Test your basic knowledge |

Project Management Using Microsoft Project

Instructions:
  • Answer 50 questions in 15 minutes.
  • If you are not ready to take this test, you can study here.
  • Match each statement with the correct term.
  • Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.

This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Two critical tasks - both same duration - vying for one resource - who wins?






2. The FILE name is what you see at the top of the screen - and is the raw name of the .mpp or .mpt FILE itself. The PROJECT NAME is set in the 'Properties' of the project. The project name will show up in reports - etc.






3. Appears: eday means: Elapsed day






4. A terminal element is the lowest element (activity or deliverable) in a WBS; it is not further subdivided. Sometimes called a 'work package' - but NOT synonymous.






5. Time delay. Sometimes - it's preferred to have lag shown as a task. You can assign costs to it - that way. Style sheets will indicate this.






6. File -> info -> Project information -> advanced properties.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


7. Appears: day means: day






8. Appears: ewk means: Elapsed week






9. Task ribbon -> 'inspect' button-> Inspect Task. It shows more details about highlighted task - including critical predecessor task. Very useful tool. Especially when resources are over allocated.






10. Hiding does not delete data. If you hide a column - data maintains - but to get it back - you'll need to right click - insert column.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


11. efines units.






12. Tables are made up of fields.






13. W = D + U Duration plus available resource units






14. Appears: mon means: month






15. Appears: emon means: Elapsed month






16. Work - resource - cost.






17. To switch between ____________: (Project 2010) - Use the bottom-left icon. Use the ribbon. Task mode column in entry table. File -> options -> schedule.






18. Contains information relative to tasks.






19. Task calendar - resource calendar - base calendar.






20. File -> Options -> Quick Access tool bar. Examples: Tables and Vies - good stuff.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


21. Ensuring that the successor activity does not begin until after the predecessor activity is completed is implementing a start-to-finish (SF) model. This is the most logical path to follow when planning a project. Those in project management should be






22. Vitally important. It shows how much time remains - which indicates whether or not tasks need to be re-planned.






23. An 'activity' - or 'task'. The bottom 'child' task - there's nothing underneath it. If there are sub-components - or 'children' tasks below a parent task - that parent task is a SUMMARY task.






24. Function key 5. You can go directly to ID - or 'date'.






25. Default view in Network Diagram. Without LINK LABELS - you won't see lag time - etc. The term finish to start refers specifically to the logical relationship that exits between the activities that make up he entirety of the project in which it is det






26. Changing the working time in the 'details' section of the working time dialog won't change the default start time in the options -> scheduling settings. Try to keep these in sync.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


27. Two tasks vying for one resource - who wins?






28. Shows closest thing to a 'resource gantt chart'. Shows tasks by resource. Also shows unassigned tasks - and unscheduled tasks. Allows for user-controlled scheduling.






29. Appears: min means: minute






30. An approach for monitoring project progress that relies on the budgeted cost of activities completed to ascribe value






31. Appears: ehr means: Elapsed hour






32. .mpp file extension. The actual project file.






33. If '______________' isn't checked - for example - then you won't be able to set a style for critical tasks.






34. A logical relationship that states that for one project to begin - another must also be underway. For example - the writing of a business proposal must have begun in order for editing of the proposal to take place.






35. View -> Timeline check box. Shows timeline - but by default - nothing's on it. To add items - right click and 'add to timeline'.






36. Appears: wk means: week






37. Start date - Current date - finish date - status date - schedule from - calendar - & priority (with project pro). Enterprise custom fields here too - if you're hooked into enterprise.






38. Fixed Duration - Fixed Units - or Fixed Work. Described on page 72 of Project 2010 book.






39. Single Start - Single Finish. No 'danglers'. Everything must be connected. No loops.






40. The WBS contains 100% of the work defined by the project scope and captures all deliverables - internal - external - interim - in terms of the work to be completed - including project management.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


41. Task ribbon -> 'task' -> recurring task. An easy way to schedule reccuring meetings.






42. 1. Initiation 2. Planning 3. Execution 4. Monitoring & Control 5. Closing






43. The number of resources required to get the tasks/assignments completed.






44. Two CRITICAL tasks vying for one resource - who wins?






45. Appears: emin means: Elapsed minute






46. Appears: hr means: hour






47. The Precedence Diagram Method is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes - referred to as nodes - to represent activities and connects them with arrows that






48. The total direct and indirect costs incurred in accomplishing work on an activity during a given period.






49. Can be added to the ribbon - and it walks user through formatting of the gantt chart. Pretty cool.






50. It is NOT an exhaustive list of work. It is instead a comprehensive classification of project scope. Contains Sub-components - work packages (child of sub-component). Further work packages can be children of other work packages. Summary tasks are the







Sorry!:) No result found.

Can you answer 50 questions in 15 minutes?


Let me suggest you:



Major Subjects



Tests & Exams


AP
CLEP
DSST
GRE
SAT
GMAT

Most popular tests