SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Predecessor Activity
Change Control Board
Organizational Project Management Maturity
Scope Baseline
2. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Product Life Cycle
Procurement Management Plan
Human Resource Plan
Program
3. The series of phases that a project passes through from its initiation to its closure.
Schedule Variance
Project Life Cycle
Scope Management Plan
Optimistic Duration
4. The measure of work performed expressed in terms of the budget authorized for that work.
Earned Value
Lead
Schedule Performance Index
Critical Path
5. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Crashing
Backward Pass
Change Request
Project Charter
6. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Risk Acceptance
Total Float
Project Scope
Quality Management Plan
7. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Bottom-up Estimating
Change Control System
Critical Chain Method
Communication Management Plan
8. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Risk Register
Cost Performance Index
Baseline
Late Finish Date
9. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Phase Gate
Human Resource Plan
WBS Dictionary
Project Phase
10. A relationship in which a schedule activity has more than one successor.
Portfolio Balancing
Deliverable
Product Life Cycle
Path Divergence
11. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Fast Tracking
Lead
Precedence Diagramming Method
Risk
12. A technique for determining the cause and degree of difference between the baseline and actual performance.
Schedule Performance Index
Start-to-Finish
Variance Analysis
Variance at Completion
13. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Early Start Date
Late Start Date
Project Life Cycle
Forward Pass
14. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Critical Path Activity
Precedence Diagramming Method
Three-Point Estimate
Decomposition
15. A limiting factor that affects the execution of a project - program - portfolio - or process.
Constraint
Predecessor Activity
Budget at Completion
Corrective Action
16. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Sponsor
Risk Breakdown Structure
S-Curve Analysis
Three-Point Estimate
17. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Schedule Baseline
Project
Gantt Chart
Successor Activity
18. A technique used to shorten the schedule duration without reducing the project scope.
Schedule Compression
Risk
Lessons Learned
Project Schedule Network Diagram
19. A group of potential causes of risk.
Trigger Condition
Resource Calendar
Risk Category
Project
20. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Finish-to-Start
Project Life Cycle
Program
Total Float
21. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Early Finish Date
Fast Tracking
Actual Cost
Communication Management Plan
22. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Schedule Performance Index
Preventive Action
Activity
Organizational Breakdown Structure
23. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Three-Point Estimate
Precedence Diagramming Method
Risk Avoidance
Critical Chain Method
24. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
What-If Sce
Start-to-Finish
Schedule Compression
Percent Complete
25. A risk that would have a positive effect on one or more project objectives.
Change Control System
Opportunity
Predecessor Activity
Risk Breakdown Structure
26. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Earned Value Management
Summary Activity
Requirements Management Plan
Critical Path
27. A calendar that identifies working days and shifts that are available for scheduled activities.
Sponsor
Critical Path
Project Calendar
Cost Management Plan
28. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Finish-to-Start
Risk Acceptance
Early Start Date
Requirements Management Plan
29. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Early Finish Date
Product Life Cycle
Risk Management Plan
Cost Performance Index
30. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Project Life Cycle
Cost Management Plan
Finish-to-Start
Effort
31. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Change Control
Program Management Office
Program Management
Percent Complete
32. A significant point or event in a project - program - or portfolio.
Start-to-Finish
Milestone
Data Date
Project Scope Statement
33. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Effort
Portfolio
Schedule Baseline
Control Account
34. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Start-to-Start
Stakeholder
Probability and Impact Matrix
Staffing Management Plan
35. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Earned Value Management
Finish-to-Finish
Baseline
Requirements Management Plan
36. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Requirements Traceability Matrix
Risk Management Plan
Lag
Project Manager
37. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Enterprise Environmental Factors
Planned Value
Late Start Date
Resource Leveling
38. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Start-to-Start
Scope Creep
Estimate at Completion
Logical Relationship
39. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Change Control System
Opportunity
Fast Tracking
Forward Pass
40. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Preventive Action
Three-Point Estimate
Start-to-Start
Resource Leveling
41. A grid that links product requirements from their origin to the deliverables that satisfy them.
Variance Analysis
Responsibility Assignment Matrix
Critical Path Activity
Requirements Traceability Matrix
42. A group of related schedule activities aggregated and displayed as a single activity.
Three-Point Estimate
Summary Activity
S-Curve Analysis
Lessons Learned
43. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Resource Leveling
Schedule Management Plan
Earned Value
Product Life Cycle
44. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Requirement
Program Management Office
Secondary Risk
Actual Cost
45. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Preventive Action
Schedule Variance
Resource Calendar
Finish-to-Finish
46. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Activity
Program Management Office
Schedule Baseline
Decision Tree Analysis
47. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Secondary Risk
Resource Calendar
Phase Gate
Requirements Management Plan
48. A numbering system used to uniquely identify each component of the work breakdown structure.
Lag
Code of Accounts
Risk Transference
Resource Breakdown Structure
49. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Optimistic Duration
Risk Acceptance
Start-to-Finish
Risk Transference
50. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Activity
Critical Path Method
Procurement Management Plan
Resource Leveling