SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Construction Management
Start Test
Study First
Subjects
:
industries
,
construction
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.
Conditions of the Contract
Estimated Final Cost
Project Meeting
Warranty
2. See: Start-up; Beneficial Occupancy The process at or near construction completion when a facility is tried out (put into use) to see if it functions as designed. Usually applied to manufacturing type projects.
Commissioning
Estimated Cost to Complete
Checks and Balances
Direct Costs
3. Also: Occupancy Schedule A schedule of the activities and events required to effect occupancy or the use of a facility for its intended purpose. It is used to determine if construction progress will meet the occupancy date.
Reimbursable Expense
Schedule of Values
Completion Schedule
Notice of Award
4. A job title usually reserved for the administrative level person who supervises the work of an on-site contractor .
Owner's Representative
Superintendent
Field Construction Manager
Construction Documents
5. Also: Warranty/Guarantee Phase; Warranty Phase; Guarantee Phase A stipulated length of time following the construction phase - during which contractors are bonded to ensure that materials - equipment - and workmanship meet the requirements of their c
CM Services
Final Design Phase
Occupancy Phase
Change Order
6. A schedule of milestones spanning from the start of construction to occupancy - used as the main measure of progress to keep the project on schedule.
Shop Drawings
Construction Schedule
Milestone Schedule
Approved Changes
7. A schedule of milestones spanning from the start of construction to occupancy - used as the main measure of progress to keep the project on schedule.
Superintendent
Direct Material Costs
Construction Schedule
Milestone Schedule
8. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.
Guaranteed Maximum Price CM (GMPCM)
Final Completion
Project Meeting
Long-Lead Items
9. Also: Reimbursable Charges to the owner covering costs for services that could not or intentionally were not quantified at the time the fee arrangement was made.
Guarantee
Labor and Material Bond
Reimbursable Expense
Design-Build (D-B) Contractor
10. A firm or business organization with the expertise and resources to manage the design - contracting - and construction aspects of project delivery. Individuals who work for a CM Firm are also referred to as Construction Managers.
Conditions of the Contract
Contingencies
Construction Manager
Long-Lead Items
11. A contractor who has a contract with a prime contractor.
Final Design Phase
Notice of Award
Milestone
Subcontractor
12. Costs accruing from expended labor excluding the bonus portion of overtime - insurances - and payroll taxes.
Direct Material Costs
Preliminary Design Phase
Contract Administration
Checks and Balances
13. A contract held by an owner.
Design-Build (D-B) Contractor
Lien
Prime Contract
Direct Labor Costs
14. Costs accruing from expended labor excluding the bonus portion of overtime - insurances - and payroll taxes.
Guarantee
Direct Material Costs
Guaranteed Maximum Price CM (GMPCM)
Commissioning
15. Also: Feasibility Phase The phase prior to the start of design.
Design Development Phase
Pre-design Phase
Budget Estimate
RFP (Request For Proposal)
16. A person assigned to a project to represent the owner on the project team at one to the three management levels.
17. The scope of services provided by a construction manager and available to owners in whole or in part. CM services are not consistent in scope or performance from one CM firm to another.
Specifications
CM Services
Approved Bidders List
Lien
18. A fixed dollar amount which includes all costs of services including overhead and profit.
Milestone Schedule
Lump Sum Fee
Pre-design Phase
Completion Schedule
19. A formal notice sent by a contractor to an owner asserting the fact that the terms of the contract have been breached and compensation is being sought by the contractor from the owner.
Approved Bidders List
Completion Schedule
Change Order
Claim
20. Also: Field CM; Level 3 Manager; Level 3 Person; Superintendent - Site Manager A person designated by the CM firm to interface with the owner's and A/E's representatives on the project team at the third management level. A person located at the site
Contract Document Phase
Milestone
Field Construction Manager
Chart of Accounts
21. Drawings - technical specification - and addenda; the contract documents that refer to the physical construction requirements established by the A/E.
Approved Changes
Construction Documents
Project Budget
RFP (Request For Proposal)
22. A fixed dollar amount which includes all costs of services including overhead and profit.
Technical Specifications
Final Completion
Checks and Balances
Lump Sum Fee
23. A form of the CM system where the construction manager guarantees - in addition to providing ACM services - a ceiling price to the owner for the cost of construction.
Guaranteed Maximum Price CM (GMPCM)
Construction Management
Critical Path(s)
Substantial Completion
24. Money put into the custody of the third party by the first party for disbursement tot the second party. A brief temporary depository for progress payments until authorized for release according to the depositor's explicit instructions.
RFP (Request For Proposal)
Project Team
Project Budget
Escrow Account
25. A contract structure where both design and construction responsibility are vested in a single contractor.
Final Design Phase
Lump Sum Fee
Specifications
Design-Build (D-B) Contracting
26. Changes of any nature in contract requirements which have been agreed upon through a change approval process and approved by the owner.
