Test your basic knowledge |

Construction Estimating

Instructions:
  • Answer 50 questions in 15 minutes.
  • If you are not ready to take this test, you can study here.
  • Match each statement with the correct term.
  • Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.

This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Order of Magnitude Estimate...






2. Explain why using overtime is not recommended for most construction projects.






3. Closely spaced beams supporting a floor or ceiling.They may be wood - steel - or concrete.






4. What is estimating in construction?






5. Describe the CSI MasterFormat and how it is used.






6. Explain why using overtime is not recommended for most construction projects.






7. What are the benefits of renting equipment?






8. The equipment used on construction projects can be divided into three categories: Owned - leased - and rented.






9. Drawings made during the progress of construction - or subsequent thereto - illustrating how various elements of the project were actually installed.






10. Five basic skills everyone should master


11. Statements or drawings that modify the basic contract documents after the latter have been issued to the bidders - but prior to the taking of bids.






12. What are the difficulties encountered by the estimator during the preparation of a project's conceptual estimate?






13. A good database of past project experiences is essential to preparing a quick and accurate estimate.






14. What are the advantages to a small contractor of renting equipment instead of owning?






15. Name three common methods of procuring equipment.






16. Describe the composition of the Construction Cost Index (CCI).






17. Describe the composition of the Building Cost Index (BCI).






18. Name 10 step process to bid


19. A bathroom sink






20. A sum withheld from each payment to the contractor in accordance with the terms of the owner-contractor agreement.






21. Working drawings - specifications - general conditions - supplementary general conditions - the owner-contractor agreement - and all addenda (if issued).






22. Legal claims against an owner for amounts due those engaged in or supplying materials for the construction of the building.






23. An invitation to a selected list of contractors furnishing information on the submission of bids on a subject.






24. An agreed-to sum chargeable against the contractor as reimbursement for damages suffered by the owner because of contractor's failure to fulfill contractual obligations






25. Name two systems that establish standards for the building design/construction estimating process.






26. Describe and provide examples of specific use equipment and general use equipment.






27. What is the maintenance bond?






28. Operation costs include...






29. How do climatic conditions influence the amount of work actually completed in an hour?






30. How are the various surety bonds that may be required on a specific project obtained?






31. Describe and provide examples of specific use equipment and general use equipment.






32. The most reliable productivity rates come from historical data






33. Construction estimating is more an art than a science






34. A work order - usually prepared by the architect and signed by the owner or the owner's agent - authorizing a change in the scope of the work and a change in the cost of the project.






35. Name three common methods of procuring equipment.






36. Where the project will be constructed does not have a major influence in the preparation of an estimate.






37. Under what conditions are wage premiums applied






38. Why is it a good idea for the general contractor to perform quantity surveys on work that is to be subcontracted out?


39. How does insurance differ from a surety bond?






40. A sum withheld from each payment to the contractor in accordance with the terms of the owner-contractor agreement.






41. Describe the composition of the Building Cost Index (BCI).






42. On certain projects the owner may accept proposals only from contractors who are invited to bid.






43. The equipment used on construction projects can be divided into three categories: Owned - leased - and rented.






44. A common error made by GCs in their dealings with subcontractors is to hand them a single technical specifications section relating to their trade - without copies of either the General Requirements or the General and Supplementary General Conditions






45. What unit of time is used to measure labor?






46. A work order - usually prepared by the architect and signed by the owner or the owner's agent - authorizing a change in the scope of the work and a change in the cost of the project.






47. Where the project will be constructed does not have a major influence in the preparation of an estimate.






48. Describe and provide examples of specific use equipment and general use equipment.






49. What is retainage? Why should a contractor be concerned with a retainage clause in a contract?






50. A surety bond guaranteeing that a bidder will sign a contract - if offered - in accordance with their proposal.