SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Level of Effort
Resource Leveling
Schedule Compression
Decision Tree Analysis
2. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
WBS Dictionary
Requirement
Risk Management Plan
Critical Path
3. The sum of all budgets established for the work to be performed.
Project Schedule Network Diagram
Three-Point Estimate
Budget at Completion
Quality Management Plan
4. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Earned Value Management
Project Management
Start-to-Start
Risk Avoidance
5. A set of conditions that is required to be met before deliverables are accepted.
Risk Register
Earned Value Management
Project Phase
Acceptance Criteria
6. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Fast Tracking
Performing Organization
Most Likely Duration
Parametric Estimating
7. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Estimate to Complete
Free Float
Lag
Performing Organization
8. A limiting factor that affects the execution of a project - program - portfolio - or process.
Constraint
Data Date
Schedule Compression
Project Schedule Network Diagram
9. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Rolling Wave Planning
WBS Dictionary
Crashing
Finish-to-Finish
10. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Risk Breakdown Structure
Crashing
Stakeholder
Requirement
11. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Path Convergence
Three-Point Estimate
Project Schedule
Program
12. A document in which the results of risk analysis and risk response planning are recorded.
Decision Tree Analysis
Change Control Board
Risk Register
Risk Mitigation
13. A group of potential causes of risk.
Schedule Baseline
Trigger Condition
Risk Category
Level of Effort
14. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Change Request
Baseline
Project Scope
Finish-to-Start
15. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Apportioned Effort
Parametric Estimating
Responsibility Assignment Matrix
Schedule Performance Index
16. A numbering system used to uniquely identify each component of the work breakdown structure.
Analogous Estimating
Code of Accounts
Estimate to Complete
Summary Activity
17. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Preventive Action
Human Resource Plan
Cost Performance Index
Portfolio Balancing
18. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Level of Effort
Path Divergence
Resource Leveling
Parametric Estimating
19. A risk that arises as a direct result of implementing a risk response.
Sponsor
Change Request
Risk Breakdown Structure
Secondary Risk
20. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Optimistic Duration
Product Life Cycle
Risk Category
Project Management
21. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Change Control
Schedule Baseline
Level of Effort
Defect Repair
22. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Project Schedule
Secondary Risk
Summary Activity
Enterprise Environmental Factors
23. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Enterprise Environmental Factors
Project Charter
Responsibility Assignment Matrix
Bottom-up Estimating
24. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Successor Activity
Rolling Wave Planning
Scope Baseline
Change Control
25. Any activity on the critical path in a project schedule.
Critical Path Activity
Acceptance Criteria
Corrective Action
Schedule Performance Index
26. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Project Management Plan
Lessons Learned
Program Management
Constraint
27. The authorized budget assigned to scheduled work.
Planned Value
Early Start Date
Change Request
Baseline
28. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Late Start Date
Constraint
Pessimistic Duration
Path Divergence
29. A distinct - scheduled portion of work performed during the course of a project.
Activity
Constraint
Corrective Action
Defect Repair
30. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Resource Breakdown Structure
Backward Pass
Data Date
Baseline
31. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Enterprise Environmental Factors
Risk Transference
Apportioned Effort
Critical Chain Method
32. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Project Life Cycle
Forward Pass
Lag
What-If Sce
33. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Risk Mitigation
Quality Management Plan
Project Phase
Risk Breakdown Structure
34. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Risk Avoidance
Backward Pass
Schedule Baseline
Schedule Variance
35. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Start-to-Start
Late Finish Date
Forward Pass
Successor Activity
36. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Performing Organization
Lessons Learned
Schedule Performance Index
Schedule Variance
37. The centralized management of one or more portfolios to achieve strategic objectives.
Program Management
Portfolio Management
Level of Effort
To-Complete Performance Index
38. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Sponsor
Earned Value
Forward Pass
Lag
39. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Start-to-Start
Variance Analysis
Communication Management Plan
Progressive Elaboration
40. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Discrete Effort
Free Float
Backward Pass
Late Finish Date
41. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Cost Management Plan
Project Management Office
What-If Sce
Project
42. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Actual Cost
Risk Register
Organizational Project Management Maturity
Probability and Impact Matrix
43. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Lessons Learned
Apportioned Effort
Assumption
Project Management Office
44. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Project Phase
Lag
Finish-to-Start
Deliverable
45. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Portfolio Balancing
Program
WBS Dictionary
Forward Pass
46. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Bottom-up Estimating
Project Scope
Scope Baseline
Finish-to-Start
47. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Actual Cost
Forward Pass
Late Finish Date
Risk Acceptance
48. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Scope Baseline
Level of Effort
Bottom-up Estimating
Project Management Office
49. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Portfolio Balancing
Summary Activity
Organizational Breakdown Structure
Critical Path
50. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Lessons Learned
Risk Avoidance
Program
Total Float