SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A relationship in which a schedule activity has more than one predecessor.
Project Management
Path Convergence
Lead
Organizational Breakdown Structure
2. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Corrective Action
Activity
Crashing
Gantt Chart
3. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Risk Acceptance
Scope Creep
Late Finish Date
Schedule Management Plan
4. A distinct - scheduled portion of work performed during the course of a project.
Activity
Start-to-Start
Baseline
Most Likely Duration
5. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Project Charter
Program Management
Pessimistic Duration
Scope Creep
6. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Schedule Performance Index
Performing Organization
Cost Variance
Estimate to Complete
7. A technique for determining the cause and degree of difference between the baseline and actual performance.
Staffing Management Plan
Variance Analysis
Control Account
Enterprise Environmental Factors
8. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Project Calendar
Lead
Deliverable
Critical Chain Method
9. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Forward Pass
Organizational Project Management Maturity
Crashing
Portfolio Balancing
10. A group of related schedule activities aggregated and displayed as a single activity.
Project Scope
Finish-to-Finish
Summary Activity
Secondary Risk
11. A group of potential causes of risk.
Project Life Cycle
Requirement
Procurement Management Plan
Risk Category
12. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Risk Avoidance
Three-Point Estimate
Stakeholder
Project Management
13. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Project Management Office
Control Account
Risk
Finish-to-Start
14. The expected cost to finish all the remaining project work.
Estimate to Complete
Start-to-Start
Data Date
Analogous Estimating
15. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
What-If Sce
Analogous Estimating
Project Scope
Resource Leveling
16. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Start-to-Start
Schedule Model Analysis
Milestone
Organizational Process Assets
17. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Acceptance Criteria
Effort
Baseline
Risk Transference
18. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Percent Complete
Risk
Precedence Diagramming Method
Optimistic Duration
19. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Project Manager
Most Likely Duration
Lag
Early Start Date
20. A dependency between two activities - or between an activity and a milestone.
Forward Pass
Early Finish Date
Logical Relationship
Communication Management Plan
21. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Requirements Management Plan
Project Calendar
Risk Avoidance
Progressive Elaboration
22. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Summary Activity
Bottom-up Estimating
Estimate to Complete
Change Control
23. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Human Resource Plan
S-Curve Analysis
Milestone
Project
24. The series of phases that a project passes through from its initiation to its closure.
What-If Sce
Project Life Cycle
Progressive Elaboration
Program
25. A limiting factor that affects the execution of a project - program - portfolio - or process.
Scope Management Plan
Procurement Management Plan
Project Calendar
Constraint
26. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Acceptance Criteria
Scope Management Plan
Portfolio
Critical Path
27. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Start-to-Finish
What-If Sce
Product Life Cycle
Gantt Chart
28. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Program Management
Pessimistic Duration
Constraint
Control Account
29. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
S-Curve Analysis
Program Management Office
Estimate at Completion
Sponsor
30. An activity that logically comes before a dependent activity in a schedule.
Resource Breakdown Structure
Risk
Predecessor Activity
Project Phase
31. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Late Finish Date
Requirements Management Plan
Early Start Date
Secondary Risk
32. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Lead
To-Complete Performance Index
Project Management Office
Finish-to-Finish
33. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Late Start Date
Assumption
Rolling Wave Planning
Successor Activity
34. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Critical Path Activity
Precedence Diagramming Method
Product Life Cycle
Organizational Project Management Maturity
35. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Lessons Learned
Path Divergence
Earned Value Management
Late Start Date
36. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Communication Management Plan
Change Control System
Resource Leveling
Product Life Cycle
37. A significant point or event in a project - program - or portfolio.
Secondary Risk
Milestone
Progressive Elaboration
Summary Activity
38. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Progressive Elaboration
Project Calendar
To-Complete Performance Index
Risk
39. An estimate of the longest activity duration - which takes into account all of the known variables that could affect performance.
Risk Breakdown Structure
Project Management Office
Human Resource Plan
Pessimistic Duration
40. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Percent Complete
Threat
Opportunity
Schedule Variance
41. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Control Account
Percent Complete
Deliverable
Phase Gate
42. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Schedule Compression
Discrete Effort
Planned Value
Organizational Process Assets
43. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Free Float
Planned Value
Staffing Management Plan
Late Start Date
44. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Scope Creep
Forward Pass
Preventive Action
Progressive Elaboration
45. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Cost Management Plan
Schedule Model
Schedule Variance
Late Start Date
46. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Risk Transference
Organizational Breakdown Structure
Cost Performance Index
Earned Value Management
47. A calendar that identifies working days and shifts that are available for scheduled activities.
Finish-to-Start
Effort
Requirements Management Plan
Project Calendar
48. A document in which the results of risk analysis and risk response planning are recorded.
Threat
Critical Chain Method
Fast Tracking
Risk Register
49. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Threat
Performing Organization
To-Complete Performance Index
Critical Path
50. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Secondary Risk
Responsibility Assignment Matrix
Late Finish Date
Cost Variance