Test your basic knowledge |

Construction Management

Instructions:
  • Answer 50 questions in 15 minutes.
  • If you are not ready to take this test, you can study here.
  • Match each statement with the correct term.
  • Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.

This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The target cost of the project established by the owner and agreed to be achievable by the team. The Project Budget usually includes the cost of construction and the CM fee - plus any other line-item costs (land - legal fees - interest - design fees






2. Drawings - technical specification - and addenda; the contract documents that refer to the physical construction requirements established by the A/E.






3. Check: Notice of Award; Notice to Proceed A notice from an owner to a contractor stating that a contract will be awarded to the contractor providing certain events occur or specific conditions are met by the contractor.






4. Term that refers to the General Conditions and the Supplementary and Special Conditions of the contract for construction.






5. An estimate of the cost still to be expended on a work-scope in order to complete it. The difference between the Cost to Date and the Estimated Final Cost.






6. A contract structure where both design and construction responsibility are vested in a single contractor.






7. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.






8. Changes of any nature in contract requirements which have been agreed upon through a change approval process and approved by the owner.






9. The initial Design Phase on an architectural project when the A/E delineates the owner's needs in a general way.






10. Also: Concealed Conditions; Latent Conditions Conditions or circumstances - physical or otherwise - which surface after a contract has been signed and which alter the circumstances or conditions on which the contract is based.






11. Servicing the interactive provisions in the contracts for construction between the owner and the contractor(s).






12. A fixed dollar amount which includes all costs of services including overhead and profit.






13. A fixed dollar amount which includes all costs of services including overhead and profit.






14. Applies to engineering projects; the initial design effort following signing of the owner; engineer agreement. It is followed by the Final Design Phase.






15. Written criteria that augment the drawings pertaining to the technical construction of the project that cannot be conveniently included on the plans.






16. Detailed statements covering procedures - and quantitative and qualitative and qualitative information pertaining to material - products - and equipment to be incorporated into a project.






17. Also: Reimbursable Charges to the owner covering costs for services that could not or intentionally were not quantified at the time the fee arrangement was made.






18. Selected strategic events of signal importance to progress used in the milestone schedule.






19. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c






20. The list of contractors that have survived prequalification tests.






21. Check: Labor and Material Bond; Surety A guarantee provided by a surety to complete a project according to the terms of the contract documents in the event that the bonded contractor defaults on the contract or to pay the owner the face value of the






22. An estimate of cost based on rough or incomplete information - with a stated degree of accuracy. The more information available - the more accurate the estimate. Loosely called a 'ballpark' estimate.






23. A contractor who has a contract with a prime contractor.






24. The point at which both parties to a contract declare the other has satisfactorily completed its responsibilities under the contract.






25. Check: As-Built Drawings A set of contract document drawings - marked up as construction proceeds - which show the exact location - geometry - and dimensions of all elements of the constructed project as installed.






26. The scope of services provided by a construction manager and available to owners in whole or in part. CM services are not consistent in scope or performance from one CM firm to another.






27. Money put into the custody of the third party by the first party for disbursement tot the second party. A brief temporary depository for progress payments until authorized for release according to the depositor's explicit instructions.






28. A pledge from a third party (usually a surety company) to pay liquidated damages to the owner to the extent of the difference between the bonded contractor bid and the next highest bidder but not to exceed the face value of the bond; if the bonded co






29. Also: Contract Modification The document that alters the contract amount - contract time - or contract requirements of the original contract entered into by the owner and a contractor.






30. Also: Mechanic's Lien The right to take - hold - or sell the property of a debtor as security or payment for a debt.






31. A contractor who has a contract with a subcontractor.






32. Also: Feasibility Phase The phase prior to the start of design.






33. The bidder who has submitted the lowest competitive proposal as determined by a cursory examination of the bids submitted.






34. A job title usually reserved for the administrative level person who supervises the work of an on-site contractor .






35. See: Start-up; Beneficial Occupancy The process at or near construction completion when a facility is tried out (put into use) to see if it functions as designed. Usually applied to manufacturing type projects.






36. Selected strategic events of signal importance to progress used in the milestone schedule.






37. The bidder who has submitted the lowest competitive proposal as determined by a cursory examination of the bids submitted.






38. Line-item amounts in the project budget - dedicated to specific cost areas where oversight is an inherent problem in project delivery.






39. The term used to describe the use of the overlapping expertise of each team member during team decision making.






40. Also: Warranty/Guarantee Phase; Warranty Phase; Guarantee Phase A stipulated length of time following the construction phase - during which contractors are bonded to ensure that materials - equipment - and workmanship meet the requirements of their c






41. The date on which a contractor reaches a point of completion - when subsequent interfacing contractors can productively begin work or the owner can occupy the project - in whole or in part - without undo interference.






42. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.






43. Also: Concealed Conditions; Latent Conditions Conditions or circumstances - physical or otherwise - which surface after a contract has been signed and which alter the circumstances or conditions on which the contract is based.






44. A pledge from a third party (usually a surety company) to pay liquidated damages to the owner to the extent of the difference between the bonded contractor bid and the next highest bidder but not to exceed the face value of the bond; if the bonded co






45. The point at which both parties to a contract declare the other has satisfactorily completed its responsibilities under the contract.






46. A form of the CM system where the construction manager guarantees - in addition to providing ACM services - a ceiling price to the owner for the cost of construction.






47. Check: Notice of Award; Notice to Proceed A notice from an owner to a contractor stating that a contract will be awarded to the contractor providing certain events occur or specific conditions are met by the contractor.






48. The initial Design Phase on an architectural project when the A/E delineates the owner's needs in a general way.






49. Also: Product Data; Samples Detailed information provided by material and equipment suppliers demonstrating that the item provided meets the requirements of the contract documents.






50. A person assigned to a project to represent the owner on the project team at one to the three management levels.