SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Project Management Using Microsoft Project
Start Test
Study First
Subjects
:
certifications
,
microsoft-project
,
business-skills
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. File -> Options -> Quick Access tool bar. Examples: Tables and Vies - good stuff.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
2. Two CRITICAL tasks vying for one resource - who wins?
Finish to Start
Task with minimum duration
Form (Project 2010)
Terminal element
3. W = D + U Duration plus available resource units
Fixed Units
Work
Units
Logical Relationships in PDM
4. Task ribbon -> 'task' -> recurring task. An easy way to schedule reccuring meetings.
Task with first ID
Reccuring Tasks
d (Abbreviations Project 2010)
Task with minimum duration
5. File -> Options -> Scheduling --> Drop down for Decimal or Percentage.
Terminal element
Calendars to consider
Accessing 'Properties' (Project 2010)
Show Assignment Units as (Project 2010)
6. Finish to start - finish to finish - start to start - start to finish. All are 'at least'.
Logical Relationships in PDM
Task with minimum duration
w (Abbreviations Project 2010)
Do not
7. Ensuring that the successor activity does not begin until after the predecessor activity is completed is implementing a start-to-finish (SF) model. This is the most logical path to follow when planning a project. Those in project management should be
Start to Finish (SF)
Views (Project 2010)
ed (Abbreviations Project 2010)
Remaining Duration
8. An 'activity' - or 'task'. The bottom 'child' task - there's nothing underneath it. If there are sub-components - or 'children' tasks below a parent task - that parent task is a SUMMARY task.
Box Styles (Project 2010)
Work Package (WBS)
mo (Abbreviations Project 2010)
Do not
9. A compact - matrix representation of a system or project. The approach can be used to model complex systems in systems engineering or systems analysis - and in project planning and project management.
GO TO (Project 2010)
File Name vs. Project name (Project 2010)
DSM Design Structure Matrix
Inspect feature (Project 2010)
10. Gantt Chart -> Format -> Bar Styles segment -> format drop down. Adjust all aspects of the bars in the gantt.
Bar Style (Project 2010)
Actual Cost
RAM
Effort Driven
11. Vitally important. It shows how much time remains - which indicates whether or not tasks need to be re-planned.
Actual Cost
Remaining Duration
Working Time & 'Default' start/end time (Project 2010)
'The 100% Rule'
12. Appears: ehr means: Elapsed hour
Relationship Diagram (Project 2010)
emo (Abbreviations Project 2010)
Reccuring Tasks
eh (Abbreviations Project 2010)
13. View -> Timeline check box. Shows timeline - but by default - nothing's on it. To add items - right click and 'add to timeline'.
mo (Abbreviations Project 2010)
Actual Cost
Dialogs (Project 2010)
Timeline (Project 2010)
14. Appears: emon means: Elapsed month
Work
Default view (Project 2010)
GO TO (Project 2010)
emo (Abbreviations Project 2010)
15. efines units.
Timeline (Project 2010)
Material resource
m (Abbreviations Project 2010)
Form (Project 2010)
16. Gantt Chart with 'Entry' table on left.
Default view (Project 2010)
Fixed Work
Terminal element
Logical Relationships in PDM
17. The Precedence Diagram Method is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes - referred to as nodes - to represent activities and connects them with arrows that
PDM
Remaining Duration
Earned Value
Project information dialog (Project 2010)
18. Appears: hr means: hour
Lag
Accessing 'Properties' (Project 2010)
Default view (Project 2010)
h (Abbreviations Project 2010)
19. Function key 5. You can go directly to ID - or 'date'.
Timeline (Project 2010)
GO TO (Project 2010)
Fixed Work
Manual and Auto scheduled tasks
20. The total direct and indirect costs incurred in accomplishing work on an activity during a given period.
Work Package (WBS)
RAM
Default view (Project 2010)
Actual Cost
21. Fixed Duration - Fixed Units - or Fixed Work. Described on page 72 of Project 2010 book.
Reccuring Tasks
Box Styles (Project 2010)
Table (Project 2010)
Task Type
22. ______ link Summary Tasks.
Project Files (Project 2010)
Finish to Start
Summary tasks (WBS)
Do not
23. Appears: day means: day
Terminal element
Gantt Chart Wizard (Project 2010)
d (Abbreviations Project 2010)
Accessing 'Properties' (Project 2010)
24. Create file. Set up file properties. Set a start date. Set up calendars and working time.
Peak
Initializing a Project (Project 2010)
Organizer (Project 2010)
Relationship Diagram (Project 2010)
25. Can be added to the ribbon - and it walks user through formatting of the gantt chart. Pretty cool.
Units
Work Package (WBS)
Splitting tasks (Project 2010)
Gantt Chart Wizard (Project 2010)
