SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Construction Management
Start Test
Study First
Subjects
:
industries
,
construction
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The bidder who has submitted the lowest competitive proposal as determined by a cursory examination of the bids submitted.
Notice of Award
apparent Low Bidder
Pre-design Phase
RFP (Request For Proposal)
2. The designation used by engineers for the last portion of the design process prior to bidding.
Special Conditions
Project Meeting
Final Design Phase
Chart of Accounts
3. See: Start-up; Beneficial Occupancy The process at or near construction completion when a facility is tried out (put into use) to see if it functions as designed. Usually applied to manufacturing type projects.
Commissioning
Sub-subcontractor
Lien
Professional Liability Insurance
4. Money put into the custody of the third party by the first party for disbursement tot the second party. A brief temporary depository for progress payments until authorized for release according to the depositor's explicit instructions.
Escrow Account
Project Team
Drawings
Milestone Schedule
5. Also: Errors and Omissions Insurance Insurance provided by design professionals and construction managers that protects the owner against the financial results of negligent acts by the insured.
Lien
Professional Liability Insurance
Performance Bond
apparent Low Bidder
6. A firm or business organization with the expertise and resources to manage the design - contracting - and construction aspects of project delivery. Individuals who work for a CM Firm are also referred to as Construction Managers.
Guarantee
Sub-subcontractor
Special Conditions
Construction Manager
7. Also: Field CM; Level 3 Manager; Level 3 Person; Superintendent - Site Manager A person designated by the CM firm to interface with the owner's and A/E's representatives on the project team at the third management level. A person located at the site
Field Construction Manager
Pre-design Phase
Prime Contract
Guarantee
8. A technical review process; the close matching of engineering design to the value an owner derives from the design.
Performance Bond
Start-Up
Clerk-of-the-Work
Value Engineering
9. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c
Contract Document Phase
Direct Material Costs
Critical Path(s)
Clerk-of-the-Work
10. Also: Concealed Conditions; Latent Conditions Conditions or circumstances - physical or otherwise - which surface after a contract has been signed and which alter the circumstances or conditions on which the contract is based.
Progress Meeting
Preconstruction Phase
Letter of Intent
Changed Conditions
11. Also: Occupancy Schedule A schedule of the activities and events required to effect occupancy or the use of a facility for its intended purpose. It is used to determine if construction progress will meet the occupancy date.
Completion Schedule
Construction Manager
Professional Liability Insurance
Notice of Award
12. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Design Development Phase
Lump Sum Fee
Direct Labor Costs
Conditions of the Contract
13. Costs accruing from expended labor excluding the bonus portion of overtime - insurances - and payroll taxes.
Superintendent
Direct Material Costs
Lien
Budget Estimate
14. Also: Detailed Construