SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Project Management Using Microsoft Project
Start Test
Study First
Subjects
:
certifications
,
microsoft-project
,
business-skills
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Appears: emon means: Elapsed month
Work
Effort Driven
emo (Abbreviations Project 2010)
Fixed Units
2. Network Diagrom -> Format ribbon -> format.
Box Styles (Project 2010)
Calendar/ Working time (Project 2010)
Effort Driven
Template (Project 2010)
3. The FILE name is what you see at the top of the screen - and is the raw name of the .mpp or .mpt FILE itself. The PROJECT NAME is set in the 'Properties' of the project. The project name will show up in reports - etc.
Calendar/ Working time (Project 2010)
File Name vs. Project name (Project 2010)
Fixed Duration
Lag
4. Their purpose is to ORGANIZE. Summary tasks have work packages or other summary tasks which comprise the parent summary task. Summary tasks are NOT scheduled. The children tasks are what need to be scheduled.
RAM
Earned Value
Summary tasks (WBS)
d (Abbreviations Project 2010)
5. Appears: eday means: Elapsed day
d (Abbreviations Project 2010)
eh (Abbreviations Project 2010)
File Name vs. Project name (Project 2010)
ed (Abbreviations Project 2010)
6. No single activity or group of activities to produce a single deliverable should be more than 80 hours of effort.
7. If '______________' isn't checked - for example - then you won't be able to set a style for critical tasks.
Dialogs (Project 2010)
Critical Tasks
Duration
SNET
8. The number of resources required to get the tasks/assignments completed.
Table (Project 2010)
WBS Code (Project 2010)
File Name vs. Project name (Project 2010)
Peak
9. ______ link Summary Tasks.
Do not
Manual and Auto scheduled tasks
Drawing on Gantt (Project 2010)
Finish to Start
10. Ensuring that the successor activity does not begin until after the predecessor activity is completed is implementing a start-to-finish (SF) model. This is the most logical path to follow when planning a project. Those in project management should be
Do not
d (Abbreviations Project 2010)
Views (Project 2010)
Start to Finish (SF)
11. File -> Info -> Organizer. Access global mpt - delete views - etc. (ADD MORE)
WBS Work Breakdown Structure
Organizer (Project 2010)
h (Abbreviations Project 2010)
Inspect feature (Project 2010)
12. Shows closest thing to a 'resource gantt chart'. Shows tasks by resource. Also shows unassigned tasks - and unscheduled tasks. Allows for user-controlled scheduling.
Material resource
Duration
Manual and Auto scheduled tasks
Team Planner (Project 2010)
13. The total direct and indirect costs incurred in accomplishing work on an activity during a given period.
GO TO (Project 2010)
Units
Actual Cost
Organizer (Project 2010)
14. Project template (.mpt) - or Global MPT file. Drives what you see in the project. Corporations may have their own.
Start to Start
Template (Project 2010)
Units
Form (Project 2010)
15. Two CRITICAL tasks vying for one resource - who wins?
Remaining Duration
Start to Finish (SF)
Work
Task with minimum duration
16. Appears: emin means: Elapsed minute
GO TO (Project 2010)
eh (Abbreviations Project 2010)
em (Abbreviations Project 2010)
ed (Abbreviations Project 2010)
17. Task calendar - resource calendar - base calendar.
GO TO (Project 2010)
Work
Calendars to consider
Task with first ID
18. The WBS contains 100% of the work defined by the project scope and captures all deliverables - internal - external - interim - in terms of the work to be completed - including project management.
19. A compact - matrix representation of a system or project. The approach can be used to model complex systems in systems engineering or systems analysis - and in project planning and project management.
DSM Design Structure Matrix
'Hiding' columns (Project 2010)
Relationship Diagram (Project 2010)
Peak
20. Amendment to task type.
'The 100% Rule'
Effort Driven
d (Abbreviations Project 2010)
ew (Abbreviations Project 2010)
21. Task ribbon -> schedule section -> broken task icon. Reschedule incomplete work - etc.
Logical Relationships in PDM
Lead
Work
Splitting tasks (Project 2010)
22. Appears: hr means: hour
Box Styles (Project 2010)
Lead
h (Abbreviations Project 2010)
em (Abbreviations Project 2010)
23. Appears: day means: day
d (Abbreviations Project 2010)
Fixed Units
Gantt Chart Wizard (Project 2010)
Lag
24. Work - resource - cost.
Resource types
Gantt Chart Wizard (Project 2010)
Critical Tasks
Earned Value
25. Focus on Gantt -> Format ribbon ->
Drawing on Gantt (Project 2010)
Critical Tasks
Gantt Chart Wizard (Project 2010)
