SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Project Management Using Microsoft Project
Start Test
Study First
Subjects
:
certifications
,
microsoft-project
,
business-skills
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. File -> Options -> Quick Access tool bar. Examples: Tables and Vies - good stuff.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
2. Task ribbon -> 'task' -> recurring task. An easy way to schedule reccuring meetings.
Gantt Chart Wizard (Project 2010)
Start to Start
Duration
Reccuring Tasks
3. Can be added to the ribbon - and it walks user through formatting of the gantt chart. Pretty cool.
Do not
Gantt Chart Wizard (Project 2010)
ed (Abbreviations Project 2010)
Units
4. Time delay. Sometimes - it's preferred to have lag shown as a task. You can assign costs to it - that way. Style sheets will indicate this.
Lag
Task with first ID
5 phases of project
Lead
5. View -> Timeline check box. Shows timeline - but by default - nothing's on it. To add items - right click and 'add to timeline'.
Default view (Project 2010)
Bar Style (Project 2010)
em (Abbreviations Project 2010)
Timeline (Project 2010)
6. Appears: ewk means: Elapsed week
Relationship Diagram (Project 2010)
m (Abbreviations Project 2010)
Team Planner (Project 2010)
ew (Abbreviations Project 2010)
7. Two tasks vying for one resource - who wins?
Manually
Show Assignment Units as (Project 2010)
The task which has the LEAST slack is more important - Min-slack wins
'80 hour rule'
8. Tables are made up of fields.
Table (Project 2010)
Earned Value
Actual Cost
SNET
9. The WBS contains 100% of the work defined by the project scope and captures all deliverables - internal - external - interim - in terms of the work to be completed - including project management.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
10. Ensuring that the successor activity does not begin until after the predecessor activity is completed is implementing a start-to-finish (SF) model. This is the most logical path to follow when planning a project. Those in project management should be
Timeline (Project 2010)
Start to Finish (SF)
5 phases of project
Project Files (Project 2010)
11. An approach for monitoring project progress that relies on the budgeted cost of activities completed to ascribe value
Earned Value
SNET
Box Styles (Project 2010)
Peak
12. The number of resources required to get the tasks/assignments completed.
Calendars to consider
'Hiding' columns (Project 2010)
m (Abbreviations Project 2010)
Peak
13. U = W / D Work divided by duration.
File Name vs. Project name (Project 2010)
ed (Abbreviations Project 2010)
Network Diagram best practices
Units
14. It is NOT an exhaustive list of work. It is instead a comprehensive classification of project scope. Contains Sub-components - work packages (child of sub-component). Further work packages can be children of other work packages. Summary tasks are the
Fixed Duration
WBS Work Breakdown Structure
Show Assignment Units as (Project 2010)
Gantt Chart Wizard (Project 2010)
15. 'Start no earlier than' constraint.
h (Abbreviations Project 2010)
eh (Abbreviations Project 2010)
SNET
Summary tasks (WBS)
16. Appears: mon means: month
Task with first ID
GO TO (Project 2010)
Material resource
mo (Abbreviations Project 2010)
17. No single activity or group of activities to produce a single deliverable should be more than 80 hours of effort.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
18. Always preserve the number of people working on a task. Changing units when fixed will impact duration.
Drawing on Gantt (Project 2010)
Fixed Units
DSM Design Structure Matrix
Working Time & 'Default' start/end time (Project 2010)
19. A compact - matrix representation of a system or project. The approach can be used to model complex systems in systems engineering or systems analysis - and in project planning and project management.
DSM Design Structure Matrix
Start to Start
Fixed Duration
Views (Project 2010)
20. The total direct and indirect costs incurred in accomplishing work on an activity during a given period.
DSM Design Structure Matrix
Network Diagram best practices
Views (Project 2010)
Actual Cost
21. Appears: emin means: Elapsed minute
DSM Design Structure Matrix
PDM
em (Abbreviations Project 2010)
'The 100% Rule'
22. Appears: day means: day
ew (Abbreviations Project 2010)
Task with minimum duration
Team Planner (Project 2010)
d (Abbreviations Project 2010)
23. Tables - charts - usage tables - and sheets.
Views (Project 2010)
Logical Relationships in PDM
Work Package (WBS)
Lead
24. A logical relationship that states that for one project to begin - another must also be underway. For example - the writing of a business proposal must have begun in order for editing of the proposal to take place.
d (Abbreviations Project 2010)
Start to Start
'Hiding' columns (Project 2010)
Working Time & 'Default' start/end time (Project 2010)
25. ______ link Summary Tasks.
Do not
Relationship Diagram (Project 2010)
em (Abbreviations Project 2010)
'Hiding' columns (Project 2010)
26. If '______________' isn't checked - for example - then you won't be able to set a style for critical tasks.
Critical Tasks
Start to Start
Logical Relationships in PDM
Views (Project 2010)
27. Task calendar - resource calendar - base calendar.
Calendars to consider
Template (Project 2010)
Material resource
GO TO (Project 2010)
28. .mpp file extension. The actual project file.
