SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Construction Management
Start Test
Study First
Subjects
:
industries
,
construction
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Term that refers to the General Conditions and the Supplementary and Special Conditions of the contract for construction.
Long-Lead Items
Conditions of the Contract
Professional Liability Insurance
Long-Lead Time
2. Also: Detailed Construction Schedule A graphic - tabular or narrative representation or depiction of the construction portion of the project- delivery process - showing activities and durations or activities in sequential order.
Project Meeting
Construction Schedule
Project Team
Performance Bond
3. Also: Feasibility Phase The phase prior to the start of design.
Pre-design Phase
Value Engineering
Lien
Long-Lead Items
4. Also: Occupancy Schedule A schedule of the activities and events required to effect occupancy or the use of a facility for its intended purpose. It is used to determine if construction progress will meet the occupancy date.
Construction Documents
Escrow Account
Completion Schedule
Final Completion
5. Check: Commissioning; Beneficial Occupancy The period prior to owner occupancy when mechanical - electrical - and other systems are activated and the owner's operating and maintenance staff are instructed in their use.
Long-Lead Items
Start-Up
Construction Budget
Budget Estimate
6. Also: Occupancy Schedule A schedule of the activities and events required to effect occupancy or the use of a facility for its intended purpose. It is used to determine if construction progress will meet the occupancy date.
Guaranteed Maximum Price CM (GMPCM)
Completion Schedule
Superintendent
Progress Meeting
7. See: Start-up; Beneficial Occupancy The process at or near construction completion when a facility is tried out (put into use) to see if it functions as designed. Usually applied to manufacturing type projects.
Warranty
Prime Contract
Progress Meeting
Commissioning
8. The initial Design Phase on an architectural project when the A/E delineates the owner's needs in a general way.
Schematic Design Phase
Chart of Accounts
Fast-Track(ing)
Pre-design Phase
9. Also: Field CM; Level 3 Manager; Level 3 Person; Superintendent - Site Manager A person designated by the CM firm to interface with the owner's and A/E's representatives on the project team at the third management level. A person located at the site
Clerk-of-the-Work
Chart of Accounts
Field Construction Manager
Milestone Schedule
10. Also: Account Codes; Codes of Accounts An alpha/numeric identification system for budget line items that ensures that project expenditures are properly debited/credited in the project budget as payments are made in behalf of the project.
Chart of Accounts
Claim
Warranty
Progress Meeting
11. Also: Feasibility Phase The phase prior to the start of design.
Direct Material Costs
Project Meeting
Pre-design Phase
Owner's Representative
12. Also: Site Coordination Meeting - Coordination meeting A meeting dedicated essentially to contractor progress during the construction phase.
Start-Up
Pre-design Phase
Progress Meeting
Fast-Track(ing)
13. Partial payments on a contractor's contract amount - periodically paid by the owner for work accomplished by the contractor to date.
Record Drawings
Progress Payment
Specifications
Owner's Representative
14. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c
Guarantee
Life-Cycle Cost
Critical Path(s)
Bid Bond
15. An estimate of cost based on rough or incomplete information - with a stated degree of accuracy. The more information available - the more accurate the estimate. Loosely called a 'ballpark' estimate.
Budget Estimate
Guarantee
Design Development Phase
Labor and Material Bond
16. Check: Letter of Intent; Notice to Proceed A letter from an owner to a contractor stating that a contract has been awarded to the contractor and a contract will be forthcoming.
Schematic Design Phase
Notice of Award
Performance Bond
Direct Costs
17. Also: Contract Modification The document that alters the contract amount - contract time - or contract requirements of the original contract entered into by the owner and a contractor.
Notice of Award
Change Order
Progress Meeting
Lien
18. A form of the CM system where the construction manager guarantees - in addition to providing ACM services - a ceiling price to the owner for the cost of construction.
Guaranteed Maximum Price CM (GMPCM)
Technical Specifications
Field Construction Manager
Budget Estimate
19. Detailed statements covering procedures - and quantitative and qualitative and qualitative information pertaining to material - products - and equipment to be incorporated into a project.
Project Meeting
Specifications
Schedule of Values
Guaranteed Maximum Price CM (GMPCM)
20. Check: As-Built Drawings A set of contract document drawings - marked up as construction proceeds - which show the exact location - geometry - and dimensions of all elements of the constructed project as installed.
Notice to Proceed
Sub-subcontractor
Record Drawings
Superintendent
21. A schedule of milestones spanning from the start of construction to occupancy - used as the main measure of progress to keep the project on schedule.
Milestone Schedule
Labor and Material Bond
Critical Path(s)
Escrow Account
22. Costs accruing from expended labor excluding the bonus portion of overtime - insurances - and payroll taxes.
Direct Material Costs
Subcontractor
Construction Schedule
Progress Payment
23. Check: Notice of Award; Notice to Proceed A notice from an owner to a contractor stating that a contract will be awarded to the contractor providing certain events occur or specific conditions are met by the contractor.
Design-Build (D-B) Contracting
Letter of Intent
Change Order
Bid Bond
24. A physical location where trade contractor proposals are fled the day before general contractor bids are to be received by an owner for pickup - opening - acceptance - or rejection by general contractors bidding the owner's project.
