SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Construction Management
Start Test
Study First
Subjects
:
industries
,
construction
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The initial Design Phase on an architectural project when the A/E delineates the owner's needs in a general way.
Preliminary Design Phase
Critical Path(s)
Schematic Design Phase
Life-Cycle Cost
2. Check: Notice of Award; Notice to Proceed A notice from an owner to a contractor stating that a contract will be awarded to the contractor providing certain events occur or specific conditions are met by the contractor.
Lump Sum Fee
Record Drawings
Project Manual
Letter of Intent
3. Check: Labor and Material Bond; Surety A guarantee provided by a surety to complete a project according to the terms of the contract documents in the event that the bonded contractor defaults on the contract or to pay the owner the face value of the
Notice of Award
Construction Manager
Specifications
Performance Bond
4. A contractor who has a contract with a subcontractor.
Fast-Track(ing)
Approved Changes
Sub-subcontractor
Performance Bond
5. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c
Project Manual
Changed Conditions
Completion Schedule
Critical Path(s)
6. A contractor that provides design and construction services under a single responsibility contract to an owner .
RFP (Request For Proposal)
Design-Build (D-B) Contractor
Estimated Cost to Complete
Contingencies
7. An estimate of the final cost of a work item based on its Cost to Date and the estimated cost to complete it. The sum of the Cost to Date and the Estimated Cost to Complete.
Milestone Schedule
Schematic Design Phase
Record Drawings
Estimated Final Cost
8. Changes of any nature in contract requirements which have been agreed upon through a change approval process and approved by the owner.
Clerk-of-the-Work
Critical Path(s)
General Conditions (of the Contract for Construction)
Approved Changes
9. Selected strategic events of signal importance to progress used in the milestone schedule.
Milestone
apparent Low Bidder
Design-Build (D-B) Contractor
Start-Up
10. Check: Notice of Award; Letter of Intent A notice from an owner directing a contractor to begin work on a contract - subject to specific stated conditions.
RFP (Request For Proposal)
Claim
Drawings
Notice to Proceed
11. The process of designing portions of a project while portions already designed are under construction. A series of controlled design-build sequences that collectively constitute a complete project.
Fast-Track(ing)
RFP (Request For Proposal)
Life-Cycle Cost
Design-Build (D-B) Contractor
12. The documents which collectively form the contract between the contractor and the owner. They consist of the bidding documents less bidding information plus pre-award addenda and post-award Change Orders.
Direct Costs
Long-Lead Time
Contract Documents
Start-Up
13. A technical review process; the close matching of engineering design to the value an owner derives from the design.
Direct Material Costs
Life-Cycle Cost
Value Engineering
Professional Liability Insurance
14. A fixed dollar amount which includes all costs of services including overhead and profit.
Lump Sum Fee
Design Development Phase
Design-Build (D-B) Contracting
Conditions of the Contract
15. A person assigned to a project to represent the owner on the project team at one to the three management levels.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
16. An agreement by which a party accepts responsibility for fulfilling an obligation.
Letter of Intent
Guarantee
Guaranteed Maximum Price CM (GMPCM)
Final Design Phase
17. Also: Detailed Construction Schedule A graphic - tabular or narrative representation or depiction of the construction portion of the project- delivery process - showing activities and durations or activities in sequential order.
Critical Path(s)
Construction Schedule
Value Engineering
Special Conditions
18. Also: Product Data; Samples Detailed information provided by material and equipment suppliers demonstrating that the item provided meets the requirements of the contract documents.
Approved Bidders List
Lump Sum Fee
Shop Drawings
Completion Schedule
19. Also: Mechanic's Lien The right to take - hold - or sell the property of a debtor as security or payment for a debt.
Escrow Account
Bid Bond
Lien
Schedule of Values
20. Drawings - technical specification - and addenda; the contract documents that refer to the physical construction requirements established by the A/E.
Construction Documents
Changed Conditions
Escrow Account
Letter of Intent
21. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Commissioning
Final Completion
Direct Labor Costs
apparent Low Bidder
22. A physical location where trade contractor proposals are fled the day before general contractor bids are to be received by an owner for pickup - opening - acceptance - or rejection by general contractors bidding the owner's project.
Bid Bond
Start-Up
Bid Depository
Notice to Proceed
23. The list of contractors that have survived prequalification tests.
Lien
Approved Bidders List
Design Development Phase
Construction Schedule
24. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Notice of Award
General Conditions (of the Contract for Construction)
RFP (Request For Proposal)
Direct Costs
25. A formal notice sent by a contractor to an owner asserting the fact that the terms of the contract have been breached and compensation is being sought by the contractor from the owner.