SNET
Template (Project 2010)
Project Files (Project 2010)
Relationship Diagram (Project 2010)
29. Hiding does not delete data. If you hide a column - data maintains - but to get it back - you'll need to right click - insert column.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
30. Matches the outline number initially in Project 2010. It is common for work breakdown structure elements to be numbered sequentially to reveal the hierarchical structure. For example 1.3.2 Rear Wheel identifies this item as a Level 3 WBS element - si
Project Files (Project 2010)
Task with first ID
Material resource
WBS Code (Project 2010)
31. Finish to start - finish to finish - start to start - start to finish. All are 'at least'.
Logical Relationships in PDM
Drawing on Gantt (Project 2010)
DSM Design Structure Matrix
Work Package (WBS)
32. Start date - Current date - finish date - status date - schedule from - calendar - & priority (with project pro). Enterprise custom fields here too - if you're hooked into enterprise.
Organizer (Project 2010)
Customize 'Quick Access Tool Bar'
Project information dialog (Project 2010)
Start to Start
33. Focus on Gantt -> Format ribbon ->
Project information dialog (Project 2010)
Drawing on Gantt (Project 2010)
Manual and Auto scheduled tasks
Do not
34. Add your resources names to critical tasks _______ via bar styles/text.
Manually
Bar Style (Project 2010)
Project Files (Project 2010)
Resource types
35. The FILE name is what you see at the top of the screen - and is the raw name of the .mpp or .mpt FILE itself. The PROJECT NAME is set in the 'Properties' of the project. The project name will show up in reports - etc.
Task with minimum duration
File Name vs. Project name (Project 2010)
m (Abbreviations Project 2010)
Units
36. Contains information relative to tasks.
Network Diagram best practices
Duration
Form (Project 2010)
eh (Abbreviations Project 2010)
37. Task ribbon -> schedule section -> broken task icon. Reschedule incomplete work - etc.
Material resource
ed (Abbreviations Project 2010)
Splitting tasks (Project 2010)
Work Package (WBS)
38. Appears: hr means: hour
mo (Abbreviations Project 2010)
Logical Relationships in PDM
Relationship Diagram (Project 2010)
h (Abbreviations Project 2010)
39. Appears: wk means: week
w (Abbreviations Project 2010)
ed (Abbreviations Project 2010)
m (Abbreviations Project 2010)
Inspect feature (Project 2010)
40. Default view in Network Diagram. Without LINK LABELS - you won't see lag time - etc. The term finish to start refers specifically to the logical relationship that exits between the activities that make up he entirety of the project in which it is det
Finish to Start
Task Type
Gantt Chart Wizard (Project 2010)
Manual and Auto scheduled tasks
41. Shows closest thing to a 'resource gantt chart'. Shows tasks by resource. Also shows unassigned tasks - and unscheduled tasks. Allows for user-controlled scheduling.
Show Assignment Units as (Project 2010)
Team Planner (Project 2010)
m (Abbreviations Project 2010)
Fixed Duration
42. Responsibility Assignment Matrix.
'Hiding' columns (Project 2010)
Views (Project 2010)
RAM
Logical Relationships in PDM
43. A terminal element is the lowest element (activity or deliverable) in a WBS; it is not further subdivided. Sometimes called a 'work package' - but NOT synonymous.
Task with first ID
Summary tasks (WBS)
Work
Terminal element
44. The acceloration of the successor task. 'Negative lag'
Start to Start
m (Abbreviations Project 2010)
Template (Project 2010)
Lead
45. Work - resource - cost.
'The 100% Rule'
Accessing 'Properties' (Project 2010)
Resource types
ew (Abbreviations Project 2010)
46. File -> Options -> Scheduling --> Drop down for Decimal or Percentage.
Customize 'Quick Access Tool Bar'
Show Assignment Units as (Project 2010)
The task which has the LEAST slack is more important - Min-slack wins
Table (Project 2010)
47. Vitally important. It shows how much time remains - which indicates whether or not tasks need to be re-planned.
Task with minimum duration
Timeline (Project 2010)
Remaining Duration
Earned Value
48. Gantt Chart with 'Entry' table on left.
Default view (Project 2010)
Team Planner (Project 2010)
Drawing on Gantt (Project 2010)
eh (Abbreviations Project 2010)
49. Network Diagrom -> Format ribbon -> format.
Box Styles (Project 2010)
Project Files (Project 2010)
The task which has the LEAST slack is more important - Min-slack wins
Peak
50. Always preserve the duration of a task. Changing duration when fixed will impact work.
Fixed Duration
Relationship Diagram (Project 2010)
ed (Abbreviations Project 2010)
eh (Abbreviations Project 2010)