Test your basic knowledge |
Microsoft Project
Start Test
Study First
Subjects
:
certifications
,
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Split in progress tasks
Security tab - used to set the security level (very high - high - medium or low) default is HIgh - indicating that only signed macros from trusted sources are allowed to run
Schedule tab - allows rescheduling of remaining duration and work when a task slips or reports progress ahead of shedule. default - checked
Project Information - used to specify the finish date of the current project. only available if the "Schedule from" drop down is "Project Finish date" MSP will calculat the start date with ALAP constraints
Security tab - enables a user to define how MSP shoudl handle legacy and non-default file formats. MPW formats will not open in 2007
2. Resource Assignments
Calculation tab - Used to specify how MSP sets the fixed cost accrual for new tasks. Accrued at the start of a task - prorated throughout - accrued at the end of a task - default is prorated
Calendar Tab - used to specify the day of the week on twhich the scheduleing week begins
Project Information - used to specify the base calendar to be used for the proejct calendar
Interface tab - used to specify that the feedback triangle should appear in a corner of a field if additional resources are assigned to a task that already has assigned resources - default - checked.
3. Calculate
General Tab - used to display the user name entered when project was installed (the user name can be changed by typing a new name in this box.
Interface tab - used to specify that the feedback triangle should appear in a corner of tasks name field if the task's start date or finish dates is changed. default is checked.
Schedule tab - specifies that MSP schedules tasks according to their constraint dates
Calculation tab - specifies whether MSP recalculates the acrtive project or all open projects.
4. Finish date
Used to specify whether the side pane displays the project default main page or a custom page developed by the organization
Calendar Tab - used to specify the month that begins the fiscal year. MSP displays years based on fiscal year. Default is January
View Tab - used to specify whether a project level summary task is to be displayed. It would have an ID of 0. Default is cleared
Project Information - used to specify the finish date of the current project. only available if the "Schedule from" drop down is "Project Finish date" MSP will calculat the start date with ALAP constraints
5. Default task type
Schedule tab - for any new task - determines how project recalculates the three related fields - work - duration - and units when one is value is edited
View Tab - used to specify whether MSP would accept and automatically update chanes to task dependencies between projects. default is checked. (only available when "Show Link between project dialog box on open" is cleared
Project Information - used to specify the start date of the current project. - only available if the "Schedule from" drop down is "Project Start Date" MSP will calculate the finish date with ASAP constraint.
Interface tab - used to specify that the feedback triangle should appear in a corner of the duration field or the task name field if task's work - units - or duration is changed. Default is checked
6. Default view
View Tab - used to specify the view that is diplayed at startup - Default is Gantt Chart
View Tab - used to display summary tasks. default is check
Interface tab - used to diplsy the side pane containing the Project Guide. this is a global setting and applies to all project - default is checked
Calculation tab - used to specify a single critical path throughout the master project (Treating inserted projects as summary tasks in the master project) default is checked.
7. Show outline symbol
Security tab - used to set the security level (very high - high - medium or low) default is HIgh - indicating that only signed macros from trusted sources are allowed to run
View Tab - used to specify the position of the currency symbol. default is just before amount
View Tab - used to display outline symbols next to each task name (A plus sign is displayed next to rolled up summary tasks and a minus sign next to summary tasks showing their subtasks) By default is checked.
Schedule tab - allows rescheduling of remaining duration and work when a task slips or reports progress ahead of shedule. default - checked
8. Hours per week
Project Information - used to specify the finish date of the current project. only available if the "Schedule from" drop down is "Project Finish date" MSP will calculat the start date with ALAP constraints
View Tab - used to display the outline number next to each task name - default is cleared
Calendar Tab - used to define the number of hours assigns to a task when a duration of one week is entered. default is 40
Interface tab - used to diplsy the side pane containing the Project Guide. this is a global setting and applies to all project - default is checked
9. User name
Interface tab - the project elements are matched in the organizer by using each element's internal ID. By selecting - the physical element names are ignored as they may differ between projects
General Tab - used to display the user name entered when project was installed (the user name can be changed by typing a new name in this box.
Calculation tab - goes with "move start of remaining parts before status date forward to status date;" - remaing portion of the task moves forward to start at the status date. default is cleared
Schedule tab - for any new task - determines how project recalculates the three related fields - work - duration - and units when one is value is edited
10. display project guide
Schedule tab - specifies that new tasks are scheduled such that the work on the task remains constant as a user adds or removes assignments. - if checked - adding or removing resource assignments on a fixed units taks has no effect on task duration.
