SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Scope Baseline
Schedule Model
Organizational Process Assets
Corrective Action
2. A group of potential causes of risk.
Risk Category
Scope Creep
Three-Point Estimate
Project Scope
3. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Change Control System
Product Life Cycle
Change Control Board
Scope Management Plan
4. An activity that logically comes before a dependent activity in a schedule.
Predecessor Activity
Defect Repair
Project Management Plan
Probability and Impact Matrix
5. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Critical Chain Method
Parametric Estimating
Opportunity
Schedule Performance Index
6. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Critical Path Activity
Baseline
WBS Dictionary
Trigger Condition
7. An event or situation that indicates that a risk is about to occur.
Constraint
Trigger Condition
Portfolio
Analogous Estimating
8. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Program Management Office
Probability and Impact Matrix
Decomposition
Parametric Estimating
9. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Requirements Management Plan
Successor Activity
Portfolio Management
Scope Management Plan
10. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Variance at Completion
Project Scope
Code of Accounts
Gantt Chart
11. The document that describes how the project will be executed - monitored - and controlled.
Resource Calendar
Project Management Plan
Project Calendar
Enterprise Environmental Factors
12. A set of conditions that is required to be met before deliverables are accepted.
Discrete Effort
Schedule Management Plan
Pessimistic Duration
Acceptance Criteria
13. The description of the project scope - major deliverables - assumptions - and constraints.
Schedule Variance
Project Scope Statement
Secondary Risk
Estimate at Completion
14. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Critical Path Method
Organizational Project Management Maturity
Critical Path
Late Start Date
15. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Risk Management Plan
Schedule Variance
Project Charter
Most Likely Duration
16. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Analogous Estimating
Path Divergence
Schedule Variance
Program Management
17. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Discrete Effort
Backward Pass
Critical Path Method
Schedule Variance
18. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Assumption
Project Management Plan
Project Management Office
Resource Leveling
19. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Gantt Chart
Crashing
Free Float
Project Schedule
20. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
To-Complete Performance Index
Finish-to-Finish
Product Life Cycle
Project Management
21. A relationship in which a schedule activity has more than one predecessor.
Path Convergence
Schedule Baseline
Project Schedule
Estimate at Completion
22. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Earned Value Management
Program
Project
Project Management Office
23. The sum of all budgets established for the work to be performed.
Budget at Completion
Project Calendar
Requirement
Preventive Action
24. The series of phases that a project passes through from its initiation to its closure.
Scope Baseline
Resource Calendar
Schedule Variance
Project Life Cycle
25. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Pessimistic Duration
Apportioned Effort
Threat
Progressive Elaboration
26. A point in time when the status of the project is recorded.
Data Date
Lead
Project Scope Statement
Effort
27. A calendar that identifies the working days and shifts upon which each specific resource is available.
Requirement
Scope Management Plan
Percent Complete
Resource Calendar
28. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Change Request
Cost Performance Index
Corrective Action
Estimate at Completion
29. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Threat
Early Start Date
Fast Tracking
Precedence Diagramming Method
30. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Risk Register
Program
Optimistic Duration
Requirements Management Plan
31. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Critical Path Method
Backward Pass
To-Complete Performance Index
Late Finish Date
32. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Cost Variance
Gantt Chart
What-If Sce
Threat
33. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Quality Management Plan
Predecessor Activity
Lag
Lessons Learned
34. A dependency between two activities - or between an activity and a milestone.
Forward Pass
Risk Category
Logical Relationship
Backward Pass
35. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Risk Mitigation
Crashing
Schedule Model Analysis
Critical Path Method
36. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Resource Leveling
Project Scope
Project Manager
Early Finish Date
37. A document in which the results of risk analysis and risk response planning are recorded.
Enterprise Environmental Factors
Estimate at Completion
Parametric Estimating
Risk Register
38. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Deliverable
Schedule Management Plan
Change Control
Discrete Effort
39. A risk that would have a positive effect on one or more project objectives.
Project Schedule Network Diagram
Opportunity
Discrete Effort
Cost Variance
40. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
WBS Dictionary
Backward Pass
Risk Breakdown Structure
Staffing Management Plan
41. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Cost Performance Index
Logical Relationship
Level of Effort
Project Management Office
42. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Finish-to-Start
Lag
Project Phase
Program Management
43. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Enterprise Environmental Factors
Most Likely Duration
Start-to-Finish
Risk
44. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Earned Value Management
Scope Creep
Risk Transference
Pessimistic Duration
45. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Cost Variance
Critical Path
Start-to-Finish
Variance Analysis
46. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Project Management Plan
Parametric Estimating
Schedule Performance Index
Defect Repair
47. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Free Float
Enterprise Environmental Factors
Project Management Office
Assumption
48. The realized cost incurred for the work performed on an activity during a specific time period.
Actual Cost
Variance Analysis
Total Float
Path Convergence
49. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Program Management
Project Manager
Schedule Model
Critical Path
50. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Procurement Management Plan
Baseline
Portfolio
Optimistic Duration