Test your basic knowledge |

CMMI: Capability Maturity Model Integration

Instructions:
  • Answer 50 questions in 15 minutes.
  • If you are not ready to take this test, you can study here.
  • Match each statement with the correct term.
  • Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.

This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Assign responsibility and authority for performing the process - developing the work products - and providing the services of the process.






2. Manage projects in order to quantify the way the process has been defined - to achieve the project's established quality and process performance objectives






3. Establish and maintain the description of a defined process.






4. Capability Maturity Model Integration - Best Practices for model definition - implementation and improvement of PROCESSES






5. Review the activities - status - and results of the process with higher level management and resolve issues.






6. Set of components to satisfy a specific area of interest 16 areas of common processes






7. Develop products and services






8. Goals that are repeated for multiple PA. required






9. Place designated work products of the process under appropriate levels of control.






10. Integration of project management - basis the OPD and adaptation guidelines to define the process - according to the establishment and management of the project - and included in the relevant key man for IPPD - IPM also covers the integration team to






11. Results that must be achieved to satisfy the PA. reuired






12. Monitor and control the process against the plan for performing the process and take appropriate corrective action.






13. Dev - Acq - Svc






14. Ensure continuos improvement of the process in fulfilling the relevant business objectives of the organization -






15. Perform the specific practices of the process area to develop work products and provide services to achieve the specific goals of the process area.






16. Stiffness in the selection of APs to be improved cost may be higher if the organization does not have any interest in PA






17. Deliver and support services






18. Permits comparison between organizations






19. Activities to ensure that APs are Effective- Repeatable and Durable - Can be replaced by alternative practices






20. Levels are achieved by...






21. 1 - Home 2 - Managed 3 - Set 4 - Quantitatively Managed 5 - In optimization






22. Objective evaluate adherence of the process against its process description - standards - and procedures - and address noncompliance.






23. Quantitatively Managed Process controlled by statistical techniques






24. Incomplete process not executed - or partially executed






25. Establish and maintain the plan for performing the process.






26. 0 - Incomplete 1 - Run 2 - Managed 3 - Set 4 - Quantitatively Managed 5 - Tuning In






27. Defined Process is adapted from the organization's standard






28. Stabilize the performance of one or more subprocesses to determine the ability of the process to achieve the established quantitative quality and process-performance objectives.






29. The process supports and enables achievement of specific goals of the process area by transforming identifiable input work products to produce identifiable output work products.






30. GG 1 - Achieve specific goals (SG) GG 2 - Managed GG 3 - Defined GG 4 - Managed quantitatively GG 5 - In optimization = Institutionalize a process






31. Practices related to an area that when implemeneted jointly meet a conj. goal considered important to realize significant improvements in that area.






32. Important activities to meet the SG Eexpected - Can be replaced by alternative practices






33. Supplies - services and acquisitions






34. Keeping a clear understanding with our customer and other stakeholders about the services we provide and adjusting when you find inconsistencies.






35. The process is institutionalized as managed process.






36. Provide adequate resources for performing the process - developiing the work products - and providing the services of the process.






37. Establish and maintain an organizational policy for planning and performing the process.






38. SW Eng Eng HD Systems






39. Collect work products - measures - measurement results - and improvement information derived from planning and performing the process to support the future use and improvement of the organization's processes and process assets.






40. Integrated Product Development Processes and Optional Collaboration of Stakeholders during the product life






41. There is total flexibility - dependency between PA's unproven ROI






42. Train the people performing or supporting the process as needed.






43. Establish and maintain quantitative objectives for the process - which address quality and process performance - based on customer needs and business objectives.






44. More flexible organization Easy comparison with ISO 15504






45. The process is institutionalized as a quantitatively managed process.






46. In Optimization Process continuous improvement






47. The process is institutionalized as a defined process.






48. The process is institutionalized as an optimizing process.






49. Managed Process planned and implemented in accordance with the project






50. Establish and maintain the expected involvement of stakeholders during the execution of the process.