Test your basic knowledge |
SAP PLM
Start Test
Study First
Subject
:
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Automatically calculated by the system for materials during the project based on the projected finish date of the activity.
Requirements Date
List Profile
Maintenance Order
Actual Dates Population
2. A production order used in discrete manufacturing.
List Profile
Internal Activities
Production Order
Time Scheduling Functions
3. A component of Materials Management with the following tasks; procuring materials and services externally - determining possible sources of supply for a requirement - monitoring goods deliveries and payment.
Sales Order
Purchasing
Network Plan
CN24N
4. Are entered in networks using confirmations.
Internal Order
Actual Dates
Billing plan
AF
5. A list of dates from which down payment request and sales relevant invoices are sent to customers. The planned revenues and planned incoming payments are automatically derived from the billing plan and recorded in the relevant WBS element.
CN24N
Work Center
Billing plan
Time Scheduling Functions
6. The smallest organization unit within a company - used to represent a closed system for cost accounting purposes. A controlling area may include single or multiple company codes that may use different currencies.
Work Breakdown Structure (WBS)
Time profile
Company Code
Billing plan
7. A neutral work breakdown strucutre that can be used several times over and only serves as a template for creating operative owrk breakdown structures.
Standard Work Breakdown Structure
CN24N
Relationship Linking
PDC
8. Order for detaled planning and associated documetnation of measures during maintenance.
AF
Controlling Area
General Costs Activity
Maintenance Order
9. Dates in ____: Network header (Basic and Forecast Dates) - Network activity Constraints (Earliest and Latest Dates) - Activity element
Sales Order
Actual Dates Population
Claim
Network Plan
10. Actual Finish Date
Purchase Requistion
Milestones
Internal Order
AF
11. Actual Start Date
Relationship
Work Center
AS
Activity
12. Task in a network that has a defined start and finish. Project Systems has the following activity types Internal processing - external processing - costs - service.
Relationship
Activity
Project Builder
Purchase Order
13. The system can checkthe heirachical consisteny co time scheduling within the project and extapolate dates within the project strucure automaticallly on saving using the planning methods "top down" "bottom up " and "strict bottom up."
Reduction
Automatically Carried Out
Milestones
List Profile
14. Hierachical structuring of a company's undertaking to create tangible assets or render services for an approval year.
Activity types
Internal Order
Shift Order Indicator
Work Breakdown Structure (WBS)
15. Object representing events that are particularly important for the progress of the project or are of special interest. You can assign milestones to individual acitvities or WBS elements.
Automatically Carried Out
Planning Forms
Milestones
List Profile
16. Network activities can only be linked to each other by means of relationships in the project system. The work breakdown structure has a purely hierachical structure however.
Scheduling type
Evaluation profile
Relationship
Relationship Linking
17. Determines the original direction in which scheduling is carried out. Networks are always scheduled forwards and backwards. They are used for both network and WBS scheduling.
Maintenance Order
Scheduling type
Company Code
Period profile
18. An organizationl unit that defines where and by whom an activity is to be carried otu. The data in the work center can be used for scheduling - costing - and capacity planning.
Work Center
Evaluation profile
Relationship Linking
Backward Scheduling
19. Only affects the activities for which a reduction strategy has been stored
Reduction
Cost Center
Budget
Requirements Date
20. Sets of dates - Planning form - Scheduling - Planning Different Calendars - Shift - Extrapolation - Inherit - Check dates
Standard Work Breakdown Structure
Backward Scheduling
Time Scheduling Functions
Activity
21. Factors influencing Scheduling: Internal Processing - External Processing - ____________ - Relationships (ES Earliest Start - LS Latest Start - EF Earliest Finish - TF - Total Float - FF Free Float - FS Finish Start - SF Start Finish - SS
REL
Scheduling type
Automatically Carried Out
General Costs Activity
22. Determines the earliest dates.
Sales Order
Project Definition
Production Order
Forward Scheduling
23. Project-specific notification category. A claim is used to document varioances form the project plan. You can use claims to plan costs incurred by variances - as well as initiate and monitor follow up activities.
Relationship Linking
Goods Issue
Claim
Internal Order
24. Internal cost allocation procedure where by the valuated atcitives (allocation bases) carredi out by cost centers are reallocated to the cost receiver according to the cause. In internal activity allocation - the service carried out by thte cost cent
Selection profile
Internal Activity Allocation
Claim
Evaluation profile
25. Which requirements do you want to display?
CJ2B
Network Plan
Sales Order
Evaluation profile
26. A customer request to a compnay for the delivery of goods or services at a certain time. The request is received by a sales area that is then responsible for fulfilling the contract.