Fast-Track(ing)
Claim
Occupancy Phase
Approved Changes
26. Check: As-Built Drawings A set of contract document drawings - marked up as construction proceeds - which show the exact location - geometry - and dimensions of all elements of the constructed project as installed.
Record Drawings
Progress Meeting
CM Services
Substantial Completion
27. A business entity that provides independent contractor services to owners through the use of subcontractors when using the general contracting system.
General Conditions (of the Contract for Construction)
Critical Path(s)
Superintendent
General Contractor
28. Term that refers to the General Conditions and the Supplementary and Special Conditions of the contract for construction.
Warranty
Conditions of the Contract
Contract Documents
Direct Costs
29. A professional service that applies effective management techniques to the planning - design - and construction of a project form inception to completion for the purpose of controlling time - cost and quality. (As approved by CMAA) OR A project deliv
Labor and Material Bond
Construction Manager
Special Conditions
Construction Management
30. Also: Guarantee Assurance by a providing party that the work - material - and equipment under warranty will perform as promised or as required by contract.
Milestone
Bid Bond
Lien
Warranty
31. An estimate of the final cost of a work item based on its Cost to Date and the estimated cost to complete it. The sum of the Cost to Date and the Estimated Cost to Complete.
Estimated Final Cost
Prime Contract
Letter of Intent
Subcontractor
32. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.
Project Meeting
Bid
Start-Up
Long-Lead Items
33. The term used to describe the use of the overlapping expertise of each team member during team decision making.
Conditions of the Contract
Checks and Balances
Start-Up
Contract Document Phase
34. A contractor who has a contract with a prime contractor.
Project Manual
Subcontractor
Direct Costs
Change Order
35. A formal notice sent by a contractor to an owner asserting the fact that the terms of the contract have been breached and compensation is being sought by the contractor from the owner.
Design-Build (D-B) Contractor
Claim
Design-Build (D-B) Contracting
Completion Schedule
36. See: Start-up; Beneficial Occupancy The process at or near construction completion when a facility is tried out (put into use) to see if it functions as designed. Usually applied to manufacturing type projects.
Reimbursable Expense
Specifications
Commissioning
Preconstruction Phase
37. The time between the purchase date and delivery date of long-lead items.
Bid Bond
Lump Sum Fee
Sub-subcontractor
Letter of Intent
38. The initial Design Phase on an architectural project when the A/E delineates the owner's needs in a general way.
Schedule of Values
Schematic Design Phase
Estimated Final Cost
RFP (Request For Proposal)
39. The process of designing portions of a project while portions already designed are under construction. A series of controlled design-build sequences that collectively constitute a complete project.
Bid Bond
Fast-Track(ing)
Record Drawings
Change Order
40. The cost of purchasing - installing - owning - operating - and maintaining a construction element over the life of the facility.
Shop Drawings
Specifications
Final Completion
Life-Cycle Cost
41. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Fast-Track(ing)
Schedule of Values
Substantial Completion
Direct Labor Costs
42. A binding offer - usually expressed in dollars to provide specific services within clearly stated requirements.
Estimated Cost to Complete
Long-Lead Time
Project Meeting
Bid
43. A business entity that provides independent contractor services to owners through the use of subcontractors when using the general contracting system.
Bid Bond
Shop Drawings
Contract Document Phase
General Contractor
44. The breakdown of a lump sum price into sub-items and sub-costs for identifiable construction elements - which can be evaluated by examination for contractor progress payment purposes.
Direct Costs
Construction Schedule
Schedule of Values
Fast-Track(ing)
45. A fixed dollar amount which includes all costs of services including overhead and profit.
Final Completion
Progress Payment
Lump Sum Fee
Estimated Cost to Complete
46. Check: CM Project Manual Written information that augments the drawings. The Project Manual contains the General Conditions - Supplementary and Special Conditions - the Form of Contract - Addenda - Change Orders - Bidding Information and Proposal For
Reimbursable Expense
Field Construction Manager
Project Manual
Shop Drawings
47. The bidder who has submitted the lowest competitive proposal as determined by a cursory examination of the bids submitted.
Escrow Account
Approved Changes
apparent Low Bidder
Drawings
48. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.
Technical Specifications
Chart of Accounts
Long-Lead Items
Fast-Track(ing)
49. A schedule of milestones spanning from the start of construction to occupancy - used as the main measure of progress to keep the project on schedule.
Long-Lead Time
Claim
Lump Sum Fee
Milestone Schedule
50. An estimate of the cost still to be expended on a work-scope in order to complete it. The difference between the Cost to Date and the Estimated Final Cost.
Prime Contract
Chart of Accounts
Estimated Cost to Complete
Direct Labor Costs