Test your basic knowledge |
SAP PLM
Start Test
Study First
Subject
:
it-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A customer request to a compnay for the delivery of goods or services at a certain time. The request is received by a sales area that is then responsible for fulfilling the contract.
Network
Work Breakdown Structure (WBS)
Project Definition
Sales Order
2. A request or instruction from a purchasing organization to a vendor (external supplier) or a plant to deliver a quantity of material or render a service at a certain point in time.
Requirements Date
Purchasing
Purchase Order
Reduction
3. Finally Confirmed
Internal Activities
CNF
Purchase Order
Purchase Requistion
4. Released
REL
Purchasing
AS
Internal Activities
5. List some ________: Internal processing - External processing - costs -service
Profit Center
AF
Activity types
CNF
6. An organizational unit in Accounting that reflects a management-oriented structure fo the organization for the purpose of internal control.
REL
Scheduling type
Profit Center
Automatically Carried Out
7. Factors influencing Scheduling: Internal Processing - External Processing - ____________ - Relationships (ES Earliest Start - LS Latest Start - EF Earliest Finish - TF - Total Float - FF Free Float - FS Finish Start - SF Start Finish - SS
Cost Center
General Costs Activity
Time Scheduling Functions
Backward Scheduling
8. Objects Maintained in _______: Work Breakdown Structures - Network - Milestone - Project Definition
Internal Order
Work Center
Billing plan
Project Builder
9. Plant Data Collection
Milestones
Internal Activities
Sales Order
PDC
10. Automatically calculated by the system for materials during the project based on the projected finish date of the activity.
BOM
Requirements Date
AS
Relationship Linking
11. Determines the earliest dates.
Shift Order Indicator
Forward Scheduling
Actual Dates Population
General Costs Activity
12. Which data will be evaluated
Selection profile
CNF
Standard Network
Relationship Linking
13. Determines the latest dates
Backward Scheduling
WBS Element
Internal Activities
Control profile
14. The actual dates for a WBS element can only be entered either - Manually - Calculateted by extrapoaltion of actual dates of lower ranked WSB elements - Derived from the provisional actual dates of assigned activities.
Actual Dates Population
Production Order
Network
Period profile
15. The system can checkthe heirachical consisteny co time scheduling within the project and extapolate dates within the project strucure automaticallly on saving using the planning methods "top down" "bottom up " and "strict bottom up."
Network
Standard Network
Automatically Carried Out
Billing plan
16. Actual Start Date
Customer Inquiry
Control profile
PDC
AS
17. A way of describing the link between the start and finish points of two activities in a network. Relationships determine the sequence of activities.
Project Definition
WBS Element
Relationship
Budget
18. An organizational unit within a company - used to represent a closed system for cost accounting purposes. A controlling area may include single or multiple company codes that may use different currencies.
Controlling Area
WBS Element
Reduction
Billing plan
19. Actual Finish Date
Actual Dates Population
Standard Work Breakdown Structure
AF
Milestones
20. Which fields do you want to display?
Cost Center
Selection profile
Standard Network
List Profile
21. Overall Network Scheduling Transaction with selection options
Relationship
AF
CN24N
Claim
22. A term from Inventory Management denoting a physical inward movement of goods or material from a company - usally with reference to a purchase order or production order.
Billing plan
Claim
Time Scheduling Functions
Goods Issue
23. Comparison or evaluation of data?
Billing plan
General Costs Activity
Internal Activities
Control profile
24. The smallest organization unit within a company - used to represent a closed system for cost accounting purposes. A controlling area may include single or multiple company codes that may use different currencies.
Reduction
Company Code
Evaluation profile
Project Definition
25. A structure element of the work breakdown structure. It describes a concrete task or a partial task that can be further subdivided. Planned and actual values for a project are defined and aggregated in WBS elements.
Work Center
WBS Element
Automatically Carried Out
CNF
26. A request or instruction to Purchasing to procure a quantity of a material or service so what it is available at a certain point in time.
AF
Activity types
Reduction
Purchase Requistion
27. Determines the original direction in which scheduling is carried out. Networks are always scheduled forwards and backwards. They are used for both network and WBS scheduling.
