Test your basic knowledge |
Microsoft Project
Start Test
Study First
Subjects
:
certifications
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Show project summary task
General Tab - used to change cutomer feedback and document management options
View Tab - used to specify whether a project level summary task is to be displayed. It would have an ID of 0. Default is cleared
Schedule tab - causes MSP displays messages about schedule inconsistencies - Default is checked
Security tab - removes the author - manager - company and last saved by fields from the properties dialog box when a project is saved. default is cleared
2. Duration is entered in
Schedule tab - default for Unit of time (Minutes - hours - days - weeks - or month) in Duration
Calculation tab - specifies that MSP should calculate and display a critical path for each independent network of tasks. default is cleared
Calculation tab - MSP will automatically update resource status (Actual - remaining work or cost) whenever you update task status default is checked
General Tab - used to specify the standard pay rate for new resources. can be overridden by typing a different rate in the resource form view - resource information dialog box or resource sheet. default is $0/h
3. Calendar type
Calendar Tab - used to specify the month that begins the fiscal year. MSP displays years based on fiscal year. Default is January
View Tab - used to specify the type of calendar- default is Gregorian 12 month calend start on January 1
Calculation tab - Used to specify how MSP sets the fixed cost accrual for new tasks. Accrued at the start of a task - prorated throughout - accrued at the end of a task - default is prorated
View Tab - it is used to specify the number of digits that should appear after the decimal - default is 2
4. Prompt for project infor for new projects
View Tab - used to specify the view that is diplayed at startup - Default is Gantt Chart
View Tab - used to display outline symbols next to each task name (A plus sign is displayed next to rolled up summary tasks and a minus sign next to summary tasks showing their subtasks) By default is checked.
General Tab - used to set project to open the project information dialog box whenever a new project is created
Calendar Tab - used to label the fiscal year using the calend ear in which the fiscal eyar begins. by default is cleared
5. Default start time
Calendar Tab - used to label the fiscal year using the calend ear in which the fiscal eyar begins. by default is cleared
Calendar Tab - used to specify the start time - the default setting is 8am
Interface tab - used to specify that the feedback triangle should appear in a corner of tasks name field if the task's start date or finish dates is changed. default is checked.
Interface tab - the project elements are matched in the organizer by using each element's internal ID. By selecting - the physical element names are ignored as they may differ between projects
6. User name
General Tab - used to display the user name entered when project was installed (the user name can be changed by typing a new name in this box.
Security tab - ensures that any project server or workspace sites specified on the collaborate tab of the option dialog box will be added to the list
View Tab - used to display the outline number next to each task name - default is cleared
General Tab - used to specify the overtime pay rate for new resources. can be overridden by typing a different rate in the resource form view - resource information dialog box or resource sheet. default is $0/h
7. Priority
View Tab - used to specify which currency symbol to be used - default is $
General Tab - used to display the user name entered when project was installed (the user name can be changed by typing a new name in this box.
Project Information - used to indicate how readily tasks in the current project are delayed whe resources are leveled across multiple projects. a number between 0 and 1000. the higher the number the higher the priority
Schedule tab - specifies that all new tasks have estimated durations.
8. And move end of completed parts forward to status date
View Tab - used to specify whether external predecessor tasks are show in the current project - default is checked
Calculation tab - used to specify a single critical path throughout the master project (Treating inserted projects as summary tasks in the master project) default is checked.
Calculation tab - used to specify the number of days of slack MSP uses to determin critical tasks. if the number of slack days for a taks is less than or equal to the number specified here - the task is considered critical. Default is 0 days.
Calculation tab - goes with "move start of remaining parts before status date forward to status date;" - remaing portion of the task moves forward to start at the status date. default is cleared
9. Show external predecessors
View Tab - used to specify whether external predecessor tasks are show in the current project - default is checked
View Tab - it is used to specify the number of digits that should appear after the decimal - default is 2
Schedule tab - for any new task - determines how project recalculates the three related fields - work - duration - and units when one is value is edited
Used to specify whether the side pane displays the project default main page or a custom page developed by the organization
10. Remove inforamtion form file properties on save
View Tab - used to specify whether a project level summary task is to be displayed. It would have an ID of 0. Default is cleared
Security tab - removes the author - manager - company and last saved by fields from the properties dialog box when a project is saved. default is cleared
Interface tab - the project elements are matched in the organizer by using each element's internal ID. By selecting - the physical element names are ignored as they may differ between projects
Schedule tab - causes MSP displays messages about schedule inconsistencies - Default is checked
11. Edits to work - units - or duration
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
12. Fiscal year starts in
Calendar Tab - used to specify the month that begins the fiscal year. MSP displays years based on fiscal year. Default is January
Calculation tab - used to specify a single critical path throughout the master project (Treating inserted projects as summary tasks in the master project) default is checked.
