SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An event or situation that indicates that a risk is about to occur.
Trigger Condition
Earned Value
Path Convergence
Critical Path
2. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Summary Activity
Project Manager
Organizational Project Management Maturity
Change Control
3. A distinct - scheduled portion of work performed during the course of a project.
Activity
Program Management Office
Level of Effort
WBS Dictionary
4. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Three-Point Estimate
Requirements Management Plan
Human Resource Plan
Parametric Estimating
5. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Procurement Management Plan
Communication Management Plan
Budget at Completion
Lag
6. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Lead
Resource Calendar
Code of Accounts
Optimistic Duration
7. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Gantt Chart
Deliverable
Effort
Three-Point Estimate
8. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Earned Value
Program Management
Risk Register
Lessons Learned
9. A hierarchical representation of risks that is organized according to risk categories.
Lessons Learned
Code of Accounts
Risk Breakdown Structure
Data Date
10. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Threat
Stakeholder
What-If Sce
Risk
11. An activity that logically comes before a dependent activity in a schedule.
Schedule Compression
Predecessor Activity
Path Convergence
Variance at Completion
12. A risk that would have a negative effect on one or more project objectives.
Threat
Change Control
Lessons Learned
Portfolio Management
13. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Discrete Effort
Staffing Management Plan
Schedule Baseline
Organizational Breakdown Structure
14. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Defect Repair
Risk Avoidance
Project Scope
Early Start Date
15. The sum of all budgets established for the work to be performed.
Budget at Completion
Project Schedule
Variance Analysis
Requirements Management Plan
16. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Constraint
Project Charter
Stakeholder
Schedule Model Analysis
17. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Risk Transference
Pessimistic Duration
Organizational Process Assets
Risk Acceptance
18. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Communication Management Plan
Control Account
Sponsor
Program Management
19. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Late Start Date
Cost Performance Index
Project
Schedule Model
20. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Requirement
Program Management
Discrete Effort
Data Date
21. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Path Convergence
S-Curve Analysis
Stakeholder
Deliverable
22. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Earned Value Management
Threat
Progressive Elaboration
Procurement Management Plan
23. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Resource Breakdown Structure
Phase Gate
Schedule Variance
Project Schedule
24. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Earned Value Management
Schedule Compression
Bottom-up Estimating
Procurement Management Plan
25. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Estimate to Complete
Scope Creep
Project Schedule Network Diagram
Level of Effort
26. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Critical Chain Method
Risk Transference
Level of Effort
Performing Organization
27. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Project Management Plan
Secondary Risk
Variance Analysis
Critical Path
28. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Schedule Performance Index
Project Management Office
Estimate to Complete
Risk
29. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Path Divergence
Resource Leveling
Start-to-Finish
Predecessor Activity
30. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
To-Complete Performance Index
Apportioned Effort
Resource Leveling
Planned Value
31. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Phase Gate
Communication Management Plan
Scope Management Plan
Risk
32. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Project Management Office
Risk Register
Cost Management Plan
Risk Category
33. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Project Scope Statement
Free Float
Probability and Impact Matrix
Pessimistic Duration
34. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Schedule Variance
Estimate at Completion
Defect Repair
Scope Management Plan
35. A risk that arises as a direct result of implementing a risk response.
Secondary Risk
Pessimistic Duration
Activity
Staffing Management Plan
36. A significant point or event in a project - program - or portfolio.
Cost Management Plan
S-Curve Analysis
Milestone
Free Float
37. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Change Control
Precedence Diagramming Method
Risk Transference
Successor Activity
38. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Performing Organization
Parametric Estimating
Risk Mitigation
Rolling Wave Planning
39. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Project Scope
Procurement Management Plan
Opportunity
Start-to-Finish
40. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Lead
Schedule Baseline
Assumption
Pessimistic Duration
41. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Gantt Chart
Early Finish Date
Requirement
Secondary Risk
42. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Schedule Compression
Project Phase
Schedule Performance Index
Variance at Completion
43. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Resource Leveling
Rolling Wave Planning
Budget at Completion
Late Finish Date
44. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Corrective Action
Rolling Wave Planning
Stakeholder
Gantt Chart
45. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Risk Avoidance
Program
Communication Management Plan
Start-to-Start
46. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Procurement Management Plan
Program Management
Forward Pass
Cost Performance Index
47. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Schedule Model Analysis
Lag
Risk Category
Quality Management Plan
48. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
What-If Sce
Defect Repair
Summary Activity
Decomposition
49. A calendar that identifies working days and shifts that are available for scheduled activities.
Risk Register
Sponsor
Project Calendar
Scope Creep
50. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Secondary Risk
Summary Activity
Control Account
Early Start Date