26. Amendment to task type.
Effort Driven
Task Type
Template (Project 2010)
5 phases of project
27. Appears: min means: minute
m (Abbreviations Project 2010)
Lead
PDM
Show Assignment Units as (Project 2010)
28. Default view in Network Diagram. Without LINK LABELS - you won't see lag time - etc. The term finish to start refers specifically to the logical relationship that exits between the activities that make up he entirety of the project in which it is det
ew (Abbreviations Project 2010)
Critical Tasks
Finish to Start
WBS Code (Project 2010)
29. Two critical tasks - both same duration - vying for one resource - who wins?
Team Planner (Project 2010)
Task with first ID
Resource types
DSM Design Structure Matrix
30. Matches the outline number initially in Project 2010. It is common for work breakdown structure elements to be numbered sequentially to reveal the hierarchical structure. For example 1.3.2 Rear Wheel identifies this item as a Level 3 WBS element - si
Show Assignment Units as (Project 2010)
ew (Abbreviations Project 2010)
WBS Code (Project 2010)
Finish to Start
31. The acceloration of the successor task. 'Negative lag'
Lead
Logical Relationships in PDM
Team Planner (Project 2010)
Material resource
32. Hiding does not delete data. If you hide a column - data maintains - but to get it back - you'll need to right click - insert column.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
33. Focus on Gantt -> Format ribbon ->
Views (Project 2010)
Actual Cost
Drawing on Gantt (Project 2010)
Bar Style (Project 2010)
34. Start date - Current date - finish date - status date - schedule from - calendar - & priority (with project pro). Enterprise custom fields here too - if you're hooked into enterprise.
d (Abbreviations Project 2010)
Actual Cost
Drawing on Gantt (Project 2010)
Project information dialog (Project 2010)
35. Single Start - Single Finish. No 'danglers'. Everything must be connected. No loops.
d (Abbreviations Project 2010)
Duration
Accessing 'Properties' (Project 2010)
Network Diagram best practices
36. Add your resources names to critical tasks _______ via bar styles/text.
Table (Project 2010)
Terminal element
Manually
Team Planner (Project 2010)
37. Work divided by available resource units. Formula: D=W/U
Template (Project 2010)
Duration
Fixed Duration
Box Styles (Project 2010)
38. No single activity or group of activities to produce a single deliverable should be more than 80 hours of effort.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
39. To switch between ____________: (Project 2010) - Use the bottom-left icon. Use the ribbon. Task mode column in entry table. File -> options -> schedule.
Manual and Auto scheduled tasks
Splitting tasks (Project 2010)
ed (Abbreviations Project 2010)
Project Files (Project 2010)
40. File -> Info -> Organizer. Access global mpt - delete views - etc. (ADD MORE)
Organizer (Project 2010)
Critical Tasks
Task with minimum duration
Template (Project 2010)
41. Tasks - resources - assignments - all have dialogs. Example: resource leveling. Project information dialog very important.
Dialogs (Project 2010)
Drawing on Gantt (Project 2010)
Units
Splitting tasks (Project 2010)
42. Tables - charts - usage tables - and sheets.
Duration
Project information dialog (Project 2010)
Views (Project 2010)
Calendar/ Working time (Project 2010)
43. Always preserve the duration of a task. Changing duration when fixed will impact work.
Work
Manually
Effort Driven
Fixed Duration
44. Two tasks vying for one resource - who wins?
The task which has the LEAST slack is more important - Min-slack wins
Inspect feature (Project 2010)
Lead
Drawing on Gantt (Project 2010)
45. It is NOT an exhaustive list of work. It is instead a comprehensive classification of project scope. Contains Sub-components - work packages (child of sub-component). Further work packages can be children of other work packages. Summary tasks are the
WBS Work Breakdown Structure
Calendar/ Working time (Project 2010)
Dialogs (Project 2010)
Working Time & 'Default' start/end time (Project 2010)
46. A terminal element is the lowest element (activity or deliverable) in a WBS; it is not further subdivided. Sometimes called a 'work package' - but NOT synonymous.
Work
Finish to Start
Terminal element
emo (Abbreviations Project 2010)
47. Project Tab -> Change Working time. Define the actual 'hours' of work - which days work happens (weekends grayed out by default) - and 'exceptions' to standard work times. Work weeks tab present too.
Task Type
emo (Abbreviations Project 2010)
Calendar/ Working time (Project 2010)
Accessing 'Properties' (Project 2010)
48. The WBS contains 100% of the work defined by the project scope and captures all deliverables - internal - external - interim - in terms of the work to be completed - including project management.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
49. 'Start no earlier than' constraint.
Form (Project 2010)
Logical Relationships in PDM
Terminal element
SNET
50. Always preserve the number of hours to perform a task. Changing work when fixed will impact duration.
Timeline (Project 2010)
Task Type
Bar Style (Project 2010)
Fixed Work