Prince2: Project Management In A Controlled Environment2
Start Test
Study First
Subjects
:
certifications
,
prince2
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The right to allocate resources and make decisions (applies to project - stage - and team levels)
Cost Tolerance
Avoid (risk response)
Deliverable
Authority
2. A description of the exception situation - its impact - options - recommendations and impact of the recommendation. This report is prepared by the Project Manager for the Project Board.
End Project Report
Enhance (risk response)
Assurance
Exception Report
3. The set of processes - tools and databases that are used to manage configuration data. Typically - a project will use the configuration management system of either the customer or supplier organization.
Baseline Management Product
Corrective Action
Configuration Management System
Customer
4. A risk response to an opportunity where proactive actions are taken to enhance both the probability of the event occurring and the impact of the event should it occur.
Enhance (risk response)
Benefits Tolerance
Activity
Checkpoint
5. A person or group to which the Project Board may delegate responsibility for the consideration of requests for change or off-specifications. The Change Authority may be given a change budget and can approve changes within the budget.
Daily Log
Assurance
Fallback (risk response)
Change Authority
6. The permissible deviation in the expected benefit that is allowed before the deviation needs to be escalated to the next level of management. Benefits tolerance is documented in the Business Case . See also 'tolerance'
Cost Tolerance
Configuration Management Strategy
Exploit (risk response)
Benefits Tolerance
7. The person or group (e.g. a Project Board) who is identified and authorized to approve a (management or specialist) product as being complete and fit for purpose.
Agile Methods
Approver
Assumption
Exception
8. The restrictions or limitations that the project is bound by.
Checkpoint
Event-Driven Control
Dependencies (plan)
Constraints
9. A risk response to a threat where a conscious and deliberate decision is taken to retain the threat - having discerned that it is more economical to do so than to attempt a risk response action. The threat should continue to be monitored to ensure t
Contingency
Communication Management Strategy
Customer
Accept (Risk Response)
10. This is a review by the Project Board to approve (or reject) an Exception Plan.
Approval
End Project Report
End Stage Assessment
Exception Assessment
11. Advice from the Project Board to inform all stakeholders and the host sites that the project resources can be disbanded and support services - such as space - equipment and access - demobilized. It should indicate a closure date for costs t the pr
Change Control
Closure Notification
Baseline Management Product
Communication Management Strategy
12. A corporate coordinating function for portfolios - programs and projects providing standards - consistency of methods and processes - knowledge management - assurance and training.
Acceptance Criteria
Corporate or Program Standards
Exception Report
Center of Excellence
13. All the systematic necessary to provide confidence that the target (system - process - organization - program - project - outcome - benefit - capability - product output - deliverable) is appropriate. Appropriateness might be defined subject
Benefit
Customer's Quality Expectations
Approval
Assurance
14. A progress report of the information gathered at a checkpoint - which is given by a team to the Project Manager and which provides reporting data as defined in the Work Package
Approver
Exception
Acceptance
Checkpoint Report
15. The point at which an authority is granted.
Authorization
Cost Tolerance
Assumption
End Stage Assessment
16. A risk response to an opportunity by seizing the opportunity to ensure that it will happen and that the impact will be realized.
Authority
Exploit (risk response)
Authorization
Closure Recommendation
17. The measurable improvement resulting from an outcome perceived as an advantage by one or more stakeholders.
Acceptance Criteria
Business Case
Configuration Item
Benefit
18. Used to record problems/concerns that can be handled by the Project Manager informally.
Configuration Management System
Accept (Risk Response)
Checkpoint
Daily Log
19. What an organization needs to do to adopt Prince2 as its corporate project management method. See also - in contrast - 'tailoring' - which defines what a project needs to do to apply the method to a specific project environment.
Executive
Embedding (Prince2)
Change Control
Baseline
20. A prioritized list of criteria that the project product must meet before the customer will accept it - i.e. measurable definitions of the attributes required for the set of products to be acceptable to key stakeholders
Benefits Tolerance
Acceptance Criteria
Exception Plan
Dis-benefit
21. The formal confirmation that a product is complete and meets its requirements (less any concessions) as defined by its Product Description.
Enhance (risk response)
Checkpoint
Customer
Approval
22. A risk response to a threat by putting in place a fallback plan for the actions that will be taken to reduce the impact of the threat should the risk occur.
Business Case
Fallback (risk response)
End Stage Report
Baseline
23. A risk response to a threat where the threat either can no longer have an impact or can no longer happen
Avoid (risk response)
Business Case
Deliverable
Constraints
24. An agile delivery framework developed and owned by the DSDM consortium. Atern uses a time-boxed and iterative approach to product development and is compatible with Prince2.
Corrective Action
Deliverable
DSDM Atern
Cost Tolerance
25. A description of the means and frequency of communication between the project and the project stakeholders.
Assumption
Event-Driven Control
End Stage Report
Communication Management Strategy
26. The procedure that ensures that all changes that may affect the project's agreed objectives are identified - assessed and either approved - rejected or deferred.
