SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A point in time when the status of the project is recorded.
Quality Management Plan
Data Date
Responsibility Assignment Matrix
Apportioned Effort
2. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Cost Variance
Program Management
Critical Path
Sponsor
3. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Free Float
Earned Value Management
Project Schedule
Cost Performance Index
4. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Decomposition
Trigger Condition
Procurement Management Plan
Pessimistic Duration
5. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Lag
Critical Chain Method
Organizational Project Management Maturity
Code of Accounts
6. A grid that shows the project resources assigned to each work package.
Communication Management Plan
Responsibility Assignment Matrix
Corrective Action
Estimate to Complete
7. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Resource Breakdown Structure
Product Life Cycle
Decision Tree Analysis
Predecessor Activity
8. The work performed to deliver a product - service - or result with the specified features and functions.
Organizational Project Management Maturity
Three-Point Estimate
Project Scope
Schedule Management Plan
9. The authorized budget assigned to scheduled work.
Program Management
Requirement
Assumption
Planned Value
10. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Project Schedule
Program Management
Project Life Cycle
Forward Pass
11. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Variance at Completion
Risk Acceptance
Early Start Date
Baseline
12. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Project Management Plan
Staffing Management Plan
Program
Apportioned Effort
13. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Scope Baseline
Predecessor Activity
Precedence Diagramming Method
Planned Value
14. The measure of work performed expressed in terms of the budget authorized for that work.
Earned Value
Preventive Action
Code of Accounts
Effort
15. An event or situation that indicates that a risk is about to occur.
Trigger Condition
Risk Category
Schedule Compression
Portfolio Management
16. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Procurement Management Plan
Code of Accounts
Portfolio Management
Project Charter
17. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Effort
Portfolio
Actual Cost
Opportunity
18. A relationship in which a schedule activity has more than one successor.
Planned Value
Path Divergence
Effort
Project Schedule
19. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Project Phase
Decomposition
Trigger Condition
Project Scope Statement
20. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Start-to-Finish
Cost Performance Index
What-If Sce
Earned Value
21. A limiting factor that affects the execution of a project - program - portfolio - or process.
Forward Pass
Milestone
Constraint
Estimate to Complete
22. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Forward Pass
Decomposition
Phase Gate
Procurement Management Plan
23. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Preventive Action
Logical Relationship
Stakeholder
Phase Gate
24. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Cost Variance
Preventive Action
Planned Value
Data Date
25. Any activity on the critical path in a project schedule.
Critical Path Activity
Product Life Cycle
Gantt Chart
Secondary Risk
26. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Risk Transference
Risk Management Plan
Assumption
Preventive Action
27. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Change Control Board
Apportioned Effort
Start-to-Start
Free Float
28. The description of the project scope - major deliverables - assumptions - and constraints.
Acceptance Criteria
Milestone
Control Account
Project Scope Statement
29. A technique for determining the cause and degree of difference between the baseline and actual performance.
Optimistic Duration
Secondary Risk
Variance Analysis
Portfolio Management
30. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Organizational Process Assets
Budget at Completion
Cost Management Plan
Change Control
31. A dependency between two activities - or between an activity and a milestone.
Logical Relationship
Finish-to-Start
Free Float
Parametric Estimating
32. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Lag
Critical Path
Lessons Learned
Portfolio Balancing
33. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
WBS Dictionary
Change Request
Forward Pass
Preventive Action
34. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Critical Path Activity
Control Account
Project Manager
Risk Breakdown Structure
35. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Risk Mitigation
Summary Activity
Estimate to Complete
Requirements Management Plan
36. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Forward Pass
Requirements Traceability Matrix
Precedence Diagramming Method
Organizational Process Assets
37. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Estimate at Completion
Change Control System
Free Float
Start-to-Start
38. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Path Divergence
Cost Management Plan
Trigger Condition
Change Control
39. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Earned Value Management
Schedule Model Analysis
WBS Dictionary
Baseline
40. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
What-If Sce
To-Complete Performance Index
Cost Performance Index
Earned Value Management
41. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Acceptance Criteria
Project Schedule Network Diagram
Free Float
Risk
42. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
What-If Sce
Critical Chain Method
Project Manager
Opportunity
43. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Enterprise Environmental Factors
Probability and Impact Matrix
Change Control Board
Schedule Management Plan
44. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Project Phase
Level of Effort
Bottom-up Estimating
Start-to-Finish
45. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Program Management
Risk Register
Opportunity
Critical Path Method
46. A calendar that identifies the working days and shifts upon which each specific resource is available.
Project Charter
Backward Pass
Lessons Learned
Resource Calendar
47. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Program Management
Discrete Effort
Parametric Estimating
Analogous Estimating
48. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Project Calendar
Project Management
Resource Breakdown Structure
Crashing
49. The document that describes how the project will be executed - monitored - and controlled.
Project Charter
Earned Value
Project Management Plan
WBS Dictionary
50. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Scope Creep
Resource Breakdown Structure
Portfolio Management
Start-to-Finish