View Tab - used to specify the position of the currency symbol. default is just before amount
Calculation tab - specifies that MSP calculates actual costs automatically based upon resource rates - per-use resourcee costs and fixed task costs. If checked - a user cannot enter any additional acutal cost until the task is 100% complete. Default
13. New tasks have estimated durations
Calculation tab - goes with "move end of completed parts after status date back to status date". The remaining portion of the task moves back to start at the status date otherwise it will complete as planned. by dfault is cleared
General Tab - used to turn on autofilter automatically when a new project is created - default is cleared
Calendar Tab - used to define the number of datys assigned to a task when a duration of one month is entered. Default is 20
Schedule tab - specifies that all new tasks have estimated durations.
14. Updating task status updates resource status
Security tab - ensures that any project server or workspace sites specified on the collaborate tab of the option dialog box will be added to the list
Calculation tab - MSP will automatically update resource status (Actual - remaining work or cost) whenever you update task status default is checked
Project Information - used to specify whether to project is scheduled from a project start date or a project finish date. default is start date
Calendar Tab - used to define the number of hours assigned whan a duration of one day is entered - default is 8h
15. Placement
View Tab - used to specify the position of the currency symbol. default is just before amount
Schedule tab - when checked - automatically links tasks again when a user cuts - moves - or inserts them. this applies only to contiguous finish to start task relationships. default/checked
Calendar Tab - used to specify the day of the week on twhich the scheduleing week begins
View Tab - used to specify which currency symbol to be used - default is $
16. display project guide
Interface tab - used to diplsy the side pane containing the Project Guide. this is a global setting and applies to all project - default is checked
Interface tab - the project elements are matched in the organizer by using each element's internal ID. By selecting - the physical element names are ignored as they may differ between projects
Calculation tab - used to recalculate based on the calculation mode and calculate options.
Calculation tab - specifies that MSP should calculate and display a critical path for each independent network of tasks. default is cleared
17. Show outline symbol
View Tab - used to display outline symbols next to each task name (A plus sign is displayed next to rolled up summary tasks and a minus sign next to summary tasks showing their subtasks) By default is checked.
Project Information - used to specify the start date of the current project. - only available if the "Schedule from" drop down is "Project Start Date" MSP will calculate the finish date with ASAP constraint.
Calculation tab - this is for tasks that were scheduled to start after the status date but actually started early. the completed portion of the task moves back to the finish at the status date. Defaulted is cleared.
Calculation tab - specifies that MSP should calculate and display a critical path for each independent network of tasks. default is cleared
18. Move end of completed parts after status date back to status date
Schedule tab - default for Unit of time (Minutes - hours - days - weeks - or month) in Duration
View Tab - used to specify whether the links between projects dialog box should appear when the current project opens and has links to other projects - default is checked
Calculation tab - this is for tasks that were scheduled to start after the status date but actually started early. the completed portion of the task moves back to the finish at the status date. Defaulted is cleared.
Calendar Tab - used to specify the day of the week on twhich the scheduleing week begins
19. Calculate
Calculation tab - specifies whether MSP recalculates the acrtive project or all open projects.
Security tab - used to set the security level (very high - high - medium or low) default is HIgh - indicating that only signed macros from trusted sources are allowed to run
Schedule tab - specifies that all new tasks have estimated durations.
View Tab - used to specify which type of currency is being used - default is USD
20. Schedule from
General Tab - used to set project to open the project information dialog box whenever a new project is created
Project Information - used to indicate how readily tasks in the current project are delayed whe resources are leveled across multiple projects. a number between 0 and 1000. the higher the number the higher the priority
Interface tab - used to specify that the feedback triangle should appear in a corner of the duration field or the task name field if task's work - units - or duration is changed. Default is checked
Project Information - used to specify whether to project is scheduled from a project start date or a project finish date. default is start date
21. Finish date
Schedule tab - specifies that all new tasks have estimated durations.
