SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
CAPM Cost Management
Start Test
Study First
Subjects
:
certifications
,
business-skills
,
capm
Instructions:
Answer 26 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. What is the formula for variance at completion?
BAC-EAC
-10 percent to +25 percent from actual
EV-PV
Analogous estimationg; bottom-up estimating; parametric estimating; three-point estimates; one time estimates
2. What is the formula for estimate to complete?
Estimate costs; Determine Budget; Control Costs
Cost baseline; funding requirements
EAC-AC
Scope baseline; Project schedule; Human resource plan; Enterprise environmental factors; Organizational process assests; Risk register
3. What is the formula for cost variance?
-10 percent to +25 percent from actual
EV-PV
Creating estimates based on the details of the projects which are then rolled up into project estimates
EV-AC
4. What is the range for a budget estimate?
EV-PV
+/- 50 percent from actual
+/- 10 percent from actual
-10 percent to +25 percent from actual
5. What are key outputs of the Determine Budget process?
+/- 50 percent from actual
Work performance measurements; budget forecasts; change requests; updatse to the project management plan and project documents
Cost baseline; funding requirements
+/- 10 percent from actual
6. What is parametric estimating?
+/- 50 percent from actual
Activity cost estimates; Updates to the project management plan and project documents
EV/AC
Calculating estimates using historical information
7. What is the formula for schedule variance?
+/- 50 percent from actual
(BAC-EV)/(BAC-AC)
Calculating estimates using historical information
EV-PV
8. What is the process of cost management?
Estimate costs; Determine Budget; Control Costs
(BAC-EV)/(BAC-AC)
BAC-EAC
A cost that varies with the amoutn of work done on the project; a cost that does not vary with the amount of work done on the project
9. What are key outputs of the Control Costs process?
Work performance measurements; budget forecasts; change requests; updatse to the project management plan and project documents
Finding a less costly way of doing essentially the same work.
The cost budget adds management reserve to the cost baseline
A cost directly attributable to the project; overhead costs
10. What is the formula for schedule performance index?
+/- 10 percent from actual
The cost budget adds management reserve to the cost baseline
Considering the furture cost of operating and maintaining the project or deliverable over its life when planning and managing the project
EV/PV
11. What are the main approaches to cost or schedule estimating?
Work performance measurements; budget forecasts; change requests; updatse to the project management plan and project documents
EV-PV
Analogous estimationg; bottom-up estimating; parametric estimating; three-point estimates; one time estimates
Creating estimates based on the details of the projects which are then rolled up into project estimates
12. What is earned value measurement?
Analogous estimationg; bottom-up estimating; parametric estimating; three-point estimates; one time estimates
Cost baseline; funding requirements
A method of measuring project performance that looks at the value earned for work accomplished. It can be used to predict future cost performance and project completion dates.
EV/PV
13. What is analogous estimating?
BAC-EAC
Scope baseline; Project schedule; Human resource plan; Enterprise environmental factors; Organizational process assests; Risk register
Creating estimates based on the details of the projects which are then rolled up into project estimates
Estimate costs; Determine Budget; Control Costs
14. What does life cycle costing mean?
EV/AC
Considering the furture cost of operating and maintaining the project or deliverable over its life when planning and managing the project
AC + Bottom-up ETC - BAC/CPI - AC + (BAC-EV) - AC + (BAC - EV) / (CPI x SPI)
EV/PV
15. What is the formula for cost perfrmance index?
BAC-EAC
Finding a less costly way of doing essentially the same work.
EAC-AC
EV/AC
16. What is the range for a definitive estimate?
A cost that varies with the amoutn of work done on the project; a cost that does not vary with the amount of work done on the project
EV-AC
Estimate costs; Determine Budget; Control Costs
+/- 10 percent from actual
17. In which process is the cost management plan created?
(BAC-EV)/(BAC-AC)
-10 percent to +25 percent from actual
In integration management as part of the Develop Project Management Plan process
Estimate costs; Determine Budget; Control Costs
18. What is the range for a rough order of magnitude estimate?
EV-AC
Estimate costs; Determine Budget; Control Costs
+/- 50 percent from actual
BAC-EAC
19. What is value analysis?
AC + Bottom-up ETC - BAC/CPI - AC + (BAC-EV) - AC + (BAC - EV) / (CPI x SPI)
Finding a less costly way of doing essentially the same work.
A cost that varies with the amoutn of work done on the project; a cost that does not vary with the amount of work done on the project
Creating estimates based on the details of the projects which are then rolled up into project estimates
20. Describe a varable cost and a fixed cost chargeable to the project.
EAC-AC
Calculating estimates using historical information
A cost that varies with the amoutn of work done on the project; a cost that does not vary with the amount of work done on the project
EV/AC
21. What are the formulas for estimate at completion?
AC + Bottom-up ETC - BAC/CPI - AC + (BAC-EV) - AC + (BAC - EV) / (CPI x SPI)
Creating estimates based on the details of the projects which are then rolled up into project estimates
The cost budget adds management reserve to the cost baseline
A method of measuring project performance that looks at the value earned for work accomplished. It can be used to predict future cost performance and project completion dates.
22. What is the difference between a cost budget and a cost baseline?
Creating estimates based on the details of the projects which are then rolled up into project estimates
The cost budget adds management reserve to the cost baseline
Analogous estimationg; bottom-up estimating; parametric estimating; three-point estimates; one time estimates
A method of measuring project performance that looks at the value earned for work accomplished. It can be used to predict future cost performance and project completion dates.
23. Name inputs to the Estimate Costs process.
Considering the furture cost of operating and maintaining the project or deliverable over its life when planning and managing the project
Scope baseline; Project schedule; Human resource plan; Enterprise environmental factors; Organizational process assests; Risk register
EV-PV
Calculating estimates using historical information
24. What are key outputs of the Estimate Costs process?
Activity cost estimates; Updates to the project management plan and project documents
AC + Bottom-up ETC - BAC/CPI - AC + (BAC-EV) - AC + (BAC - EV) / (CPI x SPI)
Estimate costs; Determine Budget; Control Costs
The cost budget adds management reserve to the cost baseline
25. Describe a direct cost and and indirect cost chargeable to the project
A cost directly attributable to the project; overhead costs
Work performance measurements; budget forecasts; change requests; updatse to the project management plan and project documents
EV/PV
A cost that varies with the amoutn of work done on the project; a cost that does not vary with the amount of work done on the project
26. What is the formula for TCPI?
EAC-AC
Calculating estimates using historical information
-10 percent to +25 percent from actual
(BAC-EV)/(BAC-AC)