Test your basic knowledge |
SAP PLM
Start Test
Study First
Subject
:
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A customer request to a compnay for the delivery of goods or services at a certain time. The request is received by a sales area that is then responsible for fulfilling the contract.
Customer Inquiry
AS
Milestones
Sales Order
2. Object representing events that are particularly important for the progress of the project or are of special interest. You can assign milestones to individual acitvities or WBS elements.
Project Builder
Goods Issue
Claim
Milestones
3. A list of dates from which down payment request and sales relevant invoices are sent to customers. The planned revenues and planned incoming payments are automatically derived from the billing plan and recorded in the relevant WBS element.
Billing plan
Profit Center
Time profile
AS
4. A structure element of the work breakdown structure. It describes a concrete task or a partial task that can be further subdivided. Planned and actual values for a project are defined and aggregated in WBS elements.
REL
Period profile
CN24N
WBS Element
5. Which requirements do you want to display?
Network Plan
Evaluation profile
Billing plan
Production Order
6. An organizationl unit that defines where and by whom an activity is to be carried otu. The data in the work center can be used for scheduling - costing - and capacity planning.
REL
Work Center
Production Order
Milestones
7. A component of Materials Management with the following tasks; procuring materials and services externally - determining possible sources of supply for a requirement - monitoring goods deliveries and payment.
AS
Billing plan
Work Center
Purchasing
8. Hierachical structuring of a company's undertaking to create tangible assets or render services for an approval year.
Production Order
AS
Internal Order
Requirements Date
9. A binding framework for all the organization elements created in a project. The project definition contains default and control values. When you create a work breakdown structure - you automatically create a proejct definition.
PDC
Project Definition
Time profile
Selection profile
10. What period will be evaluated?
Time profile
Time Scheduling Functions
Claim
Control profile
11. Which fields do you want to display?
Claim
List Profile
Relationship Linking
Automatically Carried Out
12. Objects Maintained in _______: Work Breakdown Structures - Network - Milestone - Project Definition
WBS Element
Project Builder
Budget
Activity
13. Automatically calculated by the system for materials during the project based on the projected finish date of the activity.
Claim
Cost Center
Requirements Date
Shift Order Indicator
14. Lifecycle of _________: Progress - Structure - Bottlenecks/Comparison - Analyses - Machines - Persons - External assignment - Work Center
Purchase Order
Goods Issue
WBS Element
Internal Activities
15. Dates in ____: Network header (Basic and Forecast Dates) - Network activity Constraints (Earliest and Latest Dates) - Activity element
Network Plan
REL
Claim
Billing plan
16. CJ29 - Project Scheduling Transaction - OSPU - Used to set control keys.
Purchasing
Internal Activities
CJ2B
Project Builder
17. Comparison or evaluation of data?
Project Builder
Control profile
Relationship Linking
Time Scheduling Functions
18. A neutral work breakdown strucutre that can be used several times over and only serves as a template for creating operative owrk breakdown structures.
Standard Work Breakdown Structure
Project Builder
Standard Network
REL
19. Plant Data Collection
Shift Order Indicator
Work Center
Relationship Linking
PDC
20. An organizational unit within a controlling area that represents a defined location of cost incurrence. The definition can be based on funcitonal requirements - allocation criteria - physical locations or responsibility for costs.
Cost Center
CJ2B
WBS Element
Selection profile
21. Finally Confirmed
CNF
Standard Work Breakdown Structure
List Profile
AF
22. Are entered in networks using confirmations.
Claim
Profit Center
General Costs Activity
Actual Dates
23. A production order used in discrete manufacturing.
Scheduling result
Cost Center
Production Order
Relationship Linking
24. Which data will be evaluated
Planning Forms
Network Plan
Selection profile
Budget
25. The system can checkthe heirachical consisteny co time scheduling within the project and extapolate dates within the project strucure automaticallly on saving using the planning methods "top down" "bottom up " and "strict bottom up."
Time profile
Actual Dates Population
Network
Automatically Carried Out
26. Determines the latest dates
Period profile
Controlling Area
Backward Scheduling
Internal Activity Allocation
27. A model of the project that shows the project activities to be fulfilled in the hierarchical form. It divides the project into clearly-structured sections. The individual elements of the work breakdown structure are called WBS elements.