View Tab - used to display summary tasks. default is check
Schedule tab - causes MSP displays messages about schedule inconsistencies - Default is checked
Project Information - used to specify the finish date of the current project. only available if the "Schedule from" drop down is "Project Finish date" MSP will calculat the start date with ALAP constraints
22. Deletions in the name column
View Tab - used to display summary tasks. default is check
Interface tab - used to specify that the delete indicator should appear in the indicators field if the text in the task name or resource name field is deleted - default is checked
Project Information - used to specify the finish date of the current project. only available if the "Schedule from" drop down is "Project Finish date" MSP will calculat the start date with ALAP constraints
Calculation tab - specifies that MSP should calculate and display a critical path for each independent network of tasks. default is cleared
23. Autolink inserted or moved tasks
Calculation tab - used to specify a single critical path throughout the master project (Treating inserted projects as summary tasks in the master project) default is checked.
Schedule tab - when checked - automatically links tasks again when a user cuts - moves - or inserts them. this applies only to contiguous finish to start task relationships. default/checked
Schedule tab - allows rescheduling of remaining duration and work when a task slips or reports progress ahead of shedule. default - checked
Calculation tab - used to recalculate based on the calculation mode and calculate options.
24. Start date
Calculation tab - goes with "move start of remaining parts before status date forward to status date;" - remaing portion of the task moves forward to start at the status date. default is cleared
Project Information - used to indicate how readily tasks in the current project are delayed whe resources are leveled across multiple projects. a number between 0 and 1000. the higher the number the higher the priority
Schedule tab - it displays a question mark for estimated duration. default - checked
Project Information - used to specify the start date of the current project. - only available if the "Schedule from" drop down is "Project Start Date" MSP will calculate the finish date with ASAP constraint.
25. Status date
Calendar Tab - used to define the number of datys assigned to a task when a duration of one month is entered. Default is 20
Calculation tab - goes with "move start of remaining parts before status date forward to status date;" - remaing portion of the task moves forward to start at the status date. default is cleared
Project Information - used to specify the status date. The status date is used to perform earned value calculations - identify the complete through date in the Update project dialog box. and place progressline. if the status date is set to NA then cu
View Tab - used to specify which interface elements should be displyed or hidden. global setting - default is all are selected. - elements are - status bar - windows in taskbar - bars and shapes in gantt vies in 3d - scroll bars - entry bar - OLE lin
26. Automatically add new resources and task
View Tab - used to specify the position of the currency symbol. default is just before amount
General Tab - used to set the number of change leverls a user can undo and redo - default is 20
General Tab - used to automatically add new resources to the resource pool and assigns them default values whenever a new resource name is entered. default is checked
Used to specify whether the side pane displays the project default main page or a custom page developed by the organization
27. Show scheduling message
Project Information - used to specify whether to project is scheduled from a project start date or a project finish date. default is start date
Schedule tab - causes MSP displays messages about schedule inconsistencies - Default is checked
Interface tab - used to specify that the feedback triangle should appear in a corner of the duration field or the task name field if task's work - units - or duration is changed. Default is checked
Calendar Tab - used to define the number of hours assigned whan a duration of one day is entered - default is 8h
28. Week starts on
Calculation tab - specifies that MSP calculates actual costs automatically based upon resource rates - per-use resourcee costs and fixed task costs. If checked - a user cannot enter any additional acutal cost until the task is 100% complete. Default
Project Information - used to specify the start date of the current project. - only available if the "Schedule from" drop down is "Project Start Date" MSP will calculate the finish date with ASAP constraint.
Calendar Tab - used to specify the day of the week on twhich the scheduleing week begins
Schedule tab - used to specify the default start date for new tasks as they are entered in the current project. Project Start Date/no constraint - Start on Current Date/a Start No Earlier Than constraint (using the current date)
29. Currency
View Tab - used to specify which type of currency is being used - default is USD
Calendar Tab - used to specify the start time - the default setting is 8am
Security tab - used to set the security level (very high - high - medium or low) default is HIgh - indicating that only signed macros from trusted sources are allowed to run
Project Information - used to specify the base calendar to be used for the proejct calendar
30. Days per month
Calendar Tab - used to define the number of datys assigned to a task when a duration of one month is entered. Default is 20
Schedule tab - specifies that MSP schedules tasks according to their constraint dates
Calculation tab - MSP will automatically update resource status (Actual - remaining work or cost) whenever you update task status default is checked
Schedule tab - when checked - automatically links tasks again when a user cuts - moves - or inserts them. this applies only to contiguous finish to start task relationships. default/checked
31. Inserted project are calculated like summary tasks
Calculation tab - used to specify a single critical path throughout the master project (Treating inserted projects as summary tasks in the master project) default is checked.
