SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Path Divergence
Resource Leveling
Path Convergence
Successor Activity
2. A grid that links product requirements from their origin to the deliverables that satisfy them.
Requirements Traceability Matrix
Organizational Process Assets
WBS Dictionary
Risk Register
3. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Assumption
Project Charter
Project Schedule
Three-Point Estimate
4. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Percent Complete
Analogous Estimating
Start-to-Start
Project Phase
5. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Start-to-Finish
Project Manager
Scope Creep
Project Phase
6. A risk that would have a positive effect on one or more project objectives.
Decision Tree Analysis
Risk Management Plan
Constraint
Opportunity
7. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Free Float
Path Convergence
Late Start Date
Cost Performance Index
8. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Preventive Action
Assumption
Level of Effort
Apportioned Effort
9. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Portfolio
Forward Pass
Schedule Performance Index
Responsibility Assignment Matrix
10. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Responsibility Assignment Matrix
Cost Management Plan
Predecessor Activity
WBS Dictionary
11. A hierarchical representation of risks that is organized according to risk categories.
Risk Breakdown Structure
Rolling Wave Planning
Crashing
Schedule Model Analysis
12. A hierarchical representation of resources by category and type.
Baseline
Resource Breakdown Structure
Start-to-Start
Lessons Learned
13. A relationship in which a schedule activity has more than one successor.
Path Divergence
Cost Management Plan
Human Resource Plan
Gantt Chart
14. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Risk Breakdown Structure
Procurement Management Plan
Finish-to-Finish
Planned Value
15. The measure of work performed expressed in terms of the budget authorized for that work.
Earned Value
Quality Management Plan
Critical Path Method
Fast Tracking
16. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Organizational Project Management Maturity
Analogous Estimating
Organizational Process Assets
S-Curve Analysis
17. Any activity on the critical path in a project schedule.
Critical Path Activity
Predecessor Activity
S-Curve Analysis
Schedule Performance Index
18. A graphical representation of the logical relationships among the project schedule activities.
Discrete Effort
Project Management
Acceptance Criteria
Project Schedule Network Diagram
19. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Project Life Cycle
Cost Management Plan
Start-to-Start
Analogous Estimating
20. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Staffing Management Plan
Most Likely Duration
Schedule Management Plan
Actual Cost
21. The centralized management of one or more portfolios to achieve strategic objectives.
Free Float
Secondary Risk
Milestone
Portfolio Management
22. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Variance at Completion
Code of Accounts
Risk
Start-to-Start
23. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Crashing
Project Schedule
Project Management Office
Risk Transference
24. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Project Charter
Schedule Baseline
Risk Avoidance
Portfolio Management
25. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Late Start Date
Portfolio Management
Risk Management Plan
Free Float
26. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Corrective Action
Late Finish Date
Backward Pass
Free Float
27. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Early Finish Date
Schedule Compression
Schedule Variance
Constraint
28. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Enterprise Environmental Factors
Start-to-Start
Staffing Management Plan
Requirement
29. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Logical Relationship
Probability and Impact Matrix
Portfolio
Precedence Diagramming Method
30. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Acceptance Criteria
Change Control
Summary Activity
Fast Tracking
31. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Early Finish Date
Schedule Performance Index
Trigger Condition
Schedule Variance
32. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Project
Percent Complete
Organizational Project Management Maturity
Project Management Plan
33. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Risk Mitigation
Estimate at Completion
Organizational Breakdown Structure
Schedule Model
34. A dependency between two activities - or between an activity and a milestone.
Responsibility Assignment Matrix
Logical Relationship
Parametric Estimating
Scope Management Plan
35. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Gantt Chart
Scope Creep
Performing Organization
Critical Path
36. A technique for determining the cause and degree of difference between the baseline and actual performance.
Variance Analysis
Project Phase
Schedule Model Analysis
Logical Relationship
37. A technique used to shorten the schedule duration without reducing the project scope.
Analogous Estimating
Gantt Chart
Schedule Compression
Budget at Completion
38. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Resource Calendar
Constraint
Risk Mitigation
Quality Management Plan
39. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Three-Point Estimate
Staffing Management Plan
WBS Dictionary
Critical Path Activity
40. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Late Finish Date
Budget at Completion
What-If Sce
Risk Avoidance
41. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Total Float
Stakeholder
Lag
Product Life Cycle
42. The work performed to deliver a product - service - or result with the specified features and functions.
Lessons Learned
Cost Variance
Risk
Project Scope
43. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Defect Repair
Predecessor Activity
Backward Pass
Schedule Variance
44. A numbering system used to uniquely identify each component of the work breakdown structure.
Code of Accounts
Risk Register
Lag
Resource Calendar
45. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Crashing
Organizational Project Management Maturity
Organizational Process Assets
What-If Sce
46. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Finish-to-Start
Critical Path Activity
Project Management Office
Procurement Management Plan
47. An intentional activity that realigns the performance of the project work with the project management plan.
Corrective Action
Variance at Completion
Risk Category
Earned Value
48. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Effort
Schedule Performance Index
Communication Management Plan
Baseline
49. An event or situation that indicates that a risk is about to occur.
Communication Management Plan
Precedence Diagramming Method
Backward Pass
Trigger Condition
50. A risk that would have a negative effect on one or more project objectives.
Start-to-Finish
Risk
Threat
Schedule Model Analysis