SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A point in time when the status of the project is recorded.
Requirement
Control Account
Data Date
Most Likely Duration
2. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Critical Path
Estimate at Completion
Early Finish Date
Lag
3. A risk that arises as a direct result of implementing a risk response.
Predecessor Activity
Project
Trigger Condition
Secondary Risk
4. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Risk Transference
Milestone
Communication Management Plan
Summary Activity
5. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Phase Gate
Project Management Plan
Effort
Performing Organization
6. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Precedence Diagramming Method
Project Management Office
Successor Activity
Early Start Date
7. A set of conditions that is required to be met before deliverables are accepted.
Planned Value
Acceptance Criteria
Project
Probability and Impact Matrix
8. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Cost Variance
Risk Acceptance
Critical Chain Method
Acceptance Criteria
9. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Progressive Elaboration
Staffing Management Plan
To-Complete Performance Index
Analogous Estimating
10. A limiting factor that affects the execution of a project - program - portfolio - or process.
Total Float
Organizational Breakdown Structure
Constraint
Program Management
11. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Backward Pass
Project Schedule
Lead
Performing Organization
12. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Precedence Diagramming Method
Resource Breakdown Structure
Requirement
S-Curve Analysis
13. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Start-to-Finish
Parametric Estimating
WBS Dictionary
Communication Management Plan
14. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Enterprise Environmental Factors
Trigger Condition
Baseline
Activity
15. The description of the project scope - major deliverables - assumptions - and constraints.
Project Schedule
Start-to-Start
Project Scope Statement
Resource Leveling
16. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Resource Calendar
Cost Performance Index
Probability and Impact Matrix
Progressive Elaboration
17. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Variance Analysis
Corrective Action
WBS Dictionary
Assumption
18. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
What-If Sce
Scope Management Plan
Staffing Management Plan
Risk Category
19. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Opportunity
Defect Repair
Risk
Schedule Baseline
20. A relationship in which a schedule activity has more than one successor.
Cost Performance Index
Early Start Date
Path Divergence
Baseline
21. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Portfolio Management
Start-to-Start
Estimate at Completion
Data Date
22. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Most Likely Duration
Portfolio
Activity
Project Phase
23. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Procurement Management Plan
Risk Breakdown Structure
Lag
Variance Analysis
24. A hierarchical representation of resources by category and type.
Successor Activity
Resource Breakdown Structure
Requirements Management Plan
Secondary Risk
25. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Project Charter
Trigger Condition
Lead
Forward Pass
26. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Scope Creep
Cost Variance
Change Control Board
Portfolio Balancing
27. A numbering system used to uniquely identify each component of the work breakdown structure.
Code of Accounts
To-Complete Performance Index
Optimistic Duration
Project Manager
28. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Percent Complete
Late Start Date
Schedule Compression
Finish-to-Finish
29. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Requirements Management Plan
Apportioned Effort
Finish-to-Start
Progressive Elaboration
30. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Effort
Phase Gate
Requirements Management Plan
Estimate to Complete
31. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Staffing Management Plan
Decomposition
Rolling Wave Planning
Organizational Process Assets
32. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Change Control
Pessimistic Duration
Data Date
Preventive Action
33. An intentional activity to modify a nonconforming product or product component.
Project Management
Risk
Defect Repair
Gantt Chart
34. A hierarchical representation of risks that is organized according to risk categories.
Portfolio Balancing
Risk Breakdown Structure
Lag
Organizational Breakdown Structure
35. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Variance at Completion
Control Account
Project Scope
Backward Pass
36. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Program Management Office
Activity
Schedule Performance Index
Gantt Chart
37. The centralized management of one or more portfolios to achieve strategic objectives.
Critical Path
Analogous Estimating
Portfolio Management
Project Management Office
38. A technique used to shorten the schedule duration without reducing the project scope.
Path Convergence
Probability and Impact Matrix
Scope Creep
Schedule Compression
39. An activity that logically comes before a dependent activity in a schedule.
Predecessor Activity
Free Float
Lead
Enterprise Environmental Factors
40. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Earned Value Management
Variance Analysis
Three-Point Estimate
Variance at Completion
41. A dependent activity that logically comes after another activity in a schedule.
Path Divergence
Schedule Compression
Successor Activity
Milestone
42. A risk that would have a negative effect on one or more project objectives.
Risk Register
Threat
Path Convergence
Finish-to-Finish
43. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Critical Path
Fast Tracking
Code of Accounts
Quality Management Plan
44. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Project Management Plan
Project
Risk Avoidance
Optimistic Duration
45. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Human Resource Plan
Schedule Variance
Early Start Date
Level of Effort
46. A dependency between two activities - or between an activity and a milestone.
Gantt Chart
Actual Cost
Risk Avoidance
Logical Relationship
47. A distinct - scheduled portion of work performed during the course of a project.
Pessimistic Duration
Activity
Schedule Baseline
Risk Transference
48. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Deliverable
Critical Path
Project Phase
Actual Cost
49. A relationship in which a schedule activity has more than one predecessor.
Path Convergence
Analogous Estimating
Late Start Date
Organizational Breakdown Structure
50. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
WBS Dictionary
Organizational Process Assets
Most Likely Duration
Critical Chain Method