General Tab - automatically opens the last proejct file that was used. Default is cleared (if cleared project creates a new project whenever it starts)
Interface tab - used to diplsy the side pane containing the Project Guide. this is a global setting and applies to all project - default is checked
Project Information - used to specify the current date. by default this is the computer date and time
11. Show links between projects dialog box on open
View Tab - used to indent the names of subtasks in the task name - default is checked
View Tab - used to specify whether the links between projects dialog box should appear when the current project opens and has links to other projects - default is checked
View Tab - used to display outline symbols next to each task name (A plus sign is displayed next to rolled up summary tasks and a minus sign next to summary tasks showing their subtasks) By default is checked.
Security tab - removes the author - manager - company and last saved by fields from the properties dialog box when a project is saved. default is cleared
12. Start date
Interface tab - used to specify that the feedback triangle should appear in a corner of a field if additional resources are assigned to a task that already has assigned resources - default - checked.
Project Information - used to specify the start date of the current project. - only available if the "Schedule from" drop down is "Project Start Date" MSP will calculate the finish date with ASAP constraint.
Schedule tab - allows rescheduling of remaining duration and work when a task slips or reports progress ahead of shedule. default - checked
Calendar Tab - used to specify the end time - default setting is 5pm
13. Open last file on startup
Calculation tab - specifies that MSP calculates actual costs automatically based upon resource rates - per-use resourcee costs and fixed task costs. If checked - a user cannot enter any additional acutal cost until the task is 100% complete. Default
View Tab - used to specify whether external predecessor tasks are show in the current project - default is checked
General Tab - automatically opens the last proejct file that was used. Default is cleared (if cleared project creates a new project whenever it starts)
View Tab - used to specify the position of the currency symbol. default is just before amount
14. Actual costs are always calculated by MSP
View Tab - used to specify whether external successor tasks are shown in the current project - default is checked
Calendar Tab - used to define the number of hours assigns to a task when a duration of one week is entered. default is 40
Schedule tab - for any new task - determines how project recalculates the three related fields - work - duration - and units when one is value is edited
Calculation tab - specifies that MSP calculates actual costs automatically based upon resource rates - per-use resourcee costs and fixed task costs. If checked - a user cannot enter any additional acutal cost until the task is 100% complete. Default
15. Show external successors
View Tab - used to specify whether external successor tasks are shown in the current project - default is checked
Calculation tab - this is for tasks that were scheduled to start after the status date but actually started early. the completed portion of the task moves back to the finish at the status date. Defaulted is cleared.
Interface tab - used to specify wheter the side pane displys the project guide content that comes with Projec tor customer content that your organization has developed.
Project Information - used to specify the current date. by default this is the computer date and time
16. Calendar type
Calendar Tab - used to define the number of hours assigns to a task when a duration of one week is entered. default is 40
Calculation tab - used to specify a single critical path throughout the master project (Treating inserted projects as summary tasks in the master project) default is checked.
View Tab - used to specify the type of calendar- default is Gregorian 12 month calend start on January 1
Project Information - used to specify the current date. by default this is the computer date and time
17. Show scheduling message
Project Information - used to specify the status date. The status date is used to perform earned value calculations - identify the complete through date in the Update project dialog box. and place progressline. if the status date is set to NA then cu
Schedule tab - causes MSP displays messages about schedule inconsistencies - Default is checked
View Tab - used to specify which interface elements should be displyed or hidden. global setting - default is all are selected. - elements are - status bar - windows in taskbar - bars and shapes in gantt vies in 3d - scroll bars - entry bar - OLE lin
Security tab - removes the author - manager - company and last saved by fields from the properties dialog box when a project is saved. default is cleared
18. Decimal digits
Calculation tab - used to specify the number of days of slack MSP uses to determin critical tasks. if the number of slack days for a taks is less than or equal to the number specified here - the task is considered critical. Default is 0 days.
General Tab - used to turn on autofilter automatically when a new project is created - default is cleared
Security tab - ensures that any project server or workspace sites specified on the collaborate tab of the option dialog box will be added to the list
View Tab - it is used to specify the number of digits that should appear after the decimal - default is 2
19. Use internal IDs to match different-language or renamed ORganizer items between projects
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
20. Remove inforamtion form file properties on save
General Tab - used to set the number of recetnly opened project file that are listed at the bottom of the file. Default is 4 project file names
Security tab - removes the author - manager - company and last saved by fields from the properties dialog box when a project is saved. default is cleared
View Tab - used to specify the view that is diplayed at startup - Default is Gantt Chart
Calculation tab - specifies that MSP calculates actual costs automatically based upon resource rates - per-use resourcee costs and fixed task costs. If checked - a user cannot enter any additional acutal cost until the task is 100% complete. Default
21. Service options button
General Tab - used to change cutomer feedback and document management options
Calculation tab - used to recalculate based on the calculation mode and calculate options.
