SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A grid that links product requirements from their origin to the deliverables that satisfy them.
Requirements Traceability Matrix
Late Finish Date
Variance Analysis
Project Charter
2. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Late Start Date
Communication Management Plan
Requirements Traceability Matrix
Schedule Model
3. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Acceptance Criteria
Risk Avoidance
Project Life Cycle
Risk Management Plan
4. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Gantt Chart
Most Likely Duration
Total Float
Lessons Learned
5. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Organizational Project Management Maturity
Project Calendar
Schedule Performance Index
Late Finish Date
6. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
S-Curve Analysis
To-Complete Performance Index
Scope Creep
Project Schedule
7. A risk that would have a positive effect on one or more project objectives.
Opportunity
Change Control
Critical Chain Method
Scope Creep
8. A significant point or event in a project - program - or portfolio.
Cost Variance
Requirements Management Plan
Milestone
Critical Path Activity
9. The centralized management of one or more portfolios to achieve strategic objectives.
Late Start Date
Scope Creep
Portfolio Management
Constraint
10. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Analogous Estimating
Preventive Action
Apportioned Effort
Percent Complete
11. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Schedule Baseline
Variance at Completion
Organizational Process Assets
Human Resource Plan
12. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Scope Creep
Resource Calendar
Project
Project Management Plan
13. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Project Life Cycle
Milestone
Preventive Action
Variance Analysis
14. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Free Float
Three-Point Estimate
Cost Management Plan
Probability and Impact Matrix
15. An intentional activity to modify a nonconforming product or product component.
Decomposition
Early Start Date
Defect Repair
Fast Tracking
16. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Control Account
Organizational Process Assets
Risk Mitigation
Sponsor
17. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
To-Complete Performance Index
Program
Staffing Management Plan
Requirements Management Plan
18. A hierarchical representation of risks that is organized according to risk categories.
WBS Dictionary
Enterprise Environmental Factors
Risk Breakdown Structure
Risk Category
19. The authorized budget assigned to scheduled work.
Change Request
Secondary Risk
Planned Value
Pessimistic Duration
20. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Risk Management Plan
Fast Tracking
Budget at Completion
Organizational Process Assets
21. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Early Start Date
S-Curve Analysis
Crashing
Optimistic Duration
22. A technique used to shorten the schedule duration without reducing the project scope.
Discrete Effort
Baseline
Schedule Compression
Product Life Cycle
23. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Decision Tree Analysis
Optimistic Duration
Pessimistic Duration
Variance Analysis
24. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Late Start Date
Risk Avoidance
Control Account
Earned Value Management
25. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Risk Acceptance
Change Control System
Apportioned Effort
Phase Gate
26. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Apportioned Effort
Gantt Chart
Planned Value
Project Management
27. A temporary endeavor undertaken to create a unique product - service - or result.
Project
Late Finish Date
Backward Pass
Cost Management Plan
28. The document that describes how the project will be executed - monitored - and controlled.
Earned Value Management
Risk Category
Project Management Plan
Responsibility Assignment Matrix
29. A calendar that identifies the working days and shifts upon which each specific resource is available.
Project Management
Critical Path Method
Resource Calendar
WBS Dictionary
30. A graphical representation of the logical relationships among the project schedule activities.
Predecessor Activity
Lag
Actual Cost
Project Schedule Network Diagram
31. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Estimate at Completion
Change Request
Precedence Diagramming Method
Actual Cost
32. A hierarchical representation of resources by category and type.
Scope Baseline
Project Life Cycle
Resource Breakdown Structure
Risk Transference
33. The expected cost to finish all the remaining project work.
Project Life Cycle
Estimate to Complete
Acceptance Criteria
Change Control Board
34. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Logical Relationship
Requirements Management Plan
Decision Tree Analysis
Project Life Cycle
35. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Portfolio
Organizational Project Management Maturity
Project Manager
Project Management
36. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Performing Organization
Opportunity
Change Control Board
Resource Leveling
37. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Performing Organization
Probability and Impact Matrix
Logical Relationship
Risk
38. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Apportioned Effort
Change Control
Budget at Completion
Cost Variance
39. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Risk
Quality Management Plan
Change Control System
Analogous Estimating
40. A formal proposal to modify any document - deliverable - or baseline.
Project Management Office
Change Request
Variance at Completion
Fast Tracking
41. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Project Management Office
Human Resource Plan
Portfolio
Organizational Project Management Maturity
42. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Resource Leveling
Requirements Management Plan
Schedule Variance
Predecessor Activity
43. A grid that shows the project resources assigned to each work package.
Trigger Condition
Responsibility Assignment Matrix
Path Convergence
Start-to-Finish
44. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
S-Curve Analysis
Assumption
Risk Register
Risk Category
45. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Risk Transference
Resource Calendar
Schedule Baseline
Quality Management Plan
46. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Finish-to-Start
Bottom-up Estimating
Deliverable
Precedence Diagramming Method
47. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Product Life Cycle
Program
Three-Point Estimate
Portfolio Management
48. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Apportioned Effort
Risk
Organizational Project Management Maturity
Predecessor Activity
49. A technique for determining the cause and degree of difference between the baseline and actual performance.
Late Finish Date
Variance Analysis
Data Date
Product Life Cycle
50. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
WBS Dictionary
Project Management
Early Start Date
Change Control