SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Preventive Action
Percent Complete
Apportioned Effort
Critical Chain Method
2. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Project Schedule
Risk Register
Predecessor Activity
Effort
3. A risk that would have a positive effect on one or more project objectives.
Assumption
Opportunity
Finish-to-Start
Resource Breakdown Structure
4. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Human Resource Plan
Preventive Action
Stakeholder
Organizational Project Management Maturity
5. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Risk Mitigation
Fast Tracking
Performing Organization
Project Manager
6. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Earned Value
Risk Register
Risk Breakdown Structure
Parametric Estimating
7. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Backward Pass
Logical Relationship
Program Management Office
Rolling Wave Planning
8. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Project Scope Statement
Resource Breakdown Structure
Project Management Office
Requirements Traceability Matrix
9. A calendar that identifies the working days and shifts upon which each specific resource is available.
Program Management
Early Finish Date
Critical Path
Resource Calendar
10. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Most Likely Duration
Apportioned Effort
Control Account
Requirements Management Plan
11. A group of potential causes of risk.
Lag
Organizational Process Assets
Estimate at Completion
Risk Category
12. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Project Calendar
Organizational Project Management Maturity
Planned Value
Progressive Elaboration
13. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Product Life Cycle
Threat
Pessimistic Duration
Change Control System
14. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Lessons Learned
Bottom-up Estimating
Project Charter
Risk Mitigation
15. A relationship in which a schedule activity has more than one predecessor.
Path Convergence
Planned Value
Effort
Early Finish Date
16. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Secondary Risk
Schedule Model
Fast Tracking
Critical Chain Method
17. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Risk Mitigation
Sponsor
Project Calendar
Effort
18. The description of the project scope - major deliverables - assumptions - and constraints.
Rolling Wave Planning
Change Request
Project Scope Statement
Path Convergence
19. A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs.
Organizational Breakdown Structure
Probability and Impact Matrix
Earned Value
Schedule Variance
20. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Project Management Plan
Start-to-Finish
Requirements Management Plan
Crashing
21. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Threat
Project Management Office
Scope Baseline
Project Management Plan
22. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Backward Pass
Change Control
Earned Value
Portfolio Balancing
23. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Bottom-up Estimating
Earned Value Management
Logical Relationship
Precedence Diagramming Method
24. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Critical Chain Method
Forward Pass
Precedence Diagramming Method
Portfolio Management
25. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Project
Variance at Completion
Early Start Date
S-Curve Analysis
26. A document in which the results of risk analysis and risk response planning are recorded.
Risk Register
Most Likely Duration
Deliverable
Assumption
27. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Risk Avoidance
Deliverable
Defect Repair
Rolling Wave Planning
28. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Program
Human Resource Plan
Successor Activity
Phase Gate
29. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Project Schedule Network Diagram
Enterprise Environmental Factors
Earned Value
Gantt Chart
30. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Start-to-Finish
Secondary Risk
Schedule Baseline
Path Divergence
31. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Organizational Process Assets
Corrective Action
Change Control
Finish-to-Finish
32. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Project Manager
Lag
Threat
Project Scope Statement
33. The document that describes how the project will be executed - monitored - and controlled.
Risk Breakdown Structure
Cost Variance
Project Management Plan
Logical Relationship
34. The series of phases that a project passes through from its initiation to its closure.
Risk Breakdown Structure
Quality Management Plan
Bottom-up Estimating
Project Life Cycle
35. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Risk Mitigation
Successor Activity
Decomposition
Project Scope
36. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Progressive Elaboration
Threat
Estimate at Completion
Lag
37. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Control Account
Critical Chain Method
Change Control Board
Progressive Elaboration
38. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Schedule Compression
Discrete Effort
Variance at Completion
Critical Chain Method
39. A significant point or event in a project - program - or portfolio.
Lead
Fast Tracking
Milestone
Change Request
40. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Earned Value Management
Data Date
Constraint
Project Management
41. A graphical representation of the logical relationships among the project schedule activities.
Resource Calendar
Project Schedule Network Diagram
Gantt Chart
Summary Activity
42. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Organizational Breakdown Structure
S-Curve Analysis
Early Start Date
Finish-to-Start
43. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Early Finish Date
Schedule Performance Index
Requirements Management Plan
Forward Pass
44. A limiting factor that affects the execution of a project - program - portfolio - or process.
Constraint
Project Life Cycle
Early Finish Date
Program Management Office
45. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Planned Value
Portfolio Balancing
Portfolio
Portfolio Management
46. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Earned Value
WBS Dictionary
Preventive Action
Rolling Wave Planning
47. A dependency between two activities - or between an activity and a milestone.
Logical Relationship
Risk Register
Actual Cost
Project Scope Statement
48. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Most Likely Duration
Communication Management Plan
Parametric Estimating
Project Scope
49. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Finish-to-Start
Analogous Estimating
Crashing
Schedule Model Analysis
50. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Program
Schedule Management Plan
To-Complete Performance Index
Three-Point Estimate