SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Construction Management
Start Test
Study First
Subjects
:
industries
,
construction
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Graphic representations showing location - geometry - and dimensions of a project or its elements in sufficient detail to facilitate construction.
Construction Manager
Estimated Final Cost
Drawings
Construction Budget
2. A job title usually reserved for the administrative level person who supervises the work of an on-site contractor .
Project Budget
Shop Drawings
Superintendent
Design Development Phase
3. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.
Prime Contract
Preconstruction Phase
Long-Lead Items
Construction Budget
4. Servicing the interactive provisions in the contracts for construction between the owner and the contractor(s).
Progress Payment
Value Engineering
General Contractor
Contract Administration
5. Also: Construction Team; Check: Program Team Consists of the architect/engineer - construction manager - and owner - represented by their Level 1 - 2 - and 3 Persons - plus the designated leaders of contracted constructors.
Project Team
Substantial Completion
Progress Payment
Bid Bond
6. Check: As-Built Drawings A set of contract document drawings - marked up as construction proceeds - which show the exact location - geometry - and dimensions of all elements of the constructed project as installed.
Clerk-of-the-Work
Record Drawings
Field Construction Manager
Changed Conditions
7. Also: Contract Modification The document that alters the contract amount - contract time - or contract requirements of the original contract entered into by the owner and a contractor.
Change Order
Lump Sum Fee
Contract Administration
Design-Build (D-B) Contracting
8. An estimate of the cost still to be expended on a work-scope in order to complete it. The difference between the Cost to Date and the Estimated Final Cost.
Substantial Completion
Construction Management
Owner's Representative
Estimated Cost to Complete
9. A physical location where trade contractor proposals are fled the day before general contractor bids are to be received by an owner for pickup - opening - acceptance - or rejection by general contractors bidding the owner's project.
Lien
Direct Costs
Bid Depository
Guaranteed Maximum Price CM (GMPCM)
10. Check: Notice of Award; Letter of Intent A notice from an owner directing a contractor to begin work on a contract - subject to specific stated conditions.
Notice to Proceed
Budget Estimate
Progress Payment
Direct Labor Costs
11. The time between the purchase date and delivery date of long-lead items.
Changed Conditions
Long-Lead Time
Drawings
Life-Cycle Cost
12. The initial Design Phase on an architectural project when the A/E delineates the owner's needs in a general way.
Commissioning
Schematic Design Phase
Budget Estimate
Project Budget
13. Check: As-Built Drawings A set of contract document drawings - marked up as construction proceeds - which show the exact location - geometry - and dimensions of all elements of the constructed project as installed.
Record Drawings
Change Order
Performance Bond
Notice of Award
14. Applies to engineering projects; the initial design effort following signing of the owner; engineer agreement. It is followed by the Final Design Phase.
Critical Path(s)
Estimated Cost to Complete
Shop Drawings
Preliminary Design Phase
15. The scope of services provided by a construction manager and available to owners in whole or in part. CM services are not consistent in scope or performance from one CM firm to another.
Performance Bond
Critical Path(s)
Direct Labor Costs
CM Services
16. Also: Guarantee Assurance by a providing party that the work - material - and equipment under warranty will perform as promised or as required by contract.
Checks and Balances
Warranty
Clerk-of-the-Work
Direct Labor Costs
17. A contractor that provides design and construction services under a single responsibility contract to an owner .
Prime Contract
Guarantee
Construction Budget
Design-Build (D-B) Contractor
18. Servicing the interactive provisions in the contracts for construction between the owner and the contractor(s).
Contract Administration
Final Design Phase
Direct Labor Costs
RFP (Request For Proposal)
19. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.
Labor and Material Bond
Shop Drawings
Bid Depository
Project Meeting
20. Selected strategic events of signal importance to progress used in the milestone schedule.
Project Team
Escrow Account
Subcontractor
Milestone
21. See: Front-End Specifications The part of the contract that prescribes the rights - responsibilities - and relationships of the parties signing the agreement and outlines the administration of the contract for construction.
Contract Administration
General Conditions (of the Contract for Construction)
Schedule of Values
Checks and Balances
22. A contractor who has a contract with a subcontractor.
Technical Specifications
Sub-subcontractor
Schedule of Values
Long-Lead Items
23. Also: Guarantee Assurance by a providing party that the work - material - and equipment under warranty will perform as promised or as required by contract.
Owner's Representative
Warranty
Notice to Proceed
Direct Material Costs
24. The designation used by engineers for the last portion of the design process prior to bidding.
Field Construction Manager
CM Services
Project Team
Final Design Phase
25. The time between the purchase date and delivery date of long-lead items.
Long-Lead Time
Lump Sum Fee
Critical Path(s)
Performance Bond
26. The point at which both parties to a contract declare the other has satisfactorily completed its responsibilities under the contract.
