Test your basic knowledge |
SAP PLM
Start Test
Study First
Subject
:
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Hierachical structuring of a company's undertaking to create tangible assets or render services for an approval year.
Relationship Linking
CNF
Purchase Requistion
Internal Order
2. A customer request to a company for a quotation or sales information that is not binding. The request is recieved by a sales area that is then responsible for processing it further.
Maintenance Order
Scheduling result
Customer Inquiry
Backward Scheduling
3. Top Down - Bottom Up - Free Planning - Strict Bottom Up
Internal Activity Allocation
Work Center
Project Definition
Planning Forms
4. An organizationl unit that defines where and by whom an activity is to be carried otu. The data in the work center can be used for scheduling - costing - and capacity planning.
CN24N
Requirements Date
Purchase Order
Work Center
5. A binding framework for all the organization elements created in a project. The project definition contains default and control values. When you create a work breakdown structure - you automatically create a proejct definition.
REL
General Costs Activity
WBS Element
Project Definition
6. What period will be evaluated?
Sales Order
Control profile
Budget
Time profile
7. Task in a network that has a defined start and finish. Project Systems has the following activity types Internal processing - external processing - costs - service.
Standard Network
Purchase Requistion
Activity
Selection profile
8. Factors influencing Scheduling: Internal Processing - External Processing - ____________ - Relationships (ES Earliest Start - LS Latest Start - EF Earliest Finish - TF - Total Float - FF Free Float - FS Finish Start - SF Start Finish - SS
Standard Work Breakdown Structure
Evaluation profile
PDC
General Costs Activity
9. Determines the latest dates
Network
Backward Scheduling
REL
Reduction
10. Which data will be evaluated
Automatically Carried Out
Selection profile
Company Code
Purchase Order
11. A neutral work breakdown strucutre that can be used several times over and only serves as a template for creating operative owrk breakdown structures.
Standard Work Breakdown Structure
Period profile
Backward Scheduling
Internal Activities
12. List some ________: Internal processing - External processing - costs -service
Network Plan
Planning Forms
Actual Dates
Activity types
13. A model of the project that shows the project activities to be fulfilled in the hierarchical form. It divides the project into clearly-structured sections. The individual elements of the work breakdown structure are called WBS elements.
Evaluation profile
Work Breakdown Structure (WBS)
Billing plan
Profit Center
14. Actual Start Date
AS
Internal Order
Maintenance Order
Actual Dates
15. Comparison or evaluation of data?
Control profile
Requirements Date
Internal Activity Allocation
Purchase Requistion
16. A structure element of the work breakdown structure. It describes a concrete task or a partial task that can be further subdivided. Planned and actual values for a project are defined and aggregated in WBS elements.
Billing plan
Relationship
WBS Element
Internal Activity Allocation
17. An organizational unit in Accounting that reflects a management-oriented structure fo the organization for the purpose of internal control.
Purchase Order
Planning Forms
Profit Center
Budget
18. A complete - structured list of the components that comprise an object. Bill of materials. The list contains a description - the quantity and the the unit of measure. The components are known as BOM items.
Project Builder
Scheduling type
Goods Issue
BOM
19. Plant Data Collection
Period profile
Selection profile
Customer Inquiry
PDC
20. Order for detaled planning and associated documetnation of measures during maintenance.
Maintenance Order
Planning Forms
Controlling Area
Billing plan
21. Only affects the activities for which a reduction strategy has been stored
Budget
Actual Dates
Reduction
Period profile
22. Automatically calculated by the system for materials during the project based on the projected finish date of the activity.
Requirements Date
Internal Order
General Costs Activity
Profit Center
23. Are entered in networks using confirmations.
Scheduling result
Actual Dates
Network Plan
Activity types
24. A request or instruction from a purchasing organization to a vendor (external supplier) or a plant to deliver a quantity of material or render a service at a certain point in time.
