Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Priority
Project Information - used to indicate how readily tasks in the current project are delayed whe resources are leveled across multiple projects. a number between 0 and 1000. the higher the number the higher the priority
Schedule tab - default for Unit of time (Minutes - hours - days - weeks - or month) in Work
General Tab - (this button specifically turns on all planning wizards) you can check individual messages. by default this box is cleared
Calendar Tab - used to specify the start time - the default setting is 8am
2. Date format
View Tab - used to specify the format for displaying dates in all project files. Default format is Mon 1/23/02
General Tab - used to turn on autofilter automatically when a new project is created - default is cleared
View Tab - used to specify whether external predecessor tasks are show in the current project - default is checked
Used to specify whether the side pane displays the project default main page or a custom page developed by the organization
3. Legacy formats section
Schedule tab - when checked - automatically links tasks again when a user cuts - moves - or inserts them. this applies only to contiguous finish to start task relationships. default/checked
General Tab - used to specify the standard pay rate for new resources. can be overridden by typing a different rate in the resource form view - resource information dialog box or resource sheet. default is $0/h
Project Information - used to specify the finish date of the current project. only available if the "Schedule from" drop down is "Project Finish date" MSP will calculat the start date with ALAP constraints
Security tab - enables a user to define how MSP shoudl handle legacy and non-default file formats. MPW formats will not open in 2007
4. Default end time
General Tab - used to set project to open the project information dialog box whenever a new project is created
Calculation tab - used to specify a single critical path throughout the master project (Treating inserted projects as summary tasks in the master project) default is checked.
Calendar Tab - used to specify the end time - default setting is 5pm
Calendar Tab - used to specify the day of the week on twhich the scheduleing week begins
5. Edits to start and finishe dates
6. Hours per week
Calendar Tab - used to define the number of hours assigns to a task when a duration of one week is entered. default is 40
Calendar Tab - used to define the number of datys assigned to a task when a duration of one month is entered. Default is 20
Calculation tab - specifies that MSP should calculate and display a critical path for each independent network of tasks. default is cleared
Schedule tab - specifies that MSP schedules tasks according to their constraint dates
7. Currency
Calculation tab - Used to specify how MSP sets the fixed cost accrual for new tasks. Accrued at the start of a task - prorated throughout - accrued at the end of a task - default is prorated
Calculation tab - goes with "move end of completed parts after status date back to status date". The remaining portion of the task moves back to start at the status date otherwise it will complete as planned. by dfault is cleared
View Tab - it is used to specify the number of digits that should appear after the decimal - default is 2
View Tab - used to specify which type of currency is being used - default is USD
8. Prompt for project infor for new projects
Schedule tab - specifies that MSP schedules tasks according to their constraint dates
Calendar Tab - used to specify the start time - the default setting is 8am
Schedule tab - when checked - automatically links tasks again when a user cuts - moves - or inserts them. this applies only to contiguous finish to start task relationships. default/checked
General Tab - used to set project to open the project information dialog box whenever a new project is created
9. Show external successors
View Tab - used to specify whether external successor tasks are shown in the current project - default is checked
Interface tab - the project elements are matched in the organizer by using each element's internal ID. By selecting - the physical element names are ignored as they may differ between projects
Schedule tab - default for Unit of time (Minutes - hours - days - weeks - or month) in Work
Calculation tab - this is for tasks that were scheduled to start after the status date but actually started early. the completed portion of the task moves back to the finish at the status date. Defaulted is cleared.
10. Work is entered in
Schedule tab - default for Unit of time (Minutes - hours - days - weeks - or month) in Work
View Tab - used to display the outline number next to each task name - default is cleared
Calendar Tab - used to define the number of hours assigned whan a duration of one day is entered - default is 8h
View Tab - used to specify which currency symbol to be used - default is $
11. Use internal IDs to match different-language or renamed ORganizer items between projects
12. Default task type
View Tab - used to specify whether a project level summary task is to be displayed. It would have an ID of 0. Default is cleared
View Tab - used to specify which currency symbol to be used - default is $
Schedule tab - for any new task - determines how project recalculates the three related fields - work - duration - and units when one is value is edited
Schedule tab - allows rescheduling of remaining duration and work when a task slips or reports progress ahead of shedule. default - checked
13. Open last file on startup
General Tab - automatically opens the last proejct file that was used. Default is cleared (if cleared project creates a new project whenever it starts)
Project Information - used to specify the status date. The status date is used to perform earned value calculations - identify the complete through date in the Update project dialog box. and place progressline. if the status date is set to NA then cu
Schedule tab - for any new task - determines how project recalculates the three related fields - work - duration - and units when one is value is edited
Calendar Tab - used to define the number of hours assigns to a task when a duration of one week is entered. default is 40
14. Move start of remaining parts before status date forward to status date
View Tab - used to display outline symbols next to each task name (A plus sign is displayed next to rolled up summary tasks and a minus sign next to summary tasks showing their subtasks) By default is checked.
