SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
CAPM Time Management
Start Test
Study First
Subjects
:
certifications
,
business-skills
,
capm
Instructions:
Answer 31 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Means of gathering expert judgment where the participants do not know who the others are and therefore are not able to influence each other's opinion. Designed to prevent "groupthink."
Free Float
Heuristics
Delphi Technique
Activity on Arrow Diagram
2. Probable number of periods this activity should take with the probable range of results (1 week +/- 3 days)
Free Float
Activity Decomposition
Backward Pass
Activity Duration Estimates
3. A situation that occurs when an activity's start date comes before a preceding activity's finish date.
Activity on Arrow Diagram
Schedule Baseline
Negative Float
Activity Duration Estimates
4. An activity in a network diagram that does not have any time associated with it. Only included to show relationship and is usually dotted or dashed line.
Dummy Activity
Lead
Critical Path
Activity Duration Estimates
5. A rarely used type of network diagram where activities are represented by arrows connecting the nodes.
Backward Pass
Reserve Time (Contingency)
Lag
Activity on Arrow Diagram
6. High-level points in the schedule used to track and report progress.
Milestones
Activity on Node Diagram
Activity on Arrow Diagram
Variance Analysis
7. Final result is an activity list (similar to Scope Decomposition where the result is a WBS)
Variance Analysis
Activity Decomposition
Activity on Arrow Diagram
Lag
8. A schedule buffer used to reduce schedule risk.
Reserve Time (Contingency)
Dependencies
Delphi Technique
Milestones
9. A technique to show scheduling possibilities where early and late start and finish dates are calculated for every activity without looking at resource estimates.
Reserve Time (Contingency)
Precedence Diagramming Method
Crashing
Mathematical Analysis
10. Perform activities in parallel that normally are done in sequence; increases risk
Critical Path
Reserve Time (Contingency)
Network Diagram
Fast Tracking
11. The approved schedule that is used as a basis for measuring and reporting. It includes the original project schedule plus all approved updates.
Schedule Baseline
Critical Path
Precedence Diagramming Method
Duration Compression
12. Delay between an activity and the subsequent one dependent upon it.
Variance Analysis
Dependencies
Lag
Backward Pass
13. Rules for which no formula exists; usually derived through trial and error.
Heuristics
Variance Analysis
Crashing
Lead
14. Method of estimated where experts are asked to provide input to the schedule.
Expert Judgment
Activity Decomposition
Variance Analysis
Schedule Baseline
15. A type of network diagram where the boxes are activities - and the arrows are used to show dependencies between the activities.
Heuristics
Activity List
Precedence Diagramming Method
Expert Judgment
16. Method for calculating late start and late finish dates for an activity.
Backward Pass
Precedence Diagramming Method
Activity Decomposition
Analogous Estimating
17. Activities that must be completed before other activities either start or finish (mandatory - discretionary - and external).
Activity on Arrow Diagram
Dependencies
Negative Float
Analogous Estimating
18. The method for calculating early start and early finish dates for an activity.
Variance Analysis
Forward Pass
Lead
Reserve Time (Contingency)
19. A form of expert judgment often used early on when there is little information available. It is performed from the top down - focusing on the big picture.
Free Float
Analogous Estimating
Activity List
Lag
20. Activities with finish to start relationships cannot start until their predecessors have been finished; however - if you have 5 days of lead time on an activity - it may begin 5 days before its predecessor.
Schedule Baseline
Float
Duration Compression
Lead
21. Applying more resources; increases cost
Crashing
Dependencies
Negative Float
Activity Decomposition
22. A type of network diagram where activities are represented on rectangular nodes with arrows representing the dependencies.
Activity on Node Diagram
Float
Monte Carlo Analysis
Negative Float
23. A technique primarily made up of two means of compressing the schedule: crashing and fast-tracking.
Precedence Diagramming Method
Dummy Activity
Duration Compression
Lag
24. Or free slack--how much time an activity can be delayed without affecting the early start date of subsequent dependent activities.
Lead
Free Float
Network Diagram
Precedence Diagramming Method
25. The path through the network diagram that show which activities - if delayed - will affect the project finish date.
Critical Path
Analogous Estimating
Forward Pass
Activity on Node Diagram
26. List of every activity that will be performed on the project.
Float
Activity List
Crashing
Monte Carlo Analysis
27. Computer simulation that throws a high number of "what if" scenarios at the project schedule to determine probable results.
Lag
Crashing
Heuristics
Monte Carlo Analysis
28. Method of diagramming project activities to show sequence and dependencies.
Network Diagram
Free Float
Activity Decomposition
Activity on Arrow Diagram
29. How much time an activity can be delayed without affecting the project's finish date.
Float
Fast Tracking
Milestones
Analogous Estimating
30. Float.
Critical Path
Mathematical Analysis
Activity List
Slack
31. Comparing planned versus actual schedule dates.
Backward Pass
Lag
Variance Analysis
Free Float