SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A grid that links product requirements from their origin to the deliverables that satisfy them.
Lag
Requirements Traceability Matrix
Risk Breakdown Structure
Schedule Compression
2. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Project Management
Critical Chain Method
Crashing
Lead
3. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Trigger Condition
Percent Complete
Three-Point Estimate
Cost Performance Index
4. A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Resource Breakdown Structure
Finish-to-Finish
Phase Gate
Optimistic Duration
5. A risk that would have a positive effect on one or more project objectives.
Earned Value Management
Three-Point Estimate
Opportunity
Optimistic Duration
6. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Organizational Breakdown Structure
Finish-to-Start
Most Likely Duration
Requirements Management Plan
7. The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Change Control
Lag
Corrective Action
Late Start Date
8. A set of conditions that is required to be met before deliverables are accepted.
Acceptance Criteria
Percent Complete
Project Schedule
Estimate to Complete
9. A significant point or event in a project - program - or portfolio.
Start-to-Start
Requirements Traceability Matrix
Milestone
Predecessor Activity
10. The series of phases that a project passes through from its initiation to its closure.
Start-to-Finish
Project Life Cycle
Project Scope Statement
Secondary Risk
11. A graphical representation of the logical relationships among the project schedule activities.
Project Schedule Network Diagram
Free Float
Earned Value Management
Procurement Management Plan
12. A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact.
Risk Avoidance
Late Start Date
Organizational Process Assets
Organizational Breakdown Structure
13. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Risk Avoidance
Apportioned Effort
Schedule Model
Trigger Condition
14. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Finish-to-Start
Phase Gate
Scope Baseline
Threat
15. A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Backward Pass
Project Calendar
Change Control System
Threat
16. Any unique and verifiable product - result - or capability to perform a service that is required to be produced to complete a process - phase - or project.
Free Float
Deliverable
Critical Path
What-If Sce
17. The amount of budget deficit or surplus at a given point in time - expressed as the difference between the earned value and the actual cost.
Decision Tree Analysis
Cost Variance
Program
Responsibility Assignment Matrix
18. A review at the end of a phase in which a decision is made to continue to the next phase - to continue with modification - or to end a project or program.
Portfolio Balancing
Schedule Management Plan
Phase Gate
Opportunity
19. Any activity on the critical path in a project schedule.
Threat
Change Request
Earned Value Management
Critical Path Activity
20. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
Schedule Variance
What-If Sce
Variance Analysis
Estimate at Completion
21. A risk that would have a negative effect on one or more project objectives.
Constraint
Forward Pass
Threat
Change Control
22. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Predecessor Activity
Path Convergence
Rolling Wave Planning
Schedule Variance
23. A point in time when the status of the project is recorded.
Data Date
Schedule Compression
Summary Activity
Defect Repair
24. Projects - programs - subportfolios - and operations managed as a group to achieve strategic objectives.
Performing Organization
Analogous Estimating
Schedule Baseline
Portfolio
25. A representation of the plan for executing the project's activities including durations - dependencies and other planning information - used to produce a project schedule along with other scheduling artifacts.
Schedule Model
Precedence Diagramming Method
Lag
Organizational Project Management Maturity
26. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Schedule Management Plan
Acceptance Criteria
Risk
Resource Breakdown Structure
27. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Decision Tree Analysis
Early Finish Date
Risk
Procurement Management Plan
28. The number of labor units required to complete a schedule activity or work breakdown structure component - often expressed in hours - days - or weeks.
Effort
Risk Acceptance
Scope Management Plan
Assumption
29. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Early Start Date
Defect Repair
Project Charter
Total Float
30. Plans - processes - policies - procedures and knowledge bases specific to and used by the performing organization.
Organizational Process Assets
Effort
Percent Complete
Estimate to Complete
31. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Organizational Breakdown Structure
Finish-to-Start
Critical Path Activity
Portfolio Balancing
32. A person or group who provides resources and support for the project - program - or portfolio - and is accountable for enabling success.
Optimistic Duration
Bottom-up Estimating
Sponsor
S-Curve Analysis
33. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the project completion date - and any schedule constraints.
Organizational Process Assets
Late Finish Date
Risk Category
Path Divergence
34. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Early Start Date
Assumption
Project Charter
To-Complete Performance Index
35. The application of knowledge - skills - tools - and techniques to project activities to meet the project requirements.
Finish-to-Finish
Project Management
Late Start Date
Discrete Effort
36. An earned value management technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period.
Parametric Estimating
Portfolio Management
Corrective Action
S-Curve Analysis
37. The level of an organization's ability to deliver the desired strategic outcomes in a predictable - controllable - and reliable manner.
Organizational Project Management Maturity
Project Scope Statement
Finish-to-Finish
Percent Complete
38. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Pessimistic Duration
Start-to-Start
Project Charter
Critical Path
39. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Schedule Variance
Stakeholder
Schedule Performance Index
Responsibility Assignment Matrix
40. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Performing Organization
Lessons Learned
Finish-to-Start
Risk Category
41. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Portfolio Management
Lag
Communication Management Plan
Project
42. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
WBS Dictionary
Sponsor
Variance at Completion
Responsibility Assignment Matrix
43. A technique used to shorten the schedule duration without reducing the project scope.
Crashing
Organizational Project Management Maturity
Schedule Compression
Logical Relationship
44. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Summary Activity
Risk Management Plan
Quality Management Plan
Project Life Cycle
45. A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs.
Baseline
Risk Acceptance
Portfolio Balancing
Project Schedule
46. The series of phases that represent the evolution of a product - from concept through delivery - growth - maturity - and to retirement.
Activity
Product Life Cycle
Early Start Date
Project Management Office
47. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Gantt Chart
Schedule Performance Index
Requirements Management Plan
Percent Complete
48. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Sponsor
Code of Accounts
Late Start Date
Project Charter
49. A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Project Management Plan
Decomposition
Bottom-up Estimating
Risk Management Plan
50. A management structure that standardizes the project-related governance processes and facilitates the sharing of resources - methodologies - tools - and techniques.
Project Management Office
Schedule Baseline
Cost Variance
Estimate at Completion