SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Path Divergence
Earned Value
Risk
Precedence Diagramming Method
2. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Requirements Management Plan
Critical Path Activity
Assumption
Analogous Estimating
3. The measure of work performed expressed in terms of the budget authorized for that work.
Three-Point Estimate
Earned Value
Variance at Completion
Effort
4. A distinct - scheduled portion of work performed during the course of a project.
Risk Category
Control Account
Total Float
Activity
5. A significant point or event in a project - program - or portfolio.
Milestone
Human Resource Plan
Phase Gate
Forward Pass
6. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Finish-to-Start
Resource Breakdown Structure
Resource Leveling
Early Start Date
7. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Project Management Plan
Procurement Management Plan
Change Control System
Total Float
8. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Performing Organization
Project Phase
Planned Value
Baseline
9. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Risk
Variance at Completion
Backward Pass
Schedule Variance
10. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Free Float
Early Start Date
Project Schedule
Project Management
11. A group of potential causes of risk.
Pessimistic Duration
Optimistic Duration
Risk Category
Milestone
12. A hierarchical representation of resources by category and type.
Stakeholder
Resource Breakdown Structure
Finish-to-Start
Schedule Compression
13. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Estimate at Completion
Lessons Learned
Project Scope
Cost Performance Index
14. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Early Finish Date
Performing Organization
Decomposition
Enterprise Environmental Factors
15. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Project Life Cycle
Path Convergence
Threat
Cost Variance
16. The description of the project scope - major deliverables - assumptions - and constraints.
Start-to-Finish
Predecessor Activity
Deliverable
Project Scope Statement
17. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Risk Register
Assumption
Budget at Completion
Organizational Process Assets
18. A temporary endeavor undertaken to create a unique product - service - or result.
Acceptance Criteria
Project
Risk
Analogous Estimating
19. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Organizational Process Assets
Program
Critical Path
Gantt Chart
20. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Schedule Performance Index
Start-to-Start
Deliverable
Estimate at Completion
21. A methodology that combines scope - schedule - and resource measurements to assess project performance and progress.
Risk Avoidance
Opportunity
Variance at Completion
Earned Value Management
22. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Risk Acceptance
Acceptance Criteria
Data Date
Precedence Diagramming Method
23. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Optimistic Duration
To-Complete Performance Index
Percent Complete
Probability and Impact Matrix
24. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Portfolio Management
Crashing
Procurement Management Plan
Gantt Chart
25. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint.
Cost Variance
Free Float
Risk Mitigation
Earned Value Management
26. A document in which the results of risk analysis and risk response planning are recorded.
Risk Register
Phase Gate
Project Scope Statement
Finish-to-Start
27. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
To-Complete Performance Index
What-If Sce
Risk
Resource Calendar
28. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Start-to-Start
Decomposition
Variance at Completion
WBS Dictionary
29. Conditions - not under the immediate control of the team - that influence - constrain - or direct the project - program - or portfolio.
Fast Tracking
Critical Chain Method
Free Float
Enterprise Environmental Factors
30. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Product Life Cycle
Scope Management Plan
Decision Tree Analysis
Risk Register
31. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Code of Accounts
Risk Transference
Precedence Diagramming Method
Portfolio
32. A calendar that identifies the working days and shifts upon which each specific resource is available.
Responsibility Assignment Matrix
Enterprise Environmental Factors
Start-to-Finish
Resource Calendar
33. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Product Life Cycle
To-Complete Performance Index
Bottom-up Estimating
Level of Effort
34. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Estimate at Completion
Critical Path Method
Sponsor
Budget at Completion
35. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Phase Gate
Change Control
Apportioned Effort
Change Request
36. A formal proposal to modify any document - deliverable - or baseline.
Requirements Traceability Matrix
Change Request
Risk Transference
Baseline
37. A limiting factor that affects the execution of a project - program - portfolio - or process.
Lessons Learned
Constraint
Variance at Completion
Milestone
38. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Cost Variance
Late Start Date
Change Request
Start-to-Finish
39. A collection of logically related project activities that culminates in the completion of one or more deliverables.
Project Phase
Predecessor Activity
Risk Mitigation
Project Scope Statement
40. An event or situation that indicates that a risk is about to occur.
Estimate to Complete
Enterprise Environmental Factors
Constraint
Trigger Condition
41. The realized cost incurred for the work performed on an activity during a specific time period.
Milestone
Lag
Cost Performance Index
Actual Cost
42. The centralized management of one or more portfolios to achieve strategic objectives.
Scope Baseline
Change Request
Variance Analysis
Portfolio Management
43. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Risk Register
Procurement Management Plan
Most Likely Duration
Crashing
44. An intentional activity that realigns the performance of the project work with the project management plan.
Corrective Action
Optimistic Duration
Total Float
Crashing
45. A graphical representation of the logical relationships among the project schedule activities.
Enterprise Environmental Factors
Lag
Project Schedule Network Diagram
Risk Category
46. A calendar that identifies working days and shifts that are available for scheduled activities.
Risk Acceptance
Project Life Cycle
Project Calendar
Requirements Management Plan
47. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Variance at Completion
Critical Path Activity
Constraint
Project Charter
48. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Change Control Board
Late Start Date
Parametric Estimating
Scope Management Plan
49. A technique used to shorten the schedule duration without reducing the project scope.
Schedule Compression
Early Finish Date
Deliverable
Organizational Breakdown Structure
50. A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Total Float
Activity
Fast Tracking
Level of Effort