AF
Project Builder
Purchase Order
Maintenance Order
25. CJ29 - Project Scheduling Transaction - OSPU - Used to set control keys.
Actual Dates Population
CJ2B
AS
Requirements Date
26. Lifecycle of _________: Progress - Structure - Bottlenecks/Comparison - Analyses - Machines - Persons - External assignment - Work Center
Production Order
Internal Activities
Reduction
Company Code
27. Which fields do you want to display?
List Profile
Automatically Carried Out
Sales Order
Network
28. Overall Network Scheduling Transaction with selection options
Cost Center
Company Code
CN24N
Internal Activity Allocation
29. Released
Internal Activities
Network
REL
Backward Scheduling
30. An organizational unit within a company - used to represent a closed system for cost accounting purposes. A controlling area may include single or multiple company codes that may use different currencies.
Controlling Area
Standard Network
AF
Activity types
31. A production order used in discrete manufacturing.
Production Order
Standard Network
General Costs Activity
Internal Activities
32. Internal cost allocation procedure where by the valuated atcitives (allocation bases) carredi out by cost centers are reallocated to the cost receiver according to the cause. In internal activity allocation - the service carried out by thte cost cent
Control profile
Project Definition
Internal Activity Allocation
PDC
33. Objects Maintained in _______: Work Breakdown Structures - Network - Milestone - Project Definition
Project Builder
Actual Dates
Relationship
PDC
34. A list of dates from which down payment request and sales relevant invoices are sent to customers. The planned revenues and planned incoming payments are automatically derived from the billing plan and recorded in the relevant WBS element.
Billing plan
CJ2B
Reduction
Network
35. Which requirements do you want to display?
AS
Scheduling type
Requirements Date
Evaluation profile
36. The system can checkthe heirachical consisteny co time scheduling within the project and extapolate dates within the project strucure automaticallly on saving using the planning methods "top down" "bottom up " and "strict bottom up."
Automatically Carried Out
Purchase Order
Network
Activity
37. Which period do you want to split?
Profit Center
Relationship Linking
Purchase Requistion
Period profile
38. A component of Materials Management with the following tasks; procuring materials and services externally - determining possible sources of supply for a requirement - monitoring goods deliveries and payment.
Purchasing
REL
Relationship
Relationship Linking
39. Actual Finish Date
Controlling Area
Internal Order
AF
Network Plan
40. The actual dates for a WBS element can only be entered either - Manually - Calculateted by extrapoaltion of actual dates of lower ranked WSB elements - Derived from the provisional actual dates of assigned activities.
Actual Dates Population
Shift Order Indicator
Project Definition
Activity types
41. Finally Confirmed
Network
Activity
Automatically Carried Out
CNF
42. Controls how actual dates from partial confirmations affect further scheduling runs
AS
Shift Order Indicator
Project Definition
Control profile
43. Sets of dates - Planning form - Scheduling - Planning Different Calendars - Shift - Extrapolation - Inherit - Check dates
AF
Scheduling result
Cost Center
Time Scheduling Functions
44. An organizational unit within a controlling area that represents a defined location of cost incurrence. The definition can be based on funcitonal requirements - allocation criteria - physical locations or responsibility for costs.
Billing plan
BOM
Internal Activity Allocation
Cost Center
45. Network activities can only be linked to each other by means of relationships in the project system. The work breakdown structure has a purely hierachical structure however.
Relationship Linking
Cost Center
BOM
Relationship
46. Describes the chronological sequence of and dependencies between events and activites in a project - and maps the actual flow of the project.
Actual Dates
Billing plan
Profit Center
Network
47. Object representing events that are particularly important for the progress of the project or are of special interest. You can assign milestones to individual acitvities or WBS elements.
CNF
Standard Network
Milestones
Scheduling result
48. Project-specific notification category. A claim is used to document varioances form the project plan. You can use claims to plan costs incurred by variances - as well as initiate and monitor follow up activities.
Scheduling type
Activity
Claim
Internal Activities
49. A request or instruction to Purchasing to procure a quantity of a material or service so what it is available at a certain point in time.
Work Breakdown Structure (WBS)
Evaluation profile
Purchase Requistion
AS
50. The network structures that are not directly associated with a project and can be used as templates for creating other standard networks or operative networks.
Time profile
Network
Standard Work Breakdown Structure
Standard Network