SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A group of potential causes of risk.
Early Finish Date
Risk Category
Project Management Plan
Schedule Compression
2. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Program Management
S-Curve Analysis
Critical Path
Portfolio
3. The document that describes how the project will be executed - monitored - and controlled.
Risk Avoidance
Estimate to Complete
Control Account
Project Management Plan
4. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Risk Breakdown Structure
Enterprise Environmental Factors
Milestone
Path Convergence
5. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Early Start Date
Lead
Organizational Project Management Maturity
Risk Acceptance
6. A hierarchical representation of risks that is organized according to risk categories.
Communication Management Plan
Schedule Model Analysis
Risk Breakdown Structure
Late Finish Date
7. A relationship in which a schedule activity has more than one predecessor.
Phase Gate
Path Convergence
Control Account
Human Resource Plan
8. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Change Control
Risk Transference
Logical Relationship
Communication Management Plan
9. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Discrete Effort
Lead
Preventive Action
Acceptance Criteria
10. The realized cost incurred for the work performed on an activity during a specific time period.
Risk Avoidance
Corrective Action
Finish-to-Finish
Actual Cost
11. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
What-If Sce
Finish-to-Finish
Early Finish Date
Communication Management Plan
12. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Change Control
Risk Avoidance
Pessimistic Duration
Schedule Performance Index
13. A technique for determining the cause and degree of difference between the baseline and actual performance.
Critical Path
Variance Analysis
Project Phase
Precedence Diagramming Method
14. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Finish-to-Finish
Crashing
S-Curve Analysis
Critical Path
15. A formal proposal to modify any document - deliverable - or baseline.
Change Request
Budget at Completion
Risk
Analogous Estimating
16. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Project Schedule
Level of Effort
Earned Value
Cost Management Plan
17. A dependent activity that logically comes after another activity in a schedule.
Successor Activity
Rolling Wave Planning
Acceptance Criteria
Earned Value Management
18. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Schedule Model Analysis
Parametric Estimating
Level of Effort
Project Scope
19. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Risk
Finish-to-Start
Critical Path Activity
Risk Acceptance
20. Any activity on the critical path in a project schedule.
Code of Accounts
Risk Avoidance
Estimate at Completion
Critical Path Activity
21. An activity that logically comes before a dependent activity in a schedule.
Path Divergence
Organizational Process Assets
Phase Gate
Predecessor Activity
22. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
WBS Dictionary
Cost Management Plan
Program Management Office
Bottom-up Estimating
23. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Schedule Model
Change Control
Precedence Diagramming Method
Portfolio
24. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Performing Organization
Risk
Enterprise Environmental Factors
Resource Leveling
25. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Project Manager
WBS Dictionary
Forward Pass
Procurement Management Plan
26. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Project Scope
Critical Chain Method
Percent Complete
To-Complete Performance Index
27. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Late Start Date
Change Request
Code of Accounts
Project Charter
28. A document in which the results of risk analysis and risk response planning are recorded.
Risk Register
Percent Complete
Requirements Management Plan
Assumption
29. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Estimate at Completion
Apportioned Effort
Project Management Office
Project Schedule
30. A dependency between two activities - or between an activity and a milestone.
Project Schedule
Acceptance Criteria
Logical Relationship
Quality Management Plan
31. A grid that links product requirements from their origin to the deliverables that satisfy them.
Logical Relationship
Change Control
Backward Pass
Requirements Traceability Matrix
32. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Change Control
Analogous Estimating
Schedule Model
Milestone
33. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Product Life Cycle
Decomposition
Project Charter
Schedule Management Plan
34. A set of conditions that is required to be met before deliverables are accepted.
Acceptance Criteria
Start-to-Finish
Trigger Condition
Risk Category
35. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Start-to-Finish
Threat
Critical Chain Method
Pessimistic Duration
36. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Risk
Late Start Date
Percent Complete
Cost Performance Index
37. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Crashing
Portfolio Management
Percent Complete
Phase Gate
38. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Resource Breakdown Structure
Late Start Date
Risk Management Plan
Project Charter
39. A calendar that identifies the working days and shifts upon which each specific resource is available.
Baseline
Requirements Traceability Matrix
Resource Calendar
Backward Pass
40. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Total Float
Change Control Board
Discrete Effort
Acceptance Criteria
41. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Baseline
Change Control System
Preventive Action
Phase Gate
42. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Project Calendar
Estimate to Complete
Apportioned Effort
Critical Path
43. A graphical representation of the logical relationships among the project schedule activities.
Project Schedule Network Diagram
Defect Repair
Parametric Estimating
Schedule Management Plan
44. A point in time when the status of the project is recorded.
Requirements Traceability Matrix
Variance Analysis
Data Date
Schedule Model Analysis
45. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Cost Management Plan
Finish-to-Finish
Procurement Management Plan
Risk Avoidance
46. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
What-If Sce
Baseline
Schedule Baseline
Program Management Office
47. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Probability and Impact Matrix
Preventive Action
Critical Path Activity
Phase Gate
48. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Variance at Completion
Project Calendar
Estimate at Completion
Lag
49. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Risk Breakdown Structure
Organizational Breakdown Structure
Earned Value
Control Account
50. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Bottom-up Estimating
Cost Management Plan
Human Resource Plan
Critical Path Method