SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A group of potential causes of risk.
Risk Category
Trigger Condition
Apportioned Effort
Control Account
2. A technique used to shorten the schedule duration without reducing the project scope.
Schedule Compression
Variance at Completion
Scope Management Plan
S-Curve Analysis
3. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Risk Acceptance
Discrete Effort
Scope Baseline
Organizational Project Management Maturity
4. A set of conditions that is required to be met before deliverables are accepted.
Quality Management Plan
Acceptance Criteria
Free Float
Requirement
5. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Preventive Action
Baseline
Bottom-up Estimating
Risk Breakdown Structure
6. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Late Finish Date
Project Management Office
Risk Register
Schedule Compression
7. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Scope Baseline
Project Manager
Portfolio Balancing
Forward Pass
8. A relationship in which a schedule activity has more than one successor.
Trigger Condition
Resource Breakdown Structure
Path Divergence
Free Float
9. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Scope Management Plan
Procurement Management Plan
Schedule Performance Index
Risk Management Plan
10. A document in which the results of risk analysis and risk response planning are recorded.
Procurement Management Plan
Risk Register
Data Date
Cost Performance Index
11. Any activity on the critical path in a project schedule.
Probability and Impact Matrix
Start-to-Finish
Critical Path Activity
Risk
12. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Estimate at Completion
Opportunity
Forward Pass
Preventive Action
13. A numbering system used to uniquely identify each component of the work breakdown structure.
Lessons Learned
Secondary Risk
Code of Accounts
Risk Category
14. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Project Charter
Progressive Elaboration
Variance Analysis
Risk Breakdown Structure
15. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Change Control
Risk Category
Risk Management Plan
Organizational Breakdown Structure
16. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Procurement Management Plan
Requirement
Risk Breakdown Structure
Earned Value Management
17. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
What-If Sce
Procurement Management Plan
Early Start Date
Planned Value
18. A significant point or event in a project - program - or portfolio.
Milestone
Progressive Elaboration
Scope Management Plan
Sponsor
19. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Variance at Completion
Finish-to-Start
Critical Path Method
Milestone
20. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Staffing Management Plan
To-Complete Performance Index
Preventive Action
Start-to-Start
21. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Change Control System
Resource Leveling
Change Control Board
Estimate to Complete
22. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Threat
Communication Management Plan
Resource Calendar
Scope Baseline
23. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Scope Creep
Backward Pass
Schedule Management Plan
Project Manager
24. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Fast Tracking
Progressive Elaboration
Actual Cost
Human Resource Plan
25. The sum of all budgets established for the work to be performed.
Organizational Project Management Maturity
Budget at Completion
Code of Accounts
Start-to-Start
26. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Enterprise Environmental Factors
Portfolio
Logical Relationship
Predecessor Activity
27. A calendar that identifies working days and shifts that are available for scheduled activities.
Decomposition
Backward Pass
Project Calendar
Activity
28. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Corrective Action
Lessons Learned
Resource Calendar
WBS Dictionary
29. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Apportioned Effort
Risk Avoidance
Risk Acceptance
Project Charter
30. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Project
Rolling Wave Planning
Crashing
Organizational Project Management Maturity
31. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Late Finish Date
Resource Leveling
Successor Activity
Responsibility Assignment Matrix
32. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Project Manager
Optimistic Duration
Start-to-Start
Change Control Board
33. The authorized budget assigned to scheduled work.
Analogous Estimating
Control Account
Planned Value
Lag
34. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Project Phase
Project Management
Backward Pass
Pessimistic Duration
35. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Code of Accounts
Lead
Analogous Estimating
Project Charter
36. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Progressive Elaboration
Constraint
Crashing
Cost Management Plan
37. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Program
Risk Category
Sponsor
Backward Pass
38. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Most Likely Duration
Finish-to-Start
Schedule Variance
Project
39. A temporary endeavor undertaken to create a unique product - service - or result.
Actual Cost
Finish-to-Start
Variance at Completion
Project
40. A grid that links product requirements from their origin to the deliverables that satisfy them.
Milestone
Requirements Traceability Matrix
S-Curve Analysis
Successor Activity
41. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Change Control
Lessons Learned
Baseline
Project Charter
42. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Optimistic Duration
Percent Complete
Late Finish Date
Schedule Model
43. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Project Management Plan
Decomposition
Risk
Lag
44. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Acceptance Criteria
Milestone
Performing Organization
Path Convergence
45. An intentional activity that realigns the performance of the project work with the project management plan.
Program Management Office
Corrective Action
Critical Path
Organizational Project Management Maturity
46. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Variance Analysis
Planned Value
Project Charter
Requirement
47. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Risk Acceptance
Late Start Date
Project Manager
Staffing Management Plan
48. A risk that would have a positive effect on one or more project objectives.
Project Manager
Risk Mitigation
Phase Gate
Opportunity
49. A hierarchical representation of risks that is organized according to risk categories.
Analogous Estimating
Most Likely Duration
Risk Breakdown Structure
Preventive Action
50. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Predecessor Activity
Risk Transference
Risk Avoidance
Schedule Baseline