SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Early Finish Date
WBS Dictionary
Project Phase
Risk Transference
2. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Project
Risk Management Plan
Three-Point Estimate
Milestone
3. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Earned Value Management
Total Float
Fast Tracking
Resource Breakdown Structure
4. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Trigger Condition
Schedule Performance Index
Enterprise Environmental Factors
Fast Tracking
5. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Schedule Baseline
Change Control System
Forward Pass
Project Schedule
6. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Predecessor Activity
Portfolio
Acceptance Criteria
Schedule Management Plan
7. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Risk Category
Parametric Estimating
Code of Accounts
Gantt Chart
8. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Critical Path
Resource Leveling
Program Management
Change Control
9. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Project Calendar
Lag
Finish-to-Start
Earned Value Management
10. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Schedule Model
What-If Sce
Portfolio
Change Request
11. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Apportioned Effort
Project Management
Stakeholder
Critical Path Method
12. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Change Control
Requirements Management Plan
Lag
Analogous Estimating
13. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
To-Complete Performance Index
Optimistic Duration
Performing Organization
Rolling Wave Planning
14. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Schedule Compression
Project Management Office
Portfolio Balancing
Summary Activity
15. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Optimistic Duration
Lead
Project
Path Convergence
16. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Finish-to-Start
Estimate to Complete
Performing Organization
Bottom-up Estimating
17. The realized cost incurred for the work performed on an activity during a specific time period.
Critical Path
Organizational Breakdown Structure
Start-to-Start
Actual Cost
18. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Preventive Action
Change Control System
Variance Analysis
Schedule Baseline
19. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Earned Value Management
Pessimistic Duration
Project Management Plan
Phase Gate
20. A point in time when the status of the project is recorded.
Staffing Management Plan
Human Resource Plan
Data Date
Rolling Wave Planning
21. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Budget at Completion
Portfolio Management
Program Management
Finish-to-Finish
22. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Activity
Organizational Project Management Maturity
Secondary Risk
Cost Variance
23. A technique used to shorten the schedule duration without reducing the project scope.
What-If Sce
Project Scope Statement
Resource Breakdown Structure
Schedule Compression
24. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Effort
Total Float
Free Float
Constraint
25. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Responsibility Assignment Matrix
Organizational Project Management Maturity
Probability and Impact Matrix
Assumption
26. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Activity
Discrete Effort
Resource Breakdown Structure
Backward Pass
27. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Schedule Variance
Data Date
Start-to-Finish
Estimate to Complete
28. A technique for determining the cause and degree of difference between the baseline and actual performance.
Schedule Variance
Gantt Chart
Variance Analysis
Assumption
29. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Schedule Performance Index
Risk Register
Early Finish Date
Probability and Impact Matrix
30. The document that describes how the project will be executed - monitored - and controlled.
Responsibility Assignment Matrix
Project Management Plan
Control Account
Defect Repair
31. A risk that would have a positive effect on one or more project objectives.
Logical Relationship
Acceptance Criteria
Opportunity
Project Management Plan
32. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Cost Performance Index
Planned Value
Schedule Variance
Requirement
33. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Effort
Logical Relationship
Product Life Cycle
S-Curve Analysis
34. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Scope Creep
Organizational Project Management Maturity
Change Control Board
Estimate to Complete
35. A calendar that identifies working days and shifts that are available for scheduled activities.
Late Finish Date
Schedule Model
Risk Acceptance
Project Calendar
36. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Critical Chain Method
Requirement
Program
Lag
37. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Decision Tree Analysis
Project Phase
Critical Path Method
Project Management
38. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Change Control System
Finish-to-Start
Schedule Model
Procurement Management Plan
39. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Critical Path Method
Sponsor
Acceptance Criteria
Program
40. A calendar that identifies the working days and shifts upon which each specific resource is available.
Change Control
Control Account
Logical Relationship
Resource Calendar
41. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Logical Relationship
Requirements Management Plan
Variance at Completion
Control Account
42. A limiting factor that affects the execution of a project - program - portfolio - or process.
Variance at Completion
Constraint
Organizational Breakdown Structure
Project Management Plan
43. A relationship in which a schedule activity has more than one predecessor.
Program Management
Phase Gate
Risk Management Plan
Path Convergence
44. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Lessons Learned
Program Management Office
Earned Value Management
What-If Sce
45. A grid that shows the project resources assigned to each work package.
Schedule Model
Risk Transference
Responsibility Assignment Matrix
Total Float
46. A dependent activity that logically comes after another activity in a schedule.
Preventive Action
Baseline
Successor Activity
Portfolio Balancing
47. A graphical representation of the logical relationships among the project schedule activities.
Predecessor Activity
Change Control Board
Project Schedule Network Diagram
Late Start Date
48. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Crashing
Organizational Process Assets
Parametric Estimating
Most Likely Duration
49. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Defect Repair
Effort
Staffing Management Plan
S-Curve Analysis
50. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Decomposition
Baseline
Requirements Management Plan
Fast Tracking