SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The measure of work performed expressed in terms of the budget authorized for that work.
Cost Performance Index
Resource Calendar
Baseline
Earned Value
2. A component of the project or program management plan that describes how the roles and responsibilities - reporting relationships - and staff management will be addressed and structured.
Human Resource Plan
Portfolio Balancing
Lessons Learned
Earned Value
3. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Estimate at Completion
Late Finish Date
Program
Risk Acceptance
4. A group of potential causes of risk.
Risk Category
Scope Baseline
Variance at Completion
Risk
5. A management structure that standardizes the program-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Program Management Office
Precedence Diagramming Method
Project Phase
Late Finish Date
6. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Schedule Model
Cost Variance
Resource Leveling
Free Float
7. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Critical Path Method
Free Float
Code of Accounts
Procurement Management Plan
8. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Phase Gate
Estimate to Complete
S-Curve Analysis
Cost Variance
9. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Project Calendar
To-Complete Performance Index
Rolling Wave Planning
Project
10. Any activity on the critical path in a project schedule.
Threat
Data Date
Portfolio Management
Critical Path Activity
11. A grid that shows the project resources assigned to each work package.
Organizational Project Management Maturity
Responsibility Assignment Matrix
Finish-to-Finish
Procurement Management Plan
12. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Data Date
Earned Value Management
Fast Tracking
Successor Activity
13. A dependency between two activities - or between an activity and a milestone.
Logical Relationship
Project Schedule Network Diagram
Predecessor Activity
Schedule Variance
14. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Corrective Action
Risk Transference
Change Control Board
Successor Activity
15. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Actual Cost
Change Control System
Schedule Variance
Project Charter
16. A numbering system used to uniquely identify each component of the work breakdown structure.
Change Control Board
Code of Accounts
Portfolio
Start-to-Start
17. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Most Likely Duration
Phase Gate
Pessimistic Duration
Performing Organization
18. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Project Phase
Risk Transference
Project Manager
Late Finish Date
19. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Resource Leveling
Preventive Action
Finish-to-Start
Early Finish Date
20. A technique used to estimate cost or duration by applying an average of optimistic - pessimistic - and most likely estimates when there is uncertainty with the individual activity estimates.
Risk Breakdown Structure
Total Float
Risk Category
Three-Point Estimate
21. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Progressive Elaboration
Scope Management Plan
Bottom-up Estimating
Rolling Wave Planning
22. A hierarchical representation of risks that is organized according to risk categories.
Risk Breakdown Structure
Risk Avoidance
Finish-to-Finish
Actual Cost
23. The series of phases that a project passes through from its initiation to its closure.
Project Life Cycle
Probability and Impact Matrix
Optimistic Duration
Finish-to-Start
24. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Threat
Portfolio Balancing
Schedule Model
Project Management Office
25. A point in time when the status of the project is recorded.
Schedule Baseline
Path Divergence
Data Date
Risk Mitigation
26. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Portfolio Balancing
Earned Value Management
Pessimistic Duration
Finish-to-Start
27. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Project Schedule
Baseline
Control Account
Change Control
28. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Parametric Estimating
Responsibility Assignment Matrix
Risk Mitigation
Program Management
29. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Trigger Condition
Forward Pass
Three-Point Estimate
Quality Management Plan
30. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Phase Gate
Risk
Human Resource Plan
Opportunity
31. A risk that would have a positive effect on one or more project objectives.
Requirement
Rolling Wave Planning
Critical Path Activity
Opportunity
32. The expected cost to finish all the remaining project work.
Schedule Model
Schedule Baseline
S-Curve Analysis
Estimate to Complete
33. An event or situation that indicates that a risk is about to occur.
Project Phase
Pessimistic Duration
Trigger Condition
Change Request
34. A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time.
Lessons Learned
Forward Pass
Successor Activity
Risk Category
35. A group of related schedule activities aggregated and displayed as a single activity.
WBS Dictionary
Backward Pass
Responsibility Assignment Matrix
Summary Activity
36. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Portfolio
Variance Analysis
Probability and Impact Matrix
Schedule Performance Index
37. A hierarchical representation of resources by category and type.
Pessimistic Duration
To-Complete Performance Index
Resource Breakdown Structure
Risk Acceptance
38. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Fast Tracking
Sponsor
Scope Creep
Three-Point Estimate
39. A distinct - scheduled portion of work performed during the course of a project.
Preventive Action
Activity
Program Management Office
Decision Tree Analysis
40. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Effort
Change Control
Apportioned Effort
Bottom-up Estimating
41. A technique used to shorten the schedule duration without reducing the project scope.
Rolling Wave Planning
Portfolio Balancing
Project Schedule
Schedule Compression
42. The centralized management of one or more portfolios to achieve strategic objectives.
Project Schedule
Human Resource Plan
Portfolio Management
Critical Chain Method
43. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Schedule Baseline
Risk Category
Schedule Management Plan
Project Management Plan
44. A formal proposal to modify any document - deliverable - or baseline.
Change Request
Early Finish Date
Lessons Learned
Free Float
45. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Earned Value Management
Scope Management Plan
Decision Tree Analysis
Deliverable
46. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Forward Pass
Progressive Elaboration
Path Convergence
Cost Variance
47. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Schedule Model
Program
Three-Point Estimate
Risk Register
48. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Cost Performance Index
Project Management
Summary Activity
Precedence Diagramming Method
49. A calendar that identifies the working days and shifts upon which each specific resource is available.
Stakeholder
Analogous Estimating
Resource Calendar
Requirement
50. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Gantt Chart
Quality Management Plan
Rolling Wave Planning
To-Complete Performance Index