SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Project Phase
Cost Management Plan
Scope Creep
Actual Cost
2. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Schedule Baseline
Path Divergence
Variance Analysis
Lead
3. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Performing Organization
Start-to-Finish
Project Life Cycle
Resource Leveling
4. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Phase Gate
Parametric Estimating
Enterprise Environmental Factors
Requirement
5. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Variance at Completion
Resource Calendar
Optimistic Duration
Earned Value
6. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Procurement Management Plan
Corrective Action
Discrete Effort
Decomposition
7. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Risk Avoidance
Cost Performance Index
Schedule Performance Index
Lessons Learned
8. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Project Management
Cost Management Plan
Portfolio Balancing
Critical Path Method
9. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Assumption
Percent Complete
Project Life Cycle
Organizational Process Assets
10. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Schedule Baseline
Risk Avoidance
Product Life Cycle
Trigger Condition
11. A limiting factor that affects the execution of a project - program - portfolio - or process.
Organizational Breakdown Structure
Responsibility Assignment Matrix
Phase Gate
Constraint
12. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Project Management
Risk Acceptance
Organizational Project Management Maturity
Critical Path Activity
13. A hierarchical representation of risks that is organized according to risk categories.
Secondary Risk
Resource Breakdown Structure
Risk Breakdown Structure
Late Start Date
14. An event or situation that indicates that a risk is about to occur.
Pessimistic Duration
Trigger Condition
Apportioned Effort
Analogous Estimating
15. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Scope Creep
Project Management Office
Phase Gate
Cost Variance
16. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Preventive Action
Human Resource Plan
Lag
Change Control System
17. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Discrete Effort
Level of Effort
Scope Creep
Risk Register
18. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Program Management Office
Critical Path Method
Critical Path
Milestone
19. The centralized management of one or more portfolios to achieve strategic objectives.
Apportioned Effort
Forward Pass
Portfolio Management
Fast Tracking
20. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Program Management Office
Finish-to-Start
Schedule Model Analysis
Schedule Compression
21. A point in time when the status of the project is recorded.
Secondary Risk
Data Date
Schedule Model Analysis
Baseline
22. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Lessons Learned
Project Manager
Critical Path Method
Total Float
23. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Procurement Management Plan
Fast Tracking
Assumption
Schedule Variance
24. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Progressive Elaboration
Effort
Late Start Date
Project Management Office
25. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Predecessor Activity
Organizational Project Management Maturity
Constraint
Pessimistic Duration
26. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Performing Organization
Baseline
Risk Mitigation
Schedule Variance
27. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Bottom-up Estimating
Program
Effort
Project Calendar
28. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Change Control System
Opportunity
Crashing
Effort
29. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Organizational Process Assets
Control Account
Acceptance Criteria
Apportioned Effort
30. A grid that links product requirements from their origin to the deliverables that satisfy them.
Requirements Traceability Matrix
Project Phase
Change Control Board
Requirements Management Plan
31. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Forward Pass
Progressive Elaboration
Summary Activity
Finish-to-Start
32. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Scope Baseline
Opportunity
Progressive Elaboration
Acceptance Criteria
33. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Cost Performance Index
Analogous Estimating
Schedule Model
Risk Avoidance
34. A group of potential causes of risk.
Schedule Performance Index
What-If Sce
Risk Category
Crashing
35. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Risk Transference
Decomposition
Responsibility Assignment Matrix
Decision Tree Analysis
36. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Control Account
Variance at Completion
To-Complete Performance Index
Level of Effort
37. A distinct - scheduled portion of work performed during the course of a project.
Budget at Completion
Lead
Activity
Rolling Wave Planning
38. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Critical Path Method
Most Likely Duration
Analogous Estimating
Program Management Office
39. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Schedule Compression
Performing Organization
Secondary Risk
Risk
40. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Communication Management Plan
Apportioned Effort
Early Finish Date
Late Start Date
41. A graphical representation of the logical relationships among the project schedule activities.
Project Schedule Network Diagram
Requirements Traceability Matrix
Analogous Estimating
Variance Analysis
42. A hierarchical representation of resources by category and type.
Resource Breakdown Structure
Precedence Diagramming Method
Project Charter
What-If Sce
43. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Lag
Earned Value
Earned Value Management
Communication Management Plan
44. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Planned Value
Free Float
Finish-to-Start
Procurement Management Plan
45. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Project Calendar
Crashing
Fast Tracking
Assumption
46. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Change Control Board
Portfolio Balancing
Code of Accounts
Enterprise Environmental Factors
47. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Organizational Process Assets
Pessimistic Duration
Project Calendar
Project Charter
48. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Project Schedule
Change Control
Successor Activity
Requirements Management Plan
49. A relationship in which a schedule activity has more than one predecessor.
Start-to-Finish
Lessons Learned
Path Convergence
Free Float
50. The document that describes how the project will be executed - monitored - and controlled.
Project Management Plan
Schedule Variance
Planned Value
Program Management