Test your basic knowledge |

PMI Project Management Vocab

Instructions:
  • Answer 50 questions in 15 minutes.
  • If you are not ready to take this test, you can study here.
  • Match each statement with the correct term.
  • Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.

This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.






2. An intentional activity that realigns the performance of the project work with the project management plan.






3. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.






4. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.






5. A technique used to shorten the schedule duration without reducing the project scope.






6. A grid that shows the project resources assigned to each work package.






7. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.






8. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.






9. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.






10. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.






11. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.






12. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.






13. The series of phases that a project passes through from its initiation to its closure.






14. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.






15. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.






16. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.






17. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.






18. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.






19. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.






20. A set of conditions that is required to be met before deliverables are accepted.






21. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.






22. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.






23. An event or situation that indicates that a risk is about to occur.






24. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.






25. A measure of schedule efficiency expressed as the ratio of earned value to planned value.






26. Any activity on the critical path in a project schedule.






27. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.






28. A temporary endeavor undertaken to create a unique product - service - or result.






29. A collection of logically related project activities that culminates in the completion of one or more deliverables.






30. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.






31. A risk that would have a positive effect on one or more project objectives.






32. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.






33. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.






34. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.






35. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.






36. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.






37. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.






38. An enterprise whose personnel are the most directly involved in doing the work of the project or program.






39. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.






40. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.






41. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.






42. A limiting factor that affects the execution of a project - program - portfolio - or process.






43. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.






44. A significant point or event in a project - program - or portfolio.






45. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.






46. A relationship in which a schedule activity has more than one successor.






47. The realized cost incurred for the work performed on an activity during a specific time period.






48. A numbering system used to uniquely identify each component of the work breakdown structure.






49. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.






50. A distinct - scheduled portion of work performed during the course of a project.