SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Early Finish Date
Risk Acceptance
Start-to-Start
Risk Category
2. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Planned Value
Organizational Process Assets
Sponsor
Organizational Breakdown Structure
3. A calendar that identifies working days and shifts that are available for scheduled activities.
Forward Pass
Backward Pass
Project Calendar
Lead
4. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Change Control System
Schedule Performance Index
Baseline
Change Control Board
5. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Free Float
Early Finish Date
Code of Accounts
Backward Pass
6. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Earned Value Management
What-If Sce
Budget at Completion
Logical Relationship
7. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Project Management Office
Apportioned Effort
Deliverable
Three-Point Estimate
8. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Control Account
Data Date
Project Charter
Probability and Impact Matrix
9. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Risk Breakdown Structure
To-Complete Performance Index
Finish-to-Finish
Requirement
10. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Phase Gate
Quality Management Plan
Project Calendar
Procurement Management Plan
11. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Variance at Completion
Schedule Variance
Project Charter
To-Complete Performance Index
12. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Product Life Cycle
Organizational Process Assets
To-Complete Performance Index
Communication Management Plan
13. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Early Finish Date
Estimate to Complete
Actual Cost
S-Curve Analysis
14. A point in time when the status of the project is recorded.
Organizational Process Assets
Project Scope
Data Date
Defect Repair
15. An activity that logically comes before a dependent activity in a schedule.
Product Life Cycle
Planned Value
Staffing Management Plan
Predecessor Activity
16. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Project
Project Management
Effort
Product Life Cycle
17. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Decision Tree Analysis
Enterprise Environmental Factors
Project Schedule
Level of Effort
18. A dependency between two activities - or between an activity and a milestone.
Logical Relationship
Opportunity
Control Account
Risk Transference
19. A document in which the results of risk analysis and risk response planning are recorded.
Baseline
Risk Register
Schedule Management Plan
Program Management
20. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Rolling Wave Planning
Project Charter
Project Management
Risk
21. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Probability and Impact Matrix
Risk Breakdown Structure
Stakeholder
Decomposition
22. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Portfolio Balancing
Secondary Risk
Lessons Learned
Variance Analysis
23. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Path Convergence
Planned Value
Deliverable
Start-to-Start
24. A risk that would have a positive effect on one or more project objectives.
Opportunity
Cost Variance
Start-to-Finish
Parametric Estimating
25. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Scope Baseline
Human Resource Plan
To-Complete Performance Index
Resource Breakdown Structure
26. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Schedule Variance
Change Control Board
Product Life Cycle
Risk Mitigation
27. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Program Management
Organizational Process Assets
Requirements Traceability Matrix
Decision Tree Analysis
28. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Most Likely Duration
Estimate at Completion
Progressive Elaboration
Risk Transference
29. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Performing Organization
Budget at Completion
Effort
Phase Gate
30. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Data Date
Three-Point Estimate
Cost Management Plan
Backward Pass
31. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Schedule Management Plan
Responsibility Assignment Matrix
Risk
Effort
32. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Trigger Condition
Project Phase
Constraint
Portfolio
33. A hierarchical representation of resources by category and type.
Risk Category
Percent Complete
Critical Path Activity
Resource Breakdown Structure
34. A calendar that identifies the working days and shifts upon which each specific resource is available.
Crashing
Resource Calendar
Scope Creep
Variance at Completion
35. A formal proposal to modify any document - deliverable - or baseline.
Critical Path
Free Float
Project Schedule
Change Request
36. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Program Management Office
Risk Breakdown Structure
Critical Path Method
Project Phase
37. The work performed to deliver a product - service - or result with the specified features and functions.
Project Scope
Opportunity
Critical Path Activity
Cost Management Plan
38. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Effort
Quality Management Plan
Summary Activity
Constraint
39. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Cost Performance Index
Pessimistic Duration
Schedule Baseline
Risk Breakdown Structure
40. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Resource Breakdown Structure
Cost Performance Index
Precedence Diagramming Method
Schedule Compression
41. The centralized management of one or more portfolios to achieve strategic objectives.
Crashing
Baseline
Portfolio Management
Percent Complete
42. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
What-If Sce
S-Curve Analysis
Estimate to Complete
Early Finish Date
43. A dependent activity that logically comes after another activity in a schedule.
Risk
Successor Activity
Risk Management Plan
Procurement Management Plan
44. A grid that links product requirements from their origin to the deliverables that satisfy them.
Program
Estimate at Completion
Requirements Traceability Matrix
Early Finish Date
45. An event or situation that indicates that a risk is about to occur.
Trigger Condition
Data Date
Threat
Finish-to-Finish
46. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Precedence Diagramming Method
Project Charter
Threat
Lag
47. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Lessons Learned
Level of Effort
Project Life Cycle
Performing Organization
48. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Late Start Date
Procurement Management Plan
Risk Acceptance
Early Finish Date
49. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Cost Management Plan
Bottom-up Estimating
Organizational Project Management Maturity
Lessons Learned
50. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Risk Breakdown Structure
Schedule Model
Path Convergence
Lead