SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Construction Management
Start Test
Study First
Subjects
:
industries
,
construction
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A fixed dollar amount which includes all costs of services including overhead and profit.
Guarantee
Lump Sum Fee
Pre-design Phase
Commissioning
2. Selected strategic events of signal importance to progress used in the milestone schedule.
CM Services
RFP (Request For Proposal)
Milestone
Direct Labor Costs
3. The term used to describe the use of the overlapping expertise of each team member during team decision making.
Prime Contract
Checks and Balances
Construction Manager
Warranty
4. The designation used by engineers for the last portion of the design process prior to bidding.
Commissioning
apparent Low Bidder
Start-Up
Final Design Phase
5. Term that refers to the General Conditions and the Supplementary and Special Conditions of the contract for construction.
Conditions of the Contract
Guaranteed Maximum Price CM (GMPCM)
Guarantee
Direct Labor Costs
6. The target cost of the project established by the owner and agreed to be achievable by the team. The Project Budget usually includes the cost of construction and the CM fee - plus any other line-item costs (land - legal fees - interest - design fees
Guarantee
Escrow Account
Project Budget
Reimbursable Expense
7. A formal notice sent by a contractor to an owner asserting the fact that the terms of the contract have been breached and compensation is being sought by the contractor from the owner.
Claim
Occupancy Phase
Performance Bond
Warranty
8. A contractor that provides design and construction services under a single responsibility contract to an owner .
Performance Bond
Sub-subcontractor
Design-Build (D-B) Contractor
Construction Manager
9. Also: Field CM; Level 3 Manager; Level 3 Person; Superintendent - Site Manager A person designated by the CM firm to interface with the owner's and A/E's representatives on the project team at the third management level. A person located at the site
Change Order
Field Construction Manager
Bid Bond
Progress Meeting
10. Also: Mechanic's Lien The right to take - hold - or sell the property of a debtor as security or payment for a debt.
Drawings
Lien
Construction Budget
Value Engineering
11. A schedule of milestones spanning from the start of construction to occupancy - used as the main measure of progress to keep the project on schedule.
Project Budget
RFP (Request For Proposal)
Lien
Milestone Schedule
12. The scope of services provided by a construction manager and available to owners in whole or in part. CM services are not consistent in scope or performance from one CM firm to another.
Completion Schedule
CM Services
Milestone Schedule
Preconstruction Phase
13. The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors - construction support items other purchased labor - material and equipment - and the construction manager's cost but not th
Construction Budget
Project Budget
Prime Contract
Contingencies
14. The final phase of design on an architectural project when construction documents are completed and bidding documents formulated.
Lien
Checks and Balances
Contract Document Phase
Completion Schedule
15. Also: Account Codes; Codes of Accounts An alpha/numeric identification system for budget line items that ensures that project expenditures are properly debited/credited in the project budget as payments are made in behalf of the project.
Pre-design Phase
Chart of Accounts
Start-Up
Direct Labor Costs
16. A pledge from a third party (usually a surety company) to pay liquidated damages to the owner to the extent of the difference between the bonded contractor bid and the next highest bidder but not to exceed the face value of the bond; if the bonded co
Design-Build (D-B) Contractor
Schedule of Values
Project Manual
Bid Bond
17. Also: Construction Team; Check: Program Team Consists of the architect/engineer - construction manager - and owner - represented by their Level 1 - 2 - and 3 Persons - plus the designated leaders of contracted constructors.
Critical Path(s)
Construction Schedule
Performance Bond
Project Team
18. Check: CM Project Manual Written information that augments the drawings. The Project Manual contains the General Conditions - Supplementary and Special Conditions - the Form of Contract - Addenda - Change Orders - Bidding Information and Proposal For
Project Manual
Preliminary Design Phase
Changed Conditions
Project Budget
19. The term used on architectural projects to describe the transitional phase from the Schematic Phase to the Contract Document during design.
General Conditions (of the Contract for Construction)
Shop Drawings
Bid
Design Development Phase
20. A business entity that provides independent contractor services to owners through the use of subcontractors when using the general contracting system.
General Contractor
Design-Build (D-B) Contractor
Occupancy Phase
Escrow Account
21. The list of contractors that have survived prequalification tests.
Letter of Intent
Direct Material Costs
Owner's Representative
Approved Bidders List
22. An estimate of cost based on rough or incomplete information - with a stated degree of accuracy. The more information available - the more accurate the estimate. Loosely called a 'ballpark' estimate.
CM Services
Long-Lead Time
Budget Estimate
Change Order
23. Selected strategic events of signal importance to progress used in the milestone schedule.
Design-Build (D-B) Contracting
Guaranteed Maximum Price CM (GMPCM)
Budget Estimate
Milestone
24. Partial payments on a contractor's contract amount - periodically paid by the owner for work accomplished by the contractor to date.
