/* */
SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Prince2: Project Management In A Controlled Environment2
Start Test
Study First
Subjects
:
certifications
,
prince2
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The formal confirmation that a product is complete and meets its requirements (less any concessions) as defined by its Product Description.
Dependencies (plan)
Exploit (risk response)
Change Budget
Approval
2. A team-level - time-driven review of progress.
Assumption
Checkpoint
Cost Tolerance
Dis-benefit
3. A type of management product that defines aspects of the project and - once approved - is subject to change control.
Authorization
Closure Notification
Baseline Management Product
Configuration Item
4. What an organization needs to do to adopt Prince2 as its corporate project management method. See also - in contrast - 'tailoring' - which defines what a project needs to do to apply the method to a specific project environment.
Executive
Accept (Risk Response)
Embedding (Prince2)
Benefits Tolerance
5. A progress report of the information gathered at a checkpoint - which is given by a team to the Project Manager and which provides reporting data as defined in the Work Package
Customer
Avoid (risk response)
Corrective Action
Checkpoint Report
6. A risk response to a threat where the threat either can no longer have an impact or can no longer happen
Configuration Management System
Corrective Action
Avoid (risk response)
Activity
7. The right to allocate resources and make decisions (applies to project - stage - and team levels)
Authority
Exception
Exploit (risk response)
Activity
8. This is a review by the Project Board to approve (or reject) an Exception Plan.
Corrective Action
Accept (Risk Response)
Dependencies (plan)
Exception Assessment
9. A risk response to a threat where a conscious and deliberate decision is taken to retain the threat - having discerned that it is more economical to do so than to attempt a risk response action. The threat should continue to be monitored to ensure t
Baseline
Benefits Review Plan
End Stage Report
Accept (Risk Response)
10. A report given by the Project Manager to the Project Board at the end of each management stage of the project. This provides information about the project performance during the stage and the project status at stage end.
Benefits Tolerance
Assumption
End Stage Report
Assurance
11. Used to record problems/concerns that can be handled by the Project Manager informally.
Embedding (Prince2)
Fallback (risk response)
Daily Log
Exception Plan
12. The money allocated to the Change Authority available to be spent on authorized requests for change.
Baseline Management Product
Approver
Constraints
Change Budget
13. A situation where it can be forecast that there will be a deviation beyond the tolerance levels agreed between Project Manager and Project Board (or between Project Board and corporate or program management)
Contingency
Benefits Tolerance
Agile Methods
Exception
14. All the systematic necessary to provide confidence that the target (system - process - organization - program - project - outcome - benefit - capability - product output - deliverable) is appropriate. Appropriateness might be defined subject
Assurance
Exception Report
Communication Management Strategy
Corporate or Program Standards
15. A recommendation prepared by the Project Manager for the Project Board to send as a project closure notification when the board is satisfied that the project can be closed.
End Stage Assessment
Checkpoint
Closure Recommendation
Exception Report
16. A plan that defines how and when a measurement of the achievement of the project's benefits can be made. If the project is being managed within a program - this information may be created and maintained at the program level.
Benefits Review Plan
Assurance
Event-Driven Control
Communication Management Strategy
17. Advice from the Project Board to inform all stakeholders and the host sites that the project resources can be disbanded and support services - such as space - equipment and access - demobilized. It should indicate a closure date for costs t the pr
Closure Notification
Center of Excellence
Assurance
Executive
18. The permissible deviation in the expected benefit that is allowed before the deviation needs to be escalated to the next level of management. Benefits tolerance is documented in the Business Case . See also 'tolerance'
Configuration Item Record
Closure Recommendation
Benefits Tolerance
Event-Driven Control
19. Technical and administrative activities concerned with the creation - maintenance and controlled change of configuration throughout the life of the product.
Change Control
End Stage Report
Configuration Management
Authority
20. The person or group (e.g. a Project Board) who is identified and authorized to approve a (management or specialist) product as being complete and fit for purpose.
Approver
Authority
Cost Tolerance
Activity
21. A description of how and by whom the project's products will be controlled and protected.
Exception
Benefit
Corporate or Program Standards
Configuration Management Strategy
22. A person or group to which the Project Board may delegate responsibility for the consideration of requests for change or off-specifications. The Change Authority may be given a change budget and can approve changes within the budget.
Change Authority
Dis-benefit
Configuration Management System
Closure Notification
23. An off-specification that is accepted by the Project Board without corrective action.
Concession
Constraints
Approval
Configuration Item Record
24. A description of the means and frequency of communication between the project and the project stakeholders.
Center of Excellence
Baseline Management Product
Communication Management Strategy
Benefits Review Plan
25. An agile delivery framework developed and owned by the DSDM consortium. Atern uses a time-boxed and iterative approach to product development and is compatible with Prince2.
