SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Construction Management
Start Test
Study First
Subjects
:
industries
,
construction
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The process of designing portions of a project while portions already designed are under construction. A series of controlled design-build sequences that collectively constitute a complete project.
Warranty
Letter of Intent
Clerk-of-the-Work
Fast-Track(ing)
2. A contract held by an owner.
Life-Cycle Cost
Prime Contract
Conditions of the Contract
Estimated Cost to Complete
3. Also: Site Coordination Meeting - Coordination meeting A meeting dedicated essentially to contractor progress during the construction phase.
Progress Meeting
Contract Document Phase
Milestone Schedule
Pre-design Phase
4. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.
Bid
Long-Lead Items
General Conditions (of the Contract for Construction)
Approved Changes
5. Also: Supplementary Conditions Amendments to the General Conditions that change standard requirements to unique requirements - appropriate for a specific project.
Design Development Phase
Special Conditions
RFP (Request For Proposal)
Lien
6. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c
Project Budget
Field Construction Manager
Critical Path(s)
Owner's Representative
7. Servicing the interactive provisions in the contracts for construction between the owner and the contractor(s).
Sub-subcontractor
Contract Administration
Schematic Design Phase
Special Conditions
8. See: Front-End Specifications The part of the contract that prescribes the rights - responsibilities - and relationships of the parties signing the agreement and outlines the administration of the contract for construction.
Schematic Design Phase
General Conditions (of the Contract for Construction)
Construction Management
Project Team
9. A contractor that provides design and construction services under a single responsibility contract to an owner .
Guarantee
Construction Manager
Chart of Accounts
Design-Build (D-B) Contractor
10. The documents which collectively form the contract between the contractor and the owner. They consist of the bidding documents less bidding information plus pre-award addenda and post-award Change Orders.
Contract Documents
Guarantee
Change Order
Technical Specifications
11. A professional service that applies effective management techniques to the planning - design - and construction of a project form inception to completion for the purpose of controlling time - cost and quality. (As approved by CMAA) OR A project deliv
Subcontractor
Direct Labor Costs
Construction Management
Design-Build (D-B) Contracting
12. Also: Feasibility Phase The phase prior to the start of design.
Pre-design Phase
Contract Administration
Preconstruction Phase
Schedule of Values
13. Check: Notice of Award; Notice to Proceed A notice from an owner to a contractor stating that a contract will be awarded to the contractor providing certain events occur or specific conditions are met by the contractor.
Direct Labor Costs
CM Services
Changed Conditions
Letter of Intent
14. The term used on architectural projects to describe the transitional phase from the Schematic Phase to the Contract Document during design.
Substantial Completion
Design Development Phase
Owner's Representative
Project Meeting
15. Also: Detailed Construction Schedule A graphic - tabular or narrative representation or depiction of the construction portion of the project- delivery process - showing activities and durations or activities in sequential order.
Bid
Substantial Completion
Construction Schedule
Lump Sum Fee
16. The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors - construction support items other purchased labor - material and equipment - and the construction manager's cost but not th
Design-Build (D-B) Contractor
Project Budget
Direct Labor Costs
Construction Budget
17. A technical review process; the close matching of engineering design to the value an owner derives from the design.
Owner's Representative
Approved Changes
Estimated Cost to Complete
Value Engineering
18. A contractor who has a contract with a prime contractor.
Project Team
Schedule of Values
Subcontractor
Performance Bond
19. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Warranty
Direct Labor Costs
Contingencies
Final Design Phase
20. A fixed dollar amount which includes all costs of services including overhead and profit.
Lump Sum Fee
Design-Build (D-B) Contracting
Completion Schedule
Life-Cycle Cost
21. The breakdown of a lump sum price into sub-items and sub-costs for identifiable construction elements - which can be evaluated by examination for contractor progress payment purposes.
Special Conditions
Direct Costs
Notice of Award
Schedule of Values
22. Also: Construction Team; Check: Program Team Consists of the architect/engineer - construction manager - and owner - represented by their Level 1 - 2 - and 3 Persons - plus the designated leaders of contracted constructors.
Project Team
Bid Depository
Claim
Schematic Design Phase
23. Check: CM Project Manual Written information that augments the drawings. The Project Manual contains the General Conditions - Supplementary and Special Conditions - the Form of Contract - Addenda - Change Orders - Bidding Information and Proposal For
Design-Build (D-B) Contracting
Project Manual
Schedule of Values
Critical Path(s)
24. Check: Labor and Material Bond; Surety A guarantee provided by a surety to complete a project according to the terms of the contract documents in the event that the bonded contractor defaults on the contract or to pay the owner the face value of the
Labor and Material Bond
Performance Bond
Completion Schedule
Milestone Schedule
25. The term used to describe the use of the overlapping expertise of each team member during team decision making.
Construction Management
Checks and Balances
Life-Cycle Cost
Clerk-of-the-Work
26. Also: Product Data; Samples Detailed information provided by material and equipment suppliers demonstrating that the item provided meets the requirements of the contract documents.