Actual Dates Population
Production Order
Work Breakdown Structure (WBS)
Forward Scheduling
28. The network structures that are not directly associated with a project and can be used as templates for creating other standard networks or operative networks.
Standard Network
Selection profile
Scheduling type
CN24N
29. An organizational unit in Accounting that reflects a management-oriented structure fo the organization for the purpose of internal control.
Actual Dates Population
Forward Scheduling
Work Breakdown Structure (WBS)
Profit Center
30. A request or instruction from a purchasing organization to a vendor (external supplier) or a plant to deliver a quantity of material or render a service at a certain point in time.
Purchase Order
Company Code
AF
Planning Forms
31. Describes the chronological sequence of and dependencies between events and activites in a project - and maps the actual flow of the project.
Standard Work Breakdown Structure
Controlling Area
Network
Cost Center
32. Top Down - Bottom Up - Free Planning - Strict Bottom Up
Scheduling result
Profit Center
Planning Forms
Internal Activity Allocation
33. An organizational unit within a company - used to represent a closed system for cost accounting purposes. A controlling area may include single or multiple company codes that may use different currencies.
Cost Center
Controlling Area
CNF
Production Order
34. The actual dates for a WBS element can only be entered either - Manually - Calculateted by extrapoaltion of actual dates of lower ranked WSB elements - Derived from the provisional actual dates of assigned activities.
Planning Forms
Maintenance Order
Actual Dates Population
Purchasing
35. Factors that can have an influence on the __________ of networks: The transaction used to carry out the scheduling - Relationships to other networks - The control key for the activity - Dates of assigned WBS elements - The work center in activities
Purchasing
Selection profile
Scheduling result
Billing plan
36. Task in a network that has a defined start and finish. Project Systems has the following activity types Internal processing - external processing - costs - service.
Milestones
Activity
Work Breakdown Structure (WBS)
BOM
37. Internal cost allocation procedure where by the valuated atcitives (allocation bases) carredi out by cost centers are reallocated to the cost receiver according to the cause. In internal activity allocation - the service carried out by thte cost cent
Budget
Cost Center
Internal Activity Allocation
Billing plan
38. Released
REL
Production Order
Backward Scheduling
Internal Activities
39. Actual Finish Date
WBS Element
Budget
REL
AF
40. A term from Inventory Management denoting a physical inward movement of goods or material from a company - usally with reference to a purchase order or production order.
Goods Issue
Planning Forms
Selection profile
Shift Order Indicator
41. Sets of dates - Planning form - Scheduling - Planning Different Calendars - Shift - Extrapolation - Inherit - Check dates
Milestones
Actual Dates
Time Scheduling Functions
Controlling Area
42. Predfined cost framework for a task or project within the specific period. Budgeting differs from cost planning in that it is bindiing. Whereas you must estimate your project costs as accurately as possible during project cost planning - it is the ap
Scheduling result
Purchase Order
Budget
Forward Scheduling
43. Overall Network Scheduling Transaction with selection options
Profit Center
CN24N
Time Scheduling Functions
Controlling Area
44. List some ________: Internal processing - External processing - costs -service
Controlling Area
Sales Order
Activity types
Customer Inquiry
45. The smallest organization unit within a company - used to represent a closed system for cost accounting purposes. A controlling area may include single or multiple company codes that may use different currencies.
Company Code
WBS Element
Activity
Standard Network
46. Project-specific notification category. A claim is used to document varioances form the project plan. You can use claims to plan costs incurred by variances - as well as initiate and monitor follow up activities.
Internal Activities
Evaluation profile
Claim
Backward Scheduling
47. Determines the original direction in which scheduling is carried out. Networks are always scheduled forwards and backwards. They are used for both network and WBS scheduling.
WBS Element
Activity
Scheduling type
Controlling Area
48. A way of describing the link between the start and finish points of two activities in a network. Relationships determine the sequence of activities.
Relationship
Activity
Evaluation profile
Work Center
49. Network activities can only be linked to each other by means of relationships in the project system. The work breakdown structure has a purely hierachical structure however.
Scheduling result
REL
Relationship Linking
Evaluation profile
50. Which period do you want to split?
Period profile
Scheduling result
Control profile
Backward Scheduling