SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Earned Value Management
Preventive Action
Data Date
Most Likely Duration
2. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Start-to-Finish
Project Manager
Finish-to-Finish
Risk Avoidance
3. A relationship in which a schedule activity has more than one successor.
Path Divergence
Lead
Total Float
Free Float
4. A calendar that identifies the working days and shifts upon which each specific resource is available.
Resource Calendar
Project Schedule Network Diagram
Lead
Analogous Estimating
5. A grid that links product requirements from their origin to the deliverables that satisfy them.
Lag
Activity
Requirements Traceability Matrix
Code of Accounts
6. A temporary endeavor undertaken to create a unique product - service - or result.
Level of Effort
Project
Schedule Compression
Requirements Management Plan
7. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Cost Performance Index
Early Finish Date
Project Scope Statement
Variance at Completion
8. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Finish-to-Finish
Communication Management Plan
WBS Dictionary
Project Schedule
9. The document that describes how the project will be executed - monitored - and controlled.
Project Management Plan
Code of Accounts
Estimate to Complete
Schedule Baseline
10. A grid that shows the project resources assigned to each work package.
Responsibility Assignment Matrix
Corrective Action
WBS Dictionary
Change Request
11. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Most Likely Duration
Forward Pass
Planned Value
Organizational Breakdown Structure
12. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Procurement Management Plan
Path Divergence
Estimate at Completion
Level of Effort
13. The expected cost to finish all the remaining project work.
Staffing Management Plan
Change Control Board
Estimate to Complete
Resource Calendar
14. The work performed to deliver a product - service - or result with the specified features and functions.
Project Life Cycle
Activity
Successor Activity
Project Scope
15. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Apportioned Effort
Responsibility Assignment Matrix
Path Divergence
Project Management Office
16. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Responsibility Assignment Matrix
Three-Point Estimate
Program
Summary Activity
17. A risk that would have a positive effect on one or more project objectives.
Preventive Action
Critical Path Activity
Opportunity
Project
18. A technique for determining the cause and degree of difference between the baseline and actual performance.
Risk Transference
Variance Analysis
Human Resource Plan
Trigger Condition
19. The measure of work performed expressed in terms of the budget authorized for that work.
Quality Management Plan
Cost Performance Index
Bottom-up Estimating
Earned Value
20. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Project Schedule
Opportunity
Organizational Breakdown Structure
Human Resource Plan
21. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Project Charter
Activity
Path Convergence
Critical Chain Method
22. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Pessimistic Duration
Early Start Date
Critical Chain Method
Critical Path Method
23. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Program Management
Human Resource Plan
Actual Cost
Schedule Model Analysis
24. A numbering system used to uniquely identify each component of the work breakdown structure.
Portfolio
Code of Accounts
Preventive Action
Trigger Condition
25. A risk that would have a negative effect on one or more project objectives.
Threat
Late Start Date
Optimistic Duration
Planned Value
26. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Project Manager
Scope Baseline
Finish-to-Finish
Critical Path Method
27. A set of conditions that is required to be met before deliverables are accepted.
Project Phase
Quality Management Plan
Requirements Traceability Matrix
Acceptance Criteria
28. An activity that logically comes before a dependent activity in a schedule.
Discrete Effort
Predecessor Activity
Apportioned Effort
Early Finish Date
29. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Lessons Learned
Logical Relationship
Product Life Cycle
Crashing
30. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Schedule Variance
Budget at Completion
Successor Activity
Project Management Plan
31. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Portfolio
Late Finish Date
Project Schedule
Critical Path
32. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Communication Management Plan
Assumption
Free Float
Earned Value Management
33. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Change Control System
Summary Activity
Parametric Estimating
Product Life Cycle
34. An event or situation that indicates that a risk is about to occur.
Organizational Process Assets
Constraint
Enterprise Environmental Factors
Trigger Condition
35. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Schedule Variance
Risk Register
Variance Analysis
Apportioned Effort
36. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Late Finish Date
Estimate to Complete
Analogous Estimating
Resource Leveling
37. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Three-Point Estimate
Program Management
Early Start Date
Project Management Office
38. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Product Life Cycle
Decomposition
Late Start Date
Logical Relationship
39. The centralized management of one or more portfolios to achieve strategic objectives.
Scope Creep
Portfolio Management
Level of Effort
Parametric Estimating
40. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Earned Value
Change Control
Level of Effort
Resource Breakdown Structure
41. A risk that arises as a direct result of implementing a risk response.
Secondary Risk
Start-to-Finish
Opportunity
Earned Value
42. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Late Finish Date
Change Request
S-Curve Analysis
Variance Analysis
43. The realized cost incurred for the work performed on an activity during a specific time period.
Actual Cost
Cost Management Plan
Procurement Management Plan
Parametric Estimating
44. The authorized budget assigned to scheduled work.
Cost Variance
Program Management Office
Human Resource Plan
Planned Value
45. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Change Control
Estimate at Completion
Backward Pass
Schedule Compression
46. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Deliverable
Organizational Process Assets
Lead
Successor Activity
47. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Cost Performance Index
Precedence Diagramming Method
Program Management Office
Program Management
48. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Phase Gate
Program Management
Portfolio Balancing
Late Start Date
49. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Assumption
Defect Repair
Organizational Breakdown Structure
Program Management
50. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Risk Breakdown Structure
Start-to-Start
Pessimistic Duration
Change Control Board