SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Project Management Using Microsoft Project
Start Test
Study First
Subjects
:
certifications
,
microsoft-project
,
business-skills
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Always preserve the number of hours to perform a task. Changing work when fixed will impact duration.
Start to Start
Project Files (Project 2010)
Fixed Work
Project information dialog (Project 2010)
2. The number of resources required to get the tasks/assignments completed.
Peak
Project information dialog (Project 2010)
Views (Project 2010)
Manual and Auto scheduled tasks
3. Start date - Current date - finish date - status date - schedule from - calendar - & priority (with project pro). Enterprise custom fields here too - if you're hooked into enterprise.
Remaining Duration
Project information dialog (Project 2010)
Initializing a Project (Project 2010)
Views (Project 2010)
4. Appears: mon means: month
Show Assignment Units as (Project 2010)
mo (Abbreviations Project 2010)
Table (Project 2010)
Fixed Units
5. Appears: emon means: Elapsed month
emo (Abbreviations Project 2010)
WBS Work Breakdown Structure
Timeline (Project 2010)
'The 100% Rule'
6. Gantt Chart -> Format -> Bar Styles segment -> format drop down. Adjust all aspects of the bars in the gantt.
Lead
Fixed Duration
Terminal element
Bar Style (Project 2010)
7. Contains information relative to tasks.
Form (Project 2010)
SNET
File Name vs. Project name (Project 2010)
Dialogs (Project 2010)
8. Tables are made up of fields.
Lead
h (Abbreviations Project 2010)
Terminal element
Table (Project 2010)
9. Appears: eday means: Elapsed day
Network Diagram best practices
ew (Abbreviations Project 2010)
ed (Abbreviations Project 2010)
Task with first ID
10. Project template (.mpt) - or Global MPT file. Drives what you see in the project. Corporations may have their own.
Team Planner (Project 2010)
Template (Project 2010)
Duration
Material resource
11. If '______________' isn't checked - for example - then you won't be able to set a style for critical tasks.
'80 hour rule'
Project information dialog (Project 2010)
Critical Tasks
Finish to Start
12. The Precedence Diagram Method is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes - referred to as nodes - to represent activities and connects them with arrows that
Work Package (WBS)
Summary tasks (WBS)
PDM
Network Diagram best practices
13. Network Diagrom -> Format ribbon -> format.
Effort Driven
Box Styles (Project 2010)
'80 hour rule'
WBS Code (Project 2010)
14. Focus on Gantt -> Format ribbon ->
Project information dialog (Project 2010)
Working Time & 'Default' start/end time (Project 2010)
Initializing a Project (Project 2010)
Drawing on Gantt (Project 2010)
15. File -> Info -> Organizer. Access global mpt - delete views - etc. (ADD MORE)
Organizer (Project 2010)
Peak
Splitting tasks (Project 2010)
RAM
16. Two tasks vying for one resource - who wins?
Splitting tasks (Project 2010)
Resource types
Peak
The task which has the LEAST slack is more important - Min-slack wins
17. Appears: min means: minute
Lag
m (Abbreviations Project 2010)
Organizer (Project 2010)
Work Package (WBS)
18. File -> Options -> Scheduling --> Drop down for Decimal or Percentage.
Show Assignment Units as (Project 2010)
Timeline (Project 2010)
Default view (Project 2010)
'The 100% Rule'
19. Appears: ehr means: Elapsed hour
Summary tasks (WBS)
Start to Finish (SF)
Template (Project 2010)
eh (Abbreviations Project 2010)
20. Work divided by available resource units. Formula: D=W/U
Initializing a Project (Project 2010)
Duration
Table (Project 2010)
Critical Tasks
21. Amendment to task type.
Effort Driven
Inspect feature (Project 2010)
Material resource
Task with first ID
22. Function key 5. You can go directly to ID - or 'date'.
Summary tasks (WBS)
Do not
Show Assignment Units as (Project 2010)
GO TO (Project 2010)
23. Shows closest thing to a 'resource gantt chart'. Shows tasks by resource. Also shows unassigned tasks - and unscheduled tasks. Allows for user-controlled scheduling.
'80 hour rule'
Box Styles (Project 2010)
h (Abbreviations Project 2010)
Team Planner (Project 2010)
24. Task ribbon -> 'task' -> recurring task. An easy way to schedule reccuring meetings.
Calendars to consider
Reccuring Tasks
The task which has the LEAST slack is more important - Min-slack wins
ew (Abbreviations Project 2010)
25. Appears: emin means: Elapsed minute
Work
Work Package (WBS)
em (Abbreviations Project 2010)
Default view (Project 2010)
26. Time delay. Sometimes - it's preferred to have lag shown as a task. You can assign costs to it - that way. Style sheets will indicate this.
