SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Project Management Using Microsoft Project
Start Test
Study First
Subjects
:
certifications
,
microsoft-project
,
business-skills
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Two tasks vying for one resource - who wins?
SNET
Do not
WBS Code (Project 2010)
The task which has the LEAST slack is more important - Min-slack wins
2. Hiding does not delete data. If you hide a column - data maintains - but to get it back - you'll need to right click - insert column.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
3. Always preserve the number of hours to perform a task. Changing work when fixed will impact duration.
Timeline (Project 2010)
Fixed Work
File Name vs. Project name (Project 2010)
Summary tasks (WBS)
4. An approach for monitoring project progress that relies on the budgeted cost of activities completed to ascribe value
Fixed Units
DSM Design Structure Matrix
Earned Value
Box Styles (Project 2010)
5. File -> Info -> Organizer. Access global mpt - delete views - etc. (ADD MORE)
Organizer (Project 2010)
Earned Value
Do not
Customize 'Quick Access Tool Bar'
6. Always preserve the number of people working on a task. Changing units when fixed will impact duration.
Fixed Units
Terminal element
Work
Inspect feature (Project 2010)
7. Single Start - Single Finish. No 'danglers'. Everything must be connected. No loops.
h (Abbreviations Project 2010)
Fixed Duration
Network Diagram best practices
Terminal element
8. .mpp file extension. The actual project file.
Box Styles (Project 2010)
emo (Abbreviations Project 2010)
Project Files (Project 2010)
'80 hour rule'
9. A terminal element is the lowest element (activity or deliverable) in a WBS; it is not further subdivided. Sometimes called a 'work package' - but NOT synonymous.
Summary tasks (WBS)
Team Planner (Project 2010)
Terminal element
Material resource
10. Network Diagrom -> Format ribbon -> format.
PDM
Effort Driven
Template (Project 2010)
Box Styles (Project 2010)
11. Default view in Network Diagram. Without LINK LABELS - you won't see lag time - etc. The term finish to start refers specifically to the logical relationship that exits between the activities that make up he entirety of the project in which it is det
Finish to Start
Network Diagram best practices
Fixed Units
mo (Abbreviations Project 2010)
12. File -> Options -> Scheduling --> Drop down for Decimal or Percentage.
em (Abbreviations Project 2010)
Box Styles (Project 2010)
Dialogs (Project 2010)
Show Assignment Units as (Project 2010)
13. The Precedence Diagram Method is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes - referred to as nodes - to represent activities and connects them with arrows that
Lag
Summary tasks (WBS)
WBS Work Breakdown Structure
PDM
14. Project Tab -> Change Working time. Define the actual 'hours' of work - which days work happens (weekends grayed out by default) - and 'exceptions' to standard work times. Work weeks tab present too.
Table (Project 2010)
Calendar/ Working time (Project 2010)
Terminal element
Finish to Start
15. View -> Timeline check box. Shows timeline - but by default - nothing's on it. To add items - right click and 'add to timeline'.
Summary tasks (WBS)
Timeline (Project 2010)
h (Abbreviations Project 2010)
'The 100% Rule'
16. Tables are made up of fields.
Table (Project 2010)
PDM
Start to Finish (SF)
Start to Start
17. The total direct and indirect costs incurred in accomplishing work on an activity during a given period.
Actual Cost
Reccuring Tasks
Resource types
Team Planner (Project 2010)
18. Appears: day means: day
Critical Tasks
d (Abbreviations Project 2010)
Default view (Project 2010)
Dialogs (Project 2010)
19. Focus on Gantt -> Format ribbon ->
Calendar/ Working time (Project 2010)
Form (Project 2010)
Drawing on Gantt (Project 2010)
Finish to Start
20. Appears: wk means: week
Effort Driven
w (Abbreviations Project 2010)
Earned Value
mo (Abbreviations Project 2010)
21. 1. Initiation 2. Planning 3. Execution 4. Monitoring & Control 5. Closing
Critical Tasks
Box Styles (Project 2010)
5 phases of project
Lead
22. The acceloration of the successor task. 'Negative lag'
Accessing 'Properties' (Project 2010)
Splitting tasks (Project 2010)
Lead
Form (Project 2010)
23. Work divided by available resource units. Formula: D=W/U
Default view (Project 2010)
Resource types
Units
Duration
24. Shows logical relationship between tasks. View tab -> 'split view' section -> details checked -> More views -> Select there.