Long-Lead Time
Approved Changes
apparent Low Bidder
Construction Budget
27. The target cost of the project established by the owner and agreed to be achievable by the team. The Project Budget usually includes the cost of construction and the CM fee - plus any other line-item costs (land - legal fees - interest - design fees
Field Construction Manager
Budget Estimate
Project Budget
Checks and Balances
28. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.
Construction Documents
Budget Estimate
Record Drawings
Long-Lead Items
29. Also: Supplementary Conditions Amendments to the General Conditions that change standard requirements to unique requirements - appropriate for a specific project.
Special Conditions
Estimated Final Cost
Approved Changes
Milestone
30. Written criteria that augment the drawings pertaining to the technical construction of the project that cannot be conveniently included on the plans.
Technical Specifications
Changed Conditions
Contingencies
Contract Document Phase
31. See: Start-up; Beneficial Occupancy The process at or near construction completion when a facility is tried out (put into use) to see if it functions as designed. Usually applied to manufacturing type projects.
Commissioning
Specifications
Estimated Final Cost
Long-Lead Items
32. A business entity that provides independent contractor services to owners through the use of subcontractors when using the general contracting system.
General Contractor
Schematic Design Phase
Conditions of the Contract
Direct Costs
33. Check: Commissioning; Beneficial Occupancy The period prior to owner occupancy when mechanical - electrical - and other systems are activated and the owner's operating and maintenance staff are instructed in their use.
Substantial Completion
Final Design Phase
Start-Up
General Contractor
34. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Direct Labor Costs
Field Construction Manager
Lump Sum Fee
Occupancy Phase
35. Also: As Builts; Check: Record Drawings Drawings produced during or after construction and amended to show the exact location - geometry - and dimensions of the constructed project. As-Built Drawings are not the same as Record Drawings.
Construction Documents
As-Built Drawings
Conditions of the Contract
Owner's Representative
36. A job title usually reserved for the administrative level person who supervises the work of an on-site contractor .
Completion Schedule
Superintendent
Estimated Cost to Complete
Final Design Phase
37. Also: Account Codes; Codes of Accounts An alpha/numeric identification system for budget line items that ensures that project expenditures are properly debited/credited in the project budget as payments are made in behalf of the project.
Chart of Accounts
Design Development Phase
Preconstruction Phase
Performance Bond
38. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Schedule of Values
Schedule of Values
Estimated Final Cost
Direct Costs
39. Also: Concealed Conditions; Latent Conditions Conditions or circumstances - physical or otherwise - which surface after a contract has been signed and which alter the circumstances or conditions on which the contract is based.
Changed Conditions
Technical Specifications
Construction Manager
Progress Payment
40. The list of contractors that have survived prequalification tests.
Construction Management
General Contractor
Approved Bidders List
Substantial Completion
41. The time between the purchase date and delivery date of long-lead items.
Value Engineering
Design-Build (D-B) Contractor
Lump Sum Fee
Design-Build (D-B) Contracting
42. A technical review process; the close matching of engineering design to the value an owner derives from the design.
Notice to Proceed
Lump Sum Fee
Value Engineering
Long-Lead Time
43. The term used on architectural projects to describe the transitional phase from the Schematic Phase to the Contract Document during design.
Contract Administration
Design Development Phase
Construction Manager
Contract Document Phase
44. Graphic representations showing location - geometry - and dimensions of a project or its elements in sufficient detail to facilitate construction.
Drawings
Final Design Phase
Project Meeting
Lump Sum Fee
45. The scope of services provided by a construction manager and available to owners in whole or in part. CM services are not consistent in scope or performance from one CM firm to another.
Record Drawings
Reimbursable Expense
CM Services
Start-Up
46. Also: Construction Team; Check: Program Team Consists of the architect/engineer - construction manager - and owner - represented by their Level 1 - 2 - and 3 Persons - plus the designated leaders of contracted constructors.
Project Team
Construction Budget
Labor and Material Bond
Subcontractor
47. An estimate of the final cost of a work item based on its Cost to Date and the estimated cost to complete it. The sum of the Cost to Date and the Estimated Cost to Complete.
Lien
Bid Depository
Estimated Final Cost
Superintendent
48. The bidder who has submitted the lowest competitive proposal as determined by a cursory examination of the bids submitted.
Changed Conditions
apparent Low Bidder
Chart of Accounts
RFP (Request For Proposal)
49. Check: CM Project Manual Written information that augments the drawings. The Project Manual contains the General Conditions - Supplementary and Special Conditions - the Form of Contract - Addenda - Change Orders - Bidding Information and Proposal For
Project Manual
Critical Path(s)
Schedule of Values
Special Conditions
50. An agreement by which a party accepts responsibility for fulfilling an obligation.
Project Team
Guarantee
Project Manual
General Conditions (of the Contract for Construction)