Task Type
26. Finish to start - finish to finish - start to start - start to finish. All are 'at least'.
Logical Relationships in PDM
File Name vs. Project name (Project 2010)
Working Time & 'Default' start/end time (Project 2010)
Work Package (WBS)
27. Always preserve the number of people working on a task. Changing units when fixed will impact duration.
5 phases of project
Table (Project 2010)
Fixed Units
Working Time & 'Default' start/end time (Project 2010)
28. Gantt Chart with 'Entry' table on left.
Relationship Diagram (Project 2010)
Default view (Project 2010)
Working Time & 'Default' start/end time (Project 2010)
Project Files (Project 2010)
29. Always preserve the duration of a task. Changing duration when fixed will impact work.
DSM Design Structure Matrix
Fixed Duration
Customize 'Quick Access Tool Bar'
Work
30. Tasks - resources - assignments - all have dialogs. Example: resource leveling. Project information dialog very important.
Dialogs (Project 2010)
Task with minimum duration
Task with first ID
WBS Code (Project 2010)
31. Tables are made up of fields.
Start to Start
Project information dialog (Project 2010)
Table (Project 2010)
Critical Tasks
32. Fixed Duration - Fixed Units - or Fixed Work. Described on page 72 of Project 2010 book.
Duration
Task Type
DSM Design Structure Matrix
Task with minimum duration
33. Single Start - Single Finish. No 'danglers'. Everything must be connected. No loops.
File Name vs. Project name (Project 2010)
Initializing a Project (Project 2010)
Network Diagram best practices
Bar Style (Project 2010)
34. .mpp file extension. The actual project file.
mo (Abbreviations Project 2010)
Work
Project Files (Project 2010)
SNET
35. Tables - charts - usage tables - and sheets.
Views (Project 2010)
'The 100% Rule'
'80 hour rule'
File Name vs. Project name (Project 2010)
36. File -> info -> Project information -> advanced properties.
37. 'Start no earlier than' constraint.
Calendars to consider
ed (Abbreviations Project 2010)
SNET
Default view (Project 2010)
38. Start date - Current date - finish date - status date - schedule from - calendar - & priority (with project pro). Enterprise custom fields here too - if you're hooked into enterprise.
Project information dialog (Project 2010)
Table (Project 2010)
Views (Project 2010)
Template (Project 2010)
39. An approach for monitoring project progress that relies on the budgeted cost of activities completed to ascribe value
Earned Value
Resource types
Show Assignment Units as (Project 2010)
Accessing 'Properties' (Project 2010)
40. efines units.
Table (Project 2010)
Material resource
Fixed Units
emo (Abbreviations Project 2010)
41. To switch between ____________: (Project 2010) - Use the bottom-left icon. Use the ribbon. Task mode column in entry table. File -> options -> schedule.
Manual and Auto scheduled tasks
GO TO (Project 2010)
Fixed Units
Resource types
42. Shows logical relationship between tasks. View tab -> 'split view' section -> details checked -> More views -> Select there.
RAM
Initializing a Project (Project 2010)
Timeline (Project 2010)
Relationship Diagram (Project 2010)
43. Time delay. Sometimes - it's preferred to have lag shown as a task. You can assign costs to it - that way. Style sheets will indicate this.
Effort Driven
Lag
Duration
Finish to Start
44. Task ribbon -> 'inspect' button-> Inspect Task. It shows more details about highlighted task - including critical predecessor task. Very useful tool. Especially when resources are over allocated.
Inspect feature (Project 2010)
Task Type
w (Abbreviations Project 2010)
Units
45. File -> Options -> Quick Access tool bar. Examples: Tables and Vies - good stuff.
46. Appears: wk means: week
Task with first ID
Work
Lag
w (Abbreviations Project 2010)
47. Matches the outline number initially in Project 2010. It is common for work breakdown structure elements to be numbered sequentially to reveal the hierarchical structure. For example 1.3.2 Rear Wheel identifies this item as a Level 3 WBS element - si
WBS Code (Project 2010)
Finish to Start
Customize 'Quick Access Tool Bar'
Accessing 'Properties' (Project 2010)
48. Changing the working time in the 'details' section of the working time dialog won't change the default start time in the options -> scheduling settings. Try to keep these in sync.
49. The Precedence Diagram Method is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes - referred to as nodes - to represent activities and connects them with arrows that
Start to Finish (SF)
ed (Abbreviations Project 2010)
RAM
PDM
50. Always preserve the number of hours to perform a task. Changing work when fixed will impact duration.
DSM Design Structure Matrix
Fixed Work
5 phases of project
Fixed Duration