SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An intentional activity that realigns the performance of the project work with the project management plan.
Decomposition
Program Management Office
Corrective Action
Schedule Model
2. The realized cost incurred for the work performed on an activity during a specific time period.
Early Start Date
Lag
Project Charter
Actual Cost
3. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Start-to-Start
Percent Complete
Enterprise Environmental Factors
Optimistic Duration
4. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Parametric Estimating
Forward Pass
Preventive Action
Free Float
5. An intentional activity to modify a nonconforming product or product component.
Defect Repair
WBS Dictionary
Decision Tree Analysis
Change Control Board
6. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Finish-to-Finish
Forward Pass
Lag
Parametric Estimating
7. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Decomposition
Program
Change Control System
Level of Effort
8. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Change Control System
Critical Path
Change Control
Bottom-up Estimating
9. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Parametric Estimating
Program Management
Requirement
Project Management
10. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Logical Relationship
Deliverable
S-Curve Analysis
Schedule Compression
11. A document in which the results of risk analysis and risk response planning are recorded.
Level of Effort
Activity
Risk Register
Change Control
12. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Acceptance Criteria
Scope Management Plan
Risk Avoidance
Procurement Management Plan
13. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Risk Register
Late Finish Date
Variance at Completion
Enterprise Environmental Factors
14. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Finish-to-Start
Project Phase
Constraint
Organizational Process Assets
15. The authorized budget assigned to scheduled work.
Preventive Action
Variance at Completion
Risk
Planned Value
16. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Baseline
Variance Analysis
Finish-to-Finish
Discrete Effort
17. A risk that arises as a direct result of implementing a risk response.
Secondary Risk
Decision Tree Analysis
Threat
Enterprise Environmental Factors
18. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Lead
Project Management
Defect Repair
Program Management
19. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
To-Complete Performance Index
Discrete Effort
Requirements Traceability Matrix
S-Curve Analysis
20. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Staffing Management Plan
Scope Baseline
Precedence Diagramming Method
Estimate to Complete
21. A technique used to shorten the schedule duration without reducing the project scope.
Schedule Model Analysis
Project Schedule Network Diagram
Free Float
Schedule Compression
22. The expected cost to finish all the remaining project work.
Discrete Effort
Portfolio
Estimate to Complete
Risk Avoidance
23. A grid that shows the project resources assigned to each work package.
Variance Analysis
Responsibility Assignment Matrix
Project Phase
Portfolio Management
24. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Late Finish Date
Project Charter
Gantt Chart
Probability and Impact Matrix
25. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Gantt Chart
Estimate at Completion
Change Request
Cost Variance
26. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Risk Transference
Cost Management Plan
WBS Dictionary
Change Request
27. A significant point or event in a project - program - or portfolio.
Critical Path
Responsibility Assignment Matrix
Milestone
Discrete Effort
28. A risk that would have a negative effect on one or more project objectives.
Threat
Project Calendar
Logical Relationship
Backward Pass
29. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Assumption
Schedule Compression
Acceptance Criteria
Logical Relationship
30. The work performed to deliver a product - service - or result with the specified features and functions.
Assumption
Early Start Date
Project Scope
Scope Baseline
31. A distinct - scheduled portion of work performed during the course of a project.
Activity
Decision Tree Analysis
Project Manager
Requirements Traceability Matrix
32. A group of potential causes of risk.
Risk Category
Resource Calendar
Product Life Cycle
Probability and Impact Matrix
33. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Assumption
Lessons Learned
Risk Avoidance
Lag
34. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Path Divergence
Resource Calendar
Early Start Date
Crashing
35. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Lessons Learned
Summary Activity
Variance Analysis
Risk Category
36. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Gantt Chart
Forward Pass
Free Float
Most Likely Duration
37. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
To-Complete Performance Index
Procurement Management Plan
Schedule Model Analysis
Deliverable
38. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
S-Curve Analysis
Scope Baseline
Activity
Risk Management Plan
39. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Portfolio Management
Requirements Management Plan
Decomposition
Product Life Cycle
40. A limiting factor that affects the execution of a project - program - portfolio - or process.
Stakeholder
Constraint
Data Date
Probability and Impact Matrix
41. A technique for determining the cause and degree of difference between the baseline and actual performance.
Change Control
Late Start Date
Variance at Completion
Variance Analysis
42. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Parametric Estimating
Constraint
Risk Transference
Requirements Management Plan
43. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Sponsor
Variance Analysis
Forward Pass
Opportunity
44. A hierarchical representation of risks that is organized according to risk categories.
Crashing
Risk Breakdown Structure
Organizational Breakdown Structure
What-If Sce
45. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Path Divergence
Earned Value
Summary Activity
Portfolio Balancing
46. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Finish-to-Start
Schedule Management Plan
Variance at Completion
Fast Tracking
47. The document that describes how the project will be executed - monitored - and controlled.
What-If Sce
Project Management Plan
Late Start Date
Project Calendar
48. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Risk Category
Requirements Management Plan
Corrective Action
Forward Pass
49. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Apportioned Effort
Finish-to-Start
Risk Avoidance
Cost Variance
50. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Preventive Action
Constraint
Risk Category
Risk Transference