Test your basic knowledge |

Project Management Using Microsoft Project

Instructions:
  • Answer 50 questions in 15 minutes.
  • If you are not ready to take this test, you can study here.
  • Match each statement with the correct term.
  • Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.

This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. To switch between ____________: (Project 2010) - Use the bottom-left icon. Use the ribbon. Task mode column in entry table. File -> options -> schedule.






2. Appears: hr means: hour






3. Finish to start - finish to finish - start to start - start to finish. All are 'at least'.






4. efines units.






5. Two tasks vying for one resource - who wins?






6. Appears: eday means: Elapsed day






7. The acceloration of the successor task. 'Negative lag'






8. Single Start - Single Finish. No 'danglers'. Everything must be connected. No loops.






9. Task ribbon -> 'inspect' button-> Inspect Task. It shows more details about highlighted task - including critical predecessor task. Very useful tool. Especially when resources are over allocated.






10. Contains information relative to tasks.






11. Hiding does not delete data. If you hide a column - data maintains - but to get it back - you'll need to right click - insert column.


12. Fixed Duration - Fixed Units - or Fixed Work. Described on page 72 of Project 2010 book.






13. Can be added to the ribbon - and it walks user through formatting of the gantt chart. Pretty cool.






14. Project template (.mpt) - or Global MPT file. Drives what you see in the project. Corporations may have their own.






15. Always preserve the number of people working on a task. Changing units when fixed will impact duration.






16. Shows closest thing to a 'resource gantt chart'. Shows tasks by resource. Also shows unassigned tasks - and unscheduled tasks. Allows for user-controlled scheduling.






17. 1. Initiation 2. Planning 3. Execution 4. Monitoring & Control 5. Closing






18. It is NOT an exhaustive list of work. It is instead a comprehensive classification of project scope. Contains Sub-components - work packages (child of sub-component). Further work packages can be children of other work packages. Summary tasks are the






19. Appears: mon means: month






20. Appears: min means: minute






21. Appears: day means: day






22. Task ribbon -> 'task' -> recurring task. An easy way to schedule reccuring meetings.






23. Tables are made up of fields.






24. Appears: ewk means: Elapsed week






25. Focus on Gantt -> Format ribbon ->






26. Vitally important. It shows how much time remains - which indicates whether or not tasks need to be re-planned.






27. ______ link Summary Tasks.






28. Task calendar - resource calendar - base calendar.






29. If '______________' isn't checked - for example - then you won't be able to set a style for critical tasks.






30. File -> info -> Project information -> advanced properties.


31. Work - resource - cost.






32. Their purpose is to ORGANIZE. Summary tasks have work packages or other summary tasks which comprise the parent summary task. Summary tasks are NOT scheduled. The children tasks are what need to be scheduled.






33. Appears: wk means: week






34. Work divided by available resource units. Formula: D=W/U






35. Responsibility Assignment Matrix.






36. Tables - charts - usage tables - and sheets.






37. An 'activity' - or 'task'. The bottom 'child' task - there's nothing underneath it. If there are sub-components - or 'children' tasks below a parent task - that parent task is a SUMMARY task.






38. The WBS contains 100% of the work defined by the project scope and captures all deliverables - internal - external - interim - in terms of the work to be completed - including project management.


39. U = W / D Work divided by duration.






40. A compact - matrix representation of a system or project. The approach can be used to model complex systems in systems engineering or systems analysis - and in project planning and project management.






41. Gantt Chart with 'Entry' table on left.






42. Appears: emon means: Elapsed month






43. The total direct and indirect costs incurred in accomplishing work on an activity during a given period.






44. A terminal element is the lowest element (activity or deliverable) in a WBS; it is not further subdivided. Sometimes called a 'work package' - but NOT synonymous.






45. W = D + U Duration plus available resource units






46. The number of resources required to get the tasks/assignments completed.






47. Matches the outline number initially in Project 2010. It is common for work breakdown structure elements to be numbered sequentially to reveal the hierarchical structure. For example 1.3.2 Rear Wheel identifies this item as a Level 3 WBS element - si






48. Create file. Set up file properties. Set a start date. Set up calendars and working time.






49. Start date - Current date - finish date - status date - schedule from - calendar - & priority (with project pro). Enterprise custom fields here too - if you're hooked into enterprise.






50. Shows logical relationship between tasks. View tab -> 'split view' section -> details checked -> More views -> Select there.