Calculation tab - for tasks that were schedule to start before the status date but actually started late. remaining port of the task moves forward to start at the status date. by default is cleared
Security tab - used to set the security level (very high - high - medium or low) default is HIgh - indicating that only signed macros from trusted sources are allowed to run
Interface tab - used to specify that the feedback triangle should appear in a corner of the duration field or the task name field if task's work - units - or duration is changed. Default is checked
15. Inserted project are calculated like summary tasks
Schedule tab - whether to show resource assignment units as decimal or percentage. Default - percentage
View Tab - used to specify the format for displaying dates in all project files. Default format is Mon 1/23/02
Calculation tab - used to specify a single critical path throughout the master project (Treating inserted projects as summary tasks in the master project) default is checked.
General Tab - used to change cutomer feedback and document management options
16. Show that tasks have estimated durations
Schedule tab - it displays a question mark for estimated duration. default - checked
View Tab - used to specify the format for displaying dates in all project files. Default format is Mon 1/23/02
Project Information - used to indicate how readily tasks in the current project are delayed whe resources are leveled across multiple projects. a number between 0 and 1000. the higher the number the higher the priority
Project Information - used to specify the status date. The status date is used to perform earned value calculations - identify the complete through date in the Update project dialog box. and place progressline. if the status date is set to NA then cu
17. Earned value
Interface tab - used to specify that the feedback triangle should appear in a corner of the duration field or the task name field if task's work - units - or duration is changed. Default is checked
Calculation tab - specifies that MSP should calculate and display a critical path for each independent network of tasks. default is cleared
Schedule tab - for any new task - determines how project recalculates the three related fields - work - duration - and units when one is value is edited
Calculation tab - user can specify whether % complete or Physical % Complete should be used for earned value analysis in this project
18. Status date
Project Information - used to specify the status date. The status date is used to perform earned value calculations - identify the complete through date in the Update project dialog box. and place progressline. if the status date is set to NA then cu
Security tab - ensures that any project server or workspace sites specified on the collaborate tab of the option dialog box will be added to the list
General Tab - used to set the number of change leverls a user can undo and redo - default is 20
View Tab - used to specify which interface elements should be displyed or hidden. global setting - default is all are selected. - elements are - status bar - windows in taskbar - bars and shapes in gantt vies in 3d - scroll bars - entry bar - OLE lin
19. Indent name
View Tab - used to indent the names of subtasks in the task name - default is checked
Schedule tab - allows rescheduling of remaining duration and work when a task slips or reports progress ahead of shedule. default - checked
Project Information - used to specify the status date. The status date is used to perform earned value calculations - identify the complete through date in the Update project dialog box. and place progressline. if the status date is set to NA then cu
Calculation tab - Used to specify how MSP sets the fixed cost accrual for new tasks. Accrued at the start of a task - prorated throughout - accrued at the end of a task - default is prorated
20. Edits to work - units - or duration
21. Calculate now button
Schedule tab - for any new task - determines how project recalculates the three related fields - work - duration - and units when one is value is edited
View Tab - used to indent the names of subtasks in the task name - default is checked
Calculation tab - used to recalculate based on the calculation mode and calculate options.
Calendar Tab - used to specify the month that begins the fiscal year. MSP displays years based on fiscal year. Default is January
22. Tasks are critical if slack is less than or equal to [x] days
Schedule tab - it displays a question mark for estimated duration. default - checked
Calculation tab - used to recalculate based on the calculation mode and calculate options.
Calculation tab - used to specify the number of days of slack MSP uses to determin critical tasks. if the number of slack days for a taks is less than or equal to the number specified here - the task is considered critical. Default is 0 days.
