SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Project Management Using Microsoft Project
Start Test
Study First
Subjects
:
certifications
,
microsoft-project
,
business-skills
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The WBS contains 100% of the work defined by the project scope and captures all deliverables - internal - external - interim - in terms of the work to be completed - including project management.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
2. Changing the working time in the 'details' section of the working time dialog won't change the default start time in the options -> scheduling settings. Try to keep these in sync.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
3. If '______________' isn't checked - for example - then you won't be able to set a style for critical tasks.
Critical Tasks
Working Time & 'Default' start/end time (Project 2010)
Units
Actual Cost
4. Appears: eday means: Elapsed day
Gantt Chart Wizard (Project 2010)
ed (Abbreviations Project 2010)
'80 hour rule'
Do not
5. File -> Options -> Scheduling --> Drop down for Decimal or Percentage.
Fixed Duration
Gantt Chart Wizard (Project 2010)
Show Assignment Units as (Project 2010)
h (Abbreviations Project 2010)
6. Always preserve the number of people working on a task. Changing units when fixed will impact duration.
Network Diagram best practices
Fixed Units
Start to Finish (SF)
Finish to Start
7. Gantt Chart with 'Entry' table on left.
Default view (Project 2010)
Customize 'Quick Access Tool Bar'
Initializing a Project (Project 2010)
Finish to Start
8. Work divided by available resource units. Formula: D=W/U
Timeline (Project 2010)
Duration
ed (Abbreviations Project 2010)
Lead
9. Two critical tasks - both same duration - vying for one resource - who wins?
Task with first ID
DSM Design Structure Matrix
Manually
Network Diagram best practices
10. Task calendar - resource calendar - base calendar.
Calendars to consider
Work
Logical Relationships in PDM
WBS Code (Project 2010)
11. No single activity or group of activities to produce a single deliverable should be more than 80 hours of effort.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
12. efines units.
Working Time & 'Default' start/end time (Project 2010)
ed (Abbreviations Project 2010)
Inspect feature (Project 2010)
Material resource
13. A compact - matrix representation of a system or project. The approach can be used to model complex systems in systems engineering or systems analysis - and in project planning and project management.
DSM Design Structure Matrix
ew (Abbreviations Project 2010)
Project information dialog (Project 2010)
Lag
14. Task ribbon -> 'inspect' button-> Inspect Task. It shows more details about highlighted task - including critical predecessor task. Very useful tool. Especially when resources are over allocated.
d (Abbreviations Project 2010)
'80 hour rule'
Inspect feature (Project 2010)
em (Abbreviations Project 2010)
15. Responsibility Assignment Matrix.
Gantt Chart Wizard (Project 2010)
Calendar/ Working time (Project 2010)
Earned Value
RAM
16. Can be added to the ribbon - and it walks user through formatting of the gantt chart. Pretty cool.
Show Assignment Units as (Project 2010)
Gantt Chart Wizard (Project 2010)
File Name vs. Project name (Project 2010)
Table (Project 2010)
17. U = W / D Work divided by duration.
WBS Work Breakdown Structure
Units
ed (Abbreviations Project 2010)
SNET
18. Always preserve the number of hours to perform a task. Changing work when fixed will impact duration.
Work Package (WBS)
Calendar/ Working time (Project 2010)
Fixed Work
Accessing 'Properties' (Project 2010)
19. .mpp file extension. The actual project file.
em (Abbreviations Project 2010)
eh (Abbreviations Project 2010)
Project Files (Project 2010)
Lag
20. ______ link Summary Tasks.
Do not
File Name vs. Project name (Project 2010)
emo (Abbreviations Project 2010)
Peak
21. Their purpose is to ORGANIZE. Summary tasks have work packages or other summary tasks which comprise the parent summary task. Summary tasks are NOT scheduled. The children tasks are what need to be scheduled.
The task which has the LEAST slack is more important - Min-slack wins
Reccuring Tasks
Units
Summary tasks (WBS)
22. Tables - charts - usage tables - and sheets.
Views (Project 2010)
eh (Abbreviations Project 2010)
Fixed Duration
Bar Style (Project 2010)
23. Shows logical relationship between tasks. View tab -> 'split view' section -> details checked -> More views -> Select there.
Relationship Diagram (Project 2010)
Duration
Fixed Work
Inspect feature (Project 2010)
24. File -> Info -> Organizer. Access global mpt - delete views - etc. (ADD MORE)
Calendar/ Working time (Project 2010)
Organizer (Project 2010)
em (Abbreviations Project 2010)
Critical Tasks
25. Appears: emon means: Elapsed month
emo (Abbreviations Project 2010)
Bar Style (Project 2010)
RAM
ed (Abbreviations Project 2010)
26. Tasks - resources - assignments - all have dialogs. Example: resource leveling. Project information dialog very important.
Duration
Lead
Actual Cost
Dialogs (Project 2010)
27. Vitally important. It shows how much time remains - which indicates whether or not tasks need to be re-planned.
Work Package (WBS)
Remaining Duration
Dialogs (Project 2010)
Initializing a Project (Project 2010)
28. Time delay. Sometimes - it's preferred to have lag shown as a task. You can assign costs to it - that way. Style sheets will indicate this.