Exception Assessment
Change Control
Event-Driven Control
Accept (Risk Response)
27. The relationship between products or activities. For example - the development of Product C cannot start until Products A and B have been completed. Dependencies can be internal or external. Internal dependencies are those under the control of the P
Customer's Quality Expectations
Enhance (risk response)
Avoid (risk response)
Dependencies (plan)
28. The person or group who commissioned the work and will benefit from the end results.
Assumption
Customer
Acceptance
Checkpoint Report
29. A recommendation prepared by the Project Manager for the Project Board to send as a project closure notification when the board is satisfied that the project can be closed.
Approver
Activity
Closure Recommendation
Customer
30. The permissible deviation in a plan's cost that is allowed before the deviation needs to be escalated to the next level of management. Cost tolerance is documented in the respective plan. See also 'tolerance'.
Cost Tolerance
Dependencies (plan)
Deliverable
Communication Management Strategy
31. A tangible or intangible object produced as a result of the project that is intended to be delivered to a customer (either internal or external). A deliverable could be a report - a document - a server upgrade or any other building block of an over
Benefits Tolerance
Approval
Deliverable
Closure Notification
32. These are over-arching standards that the project must adhere to. They will influence the four project strategies ( Communication Management Strategy - Configuration Management Strategy - Quality Management Strategy and the Risk Management Strategy
Accept (Risk Response)
Configuration Management
Corporate or Program Standards
Deliverable
33. An outcome that is perceived as negative by one or more stakeholders. It is an actual consequence of an activity whereas - by definition - a risk has some uncertainty about whether it will materialize.
Event-Driven Control
Dis-benefit
Enhance (risk response)
Exception
34. A report given by the Project Manger to the Project Board - that confirms the handover of all products and provides and updated Business Case and an assessment of how well the project has done against the original Project Initiation Documentation.
Change Authority
Accept (Risk Response)
Customer
End Project Report
35. This is plan that often follows an Exception Report. For a Stage Plan exception - it covers the period from the present to the end of the current stage - if the exception were at project level - the Project Plan would be replaced.
Center of Excellence
Assurance
Exception Plan
Assumption
36. Technical and administrative activities concerned with the creation - maintenance and controlled change of configuration throughout the life of the product.
Corrective Action
Customer
Change Budget
Configuration Management
37. A set of actions to resolve a threat to a plan's tolerances or a defect in a product.
Embedding (Prince2)
Corrective Action
Configuration Item Record
Daily Log
38. The formal act of acknowledging that the project has met agreed acceptance criteria and thereby met the requirements of its stakeholders
Baseline Management Product
Corrective Action
Customer
Acceptance
39. Something that is held in reserve typically to handle time and cost variances - or risks. Prince2 does not advocate the use of contingency because estimating variances are managed by setting tolerances - and risks are managed through appropriate ri
Contingency
Customer
Closure Notification
Assurance
40. A plan that defines how and when a measurement of the achievement of the project's benefits can be made. If the project is being managed within a program - this information may be created and maintained at the program level.
Corporate or Program Standards
Event-Driven Control
Dependencies (plan)
Benefits Review Plan
41. A report given by the Project Manager to the Project Board at the end of each management stage of the project. This provides information about the project performance during the stage and the project status at stage end.
Acceptance
Corporate or Program Standards
Avoid (risk response)
End Stage Report
42. An off-specification that is accepted by the Project Board without corrective action.
End Stage Report
Avoid (risk response)
Customer's Quality Expectations
Concession
43. A control that takes place when a specific event occurs. This could be - for example - the end of a stage - the completion of the Project Initiation Documentation - or the creation of an Exception Report - it could also include organizational ev
Event-Driven Control
Closure Recommendation
Contingency
Benefits Review Plan
44. A type of management product that defines aspects of the project and - once approved - is subject to change control.
Closure Recommendation
Contingency
Checkpoint Report
Baseline Management Product
45. The review by the Project Board and Project Manager of the End Stage Report to decide whether to approve the Stage Plan. According to the size and criticality of the project - the review may be formal or informal. The authority to process should be
End Stage Assessment
Assumption
Agile Methods
Assurance
46. A record that describes the status - version and variant of a configuration item - and any details of important relationships between them.
Corrective Action
Business Case
Center of Excellence
Configuration Item Record
47. A team-level - time-driven review of progress.
Configuration Management Strategy
Checkpoint
Configuration Item Record
Assurance
48. The single individual with overall responsibility that the project meets its objectives and delivers the projected benefits. This individual should ensure that the project maintains its business focus - that it has clear authority - and that the wo
Executive
Assumption
Closure Recommendation
Event-Driven Control
49. A statement about the quality expected from the project product - captured in the Project Product Description.
50. The justification for an organizational activity (project) - which typically contains costs - benefits - risks and time scales - and against which continuing viability is tested.
Business Case
Enhance (risk response)
Customer's Quality Expectations
Corrective Action