SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Bottom-up Estimating
Lessons Learned
Change Control Board
Decomposition
2. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Project Phase
Earned Value Management
Requirement
Discrete Effort
3. A graphical representation of the logical relationships among the project schedule activities.
Project Schedule Network Diagram
Project Management Plan
Fast Tracking
Risk Register
4. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Responsibility Assignment Matrix
Critical Chain Method
Risk Mitigation
Critical Path
5. A dependent activity that logically comes after another activity in a schedule.
Successor Activity
Acceptance Criteria
Schedule Management Plan
Constraint
6. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Scope Management Plan
Fast Tracking
Portfolio Management
Data Date
7. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Product Life Cycle
Most Likely Duration
Stakeholder
Schedule Model Analysis
8. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Project Phase
Scope Creep
Project Calendar
Cost Variance
9. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Rolling Wave Planning
Pessimistic Duration
Planned Value
Three-Point Estimate
10. A calendar that identifies working days and shifts that are available for scheduled activities.
Lag
Phase Gate
Project Calendar
Organizational Process Assets
11. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Project Schedule Network Diagram
Crashing
Finish-to-Start
Probability and Impact Matrix
12. The description of the project scope - major deliverables - assumptions - and constraints.
Project
Schedule Baseline
Project Scope Statement
Acceptance Criteria
13. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Project Scope Statement
Change Control Board
Portfolio Balancing
Lead
14. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Communication Management Plan
Project
Schedule Model Analysis
Performing Organization
15. The realized cost incurred for the work performed on an activity during a specific time period.
Program Management
Actual Cost
Three-Point Estimate
Portfolio Management
16. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Phase Gate
Scope Creep
Schedule Model Analysis
S-Curve Analysis
17. A risk that would have a negative effect on one or more project objectives.
Staffing Management Plan
Forward Pass
Threat
Logical Relationship
18. A document in which the results of risk analysis and risk response planning are recorded.
Human Resource Plan
Change Control Board
Enterprise Environmental Factors
Risk Register
19. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Late Finish Date
Program Management Office
Project Management
Organizational Process Assets
20. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Level of Effort
Earned Value
Project Charter
Schedule Model Analysis
21. A relationship in which a schedule activity has more than one successor.
Critical Chain Method
Path Divergence
Program
WBS Dictionary
22. A technique used to shorten the schedule duration without reducing the project scope.
Effort
Most Likely Duration
Finish-to-Finish
Schedule Compression
23. The centralized management of one or more portfolios to achieve strategic objectives.
Preventive Action
What-If Sce
Portfolio Management
Project Scope Statement
24. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Quality Management Plan
Organizational Project Management Maturity
Organizational Process Assets
Project Management
25. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Project Management Office
Level of Effort
Crashing
Secondary Risk
26. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Stakeholder
S-Curve Analysis
Requirements Management Plan
Organizational Project Management Maturity
27. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Constraint
Project Management Office
Product Life Cycle
WBS Dictionary
28. Any activity on the critical path in a project schedule.
Critical Path Activity
Estimate at Completion
Requirement
Procurement Management Plan
29. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Acceptance Criteria
Variance Analysis
Forward Pass
Project Schedule Network Diagram
30. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Project Schedule
Cost Management Plan
Change Control Board
Risk Register
31. A grid that links product requirements from their origin to the deliverables that satisfy them.
Data Date
Trigger Condition
Communication Management Plan
Requirements Traceability Matrix
32. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Gantt Chart
Project Management Plan
Critical Chain Method
Program
33. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Staffing Management Plan
Scope Baseline
Risk Avoidance
Organizational Project Management Maturity
34. A set of conditions that is required to be met before deliverables are accepted.
Portfolio Balancing
Total Float
Project Life Cycle
Acceptance Criteria
35. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Project Life Cycle
Path Convergence
Bottom-up Estimating
Lag
36. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Threat
Risk Category
Change Control Board
Predecessor Activity
37. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Percent Complete
Start-to-Finish
Lag
Project Management Office
38. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
S-Curve Analysis
Organizational Project Management Maturity
Schedule Compression
Schedule Model
39. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Earned Value
Project Schedule Network Diagram
Total Float
Schedule Compression
40. The measure of work performed expressed in terms of the budget authorized for that work.
Earned Value
Scope Creep
Pessimistic Duration
Backward Pass
41. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Project Management Office
Scope Management Plan
Earned Value Management
Product Life Cycle
42. A grid that shows the project resources assigned to each work package.
Earned Value
Responsibility Assignment Matrix
Control Account
Program
43. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Scope Baseline
Earned Value
Level of Effort
Change Control System
44. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Cost Performance Index
Assumption
Procurement Management Plan
Control Account
45. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Organizational Breakdown Structure
Schedule Performance Index
Critical Path
Project Management
46. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Earned Value
Risk Management Plan
Requirements Management Plan
Schedule Variance
47. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Project Scope Statement
Crashing
Decision Tree Analysis
Resource Leveling
48. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Assumption
Estimate to Complete
Critical Chain Method
Staffing Management Plan
49. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Scope Creep
Earned Value Management
Decomposition
Critical Path Method
50. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Cost Performance Index
Project Calendar
Start-to-Finish
Control Account
Can you answer 50 questions in 15 minutes?
Let me suggest you:
Browse all subjects
Browse all tests
Most popular tests
Major Subjects
Tests & Exams
AP
CLEP
DSST
GRE
SAT
GMAT
Certifications
CISSP go to https://www.isc2.org/
PMP
ITIL
RHCE
MCTS
More...
IT Skills
Android Programming
Data Modeling
Objective C Programming
Basic Python Programming
Adobe Illustrator
More...
Business Skills
Advertising Techniques
Business Accounting Basics
Business Strategy
Human Resource Management
Marketing Basics
More...
Soft Skills
Body Language
People Skills
Public Speaking
Persuasion
Job Hunting And Resumes
More...
Vocabulary
GRE Vocab
SAT Vocab
TOEFL Essential Vocab
Basic English Words For All
Global Words You Should Know
Business English
More...
Languages
AP German Vocab
AP Latin Vocab
SAT Subject Test: French
Italian Survival
Norwegian Survival
More...
Engineering
Audio Engineering
Computer Science Engineering
Aerospace Engineering
Chemical Engineering
Structural Engineering
More...
Health Sciences
Basic Nursing Skills
Health Science Language Fundamentals
Veterinary Technology Medical Language
Cardiology
Clinical Surgery
More...
English
Grammar Fundamentals
Literary And Rhetorical Vocab
Elements Of Style Vocab
Introduction To English Major
Complete Advanced Sentences
Literature
Homonyms
More...
Math
Algebra Formulas
Basic Arithmetic: Measurements
Metric Conversions
Geometric Properties
Important Math Facts
Number Sense Vocab
Business Math
More...
Other Major Subjects
Science
Economics
History
Law
Performing-arts
Cooking
Logic & Reasoning
Trivia
Browse all subjects
Browse all tests
Most popular tests