Test your basic knowledge |

Project Management Using Microsoft Project

Instructions:
  • Answer 50 questions in 15 minutes.
  • If you are not ready to take this test, you can study here.
  • Match each statement with the correct term.
  • Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.

This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The number of resources required to get the tasks/assignments completed.






2. Time delay. Sometimes - it's preferred to have lag shown as a task. You can assign costs to it - that way. Style sheets will indicate this.






3. View -> Timeline check box. Shows timeline - but by default - nothing's on it. To add items - right click and 'add to timeline'.






4. Create file. Set up file properties. Set a start date. Set up calendars and working time.






5. Appears: ewk means: Elapsed week






6. Appears: eday means: Elapsed day






7. Always preserve the duration of a task. Changing duration when fixed will impact work.






8. Project Tab -> Change Working time. Define the actual 'hours' of work - which days work happens (weekends grayed out by default) - and 'exceptions' to standard work times. Work weeks tab present too.






9. Appears: emon means: Elapsed month






10. The Precedence Diagram Method is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes - referred to as nodes - to represent activities and connects them with arrows that






11. Work - resource - cost.






12. Always preserve the number of people working on a task. Changing units when fixed will impact duration.






13. Two critical tasks - both same duration - vying for one resource - who wins?






14. File -> Options -> Scheduling --> Drop down for Decimal or Percentage.






15. Tasks - resources - assignments - all have dialogs. Example: resource leveling. Project information dialog very important.






16. Appears: emin means: Elapsed minute






17. Shows logical relationship between tasks. View tab -> 'split view' section -> details checked -> More views -> Select there.






18. Their purpose is to ORGANIZE. Summary tasks have work packages or other summary tasks which comprise the parent summary task. Summary tasks are NOT scheduled. The children tasks are what need to be scheduled.






19. Changing the working time in the 'details' section of the working time dialog won't change the default start time in the options -> scheduling settings. Try to keep these in sync.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


20. Function key 5. You can go directly to ID - or 'date'.






21. Focus on Gantt -> Format ribbon ->






22. The acceloration of the successor task. 'Negative lag'






23. Finish to start - finish to finish - start to start - start to finish. All are 'at least'.






24. The WBS contains 100% of the work defined by the project scope and captures all deliverables - internal - external - interim - in terms of the work to be completed - including project management.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


25. A logical relationship that states that for one project to begin - another must also be underway. For example - the writing of a business proposal must have begun in order for editing of the proposal to take place.






26. Task ribbon -> 'task' -> recurring task. An easy way to schedule reccuring meetings.






27. File -> Options -> Quick Access tool bar. Examples: Tables and Vies - good stuff.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


28. U = W / D Work divided by duration.






29. Gantt Chart with 'Entry' table on left.






30. Can be added to the ribbon - and it walks user through formatting of the gantt chart. Pretty cool.






31. Task ribbon -> schedule section -> broken task icon. Reschedule incomplete work - etc.






32. Hiding does not delete data. If you hide a column - data maintains - but to get it back - you'll need to right click - insert column.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


33. Ensuring that the successor activity does not begin until after the predecessor activity is completed is implementing a start-to-finish (SF) model. This is the most logical path to follow when planning a project. Those in project management should be






34. File -> info -> Project information -> advanced properties.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


35. Start date - Current date - finish date - status date - schedule from - calendar - & priority (with project pro). Enterprise custom fields here too - if you're hooked into enterprise.






36. Two CRITICAL tasks vying for one resource - who wins?






37. Task calendar - resource calendar - base calendar.






38. Appears: min means: minute






39. Network Diagrom -> Format ribbon -> format.






40. Tables - charts - usage tables - and sheets.






41. Responsibility Assignment Matrix.






42. Work divided by available resource units. Formula: D=W/U






43. Tables are made up of fields.






44. W = D + U Duration plus available resource units






45. A compact - matrix representation of a system or project. The approach can be used to model complex systems in systems engineering or systems analysis - and in project planning and project management.






46. Fixed Duration - Fixed Units - or Fixed Work. Described on page 72 of Project 2010 book.






47. Two tasks vying for one resource - who wins?






48. Default view in Network Diagram. Without LINK LABELS - you won't see lag time - etc. The term finish to start refers specifically to the logical relationship that exits between the activities that make up he entirety of the project in which it is det






49. The total direct and indirect costs incurred in accomplishing work on an activity during a given period.






50. Always preserve the number of hours to perform a task. Changing work when fixed will impact duration.







Sorry!:) No result found.

Can you answer 50 questions in 15 minutes?


Let me suggest you:



Major Subjects



Tests & Exams


AP
CLEP
DSST
GRE
SAT
GMAT

Most popular tests