SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Construction Management
Start Test
Study First
Subjects
:
industries
,
construction
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Check: CM Project Manual Written information that augments the drawings. The Project Manual contains the General Conditions - Supplementary and Special Conditions - the Form of Contract - Addenda - Change Orders - Bidding Information and Proposal For
Contingencies
Direct Labor Costs
Construction Manager
Project Manual
2. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c
Critical Path(s)
Progress Payment
Escrow Account
Project Team
3. The documents which collectively form the contract between the contractor and the owner. They consist of the bidding documents less bidding information plus pre-award addenda and post-award Change Orders.
Approved Changes
Progress Payment
Contract Documents
Schematic Design Phase
4. The breakdown of a lump sum price into sub-items and sub-costs for identifiable construction elements - which can be evaluated by examination for contractor progress payment purposes.
Budget Estimate
Specifications
Progress Payment
Schedule of Values
5. A contractor who has a contract with a subcontractor.
Contract Administration
Sub-subcontractor
Fast-Track(ing)
Checks and Balances
6. Also: Concealed Conditions; Latent Conditions Conditions or circumstances - physical or otherwise - which surface after a contract has been signed and which alter the circumstances or conditions on which the contract is based.
Approved Bidders List
CM Services
Changed Conditions
Design-Build (D-B) Contracting
7. The process of designing portions of a project while portions already designed are under construction. A series of controlled design-build sequences that collectively constitute a complete project.
Construction Schedule
Fast-Track(ing)
Lien
Project Meeting
8. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.
Changed Conditions
Project Meeting
Start-Up
Construction Documents
9. The bidder who has submitted the lowest competitive proposal as determined by a cursory examination of the bids submitted.
Escrow Account
apparent Low Bidder
Value Engineering
Fast-Track(ing)
10. A binding offer - usually expressed in dollars to provide specific services within clearly stated requirements.
Notice to Proceed
Bid
Substantial Completion
Schematic Design Phase
11. A job title usually reserved for the administrative level person who supervises the work of an on-site contractor .
Letter of Intent
Project Budget
Construction Schedule
Superintendent
12. The process of designing portions of a project while portions already designed are under construction. A series of controlled design-build sequences that collectively constitute a complete project.
Fast-Track(ing)
Progress Payment
Preconstruction Phase
Contingencies
13. A business entity that provides independent contractor services to owners through the use of subcontractors when using the general contracting system.
Change Order
General Contractor
Value Engineering
Completion Schedule
14. The bidder who has submitted the lowest competitive proposal as determined by a cursory examination of the bids submitted.
Clerk-of-the-Work
Direct Material Costs
apparent Low Bidder
Lien
15. Applies to engineering projects; the initial design effort following signing of the owner; engineer agreement. It is followed by the Final Design Phase.
Record Drawings
Specifications
Preliminary Design Phase
Chart of Accounts
16. Partial payments on a contractor's contract amount - periodically paid by the owner for work accomplished by the contractor to date.
Owner's Representative
Project Manual
Design-Build (D-B) Contractor
Progress Payment
17. Also: Site Coordination Meeting - Coordination meeting A meeting dedicated essentially to contractor progress during the construction phase.
Conditions of the Contract
Construction Documents
Progress Meeting
Occupancy Phase
18. The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors - construction support items other purchased labor - material and equipment - and the construction manager's cost but not th
Construction Budget
Design-Build (D-B) Contractor
Labor and Material Bond
Clerk-of-the-Work
19. Costs accruing from expended labor excluding the bonus portion of overtime - insurances - and payroll taxes.
Conditions of the Contract
Direct Material Costs
Contract Administration
Schematic Design Phase
20. The time between the purchase date and delivery date of long-lead items.
Start-Up
Approved Bidders List
Project Team
Lump Sum Fee
21. Servicing the interactive provisions in the contracts for construction between the owner and the contractor(s).
Milestone Schedule
Performance Bond
Contract Administration
Construction Schedule
22. Also: Guarantee Assurance by a providing party that the work - material - and equipment under warranty will perform as promised or as required by contract.
