SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Construction Management
Start Test
Study First
Subjects
:
industries
,
construction
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Changes of any nature in contract requirements which have been agreed upon through a change approval process and approved by the owner.
Final Completion
Progress Meeting
Approved Changes
RFP (Request For Proposal)
2. The term used on architectural projects to describe the transitional phase from the Schematic Phase to the Contract Document during design.
As-Built Drawings
Design Development Phase
Progress Meeting
Direct Labor Costs
3. Also: Contract Modification The document that alters the contract amount - contract time - or contract requirements of the original contract entered into by the owner and a contractor.
Change Order
Occupancy Phase
Commissioning
Contract Documents
4. A technical review process; the close matching of engineering design to the value an owner derives from the design.
Value Engineering
Fast-Track(ing)
Change Order
Life-Cycle Cost
5. An estimate of the final cost of a work item based on its Cost to Date and the estimated cost to complete it. The sum of the Cost to Date and the Estimated Cost to Complete.
Estimated Final Cost
Guarantee
Performance Bond
Contract Document Phase
6. A contract held by an owner.
Superintendent
Labor and Material Bond
Prime Contract
Contract Administration
7. The list of contractors that have survived prequalification tests.
Contract Administration
Approved Bidders List
Guarantee
Contract Document Phase
8. Detailed statements covering procedures - and quantitative and qualitative and qualitative information pertaining to material - products - and equipment to be incorporated into a project.
Changed Conditions
Specifications
Direct Costs
apparent Low Bidder
9. The term used to describe the use of the overlapping expertise of each team member during team decision making.
Checks and Balances
Drawings
As-Built Drawings
Contract Documents
10. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Notice of Award
Progress Payment
Specifications
Direct Costs
11. Drawings - technical specification - and addenda; the contract documents that refer to the physical construction requirements established by the A/E.
Claim
Construction Documents
Construction Schedule
Design-Build (D-B) Contracting
12. A professional service that applies effective management techniques to the planning - design - and construction of a project form inception to completion for the purpose of controlling time - cost and quality. (As approved by CMAA) OR A project deliv
Construction Management
Contingencies
Guaranteed Maximum Price CM (GMPCM)
Preliminary Design Phase
13. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c
Long-Lead Items
Lien
Construction Manager
Critical Path(s)
14. An agreement by which a party accepts responsibility for fulfilling an obligation.
Guarantee
Design Development Phase
Construction Manager
Checks and Balances
15. Check: Notice of Award; Letter of Intent A notice from an owner directing a contractor to begin work on a contract - subject to specific stated conditions.
Final Design Phase
Notice to Proceed
Direct Labor Costs
Owner's Representative
16. Costs accruing from expended labor excluding the bonus portion of overtime - insurances - and payroll taxes.
Lump Sum Fee
Long-Lead Items
Direct Material Costs
Design-Build (D-B) Contractor
17. See: Start-up; Beneficial Occupancy The process at or near construction completion when a facility is tried out (put into use) to see if it functions as designed. Usually applied to manufacturing type projects.
Drawings
Contract Document Phase
Shop Drawings
Commissioning
18. The point at which both parties to a contract declare the other has satisfactorily completed its responsibilities under the contract.
Clerk-of-the-Work
Fast-Track(ing)
Final Completion
Special Conditions
19. Money put into the custody of the third party by the first party for disbursement tot the second party. A brief temporary depository for progress payments until authorized for release according to the depositor's explicit instructions.
Chart of Accounts
Escrow Account
Fast-Track(ing)
Contract Document Phase
20. A schedule of milestones spanning from the start of construction to occupancy - used as the main measure of progress to keep the project on schedule.
Contingencies
Subcontractor
Field Construction Manager
Milestone Schedule
21. Detailed statements covering procedures - and quantitative and qualitative and qualitative information pertaining to material - products - and equipment to be incorporated into a project.
Specifications
Bid
Notice of Award
Construction Management
22. The scope of services provided by a construction manager and available to owners in whole or in part. CM services are not consistent in scope or performance from one CM firm to another.
Subcontractor
CM Services
Labor and Material Bond
Guaranteed Maximum Price CM (GMPCM)
23. A binding offer - usually expressed in dollars to provide specific services within clearly stated requirements.
Bid Depository
Progress Meeting
Completion Schedule
Bid
24. A technical review process; the close matching of engineering design to the value an owner derives from the design.
Bid Bond
Value Engineering
Design Development Phase
Approved Bidders List
25. The designation used by engineers for the last portion of the design process prior to bidding.
Project Manual
Final Design Phase
Construction Management
Preconstruction Phase
26. Changes of any nature in contract requirements which have been agreed upon through a change approval process and approved by the owner.
