Test your basic knowledge |

Prince2: Project Management In A Controlled Environment2

Instructions:
  • Answer 50 questions in 15 minutes.
  • If you are not ready to take this test, you can study here.
  • Match each statement with the correct term.
  • Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.

This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A person or group to which the Project Board may delegate responsibility for the consideration of requests for change or off-specifications. The Change Authority may be given a change budget and can approve changes within the budget.






2. A record that describes the status - version and variant of a configuration item - and any details of important relationships between them.






3. Something that is held in reserve typically to handle time and cost variances - or risks. Prince2 does not advocate the use of contingency because estimating variances are managed by setting tolerances - and risks are managed through appropriate ri






4. A set of actions to resolve a threat to a plan's tolerances or a defect in a product.






5. A statement that is taken as being true for the purposes of planning - but which could change later. An assumption is made where some facts are not yet known or decided - and is usually reserved for matters of such significance that - if they chan






6. A description of the exception situation - its impact - options - recommendations and impact of the recommendation. This report is prepared by the Project Manager for the Project Board.






7. Used to record problems/concerns that can be handled by the Project Manager informally.






8. The permissible deviation in the expected benefit that is allowed before the deviation needs to be escalated to the next level of management. Benefits tolerance is documented in the Business Case . See also 'tolerance'






9. The relationship between products or activities. For example - the development of Product C cannot start until Products A and B have been completed. Dependencies can be internal or external. Internal dependencies are those under the control of the P






10. What an organization needs to do to adopt Prince2 as its corporate project management method. See also - in contrast - 'tailoring' - which defines what a project needs to do to apply the method to a specific project environment.






11. This is plan that often follows an Exception Report. For a Stage Plan exception - it covers the period from the present to the end of the current stage - if the exception were at project level - the Project Plan would be replaced.






12. An agile delivery framework developed and owned by the DSDM consortium. Atern uses a time-boxed and iterative approach to product development and is compatible with Prince2.






13. Reference levels against which an entity is monitored and controlled.






14. A situation where it can be forecast that there will be a deviation beyond the tolerance levels agreed between Project Manager and Project Board (or between Project Board and corporate or program management)






15. A risk response to a threat where a conscious and deliberate decision is taken to retain the threat - having discerned that it is more economical to do so than to attempt a risk response action. The threat should continue to be monitored to ensure t






16. A description of how and by whom the project's products will be controlled and protected.






17. A type of management product that defines aspects of the project and - once approved - is subject to change control.






18. The formal act of acknowledging that the project has met agreed acceptance criteria and thereby met the requirements of its stakeholders






19. A risk response to a threat where the threat either can no longer have an impact or can no longer happen






20. The set of processes - tools and databases that are used to manage configuration data. Typically - a project will use the configuration management system of either the customer or supplier organization.






21. A process - function or task that occurs over time - has recognizable results and is managed. It is usually defined as part of a process or plan.






22. A tangible or intangible object produced as a result of the project that is intended to be delivered to a customer (either internal or external). A deliverable could be a report - a document - a server upgrade or any other building block of an over






23. The review by the Project Board and Project Manager of the End Stage Report to decide whether to approve the Stage Plan. According to the size and criticality of the project - the review may be formal or informal. The authority to process should be






24. A risk response to an opportunity by seizing the opportunity to ensure that it will happen and that the impact will be realized.






25. A progress report of the information gathered at a checkpoint - which is given by a team to the Project Manager and which provides reporting data as defined in the Work Package






26. Advice from the Project Board to inform all stakeholders and the host sites that the project resources can be disbanded and support services - such as space - equipment and access - demobilized. It should indicate a closure date for costs t the pr






27. A report given by the Project Manger to the Project Board - that confirms the handover of all products and provides and updated Business Case and an assessment of how well the project has done against the original Project Initiation Documentation.






28. A corporate coordinating function for portfolios - programs and projects providing standards - consistency of methods and processes - knowledge management - assurance and training.






29. A control that takes place when a specific event occurs. This could be - for example - the end of a stage - the completion of the Project Initiation Documentation - or the creation of an Exception Report - it could also include organizational ev






30. All the systematic necessary to provide confidence that the target (system - process - organization - program - project - outcome - benefit - capability - product output - deliverable) is appropriate. Appropriateness might be defined subject






31. A team-level - time-driven review of progress.






32. A statement about the quality expected from the project product - captured in the Project Product Description.


33. A report given by the Project Manager to the Project Board at the end of each management stage of the project. This provides information about the project performance during the stage and the project status at stage end.






34. A description of the means and frequency of communication between the project and the project stakeholders.






35. A risk response to an opportunity where proactive actions are taken to enhance both the probability of the event occurring and the impact of the event should it occur.






36. A prioritized list of criteria that the project product must meet before the customer will accept it - i.e. measurable definitions of the attributes required for the set of products to be acceptable to key stakeholders






37. A plan that defines how and when a measurement of the achievement of the project's benefits can be made. If the project is being managed within a program - this information may be created and maintained at the program level.






38. The procedure that ensures that all changes that may affect the project's agreed objectives are identified - assessed and either approved - rejected or deferred.






39. Technical and administrative activities concerned with the creation - maintenance and controlled change of configuration throughout the life of the product.






40. The measurable improvement resulting from an outcome perceived as an advantage by one or more stakeholders.






41. The person or group (e.g. a Project Board) who is identified and authorized to approve a (management or specialist) product as being complete and fit for purpose.






42. An off-specification that is accepted by the Project Board without corrective action.






43. A recommendation prepared by the Project Manager for the Project Board to send as a project closure notification when the board is satisfied that the project can be closed.






44. The point at which an authority is granted.






45. Principally - software development methods that apply the project approach of using short time-boxed iterations where products are incrementally developed. Prince2 is compatible with agile principles.






46. The person or group who commissioned the work and will benefit from the end results.






47. The permissible deviation in a plan's cost that is allowed before the deviation needs to be escalated to the next level of management. Cost tolerance is documented in the respective plan. See also 'tolerance'.






48. The formal confirmation that a product is complete and meets its requirements (less any concessions) as defined by its Product Description.






49. The right to allocate resources and make decisions (applies to project - stage - and team levels)






50. The restrictions or limitations that the project is bound by.