Progress Payment
General Conditions (of the Contract for Construction)
Project Manual
Claim
25. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Direct Costs
Design Development Phase
Approved Bidders List
Changed Conditions
26. A contractor who has a contract with a subcontractor.
Preconstruction Phase
Budget Estimate
Technical Specifications
Sub-subcontractor
27. Check: Notice of Award; Notice to Proceed A notice from an owner to a contractor stating that a contract will be awarded to the contractor providing certain events occur or specific conditions are met by the contractor.
Start-Up
Letter of Intent
Project Team
Direct Material Costs
28. The process of designing portions of a project while portions already designed are under construction. A series of controlled design-build sequences that collectively constitute a complete project.
Final Design Phase
Construction Manager
Fast-Track(ing)
Contingencies
29. All required phases prior to the start of construction.
As-Built Drawings
Design-Build (D-B) Contracting
As-Built Drawings
Preconstruction Phase
30. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c
Critical Path(s)
Construction Management
Changed Conditions
Notice to Proceed
31. Also: Guarantee Assurance by a providing party that the work - material - and equipment under warranty will perform as promised or as required by contract.
Construction Budget
Conditions of the Contract
Warranty
Direct Costs
32. Check: Labor and Material Bond; Surety A guarantee provided by a surety to complete a project according to the terms of the contract documents in the event that the bonded contractor defaults on the contract or to pay the owner the face value of the
Performance Bond
Special Conditions
Construction Management
Design-Build (D-B) Contractor
33. Check: Letter of Intent; Notice to Proceed A letter from an owner to a contractor stating that a contract has been awarded to the contractor and a contract will be forthcoming.
Escrow Account
Design Development Phase
Estimated Cost to Complete
Notice of Award
34. A formal notice sent by a contractor to an owner asserting the fact that the terms of the contract have been breached and compensation is being sought by the contractor from the owner.
Lien
Claim
Contingencies
Critical Path(s)
35. Also: Supplementary Conditions Amendments to the General Conditions that change standard requirements to unique requirements - appropriate for a specific project.
Special Conditions
Estimated Final Cost
Project Meeting
Substantial Completion
36. An estimate of cost based on rough or incomplete information - with a stated degree of accuracy. The more information available - the more accurate the estimate. Loosely called a 'ballpark' estimate.
Budget Estimate
Conditions of the Contract
Chart of Accounts
Preliminary Design Phase
37. The final phase of design on an architectural project when construction documents are completed and bidding documents formulated.
Contract Document Phase
Clerk-of-the-Work
Milestone
Schematic Design Phase
38. The list of contractors that have survived prequalification tests.
Shop Drawings
Milestone Schedule
Lump Sum Fee
Approved Bidders List
39. Also: Errors and Omissions Insurance Insurance provided by design professionals and construction managers that protects the owner against the financial results of negligent acts by the insured.
Direct Labor Costs
Construction Manager
Professional Liability Insurance
Conditions of the Contract
40. Also: Warranty/Guarantee Phase; Warranty Phase; Guarantee Phase A stipulated length of time following the construction phase - during which contractors are bonded to ensure that materials - equipment - and workmanship meet the requirements of their c
Completion Schedule
Occupancy Phase
Critical Path(s)
Project Team
41. Detailed statements covering procedures - and quantitative and qualitative and qualitative information pertaining to material - products - and equipment to be incorporated into a project.
Guaranteed Maximum Price CM (GMPCM)
Conditions of the Contract
Specifications
Project Manual
42. Drawings - technical specification - and addenda; the contract documents that refer to the physical construction requirements established by the A/E.
Construction Documents
Project Meeting
Bid Bond
Construction Management
43. Servicing the interactive provisions in the contracts for construction between the owner and the contractor(s).
Construction Budget
Contract Administration
Long-Lead Time
Project Team
44. A job title usually reserved for the administrative level person who supervises the work of an on-site contractor .
Superintendent
Life-Cycle Cost
Estimated Final Cost
As-Built Drawings
45. Term that refers to the General Conditions and the Supplementary and Special Conditions of the contract for construction.
Notice of Award
Start-Up
Conditions of the Contract
Performance Bond
46. A form of the CM system where the construction manager guarantees - in addition to providing ACM services - a ceiling price to the owner for the cost of construction.
Guaranteed Maximum Price CM (GMPCM)
Contract Documents
Preliminary Design Phase
Letter of Intent
47. Graphic representations showing location - geometry - and dimensions of a project or its elements in sufficient detail to facilitate construction.
Drawings
General Contractor
Progress Meeting
Conditions of the Contract
48. Also: As Builts; Check: Record Drawings Drawings produced during or after construction and amended to show the exact location - geometry - and dimensions of the constructed project. As-Built Drawings are not the same as Record Drawings.
General Conditions (of the Contract for Construction)
General Contractor
As-Built Drawings
Construction Documents
49. An individual employed by an owner to represent him on a project at the site of the work. The clerk-of- the-work's abilities - credentials - and responsibilities vary at the discretion of the owner.
Clerk-of-the-Work
Estimated Cost to Complete
Guaranteed Maximum Price CM (GMPCM)
Project Team
50. A technical review process; the close matching of engineering design to the value an owner derives from the design.
Life-Cycle Cost
Labor and Material Bond
Bid Depository
Value Engineering