Start to Finish (SF)
Lag
Working Time & 'Default' start/end time (Project 2010)
emo (Abbreviations Project 2010)
27. Appears: hr means: hour
Effort Driven
h (Abbreviations Project 2010)
Splitting tasks (Project 2010)
Resource types
28. An 'activity' - or 'task'. The bottom 'child' task - there's nothing underneath it. If there are sub-components - or 'children' tasks below a parent task - that parent task is a SUMMARY task.
Initializing a Project (Project 2010)
Timeline (Project 2010)
emo (Abbreviations Project 2010)
Work Package (WBS)
29. To switch between ____________: (Project 2010) - Use the bottom-left icon. Use the ribbon. Task mode column in entry table. File -> options -> schedule.
Manual and Auto scheduled tasks
Form (Project 2010)
Logical Relationships in PDM
DSM Design Structure Matrix
30. Single Start - Single Finish. No 'danglers'. Everything must be connected. No loops.
Network Diagram best practices
ew (Abbreviations Project 2010)
WBS Code (Project 2010)
WBS Work Breakdown Structure
31. Ensuring that the successor activity does not begin until after the predecessor activity is completed is implementing a start-to-finish (SF) model. This is the most logical path to follow when planning a project. Those in project management should be
Reccuring Tasks
Resource types
Start to Finish (SF)
Fixed Units
32. Appears: wk means: week
ed (Abbreviations Project 2010)
'The 100% Rule'
GO TO (Project 2010)
w (Abbreviations Project 2010)
33. Finish to start - finish to finish - start to start - start to finish. All are 'at least'.
Lead
The task which has the LEAST slack is more important - Min-slack wins
Earned Value
Logical Relationships in PDM
34. The acceloration of the successor task. 'Negative lag'
Show Assignment Units as (Project 2010)
Lead
The task which has the LEAST slack is more important - Min-slack wins
Start to Finish (SF)
35. Can be added to the ribbon - and it walks user through formatting of the gantt chart. Pretty cool.
Customize 'Quick Access Tool Bar'
Form (Project 2010)
Logical Relationships in PDM
Gantt Chart Wizard (Project 2010)
36. Default view in Network Diagram. Without LINK LABELS - you won't see lag time - etc. The term finish to start refers specifically to the logical relationship that exits between the activities that make up he entirety of the project in which it is det
Finish to Start
Reccuring Tasks
Timeline (Project 2010)
Gantt Chart Wizard (Project 2010)
37. Always preserve the duration of a task. Changing duration when fixed will impact work.
Material resource
Work
Finish to Start
Fixed Duration
38. Tasks - resources - assignments - all have dialogs. Example: resource leveling. Project information dialog very important.
Default view (Project 2010)
Dialogs (Project 2010)
Drawing on Gantt (Project 2010)
File Name vs. Project name (Project 2010)
39. Their purpose is to ORGANIZE. Summary tasks have work packages or other summary tasks which comprise the parent summary task. Summary tasks are NOT scheduled. The children tasks are what need to be scheduled.
Summary tasks (WBS)
ew (Abbreviations Project 2010)
Duration
Work
40. Vitally important. It shows how much time remains - which indicates whether or not tasks need to be re-planned.
Start to Start
Remaining Duration
mo (Abbreviations Project 2010)
Drawing on Gantt (Project 2010)
41. A compact - matrix representation of a system or project. The approach can be used to model complex systems in systems engineering or systems analysis - and in project planning and project management.
Project information dialog (Project 2010)
Table (Project 2010)
DSM Design Structure Matrix
ed (Abbreviations Project 2010)
42. efines units.
'Hiding' columns (Project 2010)
d (Abbreviations Project 2010)
Task Type
Material resource
43. Hiding does not delete data. If you hide a column - data maintains - but to get it back - you'll need to right click - insert column.
44. Work - resource - cost.
Resource types
Summary tasks (WBS)
5 phases of project
Units
45. 1. Initiation 2. Planning 3. Execution 4. Monitoring & Control 5. Closing
Material resource
Finish to Start
5 phases of project
Project Files (Project 2010)
46. Task calendar - resource calendar - base calendar.
m (Abbreviations Project 2010)
emo (Abbreviations Project 2010)
Calendars to consider
'Hiding' columns (Project 2010)
47. A terminal element is the lowest element (activity or deliverable) in a WBS; it is not further subdivided. Sometimes called a 'work package' - but NOT synonymous.
em (Abbreviations Project 2010)
m (Abbreviations Project 2010)
Terminal element
Summary tasks (WBS)
48. U = W / D Work divided by duration.
Duration
Reccuring Tasks
Effort Driven
Units
49. Shows logical relationship between tasks. View tab -> 'split view' section -> details checked -> More views -> Select there.
Template (Project 2010)
Relationship Diagram (Project 2010)
Dialogs (Project 2010)
h (Abbreviations Project 2010)
50. Tables - charts - usage tables - and sheets.
Views (Project 2010)
eh (Abbreviations Project 2010)
Critical Tasks
Drawing on Gantt (Project 2010)