SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Most Likely Duration
Project
Finish-to-Finish
Path Convergence
2. A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization.
Procurement Management Plan
Gantt Chart
Risk Register
Bottom-up Estimating
3. The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.
Data Date
Stakeholder
Backward Pass
Progressive Elaboration
4. A grid that shows the project resources assigned to each work package.
Early Start Date
Critical Chain Method
Path Divergence
Responsibility Assignment Matrix
5. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Finish-to-Finish
Responsibility Assignment Matrix
Control Account
Project Schedule
6. A measure of schedule performance expressed as the difference between the earned value and the planned value.
Three-Point Estimate
Schedule Variance
Parametric Estimating
Secondary Risk
7. The approved version of a scope statement - work breakdown structure (WBS) - and its associated WBS dictionary - which can be changed only through formal change control procedures and is used as a basis for comparison.
Predecessor Activity
Preventive Action
Scope Baseline
WBS Dictionary
8. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Portfolio Management
Assumption
Early Finish Date
Critical Path Method
9. A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Start-to-Finish
Scope Management Plan
Activity
Change Control System
10. A measure of schedule efficiency expressed as the ratio of earned value to planned value.
Schedule Performance Index
Discrete Effort
Forward Pass
Staffing Management Plan
11. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Project Manager
Risk Register
Resource Calendar
Optimistic Duration
12. An activity that logically comes before a dependent activity in a schedule.
Risk Acceptance
What-If Sce
Staffing Management Plan
Predecessor Activity
13. A response to a threat that has occurred - for which a prior response had not been planned or was not effective.
What-If Sce
Three-Point Estimate
Sponsor
Schedule Variance
14. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Scope Creep
Path Divergence
Decision Tree Analysis
Finish-to-Finish
15. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Project Manager
Finish-to-Start
Effort
Decomposition
16. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Requirements Traceability Matrix
Gantt Chart
Schedule Compression
Risk Mitigation
17. A technique for determining the cause and degree of difference between the baseline and actual performance.
Variance Analysis
Procurement Management Plan
Three-Point Estimate
Preventive Action
18. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Path Convergence
Constraint
Decomposition
Acceptance Criteria
19. A grid that links product requirements from their origin to the deliverables that satisfy them.
Staffing Management Plan
Requirement
Baseline
Requirements Traceability Matrix
20. A hierarchical representation of the project organization - which illustrates the relationship between project activities and the organizational units that will perform those activities.
Early Start Date
Secondary Risk
Organizational Breakdown Structure
Project Manager
21. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Risk Transference
Decision Tree Analysis
Organizational Process Assets
WBS Dictionary
22. A limiting factor that affects the execution of a project - program - portfolio - or process.
Constraint
Schedule Baseline
Program Management Office
Probability and Impact Matrix
23. A formal proposal to modify any document - deliverable - or baseline.
Change Request
Risk Management Plan
Forward Pass
Organizational Project Management Maturity
24. The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
S-Curve Analysis
Control Account
Baseline
Estimate at Completion
25. An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
Organizational Process Assets
Effort
Change Control
Stakeholder
26. An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
Risk Acceptance
Critical Path
Earned Value
Preventive Action
27. A significant point or event in a project - program - or portfolio.
Milestone
Change Control Board
Program Management Office
What-If Sce
28. An intentional activity to modify a nonconforming product or product component.
Cost Variance
Change Request
Defect Repair
Risk Transference
29. A component of the project - program - or portfolio management plan that describes how - when - and by whom information will be administered and disseminated.
Program Management Office
Project Schedule Network Diagram
Product Life Cycle
Communication Management Plan
30. The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Lead
Risk Register
Discrete Effort
Project Scope Statement
31. In the critical path method - the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the project completion date - and any schedule constraints.
Late Start Date
Responsibility Assignment Matrix
Analogous Estimating
Project Management
32. An activity that can be planned and measured and that yields a specific output. (Note: Discrete effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Discrete Effort
Progressive Elaboration
Risk
Risk Acceptance
33. A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.
Trigger Condition
Critical Path Method
Finish-to-Start
Level of Effort
34. A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal - expressed as the ratio of the cost to finish the outstanding work to the remaining budget.
Requirement
To-Complete Performance Index
Start-to-Finish
Scope Management Plan
35. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Actual Cost
Critical Path Method
Backward Pass
WBS Dictionary
36. A management control point where scope - budget - actual cost - and schedule are integrated and compared to earned value for performance measurement.
Lag
Control Account
Progressive Elaboration
Total Float
37. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Start-to-Finish
Assumption
Analogous Estimating
Quality Management Plan
38. The expected cost to finish all the remaining project work.
Fast Tracking
Finish-to-Start
Schedule Compression
Estimate to Complete
39. A graphical representation of the logical relationships among the project schedule activities.
Early Start Date
Schedule Model
Project Schedule Network Diagram
Resource Leveling
40. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Forward Pass
Staffing Management Plan
Start-to-Start
Late Start Date
41. A group of related projects - subprograms and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually.
Portfolio Balancing
Change Control System
Stakeholder
Program
42. An event or situation that indicates that a risk is about to occur.
Change Control System
Lead
Schedule Model
Trigger Condition
43. A group of potential causes of risk.
Variance Analysis
WBS Dictionary
Risk Category
Requirements Management Plan
44. The work performed to deliver a product - service - or result with the specified features and functions.
Three-Point Estimate
Project Scope
Precedence Diagramming Method
Portfolio
45. The centralized management of one or more portfolios to achieve strategic objectives.
Schedule Compression
Critical Chain Method
Crashing
Portfolio Management
46. A hierarchical representation of risks that is organized according to risk categories.
Communication Management Plan
Risk Breakdown Structure
Threat
Corrective Action
47. A relationship in which a schedule activity has more than one successor.
Variance at Completion
Path Divergence
Pessimistic Duration
Forward Pass
48. A condition or capability that is required to be present in a product - service - or result to satisfy a contract or other formally imposed specification.
Requirement
Lessons Learned
Early Start Date
Project
49. A component of the project or program management plan that establishes the activities for developing - monitoring - and controlling the project or program.
Most Likely Duration
Bottom-up Estimating
Summary Activity
Schedule Management Plan
50. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Activity
Budget at Completion
Lag
Level of Effort