SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Project Management Using Microsoft Project
Start Test
Study First
Subjects
:
certifications
,
microsoft-project
,
business-skills
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Responsibility Assignment Matrix.
The task which has the LEAST slack is more important - Min-slack wins
Peak
Drawing on Gantt (Project 2010)
RAM
2. Appears: min means: minute
ew (Abbreviations Project 2010)
Calendars to consider
Work
m (Abbreviations Project 2010)
3. Shows closest thing to a 'resource gantt chart'. Shows tasks by resource. Also shows unassigned tasks - and unscheduled tasks. Allows for user-controlled scheduling.
Team Planner (Project 2010)
Task Type
DSM Design Structure Matrix
Terminal element
4. W = D + U Duration plus available resource units
Manually
File Name vs. Project name (Project 2010)
Work
w (Abbreviations Project 2010)
5. Task calendar - resource calendar - base calendar.
Calendars to consider
Splitting tasks (Project 2010)
eh (Abbreviations Project 2010)
m (Abbreviations Project 2010)
6. If '______________' isn't checked - for example - then you won't be able to set a style for critical tasks.
Critical Tasks
Resource types
ed (Abbreviations Project 2010)
Timeline (Project 2010)
7. An 'activity' - or 'task'. The bottom 'child' task - there's nothing underneath it. If there are sub-components - or 'children' tasks below a parent task - that parent task is a SUMMARY task.
SNET
Units
ed (Abbreviations Project 2010)
Work Package (WBS)
8. A terminal element is the lowest element (activity or deliverable) in a WBS; it is not further subdivided. Sometimes called a 'work package' - but NOT synonymous.
Work Package (WBS)
Start to Start
Views (Project 2010)
Terminal element
9. The Precedence Diagram Method is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes - referred to as nodes - to represent activities and connects them with arrows that
ed (Abbreviations Project 2010)
Template (Project 2010)
Gantt Chart Wizard (Project 2010)
PDM
10. Project Tab -> Change Working time. Define the actual 'hours' of work - which days work happens (weekends grayed out by default) - and 'exceptions' to standard work times. Work weeks tab present too.
Actual Cost
Calendar/ Working time (Project 2010)
Initializing a Project (Project 2010)
RAM
11. File -> Options -> Scheduling --> Drop down for Decimal or Percentage.
Task with first ID
eh (Abbreviations Project 2010)
Finish to Start
Show Assignment Units as (Project 2010)
12. Two tasks vying for one resource - who wins?
Table (Project 2010)
The task which has the LEAST slack is more important - Min-slack wins
Default view (Project 2010)
Network Diagram best practices
13. Fixed Duration - Fixed Units - or Fixed Work. Described on page 72 of Project 2010 book.
'Hiding' columns (Project 2010)
RAM
Task Type
'80 hour rule'
14. No single activity or group of activities to produce a single deliverable should be more than 80 hours of effort.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
15. Tasks - resources - assignments - all have dialogs. Example: resource leveling. Project information dialog very important.
Dialogs (Project 2010)
Peak
DSM Design Structure Matrix
eh (Abbreviations Project 2010)
16. File -> info -> Project information -> advanced properties.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
17. Vitally important. It shows how much time remains - which indicates whether or not tasks need to be re-planned.
Resource types
Do not
Duration
Remaining Duration
18. Appears: emon means: Elapsed month
Task with minimum duration
eh (Abbreviations Project 2010)
Duration
emo (Abbreviations Project 2010)
19. Changing the working time in the 'details' section of the working time dialog won't change the default start time in the options -> scheduling settings. Try to keep these in sync.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
20. Appears: ewk means: Elapsed week
Bar Style (Project 2010)
Dialogs (Project 2010)
ew (Abbreviations Project 2010)
WBS Code (Project 2010)
21. Task ribbon -> 'inspect' button-> Inspect Task. It shows more details about highlighted task - including critical predecessor task. Very useful tool. Especially when resources are over allocated.