Notice of Award
Design Development Phase
Construction Schedule
Approved Changes
27. Partial payments on a contractor's contract amount - periodically paid by the owner for work accomplished by the contractor to date.
Estimated Final Cost
Direct Material Costs
Progress Payment
Project Manual
28. A job title usually reserved for the administrative level person who supervises the work of an on-site contractor .
Construction Budget
Superintendent
Milestone Schedule
Special Conditions
29. The designation used by engineers for the last portion of the design process prior to bidding.
Notice to Proceed
Final Design Phase
Bid Bond
Field Construction Manager
30. Check: As-Built Drawings A set of contract document drawings - marked up as construction proceeds - which show the exact location - geometry - and dimensions of all elements of the constructed project as installed.
Record Drawings
Start-Up
Completion Schedule
CM Services
31. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.
Estimated Cost to Complete
Commissioning
Project Meeting
Change Order
32. Check: Letter of Intent; Notice to Proceed A letter from an owner to a contractor stating that a contract has been awarded to the contractor and a contract will be forthcoming.
Contract Documents
Start-Up
Shop Drawings
Notice of Award
33. Applies to engineering projects; the initial design effort following signing of the owner; engineer agreement. It is followed by the Final Design Phase.
Preliminary Design Phase
Milestone
General Conditions (of the Contract for Construction)
Project Budget
34. All required phases prior to the start of construction.
Preconstruction Phase
Checks and Balances
Contract Document Phase
Subcontractor
35. A job title usually reserved for the administrative level person who supervises the work of an on-site contractor .
Technical Specifications
Performance Bond
Contract Document Phase
Superintendent
36. Also: Occupancy Schedule A schedule of the activities and events required to effect occupancy or the use of a facility for its intended purpose. It is used to determine if construction progress will meet the occupancy date.
Sub-subcontractor
Notice of Award
Design-Build (D-B) Contracting
Completion Schedule
37. Also: Detailed Construction Schedule A graphic - tabular or narrative representation or depiction of the construction portion of the project- delivery process - showing activities and durations or activities in sequential order.
Direct Labor Costs
Owner's Representative
Construction Schedule
Lump Sum Fee
38. The date on which a contractor reaches a point of completion - when subsequent interfacing contractors can productively begin work or the owner can occupy the project - in whole or in part - without undo interference.
Substantial Completion
Long-Lead Items
Preconstruction Phase
Notice of Award
39. Check: Labor and Material Bond; Surety A guarantee provided by a surety to complete a project according to the terms of the contract documents in the event that the bonded contractor defaults on the contract or to pay the owner the face value of the
Conditions of the Contract
Performance Bond
Estimated Cost to Complete
Preconstruction Phase
40. Money put into the custody of the third party by the first party for disbursement tot the second party. A brief temporary depository for progress payments until authorized for release according to the depositor's explicit instructions.
Technical Specifications
Lump Sum Fee
CM Services
Escrow Account
41. Also: Supplementary Conditions Amendments to the General Conditions that change standard requirements to unique requirements - appropriate for a specific project.
Specifications
Special Conditions
Schematic Design Phase
Preliminary Design Phase
42. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Construction Manager
As-Built Drawings
Direct Labor Costs
Guaranteed Maximum Price CM (GMPCM)
43. All required phases prior to the start of construction.
Preconstruction Phase
Milestone Schedule
Reimbursable Expense
Drawings
44. Servicing the interactive provisions in the contracts for construction between the owner and the contractor(s).
Estimated Cost to Complete
Prime Contract
Performance Bond
Contract Administration
45. Check: CM Project Manual Written information that augments the drawings. The Project Manual contains the General Conditions - Supplementary and Special Conditions - the Form of Contract - Addenda - Change Orders - Bidding Information and Proposal For
Design-Build (D-B) Contractor
Final Design Phase
Construction Management
Project Manual
46. The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors - construction support items other purchased labor - material and equipment - and the construction manager's cost but not th
Life-Cycle Cost
Design-Build (D-B) Contractor
Construction Budget
Construction Manager
47. The scope of services provided by a construction manager and available to owners in whole or in part. CM services are not consistent in scope or performance from one CM firm to another.
Record Drawings
CM Services
Checks and Balances
Guarantee
48. The bidder who has submitted the lowest competitive proposal as determined by a cursory examination of the bids submitted.
Specifications
apparent Low Bidder
Critical Path(s)
Lump Sum Fee
49. Also: Contract Modification The document that alters the contract amount - contract time - or contract requirements of the original contract entered into by the owner and a contractor.
Progress Meeting
Checks and Balances
Construction Documents
Change Order
50. A contract held by an owner.
Prime Contract
Value Engineering
Pre-design Phase
Completion Schedule