SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Constraint
Decomposition
Risk Management Plan
Optimistic Duration
2. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Probability and Impact Matrix
Change Control
Scope Baseline
Logical Relationship
3. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Change Control
Resource Calendar
Summary Activity
Cost Performance Index
4. A significant point or event in a project - program - or portfolio.
Milestone
Defect Repair
Most Likely Duration
Critical Path
5. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Human Resource Plan
Early Start Date
Variance at Completion
Percent Complete
6. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Variance at Completion
Project Calendar
Parametric Estimating
Finish-to-Finish
7. A relationship in which a schedule activity has more than one successor.
Project Calendar
Path Divergence
Schedule Baseline
Pessimistic Duration
8. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Earned Value
Activity
Project Management Plan
Organizational Process Assets
9. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Risk Transference
Program
Assumption
Baseline
10. The expected cost to finish all the remaining project work.
Project Scope
Estimate to Complete
Risk Breakdown Structure
Logical Relationship
11. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Decomposition
Critical Path Method
Organizational Breakdown Structure
Finish-to-Finish
12. A calendar that identifies the working days and shifts upon which each specific resource is available.
Resource Calendar
Quality Management Plan
Fast Tracking
Start-to-Finish
13. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Stakeholder
Pessimistic Duration
Critical Path Method
Responsibility Assignment Matrix
14. The measure of work performed expressed in terms of the budget authorized for that work.
Critical Chain Method
Portfolio
Earned Value
Risk Category
15. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Lag
Baseline
Schedule Management Plan
Estimate to Complete
16. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Baseline
Apportioned Effort
Project Charter
Scope Baseline
17. An event or situation that indicates that a risk is about to occur.
WBS Dictionary
Trigger Condition
Start-to-Finish
Risk Category
18. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Three-Point Estimate
Schedule Model
Risk Mitigation
Change Control
19. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Risk Category
Project Management
Stakeholder
Program
20. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Schedule Model
Acceptance Criteria
Schedule Compression
Late Finish Date
21. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Risk Acceptance
Acceptance Criteria
Predecessor Activity
Summary Activity
22. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Schedule Model Analysis
To-Complete Performance Index
Critical Path
Requirements Traceability Matrix
23. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Analogous Estimating
Stakeholder
Variance at Completion
Milestone
24. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Organizational Breakdown Structure
Critical Path
Schedule Baseline
Code of Accounts
25. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Baseline
Scope Management Plan
Critical Path
Requirements Traceability Matrix
26. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Human Resource Plan
Forward Pass
Change Control Board
Portfolio
27. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Lag
Total Float
Cost Performance Index
Critical Path Method
28. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Risk Mitigation
Effort
Performing Organization
Critical Chain Method
29. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Project Schedule
Finish-to-Finish
Early Finish Date
Communication Management Plan
30. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Level of Effort
Schedule Performance Index
Early Start Date
Bottom-up Estimating
31. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Portfolio Management
Cost Performance Index
Apportioned Effort
Start-to-Start
32. A relationship in which a schedule activity has more than one predecessor.
Project Scope Statement
Scope Creep
Path Convergence
Project Phase
33. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Fast Tracking
Deliverable
Threat
Program
34. A limiting factor that affects the execution of a project - program - portfolio - or process.
Change Control
Secondary Risk
Activity
Constraint
35. A risk that would have a negative effect on one or more project objectives.
Data Date
Earned Value Management
Program
Threat
36. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Free Float
WBS Dictionary
Risk Management Plan
Requirement
37. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Data Date
Project Scope
Enterprise Environmental Factors
Change Control
38. A distinct - scheduled portion of work performed during the course of a project.
Change Control System
Most Likely Duration
Program Management
Activity
39. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Risk Register
What-If Sce
Schedule Performance Index
Project Schedule
40. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Finish-to-Finish
Resource Breakdown Structure
Finish-to-Start
Requirements Traceability Matrix
41. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Planned Value
Risk Avoidance
S-Curve Analysis
Human Resource Plan
42. The sum of all budgets established for the work to be performed.
Scope Creep
Schedule Variance
Budget at Completion
Organizational Process Assets
43. A group of related schedule activities aggregated and displayed as a single activity.
Predecessor Activity
Project Management Office
Summary Activity
Project Management
44. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
WBS Dictionary
Precedence Diagramming Method
Level of Effort
Opportunity
45. A group of potential causes of risk.
Organizational Process Assets
Portfolio Balancing
WBS Dictionary
Risk Category
46. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Path Convergence
Code of Accounts
Scope Baseline
Project Management
47. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Bottom-up Estimating
Most Likely Duration
Deliverable
Enterprise Environmental Factors
48. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Cost Performance Index
Cost Variance
Trigger Condition
S-Curve Analysis
49. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Performing Organization
Optimistic Duration
Budget at Completion
Cost Performance Index
50. An intentional activity that realigns the performance of the project work with the project management plan.
Resource Breakdown Structure
Portfolio Balancing
Deliverable
Corrective Action