SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Lead
Phase Gate
Schedule Performance Index
Risk Register
2. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Path Divergence
Analogous Estimating
Early Finish Date
Change Control
3. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Procurement Management Plan
Resource Calendar
Project Charter
Lag
4. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Fast Tracking
What-If Sce
Start-to-Start
Gantt Chart
5. The authorized budget assigned to scheduled work.
Planned Value
Precedence Diagramming Method
Cost Variance
Start-to-Finish
6. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Crashing
Product Life Cycle
Optimistic Duration
Project Management Plan
7. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Scope Creep
Late Start Date
Risk Register
Program Management
8. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Analogous Estimating
Schedule Performance Index
Late Finish Date
Budget at Completion
9. A relationship in which a schedule activity has more than one successor.
Schedule Model
Risk Acceptance
Path Divergence
Summary Activity
10. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Program
Progressive Elaboration
Probability and Impact Matrix
Predecessor Activity
11. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Variance Analysis
Forward Pass
Data Date
Risk Transference
12. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Code of Accounts
Earned Value
Project Scope Statement
Crashing
13. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Percent Complete
Lead
Finish-to-Start
Project Schedule
14. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Procurement Management Plan
Predecessor Activity
Risk Acceptance
Total Float
15. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Risk Avoidance
Assumption
Cost Performance Index
Cost Variance
16. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Change Control System
Organizational Breakdown Structure
Portfolio Balancing
Planned Value
17. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
WBS Dictionary
Variance at Completion
Project
Critical Chain Method
18. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Discrete Effort
Percent Complete
Lead
Finish-to-Start
19. A relationship in which a schedule activity has more than one predecessor.
Data Date
Resource Breakdown Structure
Lead
Path Convergence
20. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Budget at Completion
Change Control System
Risk Transference
Progressive Elaboration
21. The series of phases that a project passes through from its initiation to its closure.
Scope Creep
Discrete Effort
Project Life Cycle
Probability and Impact Matrix
22. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Portfolio
Three-Point Estimate
Schedule Performance Index
Early Start Date
23. A technique used to shorten the schedule duration without reducing the project scope.
S-Curve Analysis
Schedule Compression
Project
Resource Calendar
24. A set of conditions that is required to be met before deliverables are accepted.
Deliverable
Enterprise Environmental Factors
Acceptance Criteria
Resource Breakdown Structure
25. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Predecessor Activity
Resource Leveling
Organizational Breakdown Structure
Threat
26. A risk that arises as a direct result of implementing a risk response.
Start-to-Start
Decomposition
Late Start Date
Secondary Risk
27. An event or situation that indicates that a risk is about to occur.
Project Scope
Lag
Backward Pass
Trigger Condition
28. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Project Schedule
Scope Creep
Risk Category
Discrete Effort
29. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Successor Activity
S-Curve Analysis
Risk Avoidance
Resource Calendar
30. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Acceptance Criteria
Finish-to-Finish
Stakeholder
Progressive Elaboration
31. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Optimistic Duration
Summary Activity
Scope Creep
Most Likely Duration
32. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Schedule Baseline
Crashing
Baseline
Threat
33. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Change Request
Acceptance Criteria
Risk
Parametric Estimating
34. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Cost Management Plan
Three-Point Estimate
Project Scope
Scope Baseline
35. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Project Charter
Project Management Plan
Lessons Learned
Organizational Breakdown Structure
36. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Sponsor
Opportunity
Estimate to Complete
Lag
37. A grid that links product requirements from their origin to the deliverables that satisfy them.
Schedule Baseline
Cost Management Plan
S-Curve Analysis
Requirements Traceability Matrix
38. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Early Start Date
Defect Repair
Project Scope Statement
Portfolio
39. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Apportioned Effort
Decision Tree Analysis
Project Life Cycle
Organizational Project Management Maturity
40. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Critical Path
Effort
Change Request
Actual Cost
41. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Start-to-Finish
Preventive Action
Project Manager
Requirements Management Plan
42. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Stakeholder
Project Management
Product Life Cycle
Milestone
43. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Product Life Cycle
Critical Path Activity
Critical Path Method
Project Management Office
44. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Project Life Cycle
Threat
Parametric Estimating
Risk Transference
45. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Fast Tracking
Schedule Management Plan
Change Control Board
Risk Transference
46. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Successor Activity
Backward Pass
Schedule Model Analysis
Change Control
47. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Pessimistic Duration
Crashing
Organizational Project Management Maturity
Organizational Process Assets
48. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Schedule Compression
Cost Management Plan
Critical Path Method
Change Control Board
49. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Deliverable
Corrective Action
Bottom-up Estimating
Portfolio Balancing
50. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Secondary Risk
Change Control System
Three-Point Estimate
Schedule Baseline