Final Completion
Direct Costs
Construction Manager
Construction Budget
27. Check: CM Project Manual Written information that augments the drawings. The Project Manual contains the General Conditions - Supplementary and Special Conditions - the Form of Contract - Addenda - Change Orders - Bidding Information and Proposal For
Estimated Final Cost
Construction Management
Checks and Balances
Project Manual
28. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c
Substantial Completion
Critical Path(s)
Bid Depository
Project Manual
29. The bidder who has submitted the lowest competitive proposal as determined by a cursory examination of the bids submitted.
Lien
Schedule of Values
Design Development Phase
apparent Low Bidder
30. The list of contractors that have survived prequalification tests.
Approved Bidders List
Schedule of Values
Project Budget
Project Team
31. The process of designing portions of a project while portions already designed are under construction. A series of controlled design-build sequences that collectively constitute a complete project.
Construction Management
Letter of Intent
Performance Bond
Fast-Track(ing)
32. An individual employed by an owner to represent him on a project at the site of the work. The clerk-of- the-work's abilities - credentials - and responsibilities vary at the discretion of the owner.
Notice to Proceed
Clerk-of-the-Work
Direct Labor Costs
Commissioning
33. Costs accruing from expended labor excluding the bonus portion of overtime - insurances - and payroll taxes.
Estimated Cost to Complete
Construction Budget
Reimbursable Expense
Direct Material Costs
34. A fixed dollar amount which includes all costs of services including overhead and profit.
Record Drawings
Chart of Accounts
Special Conditions
Lump Sum Fee
35. Money put into the custody of the third party by the first party for disbursement tot the second party. A brief temporary depository for progress payments until authorized for release according to the depositor's explicit instructions.
Design-Build (D-B) Contractor
Labor and Material Bond
Shop Drawings
Escrow Account
36. See: Front-End Specifications The part of the contract that prescribes the rights - responsibilities - and relationships of the parties signing the agreement and outlines the administration of the contract for construction.
Checks and Balances
General Conditions (of the Contract for Construction)
Direct Material Costs
Long-Lead Time
37. Also: Field CM; Level 3 Manager; Level 3 Person; Superintendent - Site Manager A person designated by the CM firm to interface with the owner's and A/E's representatives on the project team at the third management level. A person located at the site
Field Construction Manager
Design-Build (D-B) Contractor
Estimated Final Cost
Lump Sum Fee
38. Also: Warranty/Guarantee Phase; Warranty Phase; Guarantee Phase A stipulated length of time following the construction phase - during which contractors are bonded to ensure that materials - equipment - and workmanship meet the requirements of their c
General Conditions (of the Contract for Construction)
Guaranteed Maximum Price CM (GMPCM)
Occupancy Phase
Labor and Material Bond
39. All required phases prior to the start of construction.
Lien
Project Manual
Preconstruction Phase
Specifications
40. Also: Reimbursable Charges to the owner covering costs for services that could not or intentionally were not quantified at the time the fee arrangement was made.
Change Order
Reimbursable Expense
Change Order
Notice of Award
41. The breakdown of a lump sum price into sub-items and sub-costs for identifiable construction elements - which can be evaluated by examination for contractor progress payment purposes.
Construction Management
Value Engineering
Schedule of Values
Commissioning
42. Detailed statements covering procedures - and quantitative and qualitative and qualitative information pertaining to material - products - and equipment to be incorporated into a project.
Specifications
Completion Schedule
Construction Management
Professional Liability Insurance
43. The target cost of the project established by the owner and agreed to be achievable by the team. The Project Budget usually includes the cost of construction and the CM fee - plus any other line-item costs (land - legal fees - interest - design fees
Project Budget
RFP (Request For Proposal)
Notice to Proceed
CM Services
44. Also: Mechanic's Lien The right to take - hold - or sell the property of a debtor as security or payment for a debt.
Final Design Phase
Lien
Occupancy Phase
Guarantee
45. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Value Engineering
Critical Path(s)
Superintendent
Direct Costs
46. The documents which collectively form the contract between the contractor and the owner. They consist of the bidding documents less bidding information plus pre-award addenda and post-award Change Orders.
Lump Sum Fee
Contract Documents
Lien
Direct Material Costs
47. The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors - construction support items other purchased labor - material and equipment - and the construction manager's cost but not th
Construction Budget
As-Built Drawings
Notice of Award
Value Engineering
48. Also: Account Codes; Codes of Accounts An alpha/numeric identification system for budget line items that ensures that project expenditures are properly debited/credited in the project budget as payments are made in behalf of the project.
Notice of Award
Chart of Accounts
Guarantee
Progress Meeting
49. An agreement by which a party accepts responsibility for fulfilling an obligation.
Final Design Phase
Guarantee
Labor and Material Bond
Progress Payment
50. The final phase of design on an architectural project when construction documents are completed and bidding documents formulated.
Contract Document Phase
Contingencies
Design Development Phase
Conditions of the Contract