Calendar Tab - used to specify the end time - default setting is 5pm
23. Show links between projects dialog box on open
Calendar Tab - used to specify the end time - default setting is 5pm
View Tab - used to specify whether the links between projects dialog box should appear when the current project opens and has links to other projects - default is checked
Schedule tab - used to specify the default start date for new tasks as they are entered in the current project. Project Start Date/no constraint - Start on Current Date/a Start No Earlier Than constraint (using the current date)
View Tab - used to specify whether external predecessor tasks are show in the current project - default is checked
24. Symbol
Calculation tab - this is for tasks that were scheduled to start after the status date but actually started early. the completed portion of the task moves back to the finish at the status date. Defaulted is cleared.
View Tab - used to specify which currency symbol to be used - default is $
Calendar Tab - used to specify the day of the week on twhich the scheduleing week begins
Project Information - used to specify the status date. The status date is used to perform earned value calculations - identify the complete through date in the Update project dialog box. and place progressline. if the status date is set to NA then cu
25. Show assignments units as a
Schedule tab - whether to show resource assignment units as decimal or percentage. Default - percentage
Project Information - used to open the project statistics dialog box. is used to review scheduled and actual start and finish date - durations - work and cost.
Schedule tab - used to specify the default start date for new tasks as they are entered in the current project. Project Start Date/no constraint - Start on Current Date/a Start No Earlier Than constraint (using the current date)
Schedule tab - specifies that MSP schedules tasks according to their constraint dates
26. Automatically add new resources and task
Schedule tab - it displays a question mark for estimated duration. default - checked
General Tab - used to automatically add new resources to the resource pool and assigns them default values whenever a new resource name is entered. default is checked
General Tab - used to turn on autofilter automatically when a new project is created - default is cleared
Project Information - used to specify the current date. by default this is the computer date and time
27. Resource Assignments
Schedule tab - specifies that all new tasks have estimated durations.
Interface tab - used to specify that the feedback triangle should appear in a corner of a field if additional resources are assigned to a task that already has assigned resources - default - checked.
Schedule tab - specifies that MSP schedules tasks according to their constraint dates
General Tab - used to turn on autofilter automatically when a new project is created - default is cleared
28. And move start of remaining parts back to status date
Project Information - used to specify the base calendar to be used for the proejct calendar
Calculation tab - for tasks that were schedule to start before the status date but actually started late. remaining port of the task moves forward to start at the status date. by default is cleared
Calculation tab - goes with "move end of completed parts after status date back to status date". The remaining portion of the task moves back to start at the status date otherwise it will complete as planned. by dfault is cleared
Calculation tab - used to specify the number of days of slack MSP uses to determin critical tasks. if the number of slack days for a taks is less than or equal to the number specified here - the task is considered critical. Default is 0 days.
29. Finish date
Schedule tab - used to specify the default start date for new tasks as they are entered in the current project. Project Start Date/no constraint - Start on Current Date/a Start No Earlier Than constraint (using the current date)
Security tab - removes the author - manager - company and last saved by fields from the properties dialog box when a project is saved. default is cleared
General Tab - used to specify the standard pay rate for new resources. can be overridden by typing a different rate in the resource form view - resource information dialog box or resource sheet. default is $0/h
Project Information - used to specify the finish date of the current project. only available if the "Schedule from" drop down is "Project Finish date" MSP will calculat the start date with ALAP constraints
30. Set autofilter on for new projects
General Tab - used to turn on autofilter automatically when a new project is created - default is cleared
Schedule tab - default for Unit of time (Minutes - hours - days - weeks - or month) in Work
View Tab - used to specify the type of calendar- default is Gregorian 12 month calend start on January 1
General Tab - used to set the number of change leverls a user can undo and redo - default is 20
31. Schedule from
Calculation tab - for tasks that were schedule to start before the status date but actually started late. remaining port of the task moves forward to start at the status date. by default is cleared
General Tab - used to set the number of change leverls a user can undo and redo - default is 20
Security tab - removes the author - manager - company and last saved by fields from the properties dialog box when a project is saved. default is cleared
Project Information - used to specify whether to project is scheduled from a project start date or a project finish date. default is start date
32. Duration is entered in
Calculation tab - MSP will automatically update resource status (Actual - remaining work or cost) whenever you update task status default is checked
Calendar Tab - used to specify the start time - the default setting is 8am
Schedule tab - default for Unit of time (Minutes - hours - days - weeks - or month) in Duration
General Tab - automatically opens the last proejct file that was used. Default is cleared (if cleared project creates a new project whenever it starts)
33. New tasks have estimated durations
Schedule tab - default for Unit of time (Minutes - hours - days - weeks - or month) in Work
View Tab - it is used to specify the number of digits that should appear after the decimal - default is 2
Calendar Tab - used to specify the end time - default setting is 5pm
Schedule tab - specifies that all new tasks have estimated durations.