Construction Budget
Start-Up
Final Completion
Bid Depository
25. A contract structure where both design and construction responsibility are vested in a single contractor.
Lien
Design-Build (D-B) Contracting
Commissioning
Notice to Proceed
26. Servicing the interactive provisions in the contracts for construction between the owner and the contractor(s).
Contract Administration
Sub-subcontractor
Completion Schedule
Lump Sum Fee
27. The date on which a contractor reaches a point of completion - when subsequent interfacing contractors can productively begin work or the owner can occupy the project - in whole or in part - without undo interference.
As-Built Drawings
Construction Documents
Substantial Completion
Guarantee
28. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.
Lump Sum Fee
Project Meeting
Drawings
Changed Conditions
29. Check: As-Built Drawings A set of contract document drawings - marked up as construction proceeds - which show the exact location - geometry - and dimensions of all elements of the constructed project as installed.
Life-Cycle Cost
Record Drawings
Contract Document Phase
Direct Labor Costs
30. The list of contractors that have survived prequalification tests.
Design-Build (D-B) Contractor
Approved Bidders List
Guaranteed Maximum Price CM (GMPCM)
Labor and Material Bond
31. An estimate of the cost still to be expended on a work-scope in order to complete it. The difference between the Cost to Date and the Estimated Final Cost.
Estimated Cost to Complete
Lien
Superintendent
Fast-Track(ing)
32. Check: Notice of Award; Letter of Intent A notice from an owner directing a contractor to begin work on a contract - subject to specific stated conditions.
Budget Estimate
Construction Budget
Final Design Phase
Notice to Proceed
33. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.
Budget Estimate
Lump Sum Fee
Long-Lead Items
Notice of Award
34. A person assigned to a project to represent the owner on the project team at one to the three management levels.
Warning
: Invalid argument supplied for foreach() in
/var/www/html/basicversity.com/show_quiz.php
on line
183
35. Detailed statements covering procedures - and quantitative and qualitative and qualitative information pertaining to material - products - and equipment to be incorporated into a project.
Performance Bond
Specifications
Estimated Cost to Complete
Contingencies
36. The bidder who has submitted the lowest competitive proposal as determined by a cursory examination of the bids submitted.
Lump Sum Fee
apparent Low Bidder
Budget Estimate
As-Built Drawings
37. A physical location where trade contractor proposals are fled the day before general contractor bids are to be received by an owner for pickup - opening - acceptance - or rejection by general contractors bidding the owner's project.
Drawings
Superintendent
Bid Depository
Progress Meeting
38. A technical review process; the close matching of engineering design to the value an owner derives from the design.
Escrow Account
Notice to Proceed
Value Engineering
Progress Meeting
39. Changes of any nature in contract requirements which have been agreed upon through a change approval process and approved by the owner.
Escrow Account
Approved Changes
Project Manual
Lump Sum Fee
40. A form of the CM system where the construction manager guarantees - in addition to providing ACM services - a ceiling price to the owner for the cost of construction.
Guaranteed Maximum Price CM (GMPCM)
Conditions of the Contract
Guarantee
As-Built Drawings
41. Also: Concealed Conditions; Latent Conditions Conditions or circumstances - physical or otherwise - which surface after a contract has been signed and which alter the circumstances or conditions on which the contract is based.
Long-Lead Time
Changed Conditions
Estimated Cost to Complete
Direct Labor Costs
42. The target cost of the project established by the owner and agreed to be achievable by the team. The Project Budget usually includes the cost of construction and the CM fee - plus any other line-item costs (land - legal fees - interest - design fees
Escrow Account
Final Design Phase
Lump Sum Fee
Project Budget
43. An individual employed by an owner to represent him on a project at the site of the work. The clerk-of- the-work's abilities - credentials - and responsibilities vary at the discretion of the owner.
Owner's Representative
Record Drawings
Clerk-of-the-Work
Contract Administration
44. A professional service that applies effective management techniques to the planning - design - and construction of a project form inception to completion for the purpose of controlling time - cost and quality. (As approved by CMAA) OR A project deliv
Commissioning
Design-Build (D-B) Contractor
Lump Sum Fee
Construction Management
45. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.
Long-Lead Items
Lump Sum Fee
CM Services
Construction Management
46. A business entity that provides independent contractor services to owners through the use of subcontractors when using the general contracting system.
Schematic Design Phase
Final Design Phase
As-Built Drawings
General Contractor
47. Also: Concealed Conditions; Latent Conditions Conditions or circumstances - physical or otherwise - which surface after a contract has been signed and which alter the circumstances or conditions on which the contract is based.
Superintendent
Progress Payment
Drawings
Changed Conditions
48. The final phase of design on an architectural project when construction documents are completed and bidding documents formulated.
Warranty
Long-Lead Time
Contract Document Phase
Guaranteed Maximum Price CM (GMPCM)
49. Drawings - technical specification - and addenda; the contract documents that refer to the physical construction requirements established by the A/E.
Construction Documents
Lump Sum Fee
Contract Document Phase
Labor and Material Bond
50. Check: Notice of Award; Letter of Intent A notice from an owner directing a contractor to begin work on a contract - subject to specific stated conditions.
Construction Budget
Fast-Track(ing)
Schematic Design Phase
Notice to Proceed