendar
What-If Sce
Risk Register
Earned Value
20. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Project Scope Statement
Rolling Wave Planning
Forward Pass
Lag
21. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Analogous Estimating
Probability and Impact Matrix
Total Float
Cost Performance Index
22. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Communication Management Plan
Late Start Date
Corrective Action
Risk Management Plan
23. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Performing Organization
Assumption
Trigger Condition
Estimate to Complete
24. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Assumption
Responsibility Assignment Matrix
Portfolio
Bottom-up Estimating
25. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Risk Acceptance
Risk Management Plan
Three-Point Estimate
Change Control
26. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Schedule Model
Backward Pass
Milestone
Risk Mitigation
27. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Estimate at Completion
Actual Cost
Schedule Performance Index
Procurement Management Plan
28. A graphical representation of the logical relationships among the project schedule activities.
Project Schedule Network Diagram
Project Scope
Organizational Breakdown Structure
Apportioned Effort
29. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Risk Avoidance
Human Resource Plan
Communication Management Plan
Risk
30. A group of related schedule activities aggregated and displayed as a single activity.
Budget at Completion
Schedule Performance Index
Resource Calendar
Summary Activity
31. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Apportioned Effort
Late Start Date
Project
Stakeholder
32. The document that describes how the project will be executed - monitored - and controlled.
Stakeholder
Percent Complete
Project Management Plan
Start-to-Start
33. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Free Float
Secondary Risk
Risk Acceptance
Milestone
34. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Earned Value
Optimistic Duration
Budget at Completion
Parametric Estimating
35. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Change Request
Deliverable
Communication Management Plan
Cost Management Plan
36. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Summary Activity
Requirements Management Plan
Predecessor Activity
Early Finish Date
37. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Project
Trigger Condition
Change Control
Corrective Action
38. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Lead
Level of Effort
Quality Management Plan
Summary Activity
39. A point in time when the status of the project is recorded.
Opportunity
Estimate to Complete
Risk Transference
Data Date
40. A hierarchical representation of risks that is organized according to risk categories.
Risk Breakdown Structure
Critical Path Method
Schedule Model Analysis
Bottom-up Estimating
41. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Risk Avoidance
Stakeholder
Earned Value Management
Decision Tree Analysis
42. A calendar that identifies the working days and shifts upon which each specific resource is available.
Trigger Condition
Analogous Estimating
Preventive Action
Resource Calendar
43. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Requirement
Organizational Breakdown Structure
Gantt Chart
Discrete Effort
44. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Cost Variance
Level of Effort
Risk Mitigation
Sponsor
45. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Late Finish Date
Lag
S-Curve Analysis
Cost Variance
46. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Change Request
Organizational Process Assets
Path Divergence
Project Charter
47. A temporary endeavor undertaken to create a unique product - service - or result.
Secondary Risk
Risk Mitigation
Project
Pessimistic Duration
48. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Risk Category
Constraint
Precedence Diagramming Method
Baseline
49. A significant point or event in a project - program - or portfolio.
Project
Schedule Model Analysis
Threat
Milestone
50. A risk that would have a negative effect on one or more project objectives.
Threat
Predecessor Activity
Risk Category
Enterprise Environmental Factors