Warranty
Chart of Accounts
Estimated Cost to Complete
Subcontractor
23. Also: Supplementary Conditions Amendments to the General Conditions that change standard requirements to unique requirements - appropriate for a specific project.
Bid Bond
Change Order
Pre-design Phase
Special Conditions
24. Also: Product Data; Samples Detailed information provided by material and equipment suppliers demonstrating that the item provided meets the requirements of the contract documents.
Direct Material Costs
RFP (Request For Proposal)
Shop Drawings
Professional Liability Insurance
25. Written criteria that augment the drawings pertaining to the technical construction of the project that cannot be conveniently included on the plans.
Subcontractor
Technical Specifications
Construction Documents
Professional Liability Insurance
26. A formal notice sent by a contractor to an owner asserting the fact that the terms of the contract have been breached and compensation is being sought by the contractor from the owner.
Conditions of the Contract
Claim
Escrow Account
Progress Meeting
27. An agreement by which a party accepts responsibility for fulfilling an obligation.
Lump Sum Fee
Guarantee
CM Services
Construction Documents
28. The target cost of the project established by the owner and agreed to be achievable by the team. The Project Budget usually includes the cost of construction and the CM fee - plus any other line-item costs (land - legal fees - interest - design fees
Superintendent
Long-Lead Time
Design-Build (D-B) Contracting
Project Budget
29. Check: Notice of Award; Letter of Intent A notice from an owner directing a contractor to begin work on a contract - subject to specific stated conditions.
Commissioning
Letter of Intent
Preliminary Design Phase
Notice to Proceed
30. Also: Guarantee Assurance by a providing party that the work - material - and equipment under warranty will perform as promised or as required by contract.
Specifications
Long-Lead Items
Design Development Phase
Warranty
31. An estimate of the cost still to be expended on a work-scope in order to complete it. The difference between the Cost to Date and the Estimated Final Cost.
Estimated Cost to Complete
Long-Lead Items
Design Development Phase
Bid Bond
32. Applies to engineering projects; the initial design effort following signing of the owner; engineer agreement. It is followed by the Final Design Phase.
Direct Material Costs
Budget Estimate
Milestone Schedule
Preliminary Design Phase
33. The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors - construction support items other purchased labor - material and equipment - and the construction manager's cost but not th
Construction Budget
Sub-subcontractor
Warranty
Technical Specifications
34. Graphic representations showing location - geometry - and dimensions of a project or its elements in sufficient detail to facilitate construction.
Occupancy Phase
General Conditions (of the Contract for Construction)
Drawings
Substantial Completion
35. Also: Contract Modification The document that alters the contract amount - contract time - or contract requirements of the original contract entered into by the owner and a contractor.
Substantial Completion
Superintendent
Bid Depository
Change Order
36. The designation used by engineers for the last portion of the design process prior to bidding.
Field Construction Manager
Warranty
Bid Depository
Final Design Phase
37. Also: Account Codes; Codes of Accounts An alpha/numeric identification system for budget line items that ensures that project expenditures are properly debited/credited in the project budget as payments are made in behalf of the project.
Design Development Phase
Chart of Accounts
Owner's Representative
Budget Estimate
38. Also: Occupancy Schedule A schedule of the activities and events required to effect occupancy or the use of a facility for its intended purpose. It is used to determine if construction progress will meet the occupancy date.
Construction Manager
Specifications
Completion Schedule
Conditions of the Contract
39. Also: Concealed Conditions; Latent Conditions Conditions or circumstances - physical or otherwise - which surface after a contract has been signed and which alter the circumstances or conditions on which the contract is based.
Budget Estimate
Conditions of the Contract
Changed Conditions
Construction Documents
40. Selected strategic events of signal importance to progress used in the milestone schedule.
Project Manual
CM Services
Long-Lead Items
Milestone
41. The date on which a contractor reaches a point of completion - when subsequent interfacing contractors can productively begin work or the owner can occupy the project - in whole or in part - without undo interference.