Calculation tab - specifies whether calculations are done automatically or manually.
Security tab - enables a user to define how MSP shoudl handle legacy and non-default file formats. MPW formats will not open in 2007
Schedule tab - for any new task - determines how project recalculates the three related fields - work - duration - and units when one is value is edited
32. Symbol
Calculation tab - MSP will automatically update resource status (Actual - remaining work or cost) whenever you update task status default is checked
Project Information - used to indicate how readily tasks in the current project are delayed whe resources are leveled across multiple projects. a number between 0 and 1000. the higher the number the higher the priority
View Tab - used to specify which currency symbol to be used - default is $
Interface tab - used to specify that the delete indicator should appear in the indicators field if the text in the task name or resource name field is deleted - default is checked
33. Date format
View Tab - used to display outline symbols next to each task name (A plus sign is displayed next to rolled up summary tasks and a minus sign next to summary tasks showing their subtasks) By default is checked.
Calculation tab - goes with "move end of completed parts after status date back to status date". The remaining portion of the task moves back to start at the status date otherwise it will complete as planned. by dfault is cleared
View Tab - used to specify the format for displaying dates in all project files. Default format is Mon 1/23/02
Calendar Tab - used to specify the start time - the default setting is 8am
34. Calendar
General Tab - automatically opens the last proejct file that was used. Default is cleared (if cleared project creates a new project whenever it starts)
Interface tab - used to specify that the feedback triangle should appear in a corner of tasks name field if the task's start date or finish dates is changed. default is checked.
Calculation tab - this is for tasks that were scheduled to start after the status date but actually started early. the completed portion of the task moves back to the finish at the status date. Defaulted is cleared.
Project Information - used to specify the base calendar to be used for the proejct calendar
35. Show links between projects dialog box on open
Project Information - used to specify the base calendar to be used for the proejct calendar
Calendar Tab - used to specify the start time - the default setting is 8am
Calendar Tab - used to specify the month that begins the fiscal year. MSP displays years based on fiscal year. Default is January
View Tab - used to specify whether the links between projects dialog box should appear when the current project opens and has links to other projects - default is checked
36. Legacy formats section
Calendar Tab - used to specify the end time - default setting is 5pm
Project Information - used to specify the current date. by default this is the computer date and time
Security tab - enables a user to define how MSP shoudl handle legacy and non-default file formats. MPW formats will not open in 2007
View Tab - used to specify which type of currency is being used - default is USD
37. Current date
General Tab - used to display the user name entered when project was installed (the user name can be changed by typing a new name in this box.
Calendar Tab - used to define the number of hours assigned whan a duration of one day is entered - default is 8h
General Tab - used to specify the overtime pay rate for new resources. can be overridden by typing a different rate in the resource form view - resource information dialog box or resource sheet. default is $0/h
Project Information - used to specify the current date. by default this is the computer date and time
38. Statistics
View Tab - used to display summary tasks. default is check
Project Information - used to indicate how readily tasks in the current project are delayed whe resources are leveled across multiple projects. a number between 0 and 1000. the higher the number the higher the priority
Project Information - used to open the project statistics dialog box. is used to review scheduled and actual start and finish date - durations - work and cost.
Calculation tab - used to recalculate based on the calculation mode and calculate options.
39. Show outline number
Calculation tab - goes with "move end of completed parts after status date back to status date". The remaining portion of the task moves back to start at the status date otherwise it will complete as planned. by dfault is cleared
View Tab - used to specify which currency symbol to be used - default is $
Interface tab - the project elements are matched in the organizer by using each element's internal ID. By selecting - the physical element names are ignored as they may differ between projects
View Tab - used to display the outline number next to each task name - default is cleared
40. Show external successors
General Tab - used to specify the overtime pay rate for new resources. can be overridden by typing a different rate in the resource form view - resource information dialog box or resource sheet. default is $0/h
View Tab - used to specify whether external successor tasks are shown in the current project - default is checked
View Tab - used to specify which interface elements should be displyed or hidden. global setting - default is all are selected. - elements are - status bar - windows in taskbar - bars and shapes in gantt vies in 3d - scroll bars - entry bar - OLE lin
General Tab - used to specify the standard pay rate for new resources. can be overridden by typing a different rate in the resource form view - resource information dialog box or resource sheet. default is $0/h
41. Default overtime rate
General Tab - used to specify the overtime pay rate for new resources. can be overridden by typing a different rate in the resource form view - resource information dialog box or resource sheet. default is $0/h
View Tab - used to specify whether external successor tasks are shown in the current project - default is checked
Calculation tab - for tasks that were schedule to start before the status date but actually started late. remaining port of the task moves forward to start at the status date. by default is cleared
Schedule tab - specifies that MSP schedules tasks according to their constraint dates
42. Resource Assignments
Interface tab - used to specify that the feedback triangle should appear in a corner of a field if additional resources are assigned to a task that already has assigned resources - default - checked.
