SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Project Management Using Microsoft Project
Start Test
Study First
Subjects
:
certifications
,
microsoft-project
,
business-skills
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. An 'activity' - or 'task'. The bottom 'child' task - there's nothing underneath it. If there are sub-components - or 'children' tasks below a parent task - that parent task is a SUMMARY task.
Work Package (WBS)
'Hiding' columns (Project 2010)
DSM Design Structure Matrix
Bar Style (Project 2010)
2. U = W / D Work divided by duration.
Start to Start
ed (Abbreviations Project 2010)
Template (Project 2010)
Units
3. Responsibility Assignment Matrix.
RAM
Lead
Start to Start
Peak
4. Two critical tasks - both same duration - vying for one resource - who wins?
Task with first ID
Start to Finish (SF)
Box Styles (Project 2010)
Critical Tasks
5. Hiding does not delete data. If you hide a column - data maintains - but to get it back - you'll need to right click - insert column.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
6. Gantt Chart with 'Entry' table on left.
Timeline (Project 2010)
Initializing a Project (Project 2010)
Lag
Default view (Project 2010)
7. Always preserve the number of hours to perform a task. Changing work when fixed will impact duration.
Summary tasks (WBS)
ew (Abbreviations Project 2010)
Fixed Work
Dialogs (Project 2010)
8. The Precedence Diagram Method is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes - referred to as nodes - to represent activities and connects them with arrows that
Units
Earned Value
Peak
PDM
9. Project Tab -> Change Working time. Define the actual 'hours' of work - which days work happens (weekends grayed out by default) - and 'exceptions' to standard work times. Work weeks tab present too.
Duration
Form (Project 2010)
Calendar/ Working time (Project 2010)
Remaining Duration
10. Appears: emon means: Elapsed month
'Hiding' columns (Project 2010)
Project Files (Project 2010)
Drawing on Gantt (Project 2010)
emo (Abbreviations Project 2010)
11. The acceloration of the successor task. 'Negative lag'
m (Abbreviations Project 2010)
Lead
Task with first ID
Dialogs (Project 2010)
12. Always preserve the duration of a task. Changing duration when fixed will impact work.
mo (Abbreviations Project 2010)
'Hiding' columns (Project 2010)
Start to Finish (SF)
Fixed Duration
13. Function key 5. You can go directly to ID - or 'date'.
eh (Abbreviations Project 2010)
Calendar/ Working time (Project 2010)
Table (Project 2010)
GO TO (Project 2010)
14. Network Diagrom -> Format ribbon -> format.
m (Abbreviations Project 2010)
Box Styles (Project 2010)
eh (Abbreviations Project 2010)
Manual and Auto scheduled tasks
15. Gantt Chart -> Format -> Bar Styles segment -> format drop down. Adjust all aspects of the bars in the gantt.
Accessing 'Properties' (Project 2010)
Units
'80 hour rule'
Bar Style (Project 2010)
16. Start date - Current date - finish date - status date - schedule from - calendar - & priority (with project pro). Enterprise custom fields here too - if you're hooked into enterprise.
Initializing a Project (Project 2010)
Project information dialog (Project 2010)
Timeline (Project 2010)
Organizer (Project 2010)
17. Tasks - resources - assignments - all have dialogs. Example: resource leveling. Project information dialog very important.
'Hiding' columns (Project 2010)
Critical Tasks
Dialogs (Project 2010)
Units
18. Ensuring that the successor activity does not begin until after the predecessor activity is completed is implementing a start-to-finish (SF) model. This is the most logical path to follow when planning a project. Those in project management should be
Units
Start to Finish (SF)
Actual Cost
PDM
19. 1. Initiation 2. Planning 3. Execution 4. Monitoring & Control 5. Closing
5 phases of project
mo (Abbreviations Project 2010)
Splitting tasks (Project 2010)
eh (Abbreviations Project 2010)
20. Can be added to the ribbon - and it walks user through formatting of the gantt chart. Pretty cool.
Gantt Chart Wizard (Project 2010)
Start to Start
Drawing on Gantt (Project 2010)
Units
21. 'Start no earlier than' constraint.
Template (Project 2010)
Timeline (Project 2010)
Finish to Start
SNET
22. No single activity or group of activities to produce a single deliverable should be more than 80 hours of effort.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
23. .mpp file extension. The actual project file.
em (Abbreviations Project 2010)
w (Abbreviations Project 2010)
Do not
Project Files (Project 2010)
24. An approach for monitoring project progress that relies on the budgeted cost of activities completed to ascribe value
RAM
Calendar/ Working time (Project 2010)
WBS Code (Project 2010)
Earned Value
25. Matches the outline number initially in Project 2010. It is common for work breakdown structure elements to be numbered sequentially to reveal the hierarchical structure. For example 1.3.2 Rear Wheel identifies this item as a Level 3 WBS element - si
Fixed Duration
WBS Code (Project 2010)
Start to Finish (SF)
Task with first ID
26. Tables - charts - usage tables - and sheets.
SNET
Units
Views (Project 2010)
Gantt Chart Wizard (Project 2010)
27. Time delay. Sometimes - it's preferred to have lag shown as a task. You can assign costs to it - that way. Style sheets will indicate this.