Drawings
Progress Meeting
Warranty
Shop Drawings
27. Term that refers to the General Conditions and the Supplementary and Special Conditions of the contract for construction.
Bid Bond
Milestone Schedule
Commissioning
Conditions of the Contract
28. A business entity that provides independent contractor services to owners through the use of subcontractors when using the general contracting system.
Long-Lead Time
General Contractor
Conditions of the Contract
Project Manual
29. Applies to engineering projects; the initial design effort following signing of the owner; engineer agreement. It is followed by the Final Design Phase.
Start-Up
Owner's Representative
Preliminary Design Phase
Specifications
30. The term used on architectural projects to describe the transitional phase from the Schematic Phase to the Contract Document during design.
Design Development Phase
Schematic Design Phase
Owner's Representative
Substantial Completion
31. Line-item amounts in the project budget - dedicated to specific cost areas where oversight is an inherent problem in project delivery.
Contract Document Phase
Contingencies
Conditions of the Contract
Guaranteed Maximum Price CM (GMPCM)
32. An individual employed by an owner to represent him on a project at the site of the work. The clerk-of- the-work's abilities - credentials - and responsibilities vary at the discretion of the owner.
Life-Cycle Cost
Clerk-of-the-Work
Change Order
Final Design Phase
33. An estimate of the final cost of a work item based on its Cost to Date and the estimated cost to complete it. The sum of the Cost to Date and the Estimated Cost to Complete.
Technical Specifications
Commissioning
Estimated Final Cost
Claim
34. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Direct Costs
Design-Build (D-B) Contractor
Project Budget
Shop Drawings
35. Check: Notice of Award; Letter of Intent A notice from an owner directing a contractor to begin work on a contract - subject to specific stated conditions.
Notice to Proceed
Direct Labor Costs
Substantial Completion
Shop Drawings
36. A contract structure where both design and construction responsibility are vested in a single contractor.
Drawings
Design-Build (D-B) Contracting
General Contractor
Direct Material Costs
37. The target cost of the project established by the owner and agreed to be achievable by the team. The Project Budget usually includes the cost of construction and the CM fee - plus any other line-item costs (land - legal fees - interest - design fees
Approved Changes
Completion Schedule
Design Development Phase
Project Budget
38. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c
Value Engineering
Critical Path(s)
Bid Bond
Contingencies
39. An estimate of the final cost of a work item based on its Cost to Date and the estimated cost to complete it. The sum of the Cost to Date and the Estimated Cost to Complete.
Contingencies
Estimated Final Cost
Approved Bidders List
CM Services
40. A technical review process; the close matching of engineering design to the value an owner derives from the design.
Completion Schedule
Design-Build (D-B) Contracting
Value Engineering
Contract Documents
41. Also: Guarantee Assurance by a providing party that the work - material - and equipment under warranty will perform as promised or as required by contract.
Warranty
Letter of Intent
Design-Build (D-B) Contractor
apparent Low Bidder
42. Also: Reimbursable Charges to the owner covering costs for services that could not or intentionally were not quantified at the time the fee arrangement was made.
Performance Bond
Reimbursable Expense
Milestone Schedule
Warranty
43. The cost of purchasing - installing - owning - operating - and maintaining a construction element over the life of the facility.
Notice to Proceed
Life-Cycle Cost
Final Completion
As-Built Drawings
44. Also: Concealed Conditions; Latent Conditions Conditions or circumstances - physical or otherwise - which surface after a contract has been signed and which alter the circumstances or conditions on which the contract is based.
Critical Path(s)
Changed Conditions
Professional Liability Insurance
Estimated Cost to Complete
45. A person assigned to a project to represent the owner on the project team at one to the three management levels.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
46. Also: Account Codes; Codes of Accounts An alpha/numeric identification system for budget line items that ensures that project expenditures are properly debited/credited in the project budget as payments are made in behalf of the project.
Labor and Material Bond
Project Manual
Chart of Accounts
Guarantee
47. Graphic representations showing location - geometry - and dimensions of a project or its elements in sufficient detail to facilitate construction.
Owner's Representative
Performance Bond
Drawings
Chart of Accounts
48. The target cost of the project established by the owner and agreed to be achievable by the team. The Project Budget usually includes the cost of construction and the CM fee - plus any other line-item costs (land - legal fees - interest - design fees
Contract Documents
Completion Schedule
Project Budget
Superintendent
49. A contract held by an owner.
Prime Contract
Construction Documents
Changed Conditions
Owner's Representative
50. Written criteria that augment the drawings pertaining to the technical construction of the project that cannot be conveniently included on the plans.
Technical Specifications
Warranty
Construction Manager
Occupancy Phase