SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Construction Management
Start Test
Study First
Subjects
:
industries
,
construction
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The initial Design Phase on an architectural project when the A/E delineates the owner's needs in a general way.
Substantial Completion
As-Built Drawings
Field Construction Manager
Schematic Design Phase
2. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.
Design Development Phase
Lien
Contingencies
Long-Lead Items
3. An estimate of cost based on rough or incomplete information - with a stated degree of accuracy. The more information available - the more accurate the estimate. Loosely called a 'ballpark' estimate.
Prime Contract
Budget Estimate
Owner's Representative
Claim
4. Check: Notice of Award; Notice to Proceed A notice from an owner to a contractor stating that a contract will be awarded to the contractor providing certain events occur or specific conditions are met by the contractor.
Subcontractor
Long-Lead Items
Letter of Intent
Direct Material Costs
5. A contractor that provides design and construction services under a single responsibility contract to an owner .
Lump Sum Fee
Design-Build (D-B) Contractor
Construction Documents
Technical Specifications
6. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Completion Schedule
Change Order
Direct Labor Costs
Approved Bidders List
7. The term used to describe the use of the overlapping expertise of each team member during team decision making.
Checks and Balances
Superintendent
Bid Depository
Changed Conditions
8. An estimate of the final cost of a work item based on its Cost to Date and the estimated cost to complete it. The sum of the Cost to Date and the Estimated Cost to Complete.
Budget Estimate
Record Drawings
Direct Labor Costs
Estimated Final Cost
9. The breakdown of a lump sum price into sub-items and sub-costs for identifiable construction elements - which can be evaluated by examination for contractor progress payment purposes.
Drawings
Schedule of Values
Bid Depository
Escrow Account
10. Also: Reimbursable Charges to the owner covering costs for services that could not or intentionally were not quantified at the time the fee arrangement was made.
Preconstruction Phase
Reimbursable Expense
Project Budget
Sub-subcontractor
11. Also: Account Codes; Codes of Accounts An alpha/numeric identification system for budget line items that ensures that project expenditures are properly debited/credited in the project budget as payments are made in behalf of the project.
Field Construction Manager
Budget Estimate
Schedule of Values
Chart of Accounts
12. Check: As-Built Drawings A set of contract document drawings - marked up as construction proceeds - which show the exact location - geometry - and dimensions of all elements of the constructed project as installed.
Performance Bond
Technical Specifications
Record Drawings
Warranty
13. A formal notice sent by a contractor to an owner asserting the fact that the terms of the contract have been breached and compensation is being sought by the contractor from the owner.
Warranty
Checks and Balances
Claim
Commissioning
14. Also: Concealed Conditions; Latent Conditions Conditions or circumstances - physical or otherwise - which surface after a contract has been signed and which alter the circumstances or conditions on which the contract is based.
Schedule of Values
Sub-subcontractor
Changed Conditions
Preconstruction Phase
15. Check: Letter of Intent; Notice to Proceed A letter from an owner to a contractor stating that a contract has been awarded to the contractor and a contract will be forthcoming.
Preconstruction Phase
Notice of Award
Specifications
Specifications
16. Check: Commissioning; Beneficial Occupancy The period prior to owner occupancy when mechanical - electrical - and other systems are activated and the owner's operating and maintenance staff are instructed in their use.
Specifications
Construction Documents
Start-Up
General Contractor
17. An estimate of the final cost of a work item based on its Cost to Date and the estimated cost to complete it. The sum of the Cost to Date and the Estimated Cost to Complete.
Estimated Final Cost
Completion Schedule
Warranty
Occupancy Phase
18. The initial Design Phase on an architectural project when the A/E delineates the owner's needs in a general way.
Escrow Account
Final Design Phase
Contract Document Phase
Schematic Design Phase
19. An estimate of the cost still to be expended on a work-scope in order to complete it. The difference between the Cost to Date and the Estimated Final Cost.
Estimated Cost to Complete
Contingencies
Construction Management
Substantial Completion
20. Also: Supplementary Conditions Amendments to the General Conditions that change standard requirements to unique requirements - appropriate for a specific project.
Project Budget
Notice of Award
Special Conditions
Critical Path(s)
21. Money put into the custody of the third party by the first party for disbursement tot the second party. A brief temporary depository for progress payments until authorized for release according to the depositor's explicit instructions.
Escrow Account
Superintendent
Shop Drawings
Letter of Intent
22. A pledge from a third party (usually a surety company) to pay liquidated damages to the owner to the extent of the difference between the bonded contractor bid and the next highest bidder but not to exceed the face value of the bond; if the bonded co
Labor and Material Bond
Record Drawings
Long-Lead Items
Bid Bond
23. Also: Site Coordination Meeting - Coordination meeting A meeting dedicated essentially to contractor progress during the construction phase.
apparent Low Bidder
Project Manual
Sub-subcontractor
Progress Meeting
24. An individual employed by an owner to represent him on a project at the site of the work. The clerk-of- the-work's abilities - credentials - and responsibilities vary at the discretion of the owner.
Preconstruction Phase
Progress Meeting
General Conditions (of the Contract for Construction)
Clerk-of-the-Work
25. Also: Guarantee Assurance by a providing party that the work - material - and equipment under warranty will perform as promised or as required by contract.
