SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A significant point or event in a project - program - or portfolio.
Stakeholder
Risk Management Plan
Communication Management Plan
Milestone
2. A limiting factor that affects the execution of a project - program - portfolio - or process.
Deliverable
Cost Performance Index
Constraint
Program Management
3. A distinct - scheduled portion of work performed during the course of a project.
Resource Calendar
Forward Pass
Human Resource Plan
Activity
4. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Critical Path
Change Control Board
Project Schedule Network Diagram
S-Curve Analysis
5. A risk that would have a negative effect on one or more project objectives.
Human Resource Plan
Organizational Breakdown Structure
Threat
Risk
6. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Decision Tree Analysis
Fast Tracking
Program
Portfolio Management
7. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Free Float
Control Account
Enterprise Environmental Factors
Trigger Condition
8. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Project Management Office
Precedence Diagramming Method
Data Date
Analogous Estimating
9. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Requirements Traceability Matrix
Three-Point Estimate
Portfolio Management
Earned Value
10. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Fast Tracking
Critical Path Activity
S-Curve Analysis
Lessons Learned
11. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Portfolio
Stakeholder
Requirements Traceability Matrix
Schedule Model Analysis
12. A dependency between two activities - or between an activity and a milestone.
Resource Leveling
Quality Management Plan
Lag
Logical Relationship
13. A relationship in which a schedule activity has more than one predecessor.
Path Convergence
Requirements Traceability Matrix
Critical Path Method
Risk Mitigation
14. A calendar that identifies the working days and shifts upon which each specific resource is available.
Project Scope
Apportioned Effort
Risk Avoidance
Resource Calendar
15. A temporary endeavor undertaken to create a unique product - service - or result.
Optimistic Duration
Enterprise Environmental Factors
Requirement
Project
16. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Summary Activity
Discrete Effort
Finish-to-Start
Level of Effort
17. A set of conditions that is required to be met before deliverables are accepted.
Effort
Requirement
Acceptance Criteria
Change Request
18. A grid that shows the project resources assigned to each work package.
Responsibility Assignment Matrix
Three-Point Estimate
Schedule Variance
Effort
19. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Schedule Compression
Critical Path Method
Program Management Office
Schedule Management Plan
20. A group of potential causes of risk.
Risk Category
Planned Value
Variance Analysis
Most Likely Duration
21. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Progressive Elaboration
Staffing Management Plan
Early Finish Date
Summary Activity
22. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Risk Breakdown Structure
Risk Avoidance
Project Schedule
Probability and Impact Matrix
23. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Backward Pass
Staffing Management Plan
Deliverable
Probability and Impact Matrix
24. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Forward Pass
Program Management
Project Scope Statement
Apportioned Effort
25. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Responsibility Assignment Matrix
Early Start Date
Lessons Learned
Project Management
26. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Start-to-Finish
Project Management Office
Risk Category
Start-to-Start
27. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Crashing
Risk Transference
To-Complete Performance Index
Threat
28. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Project
Procurement Management Plan
Estimate at Completion
Successor Activity
29. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Schedule Model Analysis
Risk
Progressive Elaboration
Project Calendar
30. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Constraint
Schedule Management Plan
Responsibility Assignment Matrix
Project Management Plan
31. An activity that logically comes before a dependent activity in a schedule.
Cost Variance
Late Finish Date
Predecessor Activity
Risk Avoidance
32. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Risk Management Plan
Change Control
Deliverable
Backward Pass
33. A technique used to shorten the schedule duration without reducing the project scope.
Secondary Risk
Schedule Compression
Critical Path Method
Schedule Variance
34. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Early Finish Date
Requirements Traceability Matrix
Fast Tracking
Project Life Cycle
35. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Project Schedule Network Diagram
Lead
Estimate at Completion
Portfolio
36. A dependent activity that logically comes after another activity in a schedule.
Baseline
Path Divergence
Late Finish Date
Successor Activity
37. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Organizational Process Assets
Requirements Management Plan
Acceptance Criteria
Project Charter
38. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Organizational Breakdown Structure
Pessimistic Duration
Decision Tree Analysis
Progressive Elaboration
39. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Progressive Elaboration
Defect Repair
Code of Accounts
Level of Effort
40. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Pessimistic Duration
Portfolio Balancing
Precedence Diagramming Method
Sponsor
41. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Analogous Estimating
Stakeholder
S-Curve Analysis
Schedule Model Analysis
42. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Change Control Board
Gantt Chart
Progressive Elaboration
Logical Relationship
43. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Schedule Management Plan
Scope Management Plan
Constraint
Decision Tree Analysis
44. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Project Scope
Baseline
Program Management
Planned Value
45. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Estimate at Completion
Late Finish Date
Effort
Early Start Date
46. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Risk Register
Scope Baseline
Change Request
Human Resource Plan
47. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Estimate to Complete
Path Convergence
Logical Relationship
Optimistic Duration
48. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Schedule Performance Index
Variance at Completion
Staffing Management Plan
Project
49. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Sponsor
Project Management Plan
Schedule Performance Index
Product Life Cycle
50. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Finish-to-Finish
Schedule Compression
Project Scope
Estimate to Complete