Duration
Inspect feature (Project 2010)
Drawing on Gantt (Project 2010)
Task with first ID
22. Task ribbon -> schedule section -> broken task icon. Reschedule incomplete work - etc.
ew (Abbreviations Project 2010)
Project Files (Project 2010)
Splitting tasks (Project 2010)
Do not
23. Appears: mon means: month
Accessing 'Properties' (Project 2010)
mo (Abbreviations Project 2010)
Default view (Project 2010)
ed (Abbreviations Project 2010)
24. Work divided by available resource units. Formula: D=W/U
Splitting tasks (Project 2010)
em (Abbreviations Project 2010)
m (Abbreviations Project 2010)
Duration
25. The acceloration of the successor task. 'Negative lag'
Template (Project 2010)
Lead
File Name vs. Project name (Project 2010)
Show Assignment Units as (Project 2010)
26. Gantt Chart with 'Entry' table on left.
Task with minimum duration
Project information dialog (Project 2010)
Default view (Project 2010)
PDM
27. A compact - matrix representation of a system or project. The approach can be used to model complex systems in systems engineering or systems analysis - and in project planning and project management.
5 phases of project
Remaining Duration
DSM Design Structure Matrix
d (Abbreviations Project 2010)
28. Gantt Chart -> Format -> Bar Styles segment -> format drop down. Adjust all aspects of the bars in the gantt.
Bar Style (Project 2010)
w (Abbreviations Project 2010)
SNET
Earned Value
29. Start date - Current date - finish date - status date - schedule from - calendar - & priority (with project pro). Enterprise custom fields here too - if you're hooked into enterprise.
RAM
Working Time & 'Default' start/end time (Project 2010)
Template (Project 2010)
Project information dialog (Project 2010)
30. ______ link Summary Tasks.
Customize 'Quick Access Tool Bar'
h (Abbreviations Project 2010)
Do not
Fixed Duration
31. 1. Initiation 2. Planning 3. Execution 4. Monitoring & Control 5. Closing
Terminal element
Earned Value
5 phases of project
SNET
32. Can be added to the ribbon - and it walks user through formatting of the gantt chart. Pretty cool.
Gantt Chart Wizard (Project 2010)
Terminal element
Team Planner (Project 2010)
Lead
33. Default view in Network Diagram. Without LINK LABELS - you won't see lag time - etc. The term finish to start refers specifically to the logical relationship that exits between the activities that make up he entirety of the project in which it is det
Finish to Start
DSM Design Structure Matrix
Relationship Diagram (Project 2010)
eh (Abbreviations Project 2010)
34. Appears: ehr means: Elapsed hour
Fixed Units
Material resource
Accessing 'Properties' (Project 2010)
eh (Abbreviations Project 2010)
35. Matches the outline number initially in Project 2010. It is common for work breakdown structure elements to be numbered sequentially to reveal the hierarchical structure. For example 1.3.2 Rear Wheel identifies this item as a Level 3 WBS element - si
mo (Abbreviations Project 2010)
File Name vs. Project name (Project 2010)
emo (Abbreviations Project 2010)
WBS Code (Project 2010)
36. Their purpose is to ORGANIZE. Summary tasks have work packages or other summary tasks which comprise the parent summary task. Summary tasks are NOT scheduled. The children tasks are what need to be scheduled.
Summary tasks (WBS)
SNET
m (Abbreviations Project 2010)
Working Time & 'Default' start/end time (Project 2010)
37. The WBS contains 100% of the work defined by the project scope and captures all deliverables - internal - external - interim - in terms of the work to be completed - including project management.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
38. U = W / D Work divided by duration.
Network Diagram best practices
Start to Finish (SF)
'Hiding' columns (Project 2010)
Units
39. It is NOT an exhaustive list of work. It is instead a comprehensive classification of project scope. Contains Sub-components - work packages (child of sub-component). Further work packages can be children of other work packages. Summary tasks are the
Reccuring Tasks
WBS Work Breakdown Structure
File Name vs. Project name (Project 2010)
Accessing 'Properties' (Project 2010)
40. Tables are made up of fields.
Network Diagram best practices
Timeline (Project 2010)
'The 100% Rule'
Table (Project 2010)
41. Appears: wk means: week
Gantt Chart Wizard (Project 2010)
ew (Abbreviations Project 2010)
w (Abbreviations Project 2010)
PDM
42. 'Start no earlier than' constraint.
