SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The centralized management of one or more portfolios to achieve strategic objectives.
Portfolio Management
Schedule Model Analysis
Forward Pass
Change Control System
2. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Portfolio
Portfolio Management
Decomposition
Budget at Completion
3. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Change Control System
Acceptance Criteria
Opportunity
Lag
4. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Total Float
Schedule Baseline
Phase Gate
Requirements Traceability Matrix
5. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Backward Pass
Organizational Process Assets
Earned Value
Staffing Management Plan
6. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Defect Repair
Project Schedule
Phase Gate
Finish-to-Finish
7. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Phase Gate
Total Float
Analogous Estimating
Performing Organization
8. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Defect Repair
Variance at Completion
Early Start Date
Cost Management Plan
9. Any activity on the critical path in a project schedule.
Critical Path Activity
Precedence Diagramming Method
Three-Point Estimate
Discrete Effort
10. A risk that would have a positive effect on one or more project objectives.
Successor Activity
Earned Value
Opportunity
Threat
11. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Risk Mitigation
Risk Category
Critical Path
Earned Value
12. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Project Phase
Change Control System
Critical Path Method
Risk Transference
13. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Portfolio Management
Gantt Chart
Change Control System
Communication Management Plan
14. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Total Float
Schedule Variance
Project Schedule Network Diagram
Early Start Date
15. A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Variance Analysis
Gantt Chart
Portfolio Balancing
Start-to-Start
16. An intentional activity that realigns the performance of the project work with the project management plan.
Corrective Action
Risk Mitigation
Schedule Management Plan
Phase Gate
17. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Portfolio
Scope Creep
Critical Chain Method
Pessimistic Duration
18. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Total Float
Data Date
Portfolio
Discrete Effort
19. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Phase Gate
Forward Pass
Most Likely Duration
Decomposition
20. A graphical representation of the logical relationships among the project schedule activities.
Actual Cost
Project Schedule Network Diagram
Risk Register
Organizational Breakdown Structure
21. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Opportunity
Change Control Board
Procurement Management Plan
Cost Variance
22. The sum of all budgets established for the work to be performed.
Data Date
Project Management
Schedule Model
Budget at Completion
23. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Early Finish Date
Risk Breakdown Structure
Estimate at Completion
Human Resource Plan
24. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Project Schedule
Progressive Elaboration
Schedule Compression
Bottom-up Estimating
25. The series of phases that a project passes through from its initiation to its closure.
Schedule Performance Index
Risk
Project Life Cycle
Estimate to Complete
26. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Free Float
Communication Management Plan
Finish-to-Finish
Project Management
27. A technique for determining the cause and degree of difference between the baseline and actual performance.
Variance Analysis
Risk Transference
Predecessor Activity
Apportioned Effort
28. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Responsibility Assignment Matrix
Control Account
Procurement Management Plan
Project Schedule
29. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Threat
Rolling Wave Planning
Resource Breakdown Structure
Organizational Project Management Maturity
30. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Scope Creep
Successor Activity
Resource Leveling
Level of Effort
31. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Lead
Risk Management Plan
Predecessor Activity
Start-to-Finish
32. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Activity
Staffing Management Plan
Schedule Model Analysis
Logical Relationship
33. A limiting factor that affects the execution of a project - program - portfolio - or process.
Estimate to Complete
Change Control System
Baseline
Constraint
34. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Portfolio Balancing
Schedule Performance Index
Performing Organization
Scope Management Plan
35. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Project Charter
Organizational Process Assets
Change Request
Project Schedule
36. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Level of Effort
Risk Register
Trigger Condition
Threat
37. A point in time when the status of the project is recorded.
Schedule Performance Index
Requirements Traceability Matrix
Backward Pass
Data Date
38. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Effort
Phase Gate
Most Likely Duration
Schedule Model Analysis
39. An event or situation that indicates that a risk is about to occur.
Organizational Process Assets
Trigger Condition
Optimistic Duration
Project
40. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Requirements Traceability Matrix
Organizational Breakdown Structure
S-Curve Analysis
Project Management Plan
41. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Schedule Management Plan
Total Float
Control Account
Forward Pass
42. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Project Charter
Organizational Project Management Maturity
Three-Point Estimate
Responsibility Assignment Matrix
43. A grid that links product requirements from their origin to the deliverables that satisfy them.
Procurement Management Plan
Requirements Traceability Matrix
Progressive Elaboration
Probability and Impact Matrix
44. The authorized budget assigned to scheduled work.
Project Management Office
Risk Acceptance
Change Control System
Planned Value
45. A calendar that identifies working days and shifts that are available for scheduled activities.
Project Calendar
Optimistic Duration
Program
Pessimistic Duration
46. A relationship in which a schedule activity has more than one successor.
Path Divergence
Cost Management Plan
Actual Cost
Start-to-Finish
47. A document in which the results of risk analysis and risk response planning are recorded.
Risk Register
Change Control
Late Finish Date
Parametric Estimating
48. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Schedule Model
Program
Deliverable
Late Finish Date
49. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Organizational Process Assets
Progressive Elaboration
Project Charter
Project Management Office
50. A significant point or event in a project - program - or portfolio.
Scope Management Plan
Procurement Management Plan
Milestone
Crashing