SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Most Likely Duration
Estimate to Complete
Lag
Crashing
2. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Effort
Estimate at Completion
Program Management
Program Management Office
3. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Path Divergence
Quality Management Plan
Optimistic Duration
Project Management
4. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Schedule Model
Project Management Plan
Finish-to-Start
WBS Dictionary
5. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Cost Performance Index
Finish-to-Start
Cost Variance
Actual Cost
6. A risk that would have a positive effect on one or more project objectives.
Opportunity
Change Control
Resource Breakdown Structure
Discrete Effort
7. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Planned Value
Stakeholder
Product Life Cycle
Actual Cost
8. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Project Management
Lead
Most Likely Duration
Critical Path
9. An event or situation that indicates that a risk is about to occur.
Variance Analysis
Performing Organization
Forward Pass
Trigger Condition
10. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Threat
Communication Management Plan
Enterprise Environmental Factors
Risk Avoidance
11. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Critical Chain Method
Change Request
Apportioned Effort
Rolling Wave Planning
12. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Trigger Condition
Parametric Estimating
Control Account
Earned Value Management
13. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
To-Complete Performance Index
Program Management Office
Percent Complete
Risk Transference
14. A document in which the results of risk analysis and risk response planning are recorded.
Risk Register
Program Management Office
Assumption
Project Scope
15. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Opportunity
Discrete Effort
Forward Pass
Most Likely Duration
16. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Program Management
Variance at Completion
Project Schedule
Finish-to-Finish
17. A grid that links product requirements from their origin to the deliverables that satisfy them.
Critical Chain Method
Requirements Traceability Matrix
Change Control System
Total Float
18. A relationship in which a schedule activity has more than one predecessor.
Risk Mitigation
Enterprise Environmental Factors
Path Convergence
Scope Management Plan
19. A calendar that identifies working days and shifts that are available for scheduled activities.
Quality Management Plan
Project Calendar
Critical Path Method
Scope Baseline
20. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Budget at Completion
Late Start Date
Late Finish Date
Responsibility Assignment Matrix
21. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Three-Point Estimate
Schedule Compression
Critical Chain Method
Preventive Action
22. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Deliverable
Enterprise Environmental Factors
Baseline
Early Start Date
23. A graphical representation of the logical relationships among the project schedule activities.
Schedule Compression
Bottom-up Estimating
Project Schedule Network Diagram
Stakeholder
24. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Project Charter
Project
Change Control Board
What-If Sce
25. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Human Resource Plan
Organizational Breakdown Structure
Schedule Model
Preventive Action
26. A relationship in which a schedule activity has more than one successor.
Percent Complete
Late Finish Date
Risk Mitigation
Path Divergence
27. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Earned Value
Scope Management Plan
Human Resource Plan
Fast Tracking
28. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Schedule Model
Decision Tree Analysis
Apportioned Effort
Responsibility Assignment Matrix
29. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Project Management
Project Scope Statement
Requirement
Communication Management Plan
30. A calendar that identifies the working days and shifts upon which each specific resource is available.
Risk Register
Resource Calendar
Change Request
Requirements Traceability Matrix
31. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Staffing Management Plan
Analogous Estimating
What-If Sce
Effort
32. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Project Life Cycle
Portfolio
Resource Calendar
Decomposition
33. A risk that would have a negative effect on one or more project objectives.
Threat
Project Management
Risk
Change Control System
34. A limiting factor that affects the execution of a project - program - portfolio - or process.
Program
Bottom-up Estimating
Stakeholder
Constraint
35. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Percent Complete
Parametric Estimating
Project Schedule
Organizational Project Management Maturity
36. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Estimate to Complete
Organizational Process Assets
Logical Relationship
Project Charter
37. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Earned Value
Level of Effort
Gantt Chart
Program Management Office
38. The authorized budget assigned to scheduled work.
Program Management Office
Organizational Project Management Maturity
Planned Value
Control Account
39. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Requirements Management Plan
Most Likely Duration
Product Life Cycle
Lessons Learned
40. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Program
Fast Tracking
Analogous Estimating
Earned Value
41. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Sponsor
Finish-to-Finish
Milestone
Free Float
42. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Late Finish Date
Schedule Performance Index
Critical Path Activity
Performing Organization
43. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Requirements Management Plan
Late Finish Date
Three-Point Estimate
Product Life Cycle
44. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Progressive Elaboration
Risk Avoidance
Early Start Date
Schedule Performance Index
45. A numbering system used to uniquely identify each component of the work breakdown structure.
Responsibility Assignment Matrix
Successor Activity
Schedule Variance
Code of Accounts
46. The document that describes how the project will be executed - monitored - and controlled.
Project Management Office
Project Management Plan
Requirement
Critical Path
47. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Lag
Late Start Date
Sponsor
Late Finish Date
48. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Path Divergence
Scope Management Plan
Finish-to-Start
Resource Leveling
49. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Optimistic Duration
What-If Sce
Fast Tracking
Communication Management Plan
50. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Code of Accounts
Assumption
Corrective Action
Parametric Estimating