SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The sum of all budgets established for the work to be performed.
Budget at Completion
Deliverable
Program Management Office
Risk
2. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Total Float
Scope Management Plan
Late Start Date
Cost Performance Index
3. A risk that would have a negative effect on one or more project objectives.
Earned Value Management
Deliverable
Critical Path Activity
Threat
4. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Resource Calendar
Scope Creep
Decomposition
Actual Cost
5. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Code of Accounts
Most Likely Duration
Portfolio
Successor Activity
6. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Organizational Project Management Maturity
Baseline
Change Request
Actual Cost
7. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Decomposition
Rolling Wave Planning
Activity
Forward Pass
8. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Lead
Analogous Estimating
Program Management Office
Phase Gate
9. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Project Scope Statement
Path Convergence
Cost Performance Index
Product Life Cycle
10. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Project Manager
Secondary Risk
Apportioned Effort
Finish-to-Finish
11. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Quality Management Plan
Preventive Action
Responsibility Assignment Matrix
Organizational Project Management Maturity
12. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Scope Management Plan
Risk Breakdown Structure
Requirement
Backward Pass
13. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Decomposition
Cost Performance Index
Lead
Risk
14. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Three-Point Estimate
Bottom-up Estimating
Program
Staffing Management Plan
15. An activity that logically comes before a dependent activity in a schedule.
Late Start Date
Human Resource Plan
Predecessor Activity
Scope Management Plan
16. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
S-Curve Analysis
Earned Value Management
Probability and Impact Matrix
Resource Calendar
17. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Precedence Diagramming Method
Pessimistic Duration
Cost Management Plan
Schedule Model Analysis
18. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Risk Avoidance
Bottom-up Estimating
Pessimistic Duration
Progressive Elaboration
19. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Baseline
Estimate at Completion
Scope Creep
Start-to-Start
20. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Late Finish Date
Crashing
Free Float
Deliverable
21. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Earned Value
Probability and Impact Matrix
Procurement Management Plan
Late Start Date
22. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Enterprise Environmental Factors
Estimate to Complete
Earned Value Management
Precedence Diagramming Method
23. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Earned Value Management
Finish-to-Start
Change Control
Scope Baseline
24. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Optimistic Duration
Product Life Cycle
Responsibility Assignment Matrix
Human Resource Plan
25. The expected cost to finish all the remaining project work.
Change Control
Risk Register
Estimate to Complete
Schedule Compression
26. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Project Charter
Baseline
Successor Activity
Late Start Date
27. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Lessons Learned
Code of Accounts
Schedule Model
Requirements Management Plan
28. An intentional activity to modify a nonconforming product or product component.
Forward Pass
Change Control Board
Defect Repair
Project Scope
29. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Summary Activity
Risk Transference
Analogous Estimating
Acceptance Criteria
30. A group of related schedule activities aggregated and displayed as a single activity.
Risk
Cost Performance Index
Early Finish Date
Summary Activity
31. An intentional activity that realigns the performance of the project work with the project management plan.
Apportioned Effort
Critical Path Method
Corrective Action
Earned Value
32. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Probability and Impact Matrix
Lessons Learned
Project Management Office
Late Finish Date
33. The document that describes how the project will be executed - monitored - and controlled.
Risk Acceptance
Acceptance Criteria
Resource Calendar
Project Management Plan
34. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
WBS Dictionary
Finish-to-Start
Estimate to Complete
Enterprise Environmental Factors
35. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Backward Pass
Project Manager
Schedule Model
Scope Creep
36. A graphical representation of the logical relationships among the project schedule activities.
Fast Tracking
Portfolio Management
Pessimistic Duration
Project Schedule Network Diagram
37. A temporary endeavor undertaken to create a unique product - service - or result.
Total Float
Estimate at Completion
Project
Performing Organization
38. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Responsibility Assignment Matrix
Percent Complete
Resource Breakdown Structure
Activity
39. A relationship in which a schedule activity has more than one successor.
Project Life Cycle
Cost Performance Index
Summary Activity
Path Divergence
40. Any activity on the critical path in a project schedule.
Scope Creep
Critical Path Activity
Optimistic Duration
Earned Value
41. A risk that arises as a direct result of implementing a risk response.
Decomposition
Project Schedule
Secondary Risk
Schedule Performance Index
42. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Budget at Completion
Rolling Wave Planning
Control Account
Schedule Variance
43. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Milestone
Sponsor
Three-Point Estimate
Control Account
44. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Risk Avoidance
Optimistic Duration
Bottom-up Estimating
Backward Pass
45. A grid that shows the project resources assigned to each work package.
Predecessor Activity
Responsibility Assignment Matrix
Risk Breakdown Structure
Total Float
46. A dependent activity that logically comes after another activity in a schedule.
Defect Repair
Summary Activity
Schedule Compression
Successor Activity
47. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Level of Effort
Performing Organization
Free Float
Forward Pass
48. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Pessimistic Duration
Backward Pass
Lead
Variance Analysis
49. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Staffing Management Plan
Stakeholder
Variance at Completion
Procurement Management Plan
50. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Path Divergence
Project Schedule
Project Management Office
Discrete Effort