SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Construction Management
Start Test
Study First
Subjects
:
industries
,
construction
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Check: As-Built Drawings A set of contract document drawings - marked up as construction proceeds - which show the exact location - geometry - and dimensions of all elements of the constructed project as installed.
Record Drawings
Approved Changes
Lump Sum Fee
Bid Bond
2. A contractor that provides design and construction services under a single responsibility contract to an owner .
Fast-Track(ing)
Construction Schedule
Design-Build (D-B) Contractor
Prime Contract
3. The second request for uniform detailed information from prospective CM practitioners being screened for a project.
Budget Estimate
Design-Build (D-B) Contractor
RFP (Request For Proposal)
Direct Labor Costs
4. An estimate of the cost still to be expended on a work-scope in order to complete it. The difference between the Cost to Date and the Estimated Final Cost.
Progress Meeting
Lien
Estimated Cost to Complete
Bid
5. A form of the CM system where the construction manager guarantees - in addition to providing ACM services - a ceiling price to the owner for the cost of construction.
Owner's Representative
Construction Schedule
Guaranteed Maximum Price CM (GMPCM)
Construction Manager
6. Also: Construction Team; Check: Program Team Consists of the architect/engineer - construction manager - and owner - represented by their Level 1 - 2 - and 3 Persons - plus the designated leaders of contracted constructors.
Value Engineering
Project Team
Long-Lead Time
Specifications
7. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.
Pre-design Phase
Project Meeting
Prime Contract
Project Budget
8. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.
Long-Lead Items
Milestone
Subcontractor
Construction Management
9. The term used to describe the use of the overlapping expertise of each team member during team decision making.
Labor and Material Bond
Checks and Balances
Project Manual
Progress Meeting
10. Servicing the interactive provisions in the contracts for construction between the owner and the contractor(s).
Contract Administration
Special Conditions
Bid
Record Drawings
11. A person assigned to a project to represent the owner on the project team at one to the three management levels.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
12. Check: Notice of Award; Letter of Intent A notice from an owner directing a contractor to begin work on a contract - subject to specific stated conditions.
Owner's Representative
General Contractor
Notice to Proceed
As-Built Drawings
13. Also: Site Coordination Meeting - Coordination meeting A meeting dedicated essentially to contractor progress during the construction phase.
Progress Meeting
Long-Lead Items
Critical Path(s)
Bid Depository
14. The date on which a contractor reaches a point of completion - when subsequent interfacing contractors can productively begin work or the owner can occupy the project - in whole or in part - without undo interference.
Completion Schedule
Construction Schedule
Guaranteed Maximum Price CM (GMPCM)
Substantial Completion
15. A contractor that provides design and construction services under a single responsibility contract to an owner .
Professional Liability Insurance
Pre-design Phase
Approved Bidders List
Design-Build (D-B) Contractor
16. An estimate of the cost still to be expended on a work-scope in order to complete it. The difference between the Cost to Date and the Estimated Final Cost.
Progress Meeting
Project Team
Estimated Cost to Complete
Superintendent
17. A physical location where trade contractor proposals are fled the day before general contractor bids are to be received by an owner for pickup - opening - acceptance - or rejection by general contractors bidding the owner's project.
Claim
Bid Depository
Budget Estimate
General Contractor
18. An agreement by which a party accepts responsibility for fulfilling an obligation.
Design-Build (D-B) Contracting
Construction Manager
Guarantee
Lump Sum Fee
19. Also: Supplementary Conditions Amendments to the General Conditions that change standard requirements to unique requirements - appropriate for a specific project.
Milestone Schedule
Prime Contract
Special Conditions
Bid Bond
20. Also: Product Data; Samples Detailed information provided by material and equipment suppliers demonstrating that the item provided meets the requirements of the contract documents.
Technical Specifications
Shop Drawings
Project Meeting
Project Manual
21. A technical review process; the close matching of engineering design to the value an owner derives from the design.
Bid Depository
Project Team
Notice to Proceed
Value Engineering
22. Drawings - technical specification - and addenda; the contract documents that refer to the physical construction requirements established by the A/E.
Construction Schedule
Direct Material Costs
CM Services
Construction Documents
23. A pledge from a third party (usually a surety company) to pay liquidated damages to the owner to the extent of the difference between the bonded contractor bid and the next highest bidder but not to exceed the face value of the bond; if the bonded co
Substantial Completion
Technical Specifications
Bid Bond
Guaranteed Maximum Price CM (GMPCM)
24. Check: Notice of Award; Letter of Intent A notice from an owner directing a contractor to begin work on a contract - subject to specific stated conditions.
Notice to Proceed
Value Engineering
Design Development Phase
Completion Schedule
25. Also: Site Coordination Meeting - Coordination meeting A meeting dedicated essentially to contractor progress during the construction phase.