34. Calendar
Calendar Tab - used to label the fiscal year using the calend ear in which the fiscal eyar begins. by default is cleared
Schedule tab - specifies that new tasks are scheduled such that the work on the task remains constant as a user adds or removes assignments. - if checked - adding or removing resource assignments on a fixed units taks has no effect on task duration.
View Tab - used to specify the view that is diplayed at startup - Default is Gantt Chart
Project Information - used to specify the base calendar to be used for the proejct calendar
35. Require project server and workspace sites to be added to the IE Trusted sites list
Project Information - used to specify the current date. by default this is the computer date and time
Security tab - ensures that any project server or workspace sites specified on the collaborate tab of the option dialog box will be added to the list
General Tab - used to set project to open the project information dialog box whenever a new project is created
General Tab - (this button specifically turns on all planning wizards) you can check individual messages. by default this box is cleared
36. Autolink inserted or moved tasks
Schedule tab - when checked - automatically links tasks again when a user cuts - moves - or inserts them. this applies only to contiguous finish to start task relationships. default/checked
Schedule tab - specifies that MSP schedules tasks according to their constraint dates
View Tab - used to display the outline number next to each task name - default is cleared
Calendar Tab - used to label the fiscal year using the calend ear in which the fiscal eyar begins. by default is cleared
37. Show summary tasks
Schedule tab - specifies that all new tasks have estimated durations.
Calculation tab - for tasks that were schedule to start before the status date but actually started late. remaining port of the task moves forward to start at the status date. by default is cleared
View Tab - used to display summary tasks. default is check
View Tab - used to specify whether the links between projects dialog box should appear when the current project opens and has links to other projects - default is checked
38. Placement
View Tab - used to specify the position of the currency symbol. default is just before amount
General Tab - used to specify the standard pay rate for new resources. can be overridden by typing a different rate in the resource form view - resource information dialog box or resource sheet. default is $0/h
View Tab - used to specify which type of currency is being used - default is USD
Interface tab - used to specify that the feedback triangle should appear in a corner of tasks name field if the task's start date or finish dates is changed. default is checked.
39. Default overtime rate
Calculation tab - used to recalculate based on the calculation mode and calculate options.
General Tab - used to specify the overtime pay rate for new resources. can be overridden by typing a different rate in the resource form view - resource information dialog box or resource sheet. default is $0/h
Calculation tab - goes with "move start of remaining parts before status date forward to status date;" - remaing portion of the task moves forward to start at the status date. default is cleared
General Tab - (this button specifically turns on all planning wizards) you can check individual messages. by default this box is cleared
40. Service options button
Project Information - used to specify the status date. The status date is used to perform earned value calculations - identify the complete through date in the Update project dialog box. and place progressline. if the status date is set to NA then cu
View Tab - used to indent the names of subtasks in the task name - default is checked
General Tab - used to change cutomer feedback and document management options
Schedule tab - used to specify the default start date for new tasks as they are entered in the current project. Project Start Date/no constraint - Start on Current Date/a Start No Earlier Than constraint (using the current date)
41. New tasks are effort driven
Interface tab - used to specify that the feedback triangle should appear in a corner of the duration field or the task name field if task's work - units - or duration is changed. Default is checked
Calculation tab - user can specify whether % complete or Physical % Complete should be used for earned value analysis in this project
Schedule tab - specifies that new tasks are scheduled such that the work on the task remains constant as a user adds or removes assignments. - if checked - adding or removing resource assignments on a fixed units taks has no effect on task duration.
