SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
PMI Project Management Vocab
Start Test
Study First
Subjects
:
certifications
,
pmi
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A technique for estimating the duration or cost of an activity or a project - using historical data from a similar activity or project.
Progressive Elaboration
Baseline
Analogous Estimating
Threat
2. A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
S-Curve Analysis
Risk Avoidance
Schedule Model Analysis
Gantt Chart
3. A numbering system used to uniquely identify each component of the work breakdown structure.
Estimate to Complete
Finish-to-Start
Code of Accounts
Organizational Project Management Maturity
4. An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance
Schedule Baseline
Schedule Compression
Apportioned Effort
Finish-to-Start
5. An event or situation that indicates that a risk is about to occur.
Trigger Condition
Organizational Process Assets
Start-to-Finish
Project Schedule Network Diagram
6. An enterprise whose personnel are the most directly involved in doing the work of the project or program.
Probability and Impact Matrix
Late Start Date
Human Resource Plan
Performing Organization
7. A hierarchical representation of risks that is organized according to risk categories.
Early Finish Date
Parametric Estimating
Backward Pass
Risk Breakdown Structure
8. An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance.
Defect Repair
Schedule Model
Program Management Office
Most Likely Duration
9. The expected cost to finish all the remaining project work.
What-If Sce
Total Float
Estimate to Complete
Bottom-up Estimating
10. A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Crashing
Logical Relationship
Procurement Management Plan
Lessons Learned
11. A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Crashing
Fast Tracking
Critical Chain Method
Estimate at Completion
12. The uncontrolled expansion to product or project scope without adjustments to time - cost - and resources.
Predecessor Activity
Earned Value
Scope Creep
Critical Chain Method
13. An uncertain event or condition that - if it occurs - has a positive or negative effect on one or more project objectives.
Organizational Project Management Maturity
Assumption
Risk
Portfolio
14. An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance.
Project Phase
Change Control
Optimistic Duration
Project
15. A distinct - scheduled portion of work performed during the course of a project.
Portfolio Balancing
Risk Acceptance
Schedule Management Plan
Activity
16. A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
What-If Sce
Precedence Diagramming Method
Risk Management Plan
Path Divergence
17. A component of the project or program management plan that describes how requirements will be analyzed - documented and managed.
Opportunity
Performing Organization
Requirements Management Plan
Portfolio
18. A risk that would have a negative effect on one or more project objectives.
Forward Pass
Apportioned Effort
Threat
Constraint
19. A factor in the planning process that is considered to be true - real - or certain - without proof or demonstration.
Assumption
Gantt Chart
Decision Tree Analysis
Human Resource Plan
20. The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Level of Effort
Lessons Learned
Resource Breakdown Structure
Change Control System
21. A point in time when the status of the project is recorded.
Variance at Completion
Project Schedule
Data Date
Successor Activity
22. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Risk Management Plan
Project Schedule
Total Float
Earned Value Management
23. An activity that does not produce definitive end products and is measured by the passage of time. (Note: Level of effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Critical Path
Gantt Chart
Variance Analysis
Level of Effort
24. A bar chart of schedule information where activities are listed on the vertical axis - dates are shown on the horizontal axis - and activity durations are shown as horizontal bars placed according to start and finish dates.
Parametric Estimating
Gantt Chart
Late Finish Date
Variance at Completion
25. The sequence of activities that represents the longest path through a project - which determines the shortest possible duration.
Critical Path
Resource Leveling
Code of Accounts
Lead
26. The process of optimizing the mix of portfolio components to further the strategic objectives of the organization.
Portfolio
Code of Accounts
Portfolio Balancing
Parametric Estimating
27. A graphical representation of the logical relationships among the project schedule activities.
Variance Analysis
Project Schedule Network Diagram
Sponsor
Change Request
28. A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.
Resource Leveling
Resource Breakdown Structure
Portfolio Management
WBS Dictionary
29. A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Resource Breakdown Structure
Project Charter
Risk Category
Lead
30. A risk response strategy whereby the project team shifts the impact of a threat to a third party - together with ownership of the response.
Data Date
S-Curve Analysis
Risk Transference
Corrective Action
31. A component of the project or program management plan that describes how the scope will be defined - developed - monitored - controlled - and verified.
Critical Path Method
Change Control System
Scope Management Plan
Lead
32. A document that provides detailed deliverable - activity - and scheduling information about each component in the work breakdown structure.
