Test your basic knowledge |

Construction Management

Instructions:
  • Answer 50 questions in 15 minutes.
  • If you are not ready to take this test, you can study here.
  • Match each statement with the correct term.
  • Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.

This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Also: Concealed Conditions; Latent Conditions Conditions or circumstances - physical or otherwise - which surface after a contract has been signed and which alter the circumstances or conditions on which the contract is based.






2. The documents which collectively form the contract between the contractor and the owner. They consist of the bidding documents less bidding information plus pre-award addenda and post-award Change Orders.






3. Check: Labor and Material Bond; Surety A guarantee provided by a surety to complete a project according to the terms of the contract documents in the event that the bonded contractor defaults on the contract or to pay the owner the face value of the






4. Applies to engineering projects; the initial design effort following signing of the owner; engineer agreement. It is followed by the Final Design Phase.






5. Graphic representations showing location - geometry - and dimensions of a project or its elements in sufficient detail to facilitate construction.






6. Also: Construction Team; Check: Program Team Consists of the architect/engineer - construction manager - and owner - represented by their Level 1 - 2 - and 3 Persons - plus the designated leaders of contracted constructors.






7. Partial payments on a contractor's contract amount - periodically paid by the owner for work accomplished by the contractor to date.






8. The time between the purchase date and delivery date of long-lead items.






9. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.






10. Also: Site Coordination Meeting - Coordination meeting A meeting dedicated essentially to contractor progress during the construction phase.






11. Also: Errors and Omissions Insurance Insurance provided by design professionals and construction managers that protects the owner against the financial results of negligent acts by the insured.






12. The scope of services provided by a construction manager and available to owners in whole or in part. CM services are not consistent in scope or performance from one CM firm to another.






13. Also: Product Data; Samples Detailed information provided by material and equipment suppliers demonstrating that the item provided meets the requirements of the contract documents.






14. The time between the purchase date and delivery date of long-lead items.






15. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.






16. Also: Field CM; Level 3 Manager; Level 3 Person; Superintendent - Site Manager A person designated by the CM firm to interface with the owner's and A/E's representatives on the project team at the third management level. A person located at the site






17. Check: Notice of Award; Notice to Proceed A notice from an owner to a contractor stating that a contract will be awarded to the contractor providing certain events occur or specific conditions are met by the contractor.






18. The time between the purchase date and delivery date of long-lead items.






19. Money put into the custody of the third party by the first party for disbursement tot the second party. A brief temporary depository for progress payments until authorized for release according to the depositor's explicit instructions.






20. The breakdown of a lump sum price into sub-items and sub-costs for identifiable construction elements - which can be evaluated by examination for contractor progress payment purposes.






21. Drawings - technical specification - and addenda; the contract documents that refer to the physical construction requirements established by the A/E.






22. The term used to describe the use of the overlapping expertise of each team member during team decision making.






23. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.






24. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c






25. Graphic representations showing location - geometry - and dimensions of a project or its elements in sufficient detail to facilitate construction.






26. A schedule of milestones spanning from the start of construction to occupancy - used as the main measure of progress to keep the project on schedule.






27. Written criteria that augment the drawings pertaining to the technical construction of the project that cannot be conveniently included on the plans.






28. Changes of any nature in contract requirements which have been agreed upon through a change approval process and approved by the owner.






29. A form of the CM system where the construction manager guarantees - in addition to providing ACM services - a ceiling price to the owner for the cost of construction.






30. A formal notice sent by a contractor to an owner asserting the fact that the terms of the contract have been breached and compensation is being sought by the contractor from the owner.






31. An estimate of the final cost of a work item based on its Cost to Date and the estimated cost to complete it. The sum of the Cost to Date and the Estimated Cost to Complete.






32. Also: Occupancy Schedule A schedule of the activities and events required to effect occupancy or the use of a facility for its intended purpose. It is used to determine if construction progress will meet the occupancy date.






33. Changes of any nature in contract requirements which have been agreed upon through a change approval process and approved by the owner.






34. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.






35. A physical location where trade contractor proposals are fled the day before general contractor bids are to be received by an owner for pickup - opening - acceptance - or rejection by general contractors bidding the owner's project.






36. An individual employed by an owner to represent him on a project at the site of the work. The clerk-of- the-work's abilities - credentials - and responsibilities vary at the discretion of the owner.






37. The designation used by engineers for the last portion of the design process prior to bidding.






38. The bidder who has submitted the lowest competitive proposal as determined by a cursory examination of the bids submitted.






39. Check: As-Built Drawings A set of contract document drawings - marked up as construction proceeds - which show the exact location - geometry - and dimensions of all elements of the constructed project as installed.






40. A physical location where trade contractor proposals are fled the day before general contractor bids are to be received by an owner for pickup - opening - acceptance - or rejection by general contractors bidding the owner's project.






41. Also: Contract Modification The document that alters the contract amount - contract time - or contract requirements of the original contract entered into by the owner and a contractor.






42. A firm or business organization with the expertise and resources to manage the design - contracting - and construction aspects of project delivery. Individuals who work for a CM Firm are also referred to as Construction Managers.






43. The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors - construction support items other purchased labor - material and equipment - and the construction manager's cost but not th






44. Check: Labor and Material Bond; Surety A guarantee provided by a surety to complete a project according to the terms of the contract documents in the event that the bonded contractor defaults on the contract or to pay the owner the face value of the






45. An estimate of cost based on rough or incomplete information - with a stated degree of accuracy. The more information available - the more accurate the estimate. Loosely called a 'ballpark' estimate.






46. Also: Guarantee Assurance by a providing party that the work - material - and equipment under warranty will perform as promised or as required by contract.






47. Also: Errors and Omissions Insurance Insurance provided by design professionals and construction managers that protects the owner against the financial results of negligent acts by the insured.






48. Costs accruing from expended labor excluding the bonus portion of overtime - insurances - and payroll taxes.






49. A contract held by an owner.






50. Selected strategic events of signal importance to progress used in the milestone schedule.






Can you answer 50 questions in 15 minutes?



Let me suggest you:



Major Subjects



Tests & Exams


AP
CLEP
DSST
GRE
SAT
GMAT

Most popular tests