SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A formal proposal to modify any document - deliverable - or baseline.
Decomposition
S-Curve Analysis
Change Request
What-If Sce
2. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Schedule Compression
Three-Point Estimate
Finish-to-Finish
Effort
3. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Cost Performance Index
Project Management
Defect Repair
Program
4. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Risk Acceptance
Project Phase
Start-to-Finish
Discrete Effort
5. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Change Request
Late Start Date
Threat
Organizational Breakdown Structure
6. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Milestone
Decision Tree Analysis
Schedule Model
Project Schedule Network Diagram
7. A temporary endeavor undertaken to create a unique product - service - or result.
Responsibility Assignment Matrix
Portfolio
Assumption
Project
8. Any activity on the critical path in a project schedule.
Start-to-Finish
Pessimistic Duration
Level of Effort
Critical Path Activity
9. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Risk Transference
Path Convergence
Pessimistic Duration
Finish-to-Start
10. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Crashing
Progressive Elaboration
Successor Activity
Project Scope Statement
11. A risk that would have a negative effect on one or more project objectives.
Lessons Learned
Threat
Risk Breakdown Structure
Apportioned Effort
12. The sum of all budgets established for the work to be performed.
Baseline
Budget at Completion
Risk Breakdown Structure
Pessimistic Duration
13. A risk that would have a positive effect on one or more project objectives.
S-Curve Analysis
Probability and Impact Matrix
Opportunity
Defect Repair
14. The work performed to deliver a product - service - or result with the specified features and functions.
Finish-to-Finish
Schedule Model Analysis
Cost Performance Index
Project Scope
15. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Schedule Compression
Summary Activity
Deliverable
Bottom-up Estimating
16. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Rolling Wave Planning
Requirement
Estimate at Completion
Critical Path
17. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Risk Avoidance
Phase Gate
Schedule Performance Index
Corrective Action
18. The authorized budget assigned to scheduled work.
Planned Value
Organizational Breakdown Structure
Estimate to Complete
Successor Activity
19. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Late Finish Date
Estimate at Completion
Analogous Estimating
Gantt Chart
20. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Most Likely Duration
Communication Management Plan
Bottom-up Estimating
Constraint
21. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Lag
Performing Organization
Scope Management Plan
Project Management
22. A hierarchical representation of risks that is organized according to risk categories.
Performing Organization
Stakeholder
Level of Effort
Risk Breakdown Structure
23. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Requirements Management Plan
Successor Activity
Risk Acceptance
Organizational Breakdown Structure
24. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Portfolio
S-Curve Analysis
WBS Dictionary
Sponsor
25. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Risk
Schedule Model Analysis
Project Calendar
Change Control
26. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Level of Effort
Early Finish Date
Variance at Completion
Schedule Performance Index
27. A hierarchical representation of resources by category and type.
Estimate to Complete
Risk Transference
Successor Activity
Resource Breakdown Structure
28. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Fast Tracking
Critical Path Method
Lead
Risk Management Plan
29. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Percent Complete
Level of Effort
Change Control System
Project Phase
30. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Earned Value Management
Acceptance Criteria
Project Life Cycle
Human Resource Plan
31. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Early Finish Date
Schedule Model Analysis
Path Convergence
Project Scope
32. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Risk Mitigation
Trigger Condition
Threat
Preventive Action
33. A technique used to shorten the schedule duration without reducing the project scope.
Schedule Compression
Scope Baseline
Project Management Plan
Planned Value
34. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Enterprise Environmental Factors
Start-to-Start
Project Management
Risk Breakdown Structure
35. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Change Request
Code of Accounts
Finish-to-Finish
Sponsor
36. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Change Control System
Critical Path Method
Estimate at Completion
Risk Mitigation
37. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Late Finish Date
Constraint
Critical Path Method
Preventive Action
38. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Budget at Completion
Estimate to Complete
Enterprise Environmental Factors
Trigger Condition
39. A calendar that identifies working days and shifts that are available for scheduled activities.
Bottom-up Estimating
Project Calendar
Effort
Project Schedule
40. A point in time when the status of the project is recorded.
Project Scope Statement
Scope Baseline
Data Date
Discrete Effort
41. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Control Account
Project Life Cycle
Threat
Organizational Breakdown Structure
42. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Requirements Traceability Matrix
Threat
Late Start Date
Early Start Date
43. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Finish-to-Finish
Estimate at Completion
Forward Pass
Risk Transference
44. A grid that shows the project resources assigned to each work package.
Responsibility Assignment Matrix
Critical Path Activity
Lead
Change Control Board
45. An event or situation that indicates that a risk is about to occur.
Program Management
Trigger Condition
Critical Path Method
Probability and Impact Matrix
46. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Resource Calendar
Resource Leveling
Baseline
Performing Organization
47. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Critical Chain Method
Percent Complete
Progressive Elaboration
Data Date
48. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Deliverable
Late Finish Date
Program Management Office
Organizational Project Management Maturity
49. An intentional activity that realigns the performance of the project work with the project management plan.
Level of Effort
Actual Cost
Schedule Management Plan
Corrective Action
50. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Decomposition
Risk Transference
Backward Pass
Cost Management Plan