Warranty
Project Team
Specifications
CM Services
26. A physical location where trade contractor proposals are fled the day before general contractor bids are to be received by an owner for pickup - opening - acceptance - or rejection by general contractors bidding the owner's project.
Bid Depository
Checks and Balances
Construction Manager
Design-Build (D-B) Contracting
27. Money put into the custody of the third party by the first party for disbursement tot the second party. A brief temporary depository for progress payments until authorized for release according to the depositor's explicit instructions.
apparent Low Bidder
Contract Documents
Escrow Account
Record Drawings
28. Detailed statements covering procedures - and quantitative and qualitative and qualitative information pertaining to material - products - and equipment to be incorporated into a project.
Shop Drawings
Lien
Specifications
Completion Schedule
29. The list of contractors that have survived prequalification tests.
Approved Bidders List
Subcontractor
Final Design Phase
Project Team
30. Also: As Builts; Check: Record Drawings Drawings produced during or after construction and amended to show the exact location - geometry - and dimensions of the constructed project. As-Built Drawings are not the same as Record Drawings.
Lump Sum Fee
Lien
Long-Lead Time
As-Built Drawings
31. Check: Notice of Award; Notice to Proceed A notice from an owner to a contractor stating that a contract will be awarded to the contractor providing certain events occur or specific conditions are met by the contractor.
Milestone
Reimbursable Expense
Letter of Intent
Preliminary Design Phase
32. An individual employed by an owner to represent him on a project at the site of the work. The clerk-of- the-work's abilities - credentials - and responsibilities vary at the discretion of the owner.
CM Services
Milestone Schedule
Notice of Award
Clerk-of-the-Work
33. The point at which both parties to a contract declare the other has satisfactorily completed its responsibilities under the contract.
Chart of Accounts
Direct Costs
Substantial Completion
Final Completion
34. Check: Notice of Award; Letter of Intent A notice from an owner directing a contractor to begin work on a contract - subject to specific stated conditions.
Performance Bond
Direct Material Costs
Escrow Account
Notice to Proceed
35. The time between the purchase date and delivery date of long-lead items.
Long-Lead Time
Progress Meeting
General Conditions (of the Contract for Construction)
Superintendent
36. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.
Project Meeting
Estimated Final Cost
Contract Administration
Approved Changes
37. The term used to describe the use of the overlapping expertise of each team member during team decision making.
Checks and Balances
Chart of Accounts
Sub-subcontractor
Final Design Phase
38. The documents which collectively form the contract between the contractor and the owner. They consist of the bidding documents less bidding information plus pre-award addenda and post-award Change Orders.
Warranty
Prime Contract
Contract Documents
Reimbursable Expense
39. A binding offer - usually expressed in dollars to provide specific services within clearly stated requirements.
Bid
Estimated Final Cost
Professional Liability Insurance
Chart of Accounts
40. A schedule of milestones spanning from the start of construction to occupancy - used as the main measure of progress to keep the project on schedule.
Contract Document Phase
Approved Bidders List
Milestone Schedule
Long-Lead Time
41. A physical location where trade contractor proposals are fled the day before general contractor bids are to be received by an owner for pickup - opening - acceptance - or rejection by general contractors bidding the owner's project.
Reimbursable Expense
Bid Depository
Warranty
Preconstruction Phase
42. The target cost of the project established by the owner and agreed to be achievable by the team. The Project Budget usually includes the cost of construction and the CM fee - plus any other line-item costs (land - legal fees - interest - design fees
Notice to Proceed
Preliminary Design Phase
Project Budget
Chart of Accounts
43. A technical review process; the close matching of engineering design to the value an owner derives from the design.
Commissioning
Notice to Proceed
Value Engineering
Occupancy Phase
44. Check: CM Project Manual Written information that augments the drawings. The Project Manual contains the General Conditions - Supplementary and Special Conditions - the Form of Contract - Addenda - Change Orders - Bidding Information and Proposal For
Project Budget
Contingencies
Commissioning
Project Manual
45. Selected strategic events of signal importance to progress used in the milestone schedule.
Lump Sum Fee
Contract Document Phase
Direct Costs
Milestone
46. Also: Product Data; Samples Detailed information provided by material and equipment suppliers demonstrating that the item provided meets the requirements of the contract documents.
Sub-subcontractor
Shop Drawings
Pre-design Phase
Direct Labor Costs
47. Line-item amounts in the project budget - dedicated to specific cost areas where oversight is an inherent problem in project delivery.
Contingencies
Design-Build (D-B) Contracting
Escrow Account
Preconstruction Phase
48. An estimate of the cost still to be expended on a work-scope in order to complete it. The difference between the Cost to Date and the Estimated Final Cost.
Commissioning
Estimated Cost to Complete
Notice of Award
Warranty
49. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c
Estimated Final Cost
Approved Bidders List
Critical Path(s)
Contract Documents
50. Also: Occupancy Schedule A schedule of the activities and events required to effect occupancy or the use of a facility for its intended purpose. It is used to determine if construction progress will meet the occupancy date.
Changed Conditions
Direct Labor Costs
Occupancy Phase
Completion Schedule