SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Cost Management Plan
Acceptance Criteria
Threat
Project Schedule
2. A technique for determining the cause and degree of difference between the baseline and actual performance.
Critical Path Method
Organizational Process Assets
Variance Analysis
Optimistic Duration
3. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Stakeholder
Late Start Date
Procurement Management Plan
Scope Creep
4. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Risk Transference
Critical Path Activity
Change Control System
Activity
5. The application of knowledge - skills - tools - and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually.
Schedule Compression
Performing Organization
Effort
Program Management
6. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Procurement Management Plan
Decision Tree Analysis
Level of Effort
Lessons Learned
7. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Portfolio
Deliverable
Enterprise Environmental Factors
Variance Analysis
8. A calendar that identifies the working days and shifts upon which each specific resource is available.
Deliverable
Resource Calendar
Late Finish Date
Baseline
9. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Schedule Model Analysis
Optimistic Duration
Phase Gate
Acceptance Criteria
10. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Deliverable
Gantt Chart
Precedence Diagramming Method
Schedule Management Plan
11. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Cost Performance Index
Organizational Project Management Maturity
Risk Mitigation
Schedule Compression
12. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Cost Performance Index
Discrete Effort
Earned Value Management
Critical Chain Method
13. The series of phases that a project passes through from its initiation to its closure.
Project Charter
Sponsor
WBS Dictionary
Project Life Cycle
14. An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.
Parametric Estimating
Threat
Responsibility Assignment Matrix
Scope Baseline
15. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Successor Activity
Logical Relationship
Enterprise Environmental Factors
Project Life Cycle
16. An intentional activity that realigns the performance of the project work with the project management plan.
Corrective Action
Gantt Chart
Crashing
Change Request
17. The document that describes how the project will be executed - monitored - and controlled.
Quality Management Plan
Variance Analysis
Project Management Plan
Most Likely Duration
18. A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Backward Pass
Schedule Variance
Change Control System
Project Management Plan
19. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Fast Tracking
Precedence Diagramming Method
Organizational Process Assets
Assumption
20. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Data Date
Program
Critical Path Method
Pessimistic Duration
21. The description of the project scope - major deliverables - assumptions - and constraints.
Corrective Action
Gantt Chart
Risk Management Plan
Project Scope Statement
22. A graphical representation of the logical relationships among the project schedule activities.
Resource Calendar
Organizational Breakdown Structure
Estimate to Complete
Project Schedule Network Diagram
23. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Trigger Condition
Apportioned Effort
Probability and Impact Matrix
Organizational Breakdown Structure
24. A group of related schedule activities aggregated and displayed as a single activity.
Summary Activity
Optimistic Duration
Cost Variance
Code of Accounts
25. The expected cost to finish all the remaining project work.
Organizational Process Assets
Early Finish Date
Estimate to Complete
Control Account
26. A point in time when the status of the project is recorded.
Start-to-Finish
Data Date
Start-to-Start
Path Convergence
27. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Finish-to-Start
Effort
Finish-to-Finish
Percent Complete
28. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Variance Analysis
Performing Organization
Cost Variance
Organizational Process Assets
29. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Communication Management Plan
Backward Pass
Free Float
Earned Value
30. The authorized budget assigned to scheduled work.
Probability and Impact Matrix
Risk Register
Risk Category
Planned Value
31. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Requirement
Project Scope
Precedence Diagramming Method
Predecessor Activity
32. A limiting factor that affects the execution of a project - program - portfolio - or process.
Constraint
Earned Value Management
Data Date
Variance at Completion
33. The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Baseline
Path Divergence
Critical Path Activity
Earned Value Management
34. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Lead
Organizational Process Assets
Portfolio Balancing
Schedule Management Plan
35. A hierarchical representation of resources by category and type.
Cost Management Plan
Estimate at Completion
Resource Breakdown Structure
Quality Management Plan
36. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Scope Creep
Lessons Learned
Resource Leveling
Change Request
37. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Project Life Cycle
Performing Organization
Preventive Action
Lead
38. A process whereby modifications to documents - deliverables - or baselines associated with the project are identified - documented - approved - or rejected.
Change Control Board
Critical Chain Method
Change Control
Logical Relationship
39. The centralized management of one or more portfolios to achieve strategic objectives.
Risk Register
Portfolio Management
Secondary Risk
Predecessor Activity
40. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Responsibility Assignment Matrix
Total Float
Analogous Estimating
Planned Value
41. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Project Calendar
Estimate at Completion
Change Control
What-If Sce
42. A relationship in which a schedule activity has more than one successor.
Earned Value
Path Divergence
Portfolio Management
Cost Variance
43. A document in which the results of risk analysis and risk response planning are recorded.
Lessons Learned
Risk Register
Constraint
Procurement Management Plan
44. A formally chartered group responsible for reviewing - evaluating - approving - delaying - or rejecting changes to the project and for recording and communicating such decisions.
Change Control Board
Risk Register
Risk Breakdown Structure
Risk
45. A risk that arises as a direct result of implementing a risk response.
Preventive Action
Secondary Risk
Control Account
Critical Path Activity
46. A significant point or event in a project - program - or portfolio.
Cost Management Plan
Human Resource Plan
Milestone
Portfolio Balancing
47. A component of a project or program management plan that describes how costs will be planned - structured - and controlled.
Earned Value
Cost Management Plan
Stakeholder
Assumption
48. A distinct - scheduled portion of work performed during the course of a project.
Activity
Rolling Wave Planning
Organizational Project Management Maturity
Planned Value
49. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Free Float
Late Start Date
Milestone
Risk Category
50. A projection of the amount of budget deficit or surplus - expressed as the difference between the budget at completion and the estimate at completion.
Variance at Completion
Earned Value Management
Level of Effort
Resource Leveling
Sorry!:) No result found.
Can you answer 50 questions in 15 minutes?
Let me suggest you:
Browse all subjects
Browse all tests
Most popular tests
Major Subjects
Tests & Exams
AP
CLEP
DSST
GRE
SAT
GMAT
Certifications
CISSP go to https://www.isc2.org/
PMP
ITIL
RHCE
MCTS
More...
IT Skills
Android Programming
Data Modeling
Objective C Programming
Basic Python Programming
Adobe Illustrator
More...
Business Skills
Advertising Techniques
Business Accounting Basics
Business Strategy
Human Resource Management
Marketing Basics
More...
Soft Skills
Body Language
People Skills
Public Speaking
Persuasion
Job Hunting And Resumes
More...
Vocabulary
GRE Vocab
SAT Vocab
TOEFL Essential Vocab
Basic English Words For All
Global Words You Should Know
Business English
More...
Languages
AP German Vocab
AP Latin Vocab
SAT Subject Test: French
Italian Survival
Norwegian Survival
More...
Engineering
Audio Engineering
Computer Science Engineering
Aerospace Engineering
Chemical Engineering
Structural Engineering
More...
Health Sciences
Basic Nursing Skills
Health Science Language Fundamentals
Veterinary Technology Medical Language
Cardiology
Clinical Surgery
More...
English
Grammar Fundamentals
Literary And Rhetorical Vocab
Elements Of Style Vocab
Introduction To English Major
Complete Advanced Sentences
Literature
Homonyms
More...
Math
Algebra Formulas
Basic Arithmetic: Measurements
Metric Conversions
Geometric Properties
Important Math Facts
Number Sense Vocab
Business Math
More...
Other Major Subjects
Science
Economics
History
Law
Performing-arts
Cooking
Logic & Reasoning
Trivia
Browse all subjects
Browse all tests
Most popular tests