Concession
DSDM Atern
Contingency
Assumption
26. A description of the exception situation - its impact - options - recommendations and impact of the recommendation. This report is prepared by the Project Manager for the Project Board.
Dependencies (plan)
End Stage Assessment
Embedding (Prince2)
Exception Report
27. A prioritized list of criteria that the project product must meet before the customer will accept it - i.e. measurable definitions of the attributes required for the set of products to be acceptable to key stakeholders
Constraints
Acceptance
Benefit
Acceptance Criteria
28. The formal act of acknowledging that the project has met agreed acceptance criteria and thereby met the requirements of its stakeholders
Acceptance
Exception Plan
Corrective Action
Communication Management Strategy
29. The person or group who commissioned the work and will benefit from the end results.
Exploit (risk response)
Agile Methods
End Stage Report
Customer
30. A risk response to a threat by putting in place a fallback plan for the actions that will be taken to reduce the impact of the threat should the risk occur.
Fallback (risk response)
Concession
Change Budget
Cost Tolerance
31. Something that is held in reserve typically to handle time and cost variances - or risks. Prince2 does not advocate the use of contingency because estimating variances are managed by setting tolerances - and risks are managed through appropriate ri
End Project Report
Contingency
Corrective Action
Customer's Quality Expectations
32. A statement that is taken as being true for the purposes of planning - but which could change later. An assumption is made where some facts are not yet known or decided - and is usually reserved for matters of such significance that - if they chan
Embedding (Prince2)
Approver
Exception Assessment
Assumption
33. The permissible deviation in a plan's cost that is allowed before the deviation needs to be escalated to the next level of management. Cost tolerance is documented in the respective plan. See also 'tolerance'.
Closure Notification
Baseline Management Product
Dis-benefit
Cost Tolerance
34. The measurable improvement resulting from an outcome perceived as an advantage by one or more stakeholders.
Benefit
Customer
Accept (Risk Response)
Closure Notification
35. The single individual with overall responsibility that the project meets its objectives and delivers the projected benefits. This individual should ensure that the project maintains its business focus - that it has clear authority - and that the wo
Accept (Risk Response)
Benefits Tolerance
Executive
Acceptance
36. The restrictions or limitations that the project is bound by.
End Stage Report
DSDM Atern
Constraints
Cost Tolerance
37. The procedure that ensures that all changes that may affect the project's agreed objectives are identified - assessed and either approved - rejected or deferred.
Approver
Constraints
Change Control
Business Case
38. A record that describes the status - version and variant of a configuration item - and any details of important relationships between them.
Constraints
Approver
Configuration Item Record
Corporate or Program Standards
39. The justification for an organizational activity (project) - which typically contains costs - benefits - risks and time scales - and against which continuing viability is tested.
Configuration Item Record
Assurance
Business Case
Activity
40. An entity that is subject to configuration management. The entity may be a component of a product - a product - or a set of products in a release.
Configuration Item
Communication Management Strategy
Event-Driven Control
End Stage Report
41. A report given by the Project Manger to the Project Board - that confirms the handover of all products and provides and updated Business Case and an assessment of how well the project has done against the original Project Initiation Documentation.
Constraints
Exception Assessment
Center of Excellence
End Project Report
42. An outcome that is perceived as negative by one or more stakeholders. It is an actual consequence of an activity whereas - by definition - a risk has some uncertainty about whether it will materialize.
Contingency
Dis-benefit
End Project Report
Baseline Management Product
43. A risk response to an opportunity where proactive actions are taken to enhance both the probability of the event occurring and the impact of the event should it occur.
Baseline
End Stage Assessment
Enhance (risk response)
Change Budget
44. Reference levels against which an entity is monitored and controlled.
End Stage Report
Baseline
Daily Log
Event-Driven Control
45. A tangible or intangible object produced as a result of the project that is intended to be delivered to a customer (either internal or external). A deliverable could be a report - a document - a server upgrade or any other building block of an over
Deliverable
Exception
Cost Tolerance
Benefits Tolerance
46. The point at which an authority is granted.
Configuration Item Record
Closure Recommendation
Approval
Authorization
47. The relationship between products or activities. For example - the development of Product C cannot start until Products A and B have been completed. Dependencies can be internal or external. Internal dependencies are those under the control of the P
Change Authority
Corporate or Program Standards
Constraints
Dependencies (plan)
48. A set of actions to resolve a threat to a plan's tolerances or a defect in a product.
Enhance (risk response)
Event-Driven Control
Corrective Action
Exception Plan
49. A process - function or task that occurs over time - has recognizable results and is managed. It is usually defined as part of a process or plan.
Corrective Action
Concession
Activity
Configuration Management Strategy
50. The review by the Project Board and Project Manager of the End Stage Report to decide whether to approve the Stage Plan. According to the size and criticality of the project - the review may be formal or informal. The authority to process should be
Baseline
Authority
End Stage Assessment
Closure Notification
//
//