Progress Meeting
Bid
Lump Sum Fee
RFP (Request For Proposal)
26. The time between the purchase date and delivery date of long-lead items.
Construction Documents
Project Meeting
Lump Sum Fee
Approved Bidders List
27. An estimate of the final cost of a work item based on its Cost to Date and the estimated cost to complete it. The sum of the Cost to Date and the Estimated Cost to Complete.
Value Engineering
Reimbursable Expense
Long-Lead Items
Estimated Final Cost
28. Changes of any nature in contract requirements which have been agreed upon through a change approval process and approved by the owner.
Approved Changes
Construction Management
Lump Sum Fee
Labor and Material Bond
29. Also: Detailed Construction Schedule A graphic - tabular or narrative representation or depiction of the construction portion of the project- delivery process - showing activities and durations or activities in sequential order.
Direct Labor Costs
Approved Changes
Value Engineering
Construction Schedule
30. A business entity that provides independent contractor services to owners through the use of subcontractors when using the general contracting system.
Claim
Design Development Phase
General Contractor
Start-Up
31. Detailed statements covering procedures - and quantitative and qualitative and qualitative information pertaining to material - products - and equipment to be incorporated into a project.
Progress Meeting
Specifications
Commissioning
Technical Specifications
32. The term used to describe the use of the overlapping expertise of each team member during team decision making.
Construction Schedule
Guaranteed Maximum Price CM (GMPCM)
Long-Lead Time
Checks and Balances
33. Also: Contract Modification The document that alters the contract amount - contract time - or contract requirements of the original contract entered into by the owner and a contractor.
Milestone Schedule
Bid Bond
Contingencies
Change Order
34. Check: Labor and Material Bond; Surety A guarantee provided by a surety to complete a project according to the terms of the contract documents in the event that the bonded contractor defaults on the contract or to pay the owner the face value of the
Performance Bond
Change Order
Shop Drawings
Technical Specifications
35. The breakdown of a lump sum price into sub-items and sub-costs for identifiable construction elements - which can be evaluated by examination for contractor progress payment purposes.
Schematic Design Phase
Changed Conditions
Lump Sum Fee
Schedule of Values
36. All required phases prior to the start of construction.
Design-Build (D-B) Contracting
Critical Path(s)
Record Drawings
Preconstruction Phase
37. Also: Supplementary Conditions Amendments to the General Conditions that change standard requirements to unique requirements - appropriate for a specific project.
Drawings
Project Budget
Special Conditions
Record Drawings
38. Also: Concealed Conditions; Latent Conditions Conditions or circumstances - physical or otherwise - which surface after a contract has been signed and which alter the circumstances or conditions on which the contract is based.
RFP (Request For Proposal)
Drawings
Changed Conditions
Escrow Account
39. Drawings - technical specification - and addenda; the contract documents that refer to the physical construction requirements established by the A/E.
Contract Documents
Labor and Material Bond
Progress Payment
Construction Documents
40. A business entity that provides independent contractor services to owners through the use of subcontractors when using the general contracting system.
General Contractor
Performance Bond
Value Engineering
Budget Estimate
41. A person assigned to a project to represent the owner on the project team at one to the three management levels.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
42. The term used on architectural projects to describe the transitional phase from the Schematic Phase to the Contract Document during design.
Drawings
Construction Manager
Long-Lead Time
Design Development Phase
43. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Direct Costs
Record Drawings
Checks and Balances
Reimbursable Expense
44. Servicing the interactive provisions in the contracts for construction between the owner and the contractor(s).
Prime Contract
Estimated Cost to Complete
Direct Costs
Contract Administration
45. Also: Occupancy Schedule A schedule of the activities and events required to effect occupancy or the use of a facility for its intended purpose. It is used to determine if construction progress will meet the occupancy date.
Project Team
Long-Lead Time
Completion Schedule
Occupancy Phase
46. Check: Letter of Intent; Notice to Proceed A letter from an owner to a contractor stating that a contract has been awarded to the contractor and a contract will be forthcoming.
Direct Labor Costs
Estimated Final Cost
Notice of Award
As-Built Drawings
47. Detailed statements covering procedures - and quantitative and qualitative and qualitative information pertaining to material - products - and equipment to be incorporated into a project.
Specifications
Bid Depository
Construction Schedule
Construction Management
48. Also: Errors and Omissions Insurance Insurance provided by design professionals and construction managers that protects the owner against the financial results of negligent acts by the insured.
Changed Conditions
Lien
Direct Material Costs
Professional Liability Insurance
49. Selected strategic events of signal importance to progress used in the milestone schedule.
Checks and Balances
Preconstruction Phase
Performance Bond
Milestone
50. Also: Construction Team; Check: Program Team Consists of the architect/engineer - construction manager - and owner - represented by their Level 1 - 2 - and 3 Persons - plus the designated leaders of contracted constructors.
Special Conditions
Project Team
Conditions of the Contract
Clerk-of-the-Work