General Tab - used to display the user name entered when project was installed (the user name can be changed by typing a new name in this box.
Schedule tab - when checked - automatically links tasks again when a user cuts - moves - or inserts them. this applies only to contiguous finish to start task relationships. default/checked
22. Priority
Project Information - used to indicate how readily tasks in the current project are delayed whe resources are leveled across multiple projects. a number between 0 and 1000. the higher the number the higher the priority
Schedule tab - whether to show resource assignment units as decimal or percentage. Default - percentage
View Tab - used to specify which type of currency is being used - default is USD
General Tab - used to set project to open the project information dialog box whenever a new project is created
23. Undo levels
View Tab - used to specify whether MSP would accept and automatically update chanes to task dependencies between projects. default is checked. (only available when "Show Link between project dialog box on open" is cleared
Project Information - used to specify the base calendar to be used for the proejct calendar
Calendar Tab - used to specify the day of the week on twhich the scheduleing week begins
General Tab - used to set the number of change leverls a user can undo and redo - default is 20
24. Move end of completed parts after status date back to status date
Calculation tab - goes with "move end of completed parts after status date back to status date". The remaining portion of the task moves back to start at the status date otherwise it will complete as planned. by dfault is cleared
General Tab - used to turn on autofilter automatically when a new project is created - default is cleared
General Tab - used to change cutomer feedback and document management options
Calculation tab - this is for tasks that were scheduled to start after the status date but actually started early. the completed portion of the task moves back to the finish at the status date. Defaulted is cleared.
25. Hours per day
Calendar Tab - used to define the number of hours assigned whan a duration of one day is entered - default is 8h
Schedule tab - whether to show resource assignment units as decimal or percentage. Default - percentage
Schedule tab - for any new task - determines how project recalculates the three related fields - work - duration - and units when one is value is edited
View Tab - used to specify which interface elements should be displyed or hidden. global setting - default is all are selected. - elements are - status bar - windows in taskbar - bars and shapes in gantt vies in 3d - scroll bars - entry bar - OLE lin
26. Currency
Interface tab - the project elements are matched in the organizer by using each element's internal ID. By selecting - the physical element names are ignored as they may differ between projects
View Tab - used to display outline symbols next to each task name (A plus sign is displayed next to rolled up summary tasks and a minus sign next to summary tasks showing their subtasks) By default is checked.
View Tab - used to specify which type of currency is being used - default is USD
Calendar Tab - used to define the number of hours assigns to a task when a duration of one week is entered. default is 40
27. Default fixed costs accrual
Schedule tab - it displays a question mark for estimated duration. default - checked
Calculation tab - Used to specify how MSP sets the fixed cost accrual for new tasks. Accrued at the start of a task - prorated throughout - accrued at the end of a task - default is prorated
General Tab - used to display the user name entered when project was installed (the user name can be changed by typing a new name in this box.
View Tab - it is used to specify the number of digits that should appear after the decimal - default is 2
28. Status date
Interface tab - used to specify that the feedback triangle should appear in a corner of the duration field or the task name field if task's work - units - or duration is changed. Default is checked
Calculation tab - goes with "move start of remaining parts before status date forward to status date;" - remaing portion of the task moves forward to start at the status date. default is cleared
Project Information - used to specify the status date. The status date is used to perform earned value calculations - identify the complete through date in the Update project dialog box. and place progressline. if the status date is set to NA then cu
Used to specify whether the side pane displays the project default main page or a custom page developed by the organization
29. Week starts on
Schedule tab - causes MSP displays messages about schedule inconsistencies - Default is checked
Calculation tab - MSP will automatically update resource status (Actual - remaining work or cost) whenever you update task status default is checked
Calendar Tab - used to specify the day of the week on twhich the scheduleing week begins
General Tab - used to turn on autofilter automatically when a new project is created - default is cleared
30. Deletions in the name column
Interface tab - used to specify that the delete indicator should appear in the indicators field if the text in the task name or resource name field is deleted - default is checked
General Tab - used to set project to open the project information dialog box whenever a new project is created
Project Information - used to specify the base calendar to be used for the proejct calendar
View Tab - used to indent the names of subtasks in the task name - default is checked
31. Advice from planning wizard
Project Information - used to specify the status date. The status date is used to perform earned value calculations - identify the complete through date in the Update project dialog box. and place progressline. if the status date is set to NA then cu
General Tab - (this button specifically turns on all planning wizards) you can check individual messages. by default this box is cleared
