SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Budget at Completion
Risk Acceptance
Schedule Management Plan
Variance Analysis
2. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Decision Tree Analysis
Data Date
Critical Path Method
Three-Point Estimate
3. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Organizational Project Management Maturity
Lessons Learned
Risk Transference
Stakeholder
4. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Estimate to Complete
Project Schedule Network Diagram
Crashing
Schedule Performance Index
5. The sum of all budgets established for the work to be performed.
Staffing Management Plan
Budget at Completion
Trigger Condition
Resource Breakdown Structure
6. A numbering system used to uniquely identify each component of the work breakdown structure.
Code of Accounts
Bottom-up Estimating
Level of Effort
Opportunity
7. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Resource Calendar
Change Control Board
Project Manager
Control Account
8. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Finish-to-Start
Scope Management Plan
Stakeholder
Discrete Effort
9. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Risk Mitigation
Constraint
Requirement
Late Start Date
10. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Performing Organization
Scope Baseline
Enterprise Environmental Factors
Project Calendar
11. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Early Start Date
Rolling Wave Planning
Schedule Compression
Trigger Condition
12. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Data Date
Procurement Management Plan
Earned Value
Human Resource Plan
13. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Cost Management Plan
Enterprise Environmental Factors
Successor Activity
Start-to-Finish
14. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Schedule Performance Index
Project Manager
Project Schedule Network Diagram
Estimate to Complete
15. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Early Start Date
Opportunity
Human Resource Plan
Early Finish Date
16. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Cost Management Plan
Risk Management Plan
Control Account
Apportioned Effort
17. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Project Phase
Resource Calendar
Pessimistic Duration
Procurement Management Plan
18. The work performed to deliver a product - service - or result with the specified features and functions.
Change Control Board
Project Scope
Lead
Path Divergence
19. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Percent Complete
S-Curve Analysis
Constraint
Risk Transference
20. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Product Life Cycle
Percent Complete
Cost Performance Index
Parametric Estimating
21. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Lead
Effort
Gantt Chart
Optimistic Duration
22. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Requirements Traceability Matrix
Total Float
Communication Management Plan
Project Management Plan
23. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Responsibility Assignment Matrix
Schedule Compression
Decomposition
Discrete Effort
24. A formal proposal to modify any document - deliverable - or baseline.
Project Scope Statement
Change Request
Project Life Cycle
Schedule Performance Index
25. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Risk Breakdown Structure
Risk Transference
Variance Analysis
Project Management
26. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Probability and Impact Matrix
Requirement
Schedule Variance
Project Phase
27. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Probability and Impact Matrix
Percent Complete
Path Divergence
Bottom-up Estimating
28. A technique for determining the cause and degree of difference between the baseline and actual performance.
Variance Analysis
Resource Calendar
Risk Avoidance
Staffing Management Plan
29. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Earned Value
Change Control
Successor Activity
Crashing
30. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Project Phase
Earned Value Management
Project Life Cycle
Milestone
31. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Cost Management Plan
Risk Mitigation
Earned Value Management
Backward Pass
32. An intentional activity that realigns the performance of the project work with the project management plan.
Probability and Impact Matrix
Cost Variance
Corrective Action
Performing Organization
33. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Finish-to-Start
Schedule Model Analysis
What-If Sce
Organizational Project Management Maturity
34. A dependency between two activities - or between an activity and a milestone.
Forward Pass
Logical Relationship
Project Management
Organizational Process Assets
35. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Scope Baseline
Three-Point Estimate
Secondary Risk
Path Convergence
36. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Program Management
To-Complete Performance Index
Schedule Performance Index
Rolling Wave Planning
37. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Analogous Estimating
Optimistic Duration
Level of Effort
Scope Management Plan
38. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Schedule Variance
Optimistic Duration
Defect Repair
Preventive Action
39. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Most Likely Duration
Variance at Completion
Milestone
Acceptance Criteria
40. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Project Schedule Network Diagram
Start-to-Start
Decision Tree Analysis
Resource Breakdown Structure
41. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Program
Total Float
Organizational Breakdown Structure
Schedule Baseline
42. A dependent activity that logically comes after another activity in a schedule.
Critical Path Method
Progressive Elaboration
Resource Breakdown Structure
Successor Activity
43. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Risk Category
Risk Transference
Variance Analysis
Start-to-Start
44. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Project Schedule Network Diagram
Trigger Condition
Program Management
Actual Cost
45. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Level of Effort
Scope Management Plan
Phase Gate
Backward Pass
46. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Logical Relationship
Most Likely Duration
Late Finish Date
Finish-to-Finish
47. The authorized budget assigned to scheduled work.
Assumption
Product Life Cycle
Planned Value
Bottom-up Estimating
48. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Project Charter
Successor Activity
Defect Repair
Variance at Completion
49. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Organizational Breakdown Structure
Corrective Action
Quality Management Plan
Resource Breakdown Structure
50. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Stakeholder
Requirements Management Plan
Resource Leveling
Scope Management Plan