Units
Remaining Duration
Critical Tasks
Lag
28. Amendment to task type.
Summary tasks (WBS)
Task Type
Effort Driven
Work
29. If '______________' isn't checked - for example - then you won't be able to set a style for critical tasks.
PDM
ew (Abbreviations Project 2010)
Manual and Auto scheduled tasks
Critical Tasks
30. A compact - matrix representation of a system or project. The approach can be used to model complex systems in systems engineering or systems analysis - and in project planning and project management.
DSM Design Structure Matrix
h (Abbreviations Project 2010)
Drawing on Gantt (Project 2010)
GO TO (Project 2010)
31. Always preserve the number of people working on a task. Changing units when fixed will impact duration.
Fixed Units
Task with minimum duration
Duration
ed (Abbreviations Project 2010)
32. Single Start - Single Finish. No 'danglers'. Everything must be connected. No loops.
Project Files (Project 2010)
Network Diagram best practices
Customize 'Quick Access Tool Bar'
Drawing on Gantt (Project 2010)
33. Work divided by available resource units. Formula: D=W/U
Accessing 'Properties' (Project 2010)
'80 hour rule'
Duration
m (Abbreviations Project 2010)
34. Appears: hr means: hour
Work Package (WBS)
Finish to Start
m (Abbreviations Project 2010)
h (Abbreviations Project 2010)
35. Contains information relative to tasks.
Critical Tasks
File Name vs. Project name (Project 2010)
emo (Abbreviations Project 2010)
Form (Project 2010)
36. Appears: wk means: week
Lag
w (Abbreviations Project 2010)
Terminal element
Box Styles (Project 2010)
37. Appears: emin means: Elapsed minute
Finish to Start
Project information dialog (Project 2010)
Peak
em (Abbreviations Project 2010)
38. Fixed Duration - Fixed Units - or Fixed Work. Described on page 72 of Project 2010 book.
Inspect feature (Project 2010)
Task Type
Earned Value
Show Assignment Units as (Project 2010)
39. Tables are made up of fields.
Table (Project 2010)
'Hiding' columns (Project 2010)
File Name vs. Project name (Project 2010)
Start to Start
40. Their purpose is to ORGANIZE. Summary tasks have work packages or other summary tasks which comprise the parent summary task. Summary tasks are NOT scheduled. The children tasks are what need to be scheduled.
Summary tasks (WBS)
Start to Finish (SF)
Work Package (WBS)
Project information dialog (Project 2010)
41. W = D + U Duration plus available resource units
Team Planner (Project 2010)
eh (Abbreviations Project 2010)
Work
Fixed Duration
42. Finish to start - finish to finish - start to start - start to finish. All are 'at least'.
5 phases of project
Finish to Start
Work Package (WBS)
Logical Relationships in PDM
43. File -> Options -> Quick Access tool bar. Examples: Tables and Vies - good stuff.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
44. Appears: eday means: Elapsed day
ed (Abbreviations Project 2010)
The task which has the LEAST slack is more important - Min-slack wins
Project Files (Project 2010)
Units
45. Task ribbon -> 'task' -> recurring task. An easy way to schedule reccuring meetings.
Work Package (WBS)
Lag
Reccuring Tasks
Customize 'Quick Access Tool Bar'
46. Appears: min means: minute
Task with first ID
m (Abbreviations Project 2010)
Actual Cost
Customize 'Quick Access Tool Bar'
47. Appears: day means: day
eh (Abbreviations Project 2010)
WBS Work Breakdown Structure
Task Type
d (Abbreviations Project 2010)
48. Appears: mon means: month
mo (Abbreviations Project 2010)
Gantt Chart Wizard (Project 2010)
5 phases of project
Dialogs (Project 2010)
49. File -> Options -> Scheduling --> Drop down for Decimal or Percentage.
Task Type
Show Assignment Units as (Project 2010)
Material resource
Table (Project 2010)
50. The FILE name is what you see at the top of the screen - and is the raw name of the .mpp or .mpt FILE itself. The PROJECT NAME is set in the 'Properties' of the project. The project name will show up in reports - etc.
SNET
File Name vs. Project name (Project 2010)
'The 100% Rule'
DSM Design Structure Matrix