SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Estimate at Completion
Planned Value
Start-to-Finish
Forward Pass
2. A point in time when the status of the project is recorded.
Discrete Effort
Data Date
Assumption
Risk Mitigation
3. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Change Request
Start-to-Start
Scope Management Plan
Summary Activity
4. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Summary Activity
Scope Baseline
Secondary Risk
Crashing
5. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Risk Register
Parametric Estimating
Resource Calendar
Requirements Traceability Matrix
6. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Stakeholder
Planned Value
Corrective Action
Assumption
7. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Pessimistic Duration
Resource Leveling
Schedule Variance
Summary Activity
8. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Risk Register
Late Start Date
Budget at Completion
Corrective Action
9. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Project Schedule
Scope Baseline
Portfolio
Lead
10. A dependent activity that logically comes after another activity in a schedule.
Risk Acceptance
Successor Activity
Change Control
Forward Pass
11. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Apportioned Effort
Requirements Management Plan
Critical Path
Schedule Compression
12. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Percent Complete
Risk Acceptance
Three-Point Estimate
Lessons Learned
13. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Backward Pass
Critical Path
Risk Mitigation
Project Management
14. A grid that shows the project resources assigned to each work package.
Communication Management Plan
Responsibility Assignment Matrix
Data Date
Crashing
15. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Risk
Lag
Corrective Action
Variance Analysis
16. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Analogous Estimating
Forward Pass
Scope Baseline
Risk
17. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Budget at Completion
Earned Value
Program Management
Cost Performance Index
18. A significant point or event in a project - program - or portfolio.
Milestone
Performing Organization
Project Scope
Change Control
19. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Risk Mitigation
Lessons Learned
Preventive Action
Scope Baseline
20. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Portfolio Balancing
Free Float
Communication Management Plan
Program Management Office
21. Any activity on the critical path in a project schedule.
Scope Management Plan
Critical Path Activity
Risk Management Plan
Apportioned Effort
22. The realized cost incurred for the work performed on an activity during a specific time period.
Actual Cost
Scope Management Plan
Enterprise Environmental Factors
Risk Breakdown Structure
23. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Rolling Wave Planning
Corrective Action
Project Scope Statement
Lead
24. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Project Scope
To-Complete Performance Index
Risk Management Plan
Portfolio Balancing
25. The sum of all budgets established for the work to be performed.
Resource Leveling
Budget at Completion
Project Life Cycle
Schedule Model
26. A formal proposal to modify any document - deliverable - or baseline.
Project Schedule
Early Start Date
Change Request
Organizational Project Management Maturity
27. A risk that would have a negative effect on one or more project objectives.
Decomposition
Threat
Finish-to-Start
What-If Sce
28. A hierarchical representation of risks that is organized according to risk categories.
Summary Activity
Requirements Traceability Matrix
Planned Value
Risk Breakdown Structure
29. An intentional activity that realigns the performance of the project work with the project management plan.
Corrective Action
Total Float
Early Start Date
Schedule Management Plan
30. A risk that would have a positive effect on one or more project objectives.
Fast Tracking
Percent Complete
To-Complete Performance Index
Opportunity
31. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Lessons Learned
Organizational Process Assets
Planned Value
Project Scope
32. A graphical representation of the logical relationships among the project schedule activities.
Project Schedule Network Diagram
Program Management Office
Forward Pass
Requirements Traceability Matrix
33. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Risk Category
Risk Acceptance
Schedule Variance
Finish-to-Start
34. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Lead
Total Float
Risk Management Plan
Stakeholder
35. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
WBS Dictionary
Decision Tree Analysis
Rolling Wave Planning
Risk Breakdown Structure
36. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Finish-to-Finish
Trigger Condition
Discrete Effort
Risk Acceptance
37. The measure of work performed expressed in terms of the budget authorized for that work.
Finish-to-Start
Summary Activity
Milestone
Earned Value
38. A group of related schedule activities aggregated and displayed as a single activity.
Sponsor
Finish-to-Start
Analogous Estimating
Summary Activity
39. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Pessimistic Duration
Decomposition
Communication Management Plan
Three-Point Estimate
40. A calendar that identifies the working days and shifts upon which each specific resource is available.
Communication Management Plan
Resource Calendar
To-Complete Performance Index
Portfolio Balancing
41. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Schedule Baseline
Change Control System
Schedule Compression
Communication Management Plan
42. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Constraint
Schedule Management Plan
Parametric Estimating
Late Start Date
43. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Project Scope Statement
Deliverable
Gantt Chart
Resource Breakdown Structure
44. The authorized budget assigned to scheduled work.
Rolling Wave Planning
Performing Organization
Start-to-Start
Planned Value
45. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Scope Baseline
Risk Transference
Finish-to-Finish
Portfolio
46. An activity that logically comes before a dependent activity in a schedule.
Predecessor Activity
Earned Value Management
Precedence Diagramming Method
Level of Effort
47. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Logical Relationship
Cost Variance
Gantt Chart
Free Float
48. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Portfolio Management
Program Management
Organizational Breakdown Structure
Schedule Performance Index
49. A relationship in which a schedule activity has more than one predecessor.
Critical Path Method
Control Account
Path Convergence
Scope Creep
50. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Scope Baseline
Start-to-Finish
Total Float
Constraint