Maintenance Order
Sales Order
AS
General Costs Activity
27. A structure element of the work breakdown structure. It describes a concrete task or a partial task that can be further subdivided. Planned and actual values for a project are defined and aggregated in WBS elements.
WBS Element
Milestones
Goods Issue
Evaluation profile
28. Objects Maintained in _______: Work Breakdown Structures - Network - Milestone - Project Definition
Project Builder
Controlling Area
Control profile
Backward Scheduling
29. Factors that can have an influence on the __________ of networks: The transaction used to carry out the scheduling - Relationships to other networks - The control key for the activity - Dates of assigned WBS elements - The work center in activities
Backward Scheduling
Scheduling result
Period profile
Activity types
30. Finally Confirmed
Milestones
Budget
CNF
Work Center
31. A binding framework for all the organization elements created in a project. The project definition contains default and control values. When you create a work breakdown structure - you automatically create a proejct definition.
Scheduling result
Backward Scheduling
Project Definition
Purchase Requistion
32. What period will be evaluated?
Time profile
Controlling Area
Purchase Order
Project Definition
33. The network structures that are not directly associated with a project and can be used as templates for creating other standard networks or operative networks.
CJ2B
Standard Network
CNF
Evaluation profile
34. Controls how actual dates from partial confirmations affect further scheduling runs
Control profile
Billing plan
Budget
Shift Order Indicator
35. A customer request to a company for a quotation or sales information that is not binding. The request is recieved by a sales area that is then responsible for processing it further.
Internal Activities
Customer Inquiry
Scheduling result
Company Code
36. A complete - structured list of the components that comprise an object. Bill of materials. The list contains a description - the quantity and the the unit of measure. The components are known as BOM items.
Billing plan
Control profile
BOM
Actual Dates Population
37. The actual dates for a WBS element can only be entered either - Manually - Calculateted by extrapoaltion of actual dates of lower ranked WSB elements - Derived from the provisional actual dates of assigned activities.
Control profile
BOM
Project Definition
Actual Dates Population
38. A term from Inventory Management denoting a physical inward movement of goods or material from a company - usally with reference to a purchase order or production order.
Production Order
BOM
Goods Issue
CNF
39. Top Down - Bottom Up - Free Planning - Strict Bottom Up
Period profile
Automatically Carried Out
Planning Forms
Forward Scheduling
40. Predfined cost framework for a task or project within the specific period. Budgeting differs from cost planning in that it is bindiing. Whereas you must estimate your project costs as accurately as possible during project cost planning - it is the ap
Activity types
Budget
CJ2B
WBS Element
41. Which data will be evaluated
Relationship Linking
Relationship
Requirements Date
Selection profile
42. An organizational unit within a company - used to represent a closed system for cost accounting purposes. A controlling area may include single or multiple company codes that may use different currencies.
Claim
Activity
Controlling Area
Time profile
43. Which period do you want to split?
Customer Inquiry
Planning Forms
Period profile
Milestones
44. A request or instruction from a purchasing organization to a vendor (external supplier) or a plant to deliver a quantity of material or render a service at a certain point in time.
Relationship
Actual Dates Population
Standard Network
Purchase Order
45. Overall Network Scheduling Transaction with selection options
Controlling Area
Internal Activity Allocation
CN24N
Cost Center
46. Comparison or evaluation of data?
General Costs Activity
Selection profile
Control profile
Maintenance Order
47. An organizational unit within a controlling area that represents a defined location of cost incurrence. The definition can be based on funcitonal requirements - allocation criteria - physical locations or responsibility for costs.
Claim
AS
Cost Center
REL
48. Released
REL
Goods Issue
Purchase Requistion
Sales Order
49. A model of the project that shows the project activities to be fulfilled in the hierarchical form. It divides the project into clearly-structured sections. The individual elements of the work breakdown structure are called WBS elements.
Work Breakdown Structure (WBS)
Purchase Order
Billing plan
Planning Forms
50. Describes the chronological sequence of and dependencies between events and activites in a project - and maps the actual flow of the project.
AS
Network
General Costs Activity
Forward Scheduling