Change Control Board
WBS Dictionary
Decision Tree Analysis
Path Divergence
33. A formal proposal to modify any document - deliverable - or baseline.
Change Request
Level of Effort
Progressive Elaboration
Path Convergence
34. A significant point or event in a project - program - or portfolio.
Variance Analysis
Resource Leveling
Milestone
Assumption
35. A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed.
Cost Variance
Level of Effort
Staffing Management Plan
Stakeholder
36. An output of a schedule model that presents linked activities with planned dates - durations - milestones - and resources.
Project Schedule
Backward Pass
Schedule Baseline
Change Control System
37. A component of the project or program management plan that describes how an organization's quality policies will be implemented.
Deliverable
Early Finish Date
Quality Management Plan
Decomposition
38. A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Cost Performance Index
Baseline
Control Account
Late Finish Date
39. A technique used for dividing and sub-dividing the project scope and project deliverables into smaller - more manageable parts.
Path Divergence
Early Finish Date
Critical Path
Decomposition
40. The document that describes how the project will be executed - monitored - and controlled.
Project Management Plan
Rolling Wave Planning
Milestone
Lag
41. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic - the data date - and any schedule constraints.
Bottom-up Estimating
Project Schedule Network Diagram
Early Start Date
Portfolio Management
42. In the critical path method - the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic - the data date - and any schedule constraints.
Project Schedule
Risk Avoidance
Change Control
Early Finish Date
43. The work performed to deliver a product - service - or result with the specified features and functions.
Risk Register
Project Scope
Requirements Management Plan
Program Management Office
44. A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Finish-to-Start
Late Finish Date
Risk Mitigation
Percent Complete
45. An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component.
Data Date
Percent Complete
Variance at Completion
Change Control
46. A component of the project - program - or portfolio management plan that describes how risk management activities will be structured and performed.
Forward Pass
Acceptance Criteria
Total Float
Risk Management Plan
47. An iterative planning technique in which the work to be accomplished in the near term is planned in detail - while the work in the future is planned at a higher level.
Rolling Wave Planning
Program Management
Risk Category
Start-to-Finish
48. The centralized management of one or more portfolios to achieve strategic objectives.
Path Divergence
Portfolio Management
Schedule Model Analysis
Start-to-Start
49. A calendar that identifies the working days and shifts upon which each specific resource is available.
Resource Calendar
Resource Leveling
Early Finish Date
Preventive Action
50. A dependency between two activities - or between an activity and a milestone.
Logical Relationship
Forward Pass
Program Management
Requirement
Sorry!:) No result found.
Can you answer 50 questions in 15 minutes?
Let me suggest you:
Browse all subjects
Browse all tests
Most popular tests
Major Subjects
Tests & Exams
AP
CLEP
DSST
GRE
SAT
GMAT
Certifications
CISSP go to https://www.isc2.org/
PMP
ITIL
RHCE
MCTS
More...
IT Skills
Android Programming
Data Modeling
Objective C Programming
Basic Python Programming
Adobe Illustrator
More...
Business Skills
Advertising Techniques
Business Accounting Basics
Business Strategy
Human Resource Management
Marketing Basics
More...
Soft Skills
Body Language
People Skills
Public Speaking
Persuasion
Job Hunting And Resumes
More...
Vocabulary
GRE Vocab
SAT Vocab
TOEFL Essential Vocab
Basic English Words For All
Global Words You Should Know
Business English
More...
Languages
AP German Vocab
AP Latin Vocab
SAT Subject Test: French
Italian Survival
Norwegian Survival
More...
Engineering
Audio Engineering
Computer Science Engineering
Aerospace Engineering
Chemical Engineering
Structural Engineering
More...
Health Sciences
Basic Nursing Skills
Health Science Language Fundamentals
Veterinary Technology Medical Language
Cardiology
Clinical Surgery
More...
English
Grammar Fundamentals
Literary And Rhetorical Vocab
Elements Of Style Vocab
Introduction To English Major
Complete Advanced Sentences
Literature
Homonyms
More...
Math
Algebra Formulas
Basic Arithmetic: Measurements
Metric Conversions
Geometric Properties
Important Math Facts
Number Sense Vocab
Business Math
More...
Other Major Subjects
Science
Economics
History
Law
Performing-arts
Cooking
Logic & Reasoning
Trivia
Browse all subjects
Browse all tests
Most popular tests