Project Information - used to indicate how readily tasks in the current project are delayed whe resources are leveled across multiple projects. a number between 0 and 1000. the higher the number the higher the priority
Schedule tab - for any new task - determines how project recalculates the three related fields - work - duration - and units when one is value is edited
32. Use starting year for FY numbering
Calendar Tab - used to specify the end time - default setting is 5pm
Calendar Tab - used to label the fiscal year using the calend ear in which the fiscal eyar begins. by default is cleared
View Tab - used to display summary tasks. default is check
View Tab - used to specify the view that is diplayed at startup - Default is Gantt Chart
33. Autolink inserted or moved tasks
General Tab - automatically opens the last proejct file that was used. Default is cleared (if cleared project creates a new project whenever it starts)
Interface tab - the project elements are matched in the organizer by using each element's internal ID. By selecting - the physical element names are ignored as they may differ between projects
Schedule tab - when checked - automatically links tasks again when a user cuts - moves - or inserts them. this applies only to contiguous finish to start task relationships. default/checked
View Tab - used to specify whether the links between projects dialog box should appear when the current project opens and has links to other projects - default is checked
34. Show external predecessors
Schedule tab - it displays a question mark for estimated duration. default - checked
Schedule tab - specifies that MSP schedules tasks according to their constraint dates
View Tab - used to specify whether external predecessor tasks are show in the current project - default is checked
Project Information - used to open the project statistics dialog box. is used to review scheduled and actual start and finish date - durations - work and cost.
35. Updating task status updates resource status
Calendar Tab - used to specify the month that begins the fiscal year. MSP displays years based on fiscal year. Default is January
Project Information - used to specify the base calendar to be used for the proejct calendar
Calculation tab - MSP will automatically update resource status (Actual - remaining work or cost) whenever you update task status default is checked
Calendar Tab - used to specify the end time - default setting is 5pm
36. Inserted project are calculated like summary tasks
View Tab - used to specify whether external successor tasks are shown in the current project - default is checked
Calculation tab - used to specify a single critical path throughout the master project (Treating inserted projects as summary tasks in the master project) default is checked.
Calendar Tab - used to define the number of hours assigns to a task when a duration of one week is entered. default is 40
Schedule tab - whether to show resource assignment units as decimal or percentage. Default - percentage
37. Project Guide Content
Project Information - used to specify the base calendar to be used for the proejct calendar
Calculation tab - used to recalculate based on the calculation mode and calculate options.
General Tab - used to automatically add new resources to the resource pool and assigns them default values whenever a new resource name is entered. default is checked
Interface tab - used to specify wheter the side pane displys the project guide content that comes with Projec tor customer content that your organization has developed.
38. Show project summary task
View Tab - used to specify whether a project level summary task is to be displayed. It would have an ID of 0. Default is cleared
Project Information - used to specify the start date of the current project. - only available if the "Schedule from" drop down is "Project Start Date" MSP will calculate the finish date with ASAP constraint.
Calculation tab - used to recalculate based on the calculation mode and calculate options.
Interface tab - used to specify that the feedback triangle should appear in a corner of the duration field or the task name field if task's work - units - or duration is changed. Default is checked
39. Move start of remaining parts before status date forward to status date
Calculation tab - goes with "move start of remaining parts before status date forward to status date;" - remaing portion of the task moves forward to start at the status date. default is cleared
Calendar Tab - used to define the number of hours assigned whan a duration of one day is entered - default is 8h
Calculation tab - for tasks that were schedule to start before the status date but actually started late. remaining port of the task moves forward to start at the status date. by default is cleared
Project Information - used to specify the current date. by default this is the computer date and time
40. Work is entered in
Schedule tab - used to specify the default start date for new tasks as they are entered in the current project. Project Start Date/no constraint - Start on Current Date/a Start No Earlier Than constraint (using the current date)
Calculation tab - specifies that MSP should calculate and display a critical path for each independent network of tasks. default is cleared
Schedule tab - default for Unit of time (Minutes - hours - days - weeks - or month) in Work
View Tab - used to specify the format for displaying dates in all project files. Default format is Mon 1/23/02
41. And move start of remaining parts back to status date
Used to specify whether the side pane displays the project default main page or a custom page developed by the organization
Calculation tab - goes with "move end of completed parts after status date back to status date". The remaining portion of the task moves back to start at the status date otherwise it will complete as planned. by dfault is cleared
Interface tab - used to specify that the feedback triangle should appear in a corner of tasks name field if the task's start date or finish dates is changed. default is checked.
