SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Any activity on the critical path in a project schedule.
Critical Path Activity
Start-to-Start
Threat
Critical Path Method
2. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Project Calendar
Staffing Management Plan
Three-Point Estimate
Schedule Model Analysis
3. A document in which the results of risk analysis and risk response planning are recorded.
Risk Register
Program Management
Requirements Management Plan
Schedule Compression
4. A grid that shows the project resources assigned to each work package.
Budget at Completion
Responsibility Assignment Matrix
Earned Value
Pessimistic Duration
5. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Total Float
Schedule Model
Backward Pass
Assumption
6. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Procurement Management Plan
Staffing Management Plan
Planned Value
Schedule Baseline
7. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Schedule Model
Stakeholder
Resource Leveling
Fast Tracking
8. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Lead
Sponsor
Discrete Effort
Decomposition
9. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Change Control Board
Project Charter
Estimate at Completion
Forward Pass
10. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Risk Breakdown Structure
Organizational Process Assets
Enterprise Environmental Factors
Precedence Diagramming Method
11. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Deliverable
Earned Value Management
Baseline
Schedule Baseline
12. A risk that would have a negative effect on one or more project objectives.
Threat
Quality Management Plan
Lessons Learned
Performing Organization
13. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Schedule Management Plan
Lead
Effort
Variance at Completion
14. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Defect Repair
Lessons Learned
Predecessor Activity
Forward Pass
15. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Project Phase
Path Divergence
Resource Leveling
Enterprise Environmental Factors
16. The work performed to deliver a product - service - or result with the specified features and functions.
Risk Breakdown Structure
Start-to-Start
Critical Path Activity
Project Scope
17. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Pessimistic Duration
Successor Activity
Project Life Cycle
Resource Breakdown Structure
18. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Change Control Board
Secondary Risk
Three-Point Estimate
Acceptance Criteria
19. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Schedule Baseline
Free Float
Critical Path
Decision Tree Analysis
20. A hierarchical representation of risks that is organized according to risk categories.
Phase Gate
Risk Breakdown Structure
Finish-to-Finish
S-Curve Analysis
21. A group of potential causes of risk.
Risk Breakdown Structure
Cost Management Plan
Risk Category
Organizational Process Assets
22. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Project Schedule
Planned Value
Apportioned Effort
Change Control
23. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Requirement
Lessons Learned
Schedule Variance
Start-to-Start
24. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Actual Cost
Parametric Estimating
Risk Acceptance
Program Management Office
25. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Resource Calendar
Variance at Completion
Logical Relationship
Control Account
26. The description of the project scope - major deliverables - assumptions - and constraints.
Opportunity
Pessimistic Duration
Project Scope Statement
Resource Calendar
27. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Crashing
Change Control System
Risk Management Plan
Start-to-Finish
28. An intentional activity to modify a nonconforming product or product component.
Requirements Traceability Matrix
Defect Repair
Percent Complete
Level of Effort
29. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Phase Gate
Communication Management Plan
Free Float
Product Life Cycle
30. A set of conditions that is required to be met before deliverables are accepted.
Project Scope
Acceptance Criteria
Project Schedule
Opportunity
31. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Resource Leveling
Risk
Opportunity
Risk Mitigation
32. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Estimate to Complete
Risk Transference
Requirements Management Plan
Project Charter
33. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Summary Activity
Lessons Learned
Rolling Wave Planning
Project Charter
34. A hierarchical representation of resources by category and type.
Resource Breakdown Structure
Discrete Effort
Cost Variance
Actual Cost
35. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Decision Tree Analysis
Risk Transference
Program Management
Earned Value
36. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Resource Calendar
Bottom-up Estimating
Summary Activity
Project Management Office
37. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Control Account
Earned Value Management
Change Control
Critical Path
38. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Cost Variance
Start-to-Start
Resource Leveling
Project Life Cycle
39. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Project Charter
Schedule Performance Index
Early Start Date
Project Management
40. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Early Start Date
Schedule Baseline
What-If Sce
Control Account
41. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Start-to-Finish
Project Management Office
Forward Pass
Project Management
42. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Sponsor
Risk Breakdown Structure
Critical Chain Method
Critical Path Activity
43. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Trigger Condition
Critical Path
Change Control
Total Float
44. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Fast Tracking
Bottom-up Estimating
Effort
Risk Mitigation
45. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Optimistic Duration
Successor Activity
Project Calendar
Pessimistic Duration
46. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Risk
Free Float
Scope Baseline
Phase Gate
47. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Risk Management Plan
Cost Performance Index
Code of Accounts
Earned Value
48. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
S-Curve Analysis
Activity
Organizational Process Assets
Project Schedule Network Diagram
49. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Finish-to-Finish
Cost Management Plan
Apportioned Effort
Portfolio Balancing
50. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Most Likely Duration
Forward Pass
S-Curve Analysis
Code of Accounts