Project Files (Project 2010)
Finish to Start
Accessing 'Properties' (Project 2010)
Relationship Diagram (Project 2010)
25. Appears: min means: minute
Manually
m (Abbreviations Project 2010)
Work
Calendar/ Working time (Project 2010)
26. Appears: emin means: Elapsed minute
emo (Abbreviations Project 2010)
Units
RAM
em (Abbreviations Project 2010)
27. Contains information relative to tasks.
Team Planner (Project 2010)
emo (Abbreviations Project 2010)
Form (Project 2010)
Manual and Auto scheduled tasks
28. Gantt Chart with 'Entry' table on left.
Team Planner (Project 2010)
Inspect feature (Project 2010)
GO TO (Project 2010)
Default view (Project 2010)
29. Appears: eday means: Elapsed day
Do not
Peak
mo (Abbreviations Project 2010)
ed (Abbreviations Project 2010)
30. Tasks - resources - assignments - all have dialogs. Example: resource leveling. Project information dialog very important.
Dialogs (Project 2010)
w (Abbreviations Project 2010)
'The 100% Rule'
eh (Abbreviations Project 2010)
31. File -> Options -> Quick Access tool bar. Examples: Tables and Vies - good stuff.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
32. Task calendar - resource calendar - base calendar.
Finish to Start
Work
Template (Project 2010)
Calendars to consider
33. Task ribbon -> 'task' -> recurring task. An easy way to schedule reccuring meetings.
Reccuring Tasks
Relationship Diagram (Project 2010)
Initializing a Project (Project 2010)
WBS Code (Project 2010)
34. Two CRITICAL tasks vying for one resource - who wins?
Drawing on Gantt (Project 2010)
DSM Design Structure Matrix
PDM
Task with minimum duration
35. Fixed Duration - Fixed Units - or Fixed Work. Described on page 72 of Project 2010 book.
Finish to Start
Task Type
Start to Finish (SF)
DSM Design Structure Matrix
36. A compact - matrix representation of a system or project. The approach can be used to model complex systems in systems engineering or systems analysis - and in project planning and project management.
Calendar/ Working time (Project 2010)
DSM Design Structure Matrix
'80 hour rule'
Start to Start
37. Appears: emon means: Elapsed month
Accessing 'Properties' (Project 2010)
Dialogs (Project 2010)
Fixed Duration
emo (Abbreviations Project 2010)
38. Gantt Chart -> Format -> Bar Styles segment -> format drop down. Adjust all aspects of the bars in the gantt.
h (Abbreviations Project 2010)
ew (Abbreviations Project 2010)
The task which has the LEAST slack is more important - Min-slack wins
Bar Style (Project 2010)
39. If '______________' isn't checked - for example - then you won't be able to set a style for critical tasks.
Summary tasks (WBS)
Project information dialog (Project 2010)
'Hiding' columns (Project 2010)
Critical Tasks
40. No single activity or group of activities to produce a single deliverable should be more than 80 hours of effort.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
41. A logical relationship that states that for one project to begin - another must also be underway. For example - the writing of a business proposal must have begun in order for editing of the proposal to take place.
DSM Design Structure Matrix
Network Diagram best practices
Start to Start
Do not
42. Tables - charts - usage tables - and sheets.
Views (Project 2010)
Task Type
Box Styles (Project 2010)
Working Time & 'Default' start/end time (Project 2010)
43. Project template (.mpt) - or Global MPT file. Drives what you see in the project. Corporations may have their own.
Initializing a Project (Project 2010)
Calendar/ Working time (Project 2010)
Task with first ID
Template (Project 2010)
44. Matches the outline number initially in Project 2010. It is common for work breakdown structure elements to be numbered sequentially to reveal the hierarchical structure. For example 1.3.2 Rear Wheel identifies this item as a Level 3 WBS element - si
Bar Style (Project 2010)
WBS Code (Project 2010)
Material resource
Gantt Chart Wizard (Project 2010)
45. Changing the working time in the 'details' section of the working time dialog won't change the default start time in the options -> scheduling settings. Try to keep these in sync.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
46. ______ link Summary Tasks.
Effort Driven
Do not
Initializing a Project (Project 2010)
PDM
47. Start date - Current date - finish date - status date - schedule from - calendar - & priority (with project pro). Enterprise custom fields here too - if you're hooked into enterprise.
GO TO (Project 2010)
Logical Relationships in PDM
Gantt Chart Wizard (Project 2010)
Project information dialog (Project 2010)
48. W = D + U Duration plus available resource units
GO TO (Project 2010)
DSM Design Structure Matrix
em (Abbreviations Project 2010)
Work
49. Responsibility Assignment Matrix.
Terminal element
Peak
RAM
The task which has the LEAST slack is more important - Min-slack wins
50. U = W / D Work divided by duration.
Project Files (Project 2010)
Inspect feature (Project 2010)
em (Abbreviations Project 2010)
Units