SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Construction Management
Start Test
Study First
Subjects
:
industries
,
construction
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The breakdown of a lump sum price into sub-items and sub-costs for identifiable construction elements - which can be evaluated by examination for contractor progress payment purposes.
Bid Depository
Schedule of Values
CM Services
Drawings
2. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Value Engineering
Project Team
Contract Documents
Direct Costs
3. A contractor who has a contract with a subcontractor.
Construction Budget
Sub-subcontractor
Change Order
Warranty
4. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.
Escrow Account
Long-Lead Items
Contract Documents
Direct Labor Costs
5. An agreement by which a party accepts responsibility for fulfilling an obligation.
Bid Bond
Guarantee
Schematic Design Phase
Lump Sum Fee
6. A formal notice sent by a contractor to an owner asserting the fact that the terms of the contract have been breached and compensation is being sought by the contractor from the owner.
Lump Sum Fee
Owner's Representative
Claim
Schedule of Values
7. The documents which collectively form the contract between the contractor and the owner. They consist of the bidding documents less bidding information plus pre-award addenda and post-award Change Orders.
Drawings
Contract Documents
Preliminary Design Phase
Approved Bidders List
8. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c
Critical Path(s)
Commissioning
Construction Manager
General Conditions (of the Contract for Construction)
9. All required phases prior to the start of construction.
Preconstruction Phase
Prime Contract
Checks and Balances
Occupancy Phase
10. A professional service that applies effective management techniques to the planning - design - and construction of a project form inception to completion for the purpose of controlling time - cost and quality. (As approved by CMAA) OR A project deliv
Drawings
Bid Bond
Construction Management
Construction Budget
11. A professional service that applies effective management techniques to the planning - design - and construction of a project form inception to completion for the purpose of controlling time - cost and quality. (As approved by CMAA) OR A project deliv
Pre-design Phase
Construction Documents
General Contractor
Construction Management
12. An estimate of the final cost of a work item based on its Cost to Date and the estimated cost to complete it. The sum of the Cost to Date and the Estimated Cost to Complete.
Estimated Final Cost
Owner's Representative
Claim
Critical Path(s)
13. A job title usually reserved for the administrative level person who supervises the work of an on-site contractor .
Superintendent
Lump Sum Fee
Performance Bond
Warranty
14. Detailed statements covering procedures - and quantitative and qualitative and qualitative information pertaining to material - products - and equipment to be incorporated into a project.
Shop Drawings
Letter of Intent
Milestone
Specifications
15. Also: Feasibility Phase The phase prior to the start of design.
Escrow Account
Chart of Accounts
Pre-design Phase
Drawings
16. Also: Occupancy Schedule A schedule of the activities and events required to effect occupancy or the use of a facility for its intended purpose. It is used to determine if construction progress will meet the occupancy date.
RFP (Request For Proposal)
Design-Build (D-B) Contracting
Completion Schedule
CM Services
17. The time between the purchase date and delivery date of long-lead items.
Changed Conditions
Design-Build (D-B) Contracting
Preliminary Design Phase
Long-Lead Time
18. The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors - construction support items other purchased labor - material and equipment - and the construction manager's cost but not th
apparent Low Bidder
Project Budget
Construction Budget
Clerk-of-the-Work
19. Graphic representations showing location - geometry - and dimensions of a project or its elements in sufficient detail to facilitate construction.
Construction Budget
Estimated Cost to Complete
Drawings
Direct Costs
20. A contract structure where both design and construction responsibility are vested in a single contractor.
Final Design Phase
Design-Build (D-B) Contracting
Estimated Cost to Complete
Drawings
21. A technical review process; the close matching of engineering design to the value an owner derives from the design.
Progress Meeting
Critical Path(s)
Direct Material Costs
Value Engineering
22. The second request for uniform detailed information from prospective CM practitioners being screened for a project.
Notice of Award
Design-Build (D-B) Contractor
Final Completion
RFP (Request For Proposal)
23. The list of contractors that have survived prequalification tests.
Approved Bidders List
Professional Liability Insurance
Changed Conditions
Estimated Cost to Complete
24. Also: As Builts; Check: Record Drawings Drawings produced during or after construction and amended to show the exact location - geometry - and dimensions of the constructed project. As-Built Drawings are not the same as Record Drawings.
Contract Documents
RFP (Request For Proposal)
Long-Lead Items
As-Built Drawings
25. A binding offer - usually expressed in dollars to provide specific services within clearly stated requirements.
Bid
Lien
Guarantee
Owner's Representative
26. The time between the purchase date and delivery date of long-lead items.
Long-Lead Time
Specifications
General Conditions (of the Contract for Construction)
Conditions of the Contract
27. A business entity that provides independent contractor services to owners through the use of subcontractors when using the general contracting system.