Substantial Completion
Escrow Account
Direct Labor Costs
Guarantee
42. Detailed statements covering procedures - and quantitative and qualitative and qualitative information pertaining to material - products - and equipment to be incorporated into a project.
Subcontractor
Superintendent
Specifications
Bid Depository
43. The second request for uniform detailed information from prospective CM practitioners being screened for a project.
RFP (Request For Proposal)
General Conditions (of the Contract for Construction)
Direct Labor Costs
Project Budget
44. The initial Design Phase on an architectural project when the A/E delineates the owner's needs in a general way.
Construction Management
Critical Path(s)
Schematic Design Phase
Conditions of the Contract
45. Graphic representations showing location - geometry - and dimensions of a project or its elements in sufficient detail to facilitate construction.
Performance Bond
Drawings
RFP (Request For Proposal)
Labor and Material Bond
46. An individual employed by an owner to represent him on a project at the site of the work. The clerk-of- the-work's abilities - credentials - and responsibilities vary at the discretion of the owner.
Notice to Proceed
Drawings
Contract Document Phase
Clerk-of-the-Work
47. A technical review process; the close matching of engineering design to the value an owner derives from the design.
Life-Cycle Cost
Value Engineering
Design-Build (D-B) Contracting
Prime Contract
48. An estimate of cost based on rough or incomplete information - with a stated degree of accuracy. The more information available - the more accurate the estimate. Loosely called a 'ballpark' estimate.
Milestone
Budget Estimate
Sub-subcontractor
Completion Schedule
49. Check: Labor and Material Bond; Surety A guarantee provided by a surety to complete a project according to the terms of the contract documents in the event that the bonded contractor defaults on the contract or to pay the owner the face value of the
Pre-design Phase
Drawings
Notice of Award
Performance Bond
50. An estimate of the cost still to be expended on a work-scope in order to complete it. The difference between the Cost to Date and the Estimated Final Cost.
Changed Conditions
Project Team
General Conditions (of the Contract for Construction)
Estimated Cost to Complete
Can you answer 50 questions in 15 minutes?
Let me suggest you:
Browse all subjects
Browse all tests
Most popular tests
Major Subjects
Tests & Exams
AP
CLEP
DSST
GRE
SAT
GMAT
Certifications
CISSP go to https://www.isc2.org/
PMP
ITIL
RHCE
MCTS
More...
IT Skills
Android Programming
Data Modeling
Objective C Programming
Basic Python Programming
Adobe Illustrator
More...
Business Skills
Advertising Techniques
Business Accounting Basics
Business Strategy
Human Resource Management
Marketing Basics
More...
Soft Skills
Body Language
People Skills
Public Speaking
Persuasion
Job Hunting And Resumes
More...
Vocabulary
GRE Vocab
SAT Vocab
TOEFL Essential Vocab
Basic English Words For All
Global Words You Should Know
Business English
More...
Languages
AP German Vocab
AP Latin Vocab
SAT Subject Test: French
Italian Survival
Norwegian Survival
More...
Engineering
Audio Engineering
Computer Science Engineering
Aerospace Engineering
Chemical Engineering
Structural Engineering
More...
Health Sciences
Basic Nursing Skills
Health Science Language Fundamentals
Veterinary Technology Medical Language
Cardiology
Clinical Surgery
More...
English
Grammar Fundamentals
Literary And Rhetorical Vocab
Elements Of Style Vocab
Introduction To English Major
Complete Advanced Sentences
Literature
Homonyms
More...
Math
Algebra Formulas
Basic Arithmetic: Measurements
Metric Conversions
Geometric Properties
Important Math Facts
Number Sense Vocab
Business Math
More...
Other Major Subjects
Science
Economics
History
Law
Performing-arts
Cooking
Logic & Reasoning
Trivia
Browse all subjects
Browse all tests
Most popular tests