SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Project Management Using Microsoft Project
Start Test
Study First
Subjects
:
certifications
,
microsoft-project
,
business-skills
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Matches the outline number initially in Project 2010. It is common for work breakdown structure elements to be numbered sequentially to reveal the hierarchical structure. For example 1.3.2 Rear Wheel identifies this item as a Level 3 WBS element - si
Do not
ed (Abbreviations Project 2010)
WBS Code (Project 2010)
em (Abbreviations Project 2010)
2. Always preserve the number of people working on a task. Changing units when fixed will impact duration.
Work Package (WBS)
DSM Design Structure Matrix
Project Files (Project 2010)
Fixed Units
3. Appears: day means: day
Working Time & 'Default' start/end time (Project 2010)
Summary tasks (WBS)
d (Abbreviations Project 2010)
Critical Tasks
4. Appears: ewk means: Elapsed week
Peak
Drawing on Gantt (Project 2010)
ew (Abbreviations Project 2010)
Calendar/ Working time (Project 2010)
5. Appears: ehr means: Elapsed hour
Project information dialog (Project 2010)
WBS Work Breakdown Structure
eh (Abbreviations Project 2010)
Initializing a Project (Project 2010)
6. Shows logical relationship between tasks. View tab -> 'split view' section -> details checked -> More views -> Select there.
'80 hour rule'
Lead
Relationship Diagram (Project 2010)
m (Abbreviations Project 2010)
7. Default view in Network Diagram. Without LINK LABELS - you won't see lag time - etc. The term finish to start refers specifically to the logical relationship that exits between the activities that make up he entirety of the project in which it is det
Finish to Start
Dialogs (Project 2010)
em (Abbreviations Project 2010)
Task with first ID
8. The WBS contains 100% of the work defined by the project scope and captures all deliverables - internal - external - interim - in terms of the work to be completed - including project management.
9. Fixed Duration - Fixed Units - or Fixed Work. Described on page 72 of Project 2010 book.
mo (Abbreviations Project 2010)
Drawing on Gantt (Project 2010)
Task Type
Relationship Diagram (Project 2010)
10. 'Start no earlier than' constraint.
SNET
Do not
Organizer (Project 2010)
Resource types
11. Tables are made up of fields.
Table (Project 2010)
Do not
Task Type
5 phases of project
12. Two critical tasks - both same duration - vying for one resource - who wins?
Project Files (Project 2010)
Form (Project 2010)
Task with first ID
eh (Abbreviations Project 2010)
13. Hiding does not delete data. If you hide a column - data maintains - but to get it back - you'll need to right click - insert column.
14. Gantt Chart with 'Entry' table on left.
Reccuring Tasks
Lag
Bar Style (Project 2010)
Default view (Project 2010)
15. An approach for monitoring project progress that relies on the budgeted cost of activities completed to ascribe value
em (Abbreviations Project 2010)
'The 100% Rule'
Earned Value
w (Abbreviations Project 2010)
16. Project template (.mpt) - or Global MPT file. Drives what you see in the project. Corporations may have their own.
'Hiding' columns (Project 2010)
Template (Project 2010)
Views (Project 2010)
The task which has the LEAST slack is more important - Min-slack wins
17. Contains information relative to tasks.
Reccuring Tasks
Form (Project 2010)
Calendars to consider
Remaining Duration
18. Task calendar - resource calendar - base calendar.
Calendars to consider
Work Package (WBS)
Lag
Network Diagram best practices
19. The FILE name is what you see at the top of the screen - and is the raw name of the .mpp or .mpt FILE itself. The PROJECT NAME is set in the 'Properties' of the project. The project name will show up in reports - etc.
ed (Abbreviations Project 2010)
Terminal element
File Name vs. Project name (Project 2010)
Organizer (Project 2010)
20. It is NOT an exhaustive list of work. It is instead a comprehensive classification of project scope. Contains Sub-components - work packages (child of sub-component). Further work packages can be children of other work packages. Summary tasks are the
Units
Relationship Diagram (Project 2010)
Work
WBS Work Breakdown Structure
21. Shows closest thing to a 'resource gantt chart'. Shows tasks by resource. Also shows unassigned tasks - and unscheduled tasks. Allows for user-controlled scheduling.
Work Package (WBS)
m (Abbreviations Project 2010)
Splitting tasks (Project 2010)
Team Planner (Project 2010)
22. To switch between ____________: (Project 2010) - Use the bottom-left icon. Use the ribbon. Task mode column in entry table. File -> options -> schedule.
Manual and Auto scheduled tasks
Project Files (Project 2010)
Show Assignment Units as (Project 2010)
Manually
23. Responsibility Assignment Matrix.
Resource types
RAM
Task Type
Inspect feature (Project 2010)
24. Time delay. Sometimes - it's preferred to have lag shown as a task. You can assign costs to it - that way. Style sheets will indicate this.
