Test your basic knowledge |

Project Management Using Microsoft Project

Instructions:
  • Answer 50 questions in 15 minutes.
  • If you are not ready to take this test, you can study here.
  • Match each statement with the correct term.
  • Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.

This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. If '______________' isn't checked - for example - then you won't be able to set a style for critical tasks.






2. To switch between ____________: (Project 2010) - Use the bottom-left icon. Use the ribbon. Task mode column in entry table. File -> options -> schedule.






3. Project Tab -> Change Working time. Define the actual 'hours' of work - which days work happens (weekends grayed out by default) - and 'exceptions' to standard work times. Work weeks tab present too.






4. File -> Options -> Scheduling --> Drop down for Decimal or Percentage.






5. Task ribbon -> 'task' -> recurring task. An easy way to schedule reccuring meetings.






6. It is NOT an exhaustive list of work. It is instead a comprehensive classification of project scope. Contains Sub-components - work packages (child of sub-component). Further work packages can be children of other work packages. Summary tasks are the






7. The total direct and indirect costs incurred in accomplishing work on an activity during a given period.






8. Shows closest thing to a 'resource gantt chart'. Shows tasks by resource. Also shows unassigned tasks - and unscheduled tasks. Allows for user-controlled scheduling.






9. Their purpose is to ORGANIZE. Summary tasks have work packages or other summary tasks which comprise the parent summary task. Summary tasks are NOT scheduled. The children tasks are what need to be scheduled.






10. Gantt Chart with 'Entry' table on left.






11. Hiding does not delete data. If you hide a column - data maintains - but to get it back - you'll need to right click - insert column.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


12. Fixed Duration - Fixed Units - or Fixed Work. Described on page 72 of Project 2010 book.






13. A compact - matrix representation of a system or project. The approach can be used to model complex systems in systems engineering or systems analysis - and in project planning and project management.






14. File -> Options -> Quick Access tool bar. Examples: Tables and Vies - good stuff.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


15. Can be added to the ribbon - and it walks user through formatting of the gantt chart. Pretty cool.






16. Responsibility Assignment Matrix.






17. The acceloration of the successor task. 'Negative lag'






18. The FILE name is what you see at the top of the screen - and is the raw name of the .mpp or .mpt FILE itself. The PROJECT NAME is set in the 'Properties' of the project. The project name will show up in reports - etc.






19. Contains information relative to tasks.






20. Add your resources names to critical tasks _______ via bar styles/text.






21. An 'activity' - or 'task'. The bottom 'child' task - there's nothing underneath it. If there are sub-components - or 'children' tasks below a parent task - that parent task is a SUMMARY task.






22. No single activity or group of activities to produce a single deliverable should be more than 80 hours of effort.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


23. The number of resources required to get the tasks/assignments completed.






24. Gantt Chart -> Format -> Bar Styles segment -> format drop down. Adjust all aspects of the bars in the gantt.






25. The WBS contains 100% of the work defined by the project scope and captures all deliverables - internal - external - interim - in terms of the work to be completed - including project management.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


26. Tables are made up of fields.






27. Appears: mon means: month






28. Focus on Gantt -> Format ribbon ->






29. W = D + U Duration plus available resource units






30. Default view in Network Diagram. Without LINK LABELS - you won't see lag time - etc. The term finish to start refers specifically to the logical relationship that exits between the activities that make up he entirety of the project in which it is det






31. The Precedence Diagram Method is a tool for scheduling activities in a project plan. It is a method of constructing a project schedule network diagram that uses boxes - referred to as nodes - to represent activities and connects them with arrows that






32. A terminal element is the lowest element (activity or deliverable) in a WBS; it is not further subdivided. Sometimes called a 'work package' - but NOT synonymous.






33. Two critical tasks - both same duration - vying for one resource - who wins?






34. Appears: min means: minute






35. Start date - Current date - finish date - status date - schedule from - calendar - & priority (with project pro). Enterprise custom fields here too - if you're hooked into enterprise.






36. Project template (.mpt) - or Global MPT file. Drives what you see in the project. Corporations may have their own.






37. Appears: emin means: Elapsed minute






38. Work divided by available resource units. Formula: D=W/U






39. Appears: ewk means: Elapsed week






40. Finish to start - finish to finish - start to start - start to finish. All are 'at least'.






41. Single Start - Single Finish. No 'danglers'. Everything must be connected. No loops.






42. A logical relationship that states that for one project to begin - another must also be underway. For example - the writing of a business proposal must have begun in order for editing of the proposal to take place.






43. Task calendar - resource calendar - base calendar.






44. Task ribbon -> 'inspect' button-> Inspect Task. It shows more details about highlighted task - including critical predecessor task. Very useful tool. Especially when resources are over allocated.






45. Always preserve the duration of a task. Changing duration when fixed will impact work.






46. View -> Timeline check box. Shows timeline - but by default - nothing's on it. To add items - right click and 'add to timeline'.






47. Appears: day means: day






48. Changing the working time in the 'details' section of the working time dialog won't change the default start time in the options -> scheduling settings. Try to keep these in sync.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


49. Always preserve the number of hours to perform a task. Changing work when fixed will impact duration.






50. Appears: wk means: week







Sorry!:) No result found.

Can you answer 50 questions in 15 minutes?


Let me suggest you:



Major Subjects



Tests & Exams


AP
CLEP
DSST
GRE
SAT
GMAT

Most popular tests