Calendar Tab - used to specify the start time - the default setting is 8am
42. Automatically accept new external data
View Tab - used to specify whether MSP would accept and automatically update chanes to task dependencies between projects. default is checked. (only available when "Show Link between project dialog box on open" is cleared
View Tab - used to specify whether external successor tasks are shown in the current project - default is checked
Schedule tab - specifies that new tasks are scheduled such that the work on the task remains constant as a user adds or removes assignments. - if checked - adding or removing resource assignments on a fixed units taks has no effect on task duration.
Calendar Tab - used to define the number of hours assigns to a task when a duration of one week is entered. default is 40
43. Advice from planning wizard
Calculation tab - user can specify whether % complete or Physical % Complete should be used for earned value analysis in this project
Schedule tab - default for Unit of time (Minutes - hours - days - weeks - or month) in Duration
Interface tab - used to specify that the feedback triangle should appear in a corner of the duration field or the task name field if task's work - units - or duration is changed. Default is checked
General Tab - (this button specifically turns on all planning wizards) you can check individual messages. by default this box is cleared
44. Calculation mode
Project Information - used to indicate how readily tasks in the current project are delayed whe resources are leveled across multiple projects. a number between 0 and 1000. the higher the number the higher the priority
Calculation tab - specifies whether calculations are done automatically or manually.
Interface tab - used to specify that the feedback triangle should appear in a corner of tasks name field if the task's start date or finish dates is changed. default is checked.
General Tab - (this button specifically turns on all planning wizards) you can check individual messages. by default this box is cleared
45. Calculate multiple critcial paths
Calculation tab - specifies whether calculations are done automatically or manually.
Calculation tab - specifies whether MSP recalculates the acrtive project or all open projects.
Calculation tab - used to specify a single critical path throughout the master project (Treating inserted projects as summary tasks in the master project) default is checked.
Calculation tab - specifies that MSP should calculate and display a critical path for each independent network of tasks. default is cleared
46. Default fixed costs accrual
Schedule tab - when checked - automatically links tasks again when a user cuts - moves - or inserts them. this applies only to contiguous finish to start task relationships. default/checked
Project Information - used to open the project statistics dialog box. is used to review scheduled and actual start and finish date - durations - work and cost.
Interface tab - used to specify that the delete indicator should appear in the indicators field if the text in the task name or resource name field is deleted - default is checked
Calculation tab - Used to specify how MSP sets the fixed cost accrual for new tasks. Accrued at the start of a task - prorated throughout - accrued at the end of a task - default is prorated
47. Recently used file list
View Tab - used to specify whether external predecessor tasks are show in the current project - default is checked
General Tab - used to change cutomer feedback and document management options
Interface tab - the project elements are matched in the organizer by using each element's internal ID. By selecting - the physical element names are ignored as they may differ between projects
General Tab - used to set the number of recetnly opened project file that are listed at the bottom of the file. Default is 4 project file names
48. display project guide
Security tab - ensures that any project server or workspace sites specified on the collaborate tab of the option dialog box will be added to the list
Interface tab - used to diplsy the side pane containing the Project Guide. this is a global setting and applies to all project - default is checked
Schedule tab - used to specify the default start date for new tasks as they are entered in the current project. Project Start Date/no constraint - Start on Current Date/a Start No Earlier Than constraint (using the current date)
Calculation tab - this is for tasks that were scheduled to start after the status date but actually started early. the completed portion of the task moves back to the finish at the status date. Defaulted is cleared.
49. Split in progress tasks
Schedule tab - allows rescheduling of remaining duration and work when a task slips or reports progress ahead of shedule. default - checked
View Tab - used to specify which type of currency is being used - default is USD
Calculation tab - goes with "move start of remaining parts before status date forward to status date;" - remaing portion of the task moves forward to start at the status date. default is cleared
View Tab - used to specify the view that is diplayed at startup - Default is Gantt Chart
50. New tasks
General Tab - used to set the number of recetnly opened project file that are listed at the bottom of the file. Default is 4 project file names
Schedule tab - specifies that MSP schedules tasks according to their constraint dates
View Tab - used to specify the type of calendar- default is Gregorian 12 month calend start on January 1
Schedule tab - used to specify the default start date for new tasks as they are entered in the current project. Project Start Date/no constraint - Start on Current Date/a Start No Earlier Than constraint (using the current date)