SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Project Schedule
Backward Pass
Lessons Learned
Organizational Breakdown Structure
2. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Progressive Elaboration
Critical Path
Crashing
Pessimistic Duration
3. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Human Resource Plan
Stakeholder
Precedence Diagramming Method
Decomposition
4. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
To-Complete Performance Index
Portfolio
Project Management Plan
Schedule Model Analysis
5. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Lag
Program Management Office
Bottom-up Estimating
Path Divergence
6. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Bottom-up Estimating
Estimate at Completion
Organizational Process Assets
Budget at Completion
7. A significant point or event in a project - program - or portfolio.
Project Manager
Milestone
Schedule Management Plan
Path Divergence
8. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
What-If Sce
Three-Point Estimate
Schedule Model
Finish-to-Finish
9. The measure of work performed expressed in terms of the budget authorized for that work.
Resource Breakdown Structure
Cost Management Plan
Most Likely Duration
Earned Value
10. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Scope Management Plan
Portfolio Management
Early Start Date
Project Phase
11. The work performed to deliver a product - service - or result with the specified features and functions.
Sponsor
Actual Cost
Project Scope
Variance at Completion
12. A risk that would have a negative effect on one or more project objectives.
Resource Calendar
Resource Leveling
Threat
Progressive Elaboration
13. A limiting factor that affects the execution of a project - program - portfolio - or process.
Optimistic Duration
Constraint
Enterprise Environmental Factors
Resource Breakdown Structure
14. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Logical Relationship
Deliverable
Early Finish Date
Scope Management Plan
15. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Critical Chain Method
Variance at Completion
Portfolio Balancing
Most Likely Duration
16. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Lead
Assumption
Project Phase
Milestone
17. An intentional activity that realigns the performance of the project work with the project management plan.
Critical Path Method
Most Likely Duration
Scope Management Plan
Corrective Action
18. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Earned Value Management
Progressive Elaboration
Human Resource Plan
Change Control
19. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Project Scope
What-If Sce
Organizational Breakdown Structure
Successor Activity
20. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Resource Calendar
Requirements Traceability Matrix
Progressive Elaboration
Resource Breakdown Structure
21. A temporary endeavor undertaken to create a unique product - service - or result.
Change Request
Risk Category
Project
Baseline
22. A grid that shows the project resources assigned to each work package.
Resource Leveling
WBS Dictionary
Responsibility Assignment Matrix
Risk Category
23. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Lag
Portfolio
Risk Acceptance
Change Control System
24. A formal proposal to modify any document - deliverable - or baseline.
Change Request
Critical Path Activity
Data Date
Critical Path Method
25. A relationship in which a schedule activity has more than one predecessor.
Project Scope Statement
Late Start Date
Project Life Cycle
Path Convergence
26. The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Optimistic Duration
Rolling Wave Planning
Schedule Baseline
Data Date
27. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Precedence Diagramming Method
Budget at Completion
Path Convergence
Quality Management Plan
28. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Preventive Action
Communication Management Plan
Percent Complete
Organizational Project Management Maturity
29. The realized cost incurred for the work performed on an activity during a specific time period.
Estimate to Complete
Program
Requirements Management Plan
Actual Cost
30. A graphical representation of the logical relationships among the project schedule activities.
Communication Management Plan
Project Schedule Network Diagram
Quality Management Plan
Total Float
31. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Threat
S-Curve Analysis
Risk Management Plan
Project Manager
32. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Free Float
Control Account
Estimate to Complete
Cost Performance Index
33. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Fast Tracking
Program
Path Divergence
Earned Value Management
34. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Schedule Variance
Earned Value
Performing Organization
Backward Pass
35. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Actual Cost
Forward Pass
Critical Path Activity
Gantt Chart
36. A document in which the results of risk analysis and risk response planning are recorded.
Product Life Cycle
Optimistic Duration
Risk Register
What-If Sce
37. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Late Finish Date
Project Management Plan
Procurement Management Plan
Fast Tracking
38. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Critical Path
Cost Variance
Change Control Board
Effort
39. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Communication Management Plan
Crashing
Portfolio Balancing
Phase Gate
40. A calendar that identifies working days and shifts that are available for scheduled activities.
Project Calendar
Program
Staffing Management Plan
Critical Path Method
41. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
S-Curve Analysis
Fast Tracking
Threat
Total Float
42. An activity that logically comes before a dependent activity in a schedule.
Predecessor Activity
Forward Pass
Project Management
Responsibility Assignment Matrix
43. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Apportioned Effort
Pessimistic Duration
Communication Management Plan
Lead
44. A dependency between two activities - or between an activity and a milestone.
Rolling Wave Planning
Gantt Chart
Logical Relationship
Late Finish Date
45. The expected cost to finish all the remaining project work.
Schedule Model
Earned Value
Risk Acceptance
Estimate to Complete
46. A dependent activity that logically comes after another activity in a schedule.
Late Finish Date
Acceptance Criteria
Successor Activity
Sponsor
47. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
What-If Sce
Phase Gate
Resource Leveling
Human Resource Plan
48. The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.
Phase Gate
Estimate to Complete
Most Likely Duration
Project Manager
49. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Finish-to-Finish
Predecessor Activity
Successor Activity
Project Phase
50. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Cost Performance Index
Cost Variance
Scope Management Plan
Probability and Impact Matrix