Lag
emo (Abbreviations Project 2010)
em (Abbreviations Project 2010)
Views (Project 2010)
25. Appears: emon means: Elapsed month
emo (Abbreviations Project 2010)
Template (Project 2010)
Manual and Auto scheduled tasks
Critical Tasks
26. Appears: min means: minute
'80 hour rule'
The task which has the LEAST slack is more important - Min-slack wins
m (Abbreviations Project 2010)
Remaining Duration
27. File -> info -> Project information -> advanced properties.
28. W = D + U Duration plus available resource units
Remaining Duration
Work
Team Planner (Project 2010)
'The 100% Rule'
29. Function key 5. You can go directly to ID - or 'date'.
Earned Value
Gantt Chart Wizard (Project 2010)
GO TO (Project 2010)
Dialogs (Project 2010)
30. Task ribbon -> schedule section -> broken task icon. Reschedule incomplete work - etc.
Splitting tasks (Project 2010)
Bar Style (Project 2010)
File Name vs. Project name (Project 2010)
Box Styles (Project 2010)
31. Project Tab -> Change Working time. Define the actual 'hours' of work - which days work happens (weekends grayed out by default) - and 'exceptions' to standard work times. Work weeks tab present too.
Form (Project 2010)
Calendars to consider
Calendar/ Working time (Project 2010)
Task with first ID
32. Work divided by available resource units. Formula: D=W/U
Timeline (Project 2010)
Duration
mo (Abbreviations Project 2010)
Organizer (Project 2010)
33. Appears: hr means: hour
h (Abbreviations Project 2010)
Table (Project 2010)
Customize 'Quick Access Tool Bar'
Actual Cost
34. Focus on Gantt -> Format ribbon ->
Drawing on Gantt (Project 2010)
Fixed Duration
Manually
Summary tasks (WBS)
35. Vitally important. It shows how much time remains - which indicates whether or not tasks need to be re-planned.
Calendar/ Working time (Project 2010)
Remaining Duration
d (Abbreviations Project 2010)
'80 hour rule'
36. Two CRITICAL tasks vying for one resource - who wins?
Task with minimum duration
ed (Abbreviations Project 2010)
Drawing on Gantt (Project 2010)
Do not
37. Changing the working time in the 'details' section of the working time dialog won't change the default start time in the options -> scheduling settings. Try to keep these in sync.
38. efines units.
Project information dialog (Project 2010)
Lag
Material resource
Views (Project 2010)
39. The number of resources required to get the tasks/assignments completed.
em (Abbreviations Project 2010)
Peak
Timeline (Project 2010)
Lead
40. View -> Timeline check box. Shows timeline - but by default - nothing's on it. To add items - right click and 'add to timeline'.
w (Abbreviations Project 2010)
Manually
Timeline (Project 2010)
Remaining Duration
41. .mpp file extension. The actual project file.
GO TO (Project 2010)
Project Files (Project 2010)
Fixed Units
em (Abbreviations Project 2010)
42. Always preserve the number of hours to perform a task. Changing work when fixed will impact duration.
DSM Design Structure Matrix
Fixed Work
Start to Finish (SF)
h (Abbreviations Project 2010)
43. Work - resource - cost.
Reccuring Tasks
Resource types
Duration
m (Abbreviations Project 2010)
44. The Precedence Diagram Method is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes - referred to as nodes - to represent activities and connects them with arrows that
RAM
Fixed Work
PDM
'80 hour rule'
45. Gantt Chart -> Format -> Bar Styles segment -> format drop down. Adjust all aspects of the bars in the gantt.
Gantt Chart Wizard (Project 2010)
5 phases of project
PDM
Bar Style (Project 2010)
46. Add your resources names to critical tasks _______ via bar styles/text.
GO TO (Project 2010)
Manually
Default view (Project 2010)
Project information dialog (Project 2010)
47. Can be added to the ribbon - and it walks user through formatting of the gantt chart. Pretty cool.
Template (Project 2010)
Form (Project 2010)
Gantt Chart Wizard (Project 2010)
m (Abbreviations Project 2010)
48. Appears: eday means: Elapsed day
ed (Abbreviations Project 2010)
Do not
Calendars to consider
Duration
49. ______ link Summary Tasks.
Customize 'Quick Access Tool Bar'
h (Abbreviations Project 2010)
Summary tasks (WBS)
Do not
50. Always preserve the duration of a task. Changing duration when fixed will impact work.
Gantt Chart Wizard (Project 2010)
Resource types
Fixed Duration
Table (Project 2010)