SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Activity
Responsibility Assignment Matrix
Portfolio
Three-Point Estimate
2. A hierarchical representation of risks that is organized according to risk categories.
Budget at Completion
Portfolio
Risk Breakdown Structure
Schedule Compression
3. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Risk Mitigation
Control Account
Three-Point Estimate
Enterprise Environmental Factors
4. A graphical representation of the logical relationships among the project schedule activities.
Portfolio Management
Change Request
Project Schedule Network Diagram
Discrete Effort
5. A limiting factor that affects the execution of a project - program - portfolio - or process.
Lag
Constraint
Project Calendar
Organizational Process Assets
6. An intentional activity that realigns the performance of the project work with the project management plan.
Project Life Cycle
Risk Avoidance
Corrective Action
Product Life Cycle
7. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Pessimistic Duration
Portfolio
Project Management Plan
Path Divergence
8. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Parametric Estimating
S-Curve Analysis
Responsibility Assignment Matrix
Change Control System
9. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Schedule Baseline
Path Convergence
Critical Path
Earned Value
10. The measure of work performed expressed in terms of the budget authorized for that work.
Scope Management Plan
Earned Value
Secondary Risk
Preventive Action
11. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Cost Management Plan
Variance at Completion
Predecessor Activity
Risk Transference
12. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Logical Relationship
Path Convergence
Risk
Procurement Management Plan
13. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Change Control Board
Free Float
Baseline
Resource Calendar
14. A relationship in which a schedule activity has more than one predecessor.
Critical Path Activity
Earned Value Management
Risk Acceptance
Path Convergence
15. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Control Account
Successor Activity
Apportioned Effort
Budget at Completion
16. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Defect Repair
Precedence Diagramming Method
Parametric Estimating
Path Divergence
17. A risk that arises as a direct result of implementing a risk response.
Backward Pass
Secondary Risk
Cost Management Plan
Project Manager
18. The work performed to deliver a product - service - or result with the specified features and functions.
Project Scope
Quality Management Plan
Resource Calendar
Project Life Cycle
19. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Probability and Impact Matrix
Fast Tracking
Finish-to-Finish
Staffing Management Plan
20. A group of related schedule activities aggregated and displayed as a single activity.
Three-Point Estimate
Baseline
Summary Activity
Project Phase
21. An event or situation that indicates that a risk is about to occur.
Project Management Office
Summary Activity
Budget at Completion
Trigger Condition
22. A calendar that identifies the working days and shifts upon which each specific resource is available.
Resource Calendar
Critical Path
Resource Leveling
Optimistic Duration
23. A technique for determining the cause and degree of difference between the baseline and actual performance.
Deliverable
Backward Pass
Project Management Office
Variance Analysis
24. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Pessimistic Duration
Risk Category
Change Control Board
Schedule Model Analysis
25. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Product Life Cycle
Procurement Management Plan
Trigger Condition
Organizational Breakdown Structure
26. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Successor Activity
Product Life Cycle
Cost Variance
Critical Chain Method
27. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Total Float
Quality Management Plan
Data Date
Project Schedule
28. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Schedule Management Plan
Risk Mitigation
Effort
Fast Tracking
29. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Predecessor Activity
Estimate at Completion
Code of Accounts
Responsibility Assignment Matrix
30. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Start-to-Finish
Budget at Completion
Risk Transference
Project Management Plan
31. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Acceptance Criteria
Risk Register
Requirements Management Plan
Baseline
32. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Rolling Wave Planning
Change Control System
Level of Effort
Portfolio Management
33. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Program Management Office
Opportunity
Critical Path Method
Predecessor Activity
34. A relationship in which a schedule activity has more than one successor.
Path Divergence
Effort
To-Complete Performance Index
Corrective Action
35. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Risk Category
Risk Breakdown Structure
Schedule Variance
Assumption
36. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Early Finish Date
Decision Tree Analysis
Finish-to-Start
Optimistic Duration
37. A temporary endeavor undertaken to create a unique product - service - or result.
Project
Phase Gate
Risk Acceptance
Earned Value Management
38. The expected cost to finish all the remaining project work.
Estimate to Complete
Procurement Management Plan
Project Charter
Discrete Effort
39. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Path Divergence
Change Control System
Backward Pass
Change Request
40. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Crashing
Actual Cost
Resource Leveling
Total Float
41. A formal proposal to modify any document - deliverable - or baseline.
Schedule Baseline
Scope Management Plan
Change Request
Activity
42. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Critical Chain Method
Procurement Management Plan
Project
Phase Gate
43. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Requirements Management Plan
To-Complete Performance Index
Data Date
Cost Management Plan
44. An intentional activity to modify a nonconforming product or product component.
Defect Repair
Corrective Action
Critical Path Method
Predecessor Activity
45. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Program Management Office
Organizational Breakdown Structure
Scope Management Plan
Schedule Management Plan
46. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Discrete Effort
Finish-to-Finish
Change Control Board
S-Curve Analysis
47. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Sponsor
Quality Management Plan
Acceptance Criteria
Risk Acceptance
48. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Rolling Wave Planning
Optimistic Duration
Budget at Completion
Project Management Plan
49. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Scope Management Plan
Change Control
Portfolio Management
Start-to-Start
50. The series of phases that a project passes through from its initiation to its closure.
Acceptance Criteria
Project Life Cycle
Analogous Estimating
Organizational Process Assets