Work
SNET
Earned Value
h (Abbreviations Project 2010)
43. The FILE name is what you see at the top of the screen - and is the raw name of the .mpp or .mpt FILE itself. The PROJECT NAME is set in the 'Properties' of the project. The project name will show up in reports - etc.
Fixed Work
File Name vs. Project name (Project 2010)
Earned Value
5 phases of project
44. Ensuring that the successor activity does not begin until after the predecessor activity is completed is implementing a start-to-finish (SF) model. This is the most logical path to follow when planning a project. Those in project management should be
Start to Finish (SF)
Bar Style (Project 2010)
Fixed Work
h (Abbreviations Project 2010)
45. efines units.
The task which has the LEAST slack is more important - Min-slack wins
Material resource
Inspect feature (Project 2010)
Table (Project 2010)
46. Contains information relative to tasks.
Form (Project 2010)
Inspect feature (Project 2010)
Lag
Reccuring Tasks
47. Focus on Gantt -> Format ribbon ->
Drawing on Gantt (Project 2010)
Inspect feature (Project 2010)
Task with first ID
Fixed Units
48. File -> Info -> Organizer. Access global mpt - delete views - etc. (ADD MORE)
WBS Code (Project 2010)
Lead
The task which has the LEAST slack is more important - Min-slack wins
Organizer (Project 2010)
49. Amendment to task type.
Effort Driven
Terminal element
Show Assignment Units as (Project 2010)
Organizer (Project 2010)
50. Two critical tasks - both same duration - vying for one resource - who wins?
'Hiding' columns (Project 2010)
Resource types
Task with first ID
Summary tasks (WBS)
Sorry!:) No result found.
Can you answer 50 questions in 15 minutes?
Let me suggest you:
Browse all subjects
Browse all tests
Most popular tests
Major Subjects
Tests & Exams
AP
CLEP
DSST
GRE
SAT
GMAT
Certifications
CISSP go to https://www.isc2.org/
PMP
ITIL
RHCE
MCTS
More...
IT Skills
Android Programming
Data Modeling
Objective C Programming
Basic Python Programming
Adobe Illustrator
More...
Business Skills
Advertising Techniques
Business Accounting Basics
Business Strategy
Human Resource Management
Marketing Basics
More...
Soft Skills
Body Language
People Skills
Public Speaking
Persuasion
Job Hunting And Resumes
More...
Vocabulary
GRE Vocab
SAT Vocab
TOEFL Essential Vocab
Basic English Words For All
Global Words You Should Know
Business English
More...
Languages
AP German Vocab
AP Latin Vocab
SAT Subject Test: French
Italian Survival
Norwegian Survival
More...
Engineering
Audio Engineering
Computer Science Engineering
Aerospace Engineering
Chemical Engineering
Structural Engineering
More...
Health Sciences
Basic Nursing Skills
Health Science Language Fundamentals
Veterinary Technology Medical Language
Cardiology
Clinical Surgery
More...
English
Grammar Fundamentals
Literary And Rhetorical Vocab
Elements Of Style Vocab
Introduction To English Major
Complete Advanced Sentences
Literature
Homonyms
More...
Math
Algebra Formulas
Basic Arithmetic: Measurements
Metric Conversions
Geometric Properties
Important Math Facts
Number Sense Vocab
Business Math
More...
Other Major Subjects
Science
Economics
History
Law
Performing-arts
Cooking
Logic & Reasoning
Trivia
Browse all subjects
Browse all tests
Most popular tests