Manually
Lag
Summary tasks (WBS)
Initializing a Project (Project 2010)
29. Default view in Network Diagram. Without LINK LABELS - you won't see lag time - etc. The term finish to start refers specifically to the logical relationship that exits between the activities that make up he entirety of the project in which it is det
Finish to Start
PDM
Lag
Material resource
30. Start date - Current date - finish date - status date - schedule from - calendar - & priority (with project pro). Enterprise custom fields here too - if you're hooked into enterprise.
m (Abbreviations Project 2010)
Project information dialog (Project 2010)
Customize 'Quick Access Tool Bar'
Gantt Chart Wizard (Project 2010)
31. Finish to start - finish to finish - start to start - start to finish. All are 'at least'.
Manually
Logical Relationships in PDM
Gantt Chart Wizard (Project 2010)
Finish to Start
32. W = D + U Duration plus available resource units
WBS Code (Project 2010)
Work
'Hiding' columns (Project 2010)
DSM Design Structure Matrix
33. Project template (.mpt) - or Global MPT file. Drives what you see in the project. Corporations may have their own.
Fixed Work
Initializing a Project (Project 2010)
d (Abbreviations Project 2010)
Template (Project 2010)
34. Two tasks vying for one resource - who wins?
Drawing on Gantt (Project 2010)
The task which has the LEAST slack is more important - Min-slack wins
RAM
File Name vs. Project name (Project 2010)
35. A logical relationship that states that for one project to begin - another must also be underway. For example - the writing of a business proposal must have begun in order for editing of the proposal to take place.
Fixed Duration
Start to Start
The task which has the LEAST slack is more important - Min-slack wins
ed (Abbreviations Project 2010)
36. Ensuring that the successor activity does not begin until after the predecessor activity is completed is implementing a start-to-finish (SF) model. This is the most logical path to follow when planning a project. Those in project management should be
Default view (Project 2010)
Task with minimum duration
'Hiding' columns (Project 2010)
Start to Finish (SF)
37. It is NOT an exhaustive list of work. It is instead a comprehensive classification of project scope. Contains Sub-components - work packages (child of sub-component). Further work packages can be children of other work packages. Summary tasks are the
m (Abbreviations Project 2010)
WBS Work Breakdown Structure
Units
Task with first ID
38. An 'activity' - or 'task'. The bottom 'child' task - there's nothing underneath it. If there are sub-components - or 'children' tasks below a parent task - that parent task is a SUMMARY task.
Critical Tasks
Work Package (WBS)
Drawing on Gantt (Project 2010)
Box Styles (Project 2010)
39. Focus on Gantt -> Format ribbon ->
Manual and Auto scheduled tasks
Reccuring Tasks
Task Type
Drawing on Gantt (Project 2010)
40. An approach for monitoring project progress that relies on the budgeted cost of activities completed to ascribe value
Earned Value
Peak
Terminal element
Resource types
41. Appears: day means: day
Timeline (Project 2010)
d (Abbreviations Project 2010)
WBS Code (Project 2010)
Organizer (Project 2010)
42. Create file. Set up file properties. Set a start date. Set up calendars and working time.
Earned Value
Reccuring Tasks
RAM
Initializing a Project (Project 2010)
43. The acceloration of the successor task. 'Negative lag'
Lead
Reccuring Tasks
Start to Start
WBS Work Breakdown Structure
44. Appears: ewk means: Elapsed week
Splitting tasks (Project 2010)
RAM
ew (Abbreviations Project 2010)
'Hiding' columns (Project 2010)
45. To switch between ____________: (Project 2010) - Use the bottom-left icon. Use the ribbon. Task mode column in entry table. File -> options -> schedule.
Manual and Auto scheduled tasks
Terminal element
Gantt Chart Wizard (Project 2010)
Inspect feature (Project 2010)
46. A terminal element is the lowest element (activity or deliverable) in a WBS; it is not further subdivided. Sometimes called a 'work package' - but NOT synonymous.
Terminal element
Calendar/ Working time (Project 2010)
DSM Design Structure Matrix
Duration
47. Appears: emin means: Elapsed minute
Customize 'Quick Access Tool Bar'
Accessing 'Properties' (Project 2010)
em (Abbreviations Project 2010)
Earned Value
48. Fixed Duration - Fixed Units - or Fixed Work. Described on page 72 of Project 2010 book.
WBS Work Breakdown Structure
Network Diagram best practices
Project information dialog (Project 2010)
Task Type
49. Task ribbon -> 'task' -> recurring task. An easy way to schedule reccuring meetings.
Project information dialog (Project 2010)
SNET
GO TO (Project 2010)
Reccuring Tasks
50. 'Start no earlier than' constraint.
Accessing 'Properties' (Project 2010)
SNET
Logical Relationships in PDM
m (Abbreviations Project 2010)