Interface tab - used to specify that the feedback triangle should appear in a corner of a field if additional resources are assigned to a task that already has assigned resources - default - checked.
42. Default end time
Interface tab - used to specify that the feedback triangle should appear in a corner of a field if additional resources are assigned to a task that already has assigned resources - default - checked.
Schedule tab - default for Unit of time (Minutes - hours - days - weeks - or month) in Duration
Calculation tab - specifies that MSP should calculate and display a critical path for each independent network of tasks. default is cleared
Calendar Tab - used to specify the end time - default setting is 5pm
43. Calculate now button
Calculation tab - used to specify the number of days of slack MSP uses to determin critical tasks. if the number of slack days for a taks is less than or equal to the number specified here - the task is considered critical. Default is 0 days.
Calculation tab - used to recalculate based on the calculation mode and calculate options.
Calculation tab - Used to specify how MSP sets the fixed cost accrual for new tasks. Accrued at the start of a task - prorated throughout - accrued at the end of a task - default is prorated
View Tab - used to specify whether MSP would accept and automatically update chanes to task dependencies between projects. default is checked. (only available when "Show Link between project dialog box on open" is cleared
44. Earned value
Schedule tab - causes MSP displays messages about schedule inconsistencies - Default is checked
Schedule tab - when checked - automatically links tasks again when a user cuts - moves - or inserts them. this applies only to contiguous finish to start task relationships. default/checked
Project Information - used to specify the finish date of the current project. only available if the "Schedule from" drop down is "Project Finish date" MSP will calculat the start date with ALAP constraints
Calculation tab - user can specify whether % complete or Physical % Complete should be used for earned value analysis in this project
45. Calculate multiple critcial paths
Calculation tab - specifies that MSP should calculate and display a critical path for each independent network of tasks. default is cleared
Schedule tab - whether to show resource assignment units as decimal or percentage. Default - percentage
Schedule tab - default for Unit of time (Minutes - hours - days - weeks - or month) in Work
Interface tab - used to specify wheter the side pane displys the project guide content that comes with Projec tor customer content that your organization has developed.
46. Tasks are critical if slack is less than or equal to [x] days
Calculation tab - used to specify the number of days of slack MSP uses to determin critical tasks. if the number of slack days for a taks is less than or equal to the number specified here - the task is considered critical. Default is 0 days.
General Tab - used to set the number of recetnly opened project file that are listed at the bottom of the file. Default is 4 project file names
Calendar Tab - used to define the number of hours assigned whan a duration of one day is entered - default is 8h
View Tab - it is used to specify the number of digits that should appear after the decimal - default is 2
47. Days per month
Calculation tab - Used to specify how MSP sets the fixed cost accrual for new tasks. Accrued at the start of a task - prorated throughout - accrued at the end of a task - default is prorated
Schedule tab - specifies that new tasks are scheduled such that the work on the task remains constant as a user adds or removes assignments. - if checked - adding or removing resource assignments on a fixed units taks has no effect on task duration.
Calendar Tab - used to define the number of datys assigned to a task when a duration of one month is entered. Default is 20
General Tab - used to set the number of recetnly opened project file that are listed at the bottom of the file. Default is 4 project file names
48. Show section
Schedule tab - default for Unit of time (Minutes - hours - days - weeks - or month) in Work
Calendar Tab - used to label the fiscal year using the calend ear in which the fiscal eyar begins. by default is cleared
View Tab - used to specify which interface elements should be displyed or hidden. global setting - default is all are selected. - elements are - status bar - windows in taskbar - bars and shapes in gantt vies in 3d - scroll bars - entry bar - OLE lin
Calculation tab - used to recalculate based on the calculation mode and calculate options.
49. Calculation mode
Security tab - removes the author - manager - company and last saved by fields from the properties dialog box when a project is saved. default is cleared
Calculation tab - specifies whether calculations are done automatically or manually.
Calendar Tab - used to specify the end time - default setting is 5pm
View Tab - used to specify the format for displaying dates in all project files. Default format is Mon 1/23/02
50. Default standard rate
General Tab - used to automatically add new resources to the resource pool and assigns them default values whenever a new resource name is entered. default is checked
Calculation tab - Used to specify how MSP sets the fixed cost accrual for new tasks. Accrued at the start of a task - prorated throughout - accrued at the end of a task - default is prorated
General Tab - used to specify the standard pay rate for new resources. can be overridden by typing a different rate in the resource form view - resource information dialog box or resource sheet. default is $0/h
View Tab - used to specify which currency symbol to be used - default is $