SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Deliverable
Schedule Performance Index
Precedence Diagramming Method
Free Float
2. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Project Calendar
S-Curve Analysis
Project Schedule Network Diagram
Project
3. A technique used to shorten the schedule duration without reducing the project scope.
Assumption
Start-to-Finish
Schedule Compression
Project Calendar
4. A hierarchical representation of risks that is organized according to risk categories.
Phase Gate
Risk Breakdown Structure
Milestone
Project Schedule Network Diagram
5. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Critical Path
Finish-to-Finish
Responsibility Assignment Matrix
Percent Complete
6. A limiting factor that affects the execution of a project - program - portfolio - or process.
Change Request
Decomposition
Resource Calendar
Constraint
7. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Critical Path Activity
Start-to-Start
Decomposition
Cost Management Plan
8. A dependent activity that logically comes after another activity in a schedule.
Successor Activity
Portfolio Balancing
Baseline
Responsibility Assignment Matrix
9. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Data Date
Schedule Baseline
Project Calendar
Requirement
10. A calendar that identifies the working days and shifts upon which each specific resource is available.
Analogous Estimating
Organizational Project Management Maturity
Resource Calendar
Schedule Performance Index
11. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Requirement
Organizational Project Management Maturity
Start-to-Finish
Discrete Effort
12. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Three-Point Estimate
S-Curve Analysis
Organizational Breakdown Structure
Deliverable
13. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Earned Value Management
Estimate at Completion
Schedule Compression
Finish-to-Start
14. The realized cost incurred for the work performed on an activity during a specific time period.
Human Resource Plan
Actual Cost
Schedule Model Analysis
Program Management
15. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Product Life Cycle
Organizational Process Assets
Rolling Wave Planning
Start-to-Start
16. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Scope Baseline
Staffing Management Plan
Critical Chain Method
Change Control System
17. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Risk Register
Crashing
Lag
Finish-to-Finish
18. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Fast Tracking
Opportunity
Risk Mitigation
Phase Gate
19. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Acceptance Criteria
Control Account
Fast Tracking
Three-Point Estimate
20. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Effort
Decision Tree Analysis
Schedule Performance Index
Late Finish Date
21. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Resource Leveling
Finish-to-Finish
S-Curve Analysis
Rolling Wave Planning
22. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Decision Tree Analysis
Most Likely Duration
Product Life Cycle
Cost Performance Index
23. The document that describes how the project will be executed - monitored - and controlled.
Estimate at Completion
What-If Sce
Schedule Model
Project Management Plan
24. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Discrete Effort
Percent Complete
Acceptance Criteria
Variance at Completion
25. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Schedule Variance
Trigger Condition
Project Scope Statement
Change Control
26. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Preventive Action
Resource Calendar
Assumption
Apportioned Effort
27. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Bottom-up Estimating
Communication Management Plan
Control Account
Preventive Action
28. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Estimate at Completion
Constraint
Baseline
Backward Pass
29. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Communication Management Plan
Risk Breakdown Structure
Finish-to-Finish
Finish-to-Start
30. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Risk Category
Path Convergence
Project Management
Organizational Process Assets
31. A relationship in which a schedule activity has more than one successor.
Lessons Learned
Path Divergence
Project Charter
Responsibility Assignment Matrix
32. A point in time when the status of the project is recorded.
Apportioned Effort
Data Date
Constraint
Risk Register
33. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Program Management Office
Constraint
Schedule Model Analysis
Risk Mitigation
34. A numbering system used to uniquely identify each component of the work breakdown structure.
Code of Accounts
Change Request
Risk Mitigation
Program Management
35. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Apportioned Effort
Risk
Progressive Elaboration
Three-Point Estimate
36. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Enterprise Environmental Factors
Risk Avoidance
Backward Pass
Forward Pass
37. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Variance at Completion
Risk Breakdown Structure
Variance Analysis
Critical Path Activity
38. An intentional activity to modify a nonconforming product or product component.
Change Control
Schedule Compression
Fast Tracking
Defect Repair
39. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Lessons Learned
Critical Chain Method
Secondary Risk
Staffing Management Plan
40. A significant point or event in a project - program - or portfolio.
Fast Tracking
Cost Management Plan
Variance at Completion
Milestone
41. The centralized management of one or more portfolios to achieve strategic objectives.
Actual Cost
Portfolio Management
Project Calendar
Risk Category
42. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Path Divergence
Project Management Office
Scope Creep
Milestone
43. Any activity on the critical path in a project schedule.
Threat
Procurement Management Plan
Risk Transference
Critical Path Activity
44. A grid that links product requirements from their origin to the deliverables that satisfy them.
Successor Activity
Requirements Traceability Matrix
Late Start Date
Early Start Date
45. An event or situation that indicates that a risk is about to occur.
Schedule Model Analysis
To-Complete Performance Index
Trigger Condition
Early Finish Date
46. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Early Start Date
Product Life Cycle
Bottom-up Estimating
Lag
47. A group of potential causes of risk.
Risk Breakdown Structure
Earned Value
Risk Category
Risk Transference
48. A formal proposal to modify any document - deliverable - or baseline.
Organizational Project Management Maturity
Risk Avoidance
Change Request
To-Complete Performance Index
49. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Variance at Completion
To-Complete Performance Index
Parametric Estimating
Scope Baseline
50. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Requirements Traceability Matrix
Portfolio
To-Complete Performance Index
Project Management Office