SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An event or situation that indicates that a risk is about to occur.
Responsibility Assignment Matrix
Change Control System
Trigger Condition
Schedule Baseline
2. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Risk Category
Change Control
Organizational Project Management Maturity
Project Charter
3. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Level of Effort
Forward Pass
Portfolio Management
Most Likely Duration
4. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Optimistic Duration
Human Resource Plan
Change Request
Start-to-Start
5. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Three-Point Estimate
Scope Creep
Sponsor
Gantt Chart
6. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Schedule Model
Corrective Action
Trigger Condition
Risk Acceptance
7. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Probability and Impact Matrix
Corrective Action
Risk
Schedule Variance
8. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Opportunity
Assumption
Analogous Estimating
Risk Acceptance
9. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Earned Value Management
Budget at Completion
Variance Analysis
Assumption
10. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Control Account
Path Divergence
Secondary Risk
Level of Effort
11. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Logical Relationship
Risk Avoidance
Organizational Project Management Maturity
Portfolio Management
12. The work performed to deliver a product - service - or result with the specified features and functions.
Staffing Management Plan
Project Scope
Requirements Traceability Matrix
Secondary Risk
13. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Resource Breakdown Structure
Cost Management Plan
Schedule Performance Index
Portfolio Balancing
14. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Estimate at Completion
Optimistic Duration
Critical Chain Method
Schedule Variance
15. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Decision Tree Analysis
Early Start Date
Scope Creep
Quality Management Plan
16. The measure of work performed expressed in terms of the budget authorized for that work.
Activity
Rolling Wave Planning
Start-to-Finish
Earned Value
17. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Path Divergence
Late Finish Date
Free Float
Change Request
18. A document in which the results of risk analysis and risk response planning are recorded.
Total Float
Optimistic Duration
Risk Register
Risk Transference
19. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Schedule Management Plan
What-If Sce
Budget at Completion
Project Manager
20. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Project Calendar
Requirement
Schedule Baseline
Finish-to-Finish
21. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Finish-to-Start
Procurement Management Plan
Program Management Office
Portfolio Balancing
22. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Threat
Pessimistic Duration
Risk Acceptance
Scope Management Plan
23. A risk that arises as a direct result of implementing a risk response.
Threat
Cost Variance
Secondary Risk
Enterprise Environmental Factors
24. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
What-If Sce
Summary Activity
Variance Analysis
Three-Point Estimate
25. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Analogous Estimating
Percent Complete
Schedule Baseline
Critical Path
26. A risk that would have a negative effect on one or more project objectives.
Threat
Phase Gate
Staffing Management Plan
Organizational Project Management Maturity
27. A limiting factor that affects the execution of a project - program - portfolio - or process.
Constraint
Risk
Path Divergence
Corrective Action
28. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Resource Calendar
Crashing
Requirements Management Plan
Organizational Project Management Maturity
29. A risk that would have a positive effect on one or more project objectives.
Portfolio
Resource Breakdown Structure
Opportunity
Critical Path
30. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Cost Performance Index
Lead
Estimate to Complete
Finish-to-Start
31. The authorized budget assigned to scheduled work.
Product Life Cycle
Stakeholder
Planned Value
To-Complete Performance Index
32. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Forward Pass
Schedule Baseline
Quality Management Plan
Progressive Elaboration
33. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Risk
Requirements Management Plan
Portfolio
Schedule Performance Index
34. A grid that links product requirements from their origin to the deliverables that satisfy them.
Finish-to-Start
Start-to-Finish
Requirements Traceability Matrix
Milestone
35. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Effort
Critical Path Activity
Project Calendar
Schedule Management Plan
36. A group of related schedule activities aggregated and displayed as a single activity.
Progressive Elaboration
Schedule Model Analysis
Summary Activity
Risk Management Plan
37. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Schedule Variance
Three-Point Estimate
Project Management Office
Crashing
38. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Resource Calendar
Quality Management Plan
Program
Portfolio
39. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Requirement
Trigger Condition
Total Float
Scope Baseline
40. A significant point or event in a project - program - or portfolio.
Secondary Risk
Fast Tracking
Milestone
Lag
41. An activity that logically comes before a dependent activity in a schedule.
Project Calendar
Constraint
Summary Activity
Predecessor Activity
42. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Probability and Impact Matrix
Change Control
Earned Value Management
Change Request
43. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Early Start Date
Schedule Model
Total Float
Backward Pass
44. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Corrective Action
Organizational Project Management Maturity
Cost Performance Index
Constraint
45. A distinct - scheduled portion of work performed during the course of a project.
Schedule Performance Index
Activity
Communication Management Plan
Code of Accounts
46. The realized cost incurred for the work performed on an activity during a specific time period.
Variance Analysis
Program Management Office
Cost Performance Index
Actual Cost
47. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Resource Leveling
Critical Path Method
Late Finish Date
Path Divergence
48. A hierarchical representation of risks that is organized according to risk categories.
Risk Breakdown Structure
Schedule Performance Index
Constraint
Progressive Elaboration
49. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Parametric Estimating
WBS Dictionary
Project Life Cycle
Forward Pass
50. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Enterprise Environmental Factors
Risk Category
To-Complete Performance Index
Human Resource Plan
Sorry!:) No result found.
Can you answer 50 questions in 15 minutes?
Let me suggest you:
Browse all subjects
Browse all tests
Most popular tests
Major Subjects
Tests & Exams
AP
CLEP
DSST
GRE
SAT
GMAT
Certifications
CISSP go to https://www.isc2.org/
PMP
ITIL
RHCE
MCTS
More...
IT Skills
Android Programming
Data Modeling
Objective C Programming
Basic Python Programming
Adobe Illustrator
More...
Business Skills
Advertising Techniques
Business Accounting Basics
Business Strategy
Human Resource Management
Marketing Basics
More...
Soft Skills
Body Language
People Skills
Public Speaking
Persuasion
Job Hunting And Resumes
More...
Vocabulary
GRE Vocab
SAT Vocab
TOEFL Essential Vocab
Basic English Words For All
Global Words You Should Know
Business English
More...
Languages
AP German Vocab
AP Latin Vocab
SAT Subject Test: French
Italian Survival
Norwegian Survival
More...
Engineering
Audio Engineering
Computer Science Engineering
Aerospace Engineering
Chemical Engineering
Structural Engineering
More...
Health Sciences
Basic Nursing Skills
Health Science Language Fundamentals
Veterinary Technology Medical Language
Cardiology
Clinical Surgery
More...
English
Grammar Fundamentals
Literary And Rhetorical Vocab
Elements Of Style Vocab
Introduction To English Major
Complete Advanced Sentences
Literature
Homonyms
More...
Math
Algebra Formulas
Basic Arithmetic: Measurements
Metric Conversions
Geometric Properties
Important Math Facts
Number Sense Vocab
Business Math
More...
Other Major Subjects
Science
Economics
History
Law
Performing-arts
Cooking
Logic & Reasoning
Trivia
Browse all subjects
Browse all tests
Most popular tests