Scheduling type
Purchasing
AF
Work Center
28. CJ29 - Project Scheduling Transaction - OSPU - Used to set control keys.
CN24N
PDC
CJ2B
BOM
29. Network activities can only be linked to each other by means of relationships in the project system. The work breakdown structure has a purely hierachical structure however.
Standard Network
Network Plan
Selection profile
Relationship Linking
30. Lifecycle of _________: Progress - Structure - Bottlenecks/Comparison - Analyses - Machines - Persons - External assignment - Work Center
Internal Activities
Profit Center
List Profile
Actual Dates
31. A component of Materials Management with the following tasks; procuring materials and services externally - determining possible sources of supply for a requirement - monitoring goods deliveries and payment.
Automatically Carried Out
AS
Work Center
Purchasing
32. An organizational unit within a controlling area that represents a defined location of cost incurrence. The definition can be based on funcitonal requirements - allocation criteria - physical locations or responsibility for costs.
Profit Center
AS
Controlling Area
Cost Center
33. Predfined cost framework for a task or project within the specific period. Budgeting differs from cost planning in that it is bindiing. Whereas you must estimate your project costs as accurately as possible during project cost planning - it is the ap
Goods Issue
Budget
Billing plan
Control profile
34. Which period do you want to split?
Period profile
AF
CNF
Purchasing
35. Internal cost allocation procedure where by the valuated atcitives (allocation bases) carredi out by cost centers are reallocated to the cost receiver according to the cause. In internal activity allocation - the service carried out by thte cost cent
Internal Activity Allocation
Activity types
Project Definition
Time profile
36. Project-specific notification category. A claim is used to document varioances form the project plan. You can use claims to plan costs incurred by variances - as well as initiate and monitor follow up activities.
Billing plan
Time profile
Claim
Standard Work Breakdown Structure
37. What period will be evaluated?
Time profile
Scheduling result
List Profile
Production Order
38. Top Down - Bottom Up - Free Planning - Strict Bottom Up
CJ2B
Billing plan
Planning Forms
Relationship
39. Object representing events that are particularly important for the progress of the project or are of special interest. You can assign milestones to individual acitvities or WBS elements.
Goods Issue
General Costs Activity
Automatically Carried Out
Milestones
40. Dates in ____: Network header (Basic and Forecast Dates) - Network activity Constraints (Earliest and Latest Dates) - Activity element
Network Plan
Work Breakdown Structure (WBS)
Control profile
Planning Forms
41. A complete - structured list of the components that comprise an object. Bill of materials. The list contains a description - the quantity and the the unit of measure. The components are known as BOM items.
Company Code
BOM
Control profile
Cost Center
42. Describes the chronological sequence of and dependencies between events and activites in a project - and maps the actual flow of the project.
Sales Order
Billing plan
Network
Purchase Order
43. A list of dates from which down payment request and sales relevant invoices are sent to customers. The planned revenues and planned incoming payments are automatically derived from the billing plan and recorded in the relevant WBS element.
Control profile
CNF
Standard Network
Billing plan
44. Factors that can have an influence on the __________ of networks: The transaction used to carry out the scheduling - Relationships to other networks - The control key for the activity - Dates of assigned WBS elements - The work center in activities
Backward Scheduling
REL
Scheduling result
Purchase Order
45. Are entered in networks using confirmations.
Project Definition
Shift Order Indicator
Work Breakdown Structure (WBS)
Actual Dates
46. A customer request to a company for a quotation or sales information that is not binding. The request is recieved by a sales area that is then responsible for processing it further.
AS
General Costs Activity
Actual Dates
Customer Inquiry
47. A binding framework for all the organization elements created in a project. The project definition contains default and control values. When you create a work breakdown structure - you automatically create a proejct definition.
Milestones
Project Definition
Standard Network
Time Scheduling Functions
48. Controls how actual dates from partial confirmations affect further scheduling runs
Company Code
Shift Order Indicator
Backward Scheduling
Internal Activities
49. Task in a network that has a defined start and finish. Project Systems has the following activity types Internal processing - external processing - costs - service.
Project Definition
Reduction
Scheduling type
Activity
50. A neutral work breakdown strucutre that can be used several times over and only serves as a template for creating operative owrk breakdown structures.
Standard Work Breakdown Structure
Activity
Company Code
Internal Activity Allocation