Calendar Tab - used to define the number of datys assigned to a task when a duration of one month is entered. Default is 20
Project Information - used to specify the start date of the current project. - only available if the "Schedule from" drop down is "Project Start Date" MSP will calculate the finish date with ASAP constraint.
View Tab - used to specify whether external successor tasks are shown in the current project - default is checked
43. Automatically accept new external data
General Tab - used to set the number of recetnly opened project file that are listed at the bottom of the file. Default is 4 project file names
View Tab - used to indent the names of subtasks in the task name - default is checked
View Tab - used to specify whether MSP would accept and automatically update chanes to task dependencies between projects. default is checked. (only available when "Show Link between project dialog box on open" is cleared
Used to specify whether the side pane displays the project default main page or a custom page developed by the organization
44. Edits to start and finishe dates
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
45. And move start of remaining parts back to status date
Schedule tab - specifies that all new tasks have estimated durations.
View Tab - used to specify which interface elements should be displyed or hidden. global setting - default is all are selected. - elements are - status bar - windows in taskbar - bars and shapes in gantt vies in 3d - scroll bars - entry bar - OLE lin
Calculation tab - goes with "move end of completed parts after status date back to status date". The remaining portion of the task moves back to start at the status date otherwise it will complete as planned. by dfault is cleared
Schedule tab - for any new task - determines how project recalculates the three related fields - work - duration - and units when one is value is edited
46. Calculation mode
General Tab - used to set project to open the project information dialog box whenever a new project is created
Calculation tab - specifies whether calculations are done automatically or manually.
Calculation tab - specifies that MSP should calculate and display a critical path for each independent network of tasks. default is cleared
Calculation tab - used to specify the number of days of slack MSP uses to determin critical tasks. if the number of slack days for a taks is less than or equal to the number specified here - the task is considered critical. Default is 0 days.
47. Calculate multiple critcial paths
View Tab - used to indent the names of subtasks in the task name - default is checked
View Tab - used to specify which currency symbol to be used - default is $
Calculation tab - specifies that MSP should calculate and display a critical path for each independent network of tasks. default is cleared
Interface tab - the project elements are matched in the organizer by using each element's internal ID. By selecting - the physical element names are ignored as they may differ between projects
48. Tasks will always honor their constraint dates
General Tab - used to automatically add new resources to the resource pool and assigns them default values whenever a new resource name is entered. default is checked
Schedule tab - specifies that MSP schedules tasks according to their constraint dates
Interface tab - used to specify wheter the side pane displys the project guide content that comes with Projec tor customer content that your organization has developed.
General Tab - used to turn on autofilter automatically when a new project is created - default is cleared
49. Require project server and workspace sites to be added to the IE Trusted sites list
Security tab - ensures that any project server or workspace sites specified on the collaborate tab of the option dialog box will be added to the list
Interface tab - used to specify that the feedback triangle should appear in a corner of a field if additional resources are assigned to a task that already has assigned resources - default - checked.
Calculation tab - goes with "move end of completed parts after status date back to status date". The remaining portion of the task moves back to start at the status date otherwise it will complete as planned. by dfault is cleared
Security tab - enables a user to define how MSP shoudl handle legacy and non-default file formats. MPW formats will not open in 2007
50. Project Guide Content
Interface tab - used to specify wheter the side pane displys the project guide content that comes with Projec tor customer content that your organization has developed.
Schedule tab - allows rescheduling of remaining duration and work when a task slips or reports progress ahead of shedule. default - checked
Project Information - used to specify whether to project is scheduled from a project start date or a project finish date. default is start date
Calculation tab - user can specify whether % complete or Physical % Complete should be used for earned value analysis in this project