Contract Document Phase
General Contractor
Estimated Final Cost
Approved Bidders List
28. An estimate of cost based on rough or incomplete information - with a stated degree of accuracy. The more information available - the more accurate the estimate. Loosely called a 'ballpark' estimate.
Budget Estimate
Professional Liability Insurance
Shop Drawings
apparent Low Bidder
29. Applies to engineering projects; the initial design effort following signing of the owner; engineer agreement. It is followed by the Final Design Phase.
Lien
Bid Depository
Preliminary Design Phase
Completion Schedule
30. A contractor who has a contract with a subcontractor.
Escrow Account
Escrow Account
Design-Build (D-B) Contracting
Sub-subcontractor
31. Also: Contract Modification The document that alters the contract amount - contract time - or contract requirements of the original contract entered into by the owner and a contractor.
Subcontractor
Clerk-of-the-Work
Change Order
Bid
32. Also: Supplementary Conditions Amendments to the General Conditions that change standard requirements to unique requirements - appropriate for a specific project.
Progress Payment
General Conditions (of the Contract for Construction)
Construction Budget
Special Conditions
33. Also: Field CM; Level 3 Manager; Level 3 Person; Superintendent - Site Manager A person designated by the CM firm to interface with the owner's and A/E's representatives on the project team at the third management level. A person located at the site
Field Construction Manager
Record Drawings
Critical Path(s)
Prime Contract
34. Also: Detailed Construction Schedule A graphic - tabular or narrative representation or depiction of the construction portion of the project- delivery process - showing activities and durations or activities in sequential order.
Prime Contract
Schematic Design Phase
Direct Costs
Construction Schedule
35. Also: Warranty/Guarantee Phase; Warranty Phase; Guarantee Phase A stipulated length of time following the construction phase - during which contractors are bonded to ensure that materials - equipment - and workmanship meet the requirements of their c
Project Team
Occupancy Phase
Chart of Accounts
Guarantee
36. Also: Mechanic's Lien The right to take - hold - or sell the property of a debtor as security or payment for a debt.
Lien
Owner's Representative
Approved Changes
Special Conditions
37. A physical location where trade contractor proposals are fled the day before general contractor bids are to be received by an owner for pickup - opening - acceptance - or rejection by general contractors bidding the owner's project.
Bid Depository
Contract Administration
Occupancy Phase
Contingencies
38. An agreement by which a party accepts responsibility for fulfilling an obligation.
Construction Schedule
Approved Bidders List
Guarantee
Estimated Final Cost
39. A schedule of milestones spanning from the start of construction to occupancy - used as the main measure of progress to keep the project on schedule.
Milestone Schedule
Project Manual
RFP (Request For Proposal)
Progress Meeting
40. An estimate of cost based on rough or incomplete information - with a stated degree of accuracy. The more information available - the more accurate the estimate. Loosely called a 'ballpark' estimate.
Field Construction Manager
Reimbursable Expense
Critical Path(s)
Budget Estimate
41. Line-item amounts in the project budget - dedicated to specific cost areas where oversight is an inherent problem in project delivery.
Contingencies
Direct Costs
Labor and Material Bond
Chart of Accounts
42. Written criteria that augment the drawings pertaining to the technical construction of the project that cannot be conveniently included on the plans.
Technical Specifications
Warranty
Construction Schedule
Schematic Design Phase
43. The point at which both parties to a contract declare the other has satisfactorily completed its responsibilities under the contract.
Contract Document Phase
Approved Bidders List
Final Completion
Performance Bond
44. A person assigned to a project to represent the owner on the project team at one to the three management levels.
45. Term that refers to the General Conditions and the Supplementary and Special Conditions of the contract for construction.
Conditions of the Contract
Contract Documents
Changed Conditions
Project Team
46. The process of designing portions of a project while portions already designed are under construction. A series of controlled design-build sequences that collectively constitute a complete project.
CM Services
Fast-Track(ing)
Direct Labor Costs
Preliminary Design Phase
47. Also: Construction Team; Check: Program Team Consists of the architect/engineer - construction manager - and owner - represented by their Level 1 - 2 - and 3 Persons - plus the designated leaders of contracted constructors.
Project Team
Letter of Intent
Chart of Accounts
Field Construction Manager
48. A firm or business organization with the expertise and resources to manage the design - contracting - and construction aspects of project delivery. Individuals who work for a CM Firm are also referred to as Construction Managers.
Superintendent
Long-Lead Items
Changed Conditions
Construction Manager
49. Check: Notice of Award; Letter of Intent A notice from an owner directing a contractor to begin work on a contract - subject to specific stated conditions.
Notice to Proceed
Life-Cycle Cost
Design-Build (D-B) Contractor
Chart of Accounts
50. A fixed dollar amount which includes all costs of services including overhead and profit.
Long-Lead Time
Project Manual
Lump Sum Fee
Milestone Schedule