SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Trigger Condition
Project Management
Schedule Variance
Percent Complete
2. The description of the project scope - major deliverables - assumptions - and constraints.
Probability and Impact Matrix
WBS Dictionary
Project Scope Statement
Resource Breakdown Structure
3. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Project Scope Statement
What-If Sce
Opportunity
Corrective Action
4. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Project Scope Statement
Quality Management Plan
Start-to-Start
Requirement
5. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Level of Effort
Performing Organization
S-Curve Analysis
Project Management Office
6. A technique used to shorten the schedule duration without reducing the project scope.
Schedule Compression
Project Calendar
Program Management
Organizational Process Assets
7. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Scope Creep
Lead
Late Start Date
Schedule Baseline
8. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Stakeholder
Project Management Plan
Cost Performance Index
Program
9. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Sponsor
Constraint
Portfolio
Scope Creep
10. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Resource Leveling
Trigger Condition
Requirements Traceability Matrix
Gantt Chart
11. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Change Control System
Sponsor
Rolling Wave Planning
Earned Value Management
12. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Trigger Condition
Finish-to-Start
Parametric Estimating
Lessons Learned
13. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Project Charter
Level of Effort
Effort
Portfolio Balancing
14. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Free Float
Program Management
Most Likely Duration
Estimate to Complete
15. A group of related schedule activities aggregated and displayed as a single activity.
Stakeholder
Summary Activity
Apportioned Effort
Variance at Completion
16. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Project Calendar
Deliverable
Program Management Office
Project Scope Statement
17. The expected cost to finish all the remaining project work.
Estimate to Complete
Lessons Learned
Trigger Condition
Backward Pass
18. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Schedule Compression
Critical Chain Method
Assumption
Data Date
19. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Constraint
WBS Dictionary
Late Finish Date
Defect Repair
20. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Path Divergence
Preventive Action
Lag
Risk Acceptance
21. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Schedule Management Plan
Backward Pass
Estimate to Complete
Cost Variance
22. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Bottom-up Estimating
Risk Mitigation
Earned Value Management
Project Management
23. The realized cost incurred for the work performed on an activity during a specific time period.
Actual Cost
Variance Analysis
Budget at Completion
Quality Management Plan
24. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Change Control Board
Risk Management Plan
Lessons Learned
Portfolio Balancing
25. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Earned Value
Precedence Diagramming Method
Cost Performance Index
Project Management Plan
26. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Risk Mitigation
Threat
Percent Complete
Total Float
27. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Risk Mitigation
Secondary Risk
Cost Variance
Preventive Action
28. A set of conditions that is required to be met before deliverables are accepted.
Portfolio Management
Phase Gate
Forward Pass
Acceptance Criteria
29. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Late Finish Date
Enterprise Environmental Factors
Cost Management Plan
Organizational Breakdown Structure
30. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Earned Value Management
Optimistic Duration
Project Life Cycle
Level of Effort
31. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Human Resource Plan
Portfolio Balancing
To-Complete Performance Index
Project Scope
32. The centralized management of one or more portfolios to achieve strategic objectives.
Project Schedule Network Diagram
Portfolio Management
Path Convergence
Project Schedule
33. An intentional activity that realigns the performance of the project work with the project management plan.
Stakeholder
Earned Value
Corrective Action
Constraint
34. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Project Management Office
Project Schedule Network Diagram
Procurement Management Plan
Portfolio
35. A numbering system used to uniquely identify each component of the work breakdown structure.
Critical Path Method
Quality Management Plan
Risk Management Plan
Code of Accounts
36. A risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a risk.
Three-Point Estimate
Gantt Chart
Risk Mitigation
Critical Path Method
37. A relationship in which a schedule activity has more than one predecessor.
Logical Relationship
Path Convergence
Corrective Action
Project Life Cycle
38. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Decomposition
Project Management
Most Likely Duration
Stakeholder
39. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Late Start Date
Schedule Model
Variance Analysis
Decision Tree Analysis
40. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Program Management
Late Start Date
Path Divergence
Enterprise Environmental Factors
41. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Finish-to-Start
Organizational Project Management Maturity
Product Life Cycle
Risk Register
42. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Deliverable
Finish-to-Finish
Risk Breakdown Structure
Requirement
43. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Product Life Cycle
Change Control Board
Scope Management Plan
Schedule Management Plan
44. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Risk Register
Schedule Model Analysis
Defect Repair
Baseline
45. A grid that shows the project resources assigned to each work package.
Staffing Management Plan
Responsibility Assignment Matrix
Corrective Action
Progressive Elaboration
46. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Risk Management Plan
Schedule Compression
Organizational Process Assets
Requirements Management Plan
47. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Risk Avoidance
Schedule Model Analysis
Decision Tree Analysis
Fast Tracking
48. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Actual Cost
Path Divergence
Procurement Management Plan
Schedule Management Plan
49. The authorized budget assigned to scheduled work.
Requirements Traceability Matrix
Planned Value
Program Management
Performing Organization
50. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Requirements Management Plan
Planned Value
Three-Point Estimate
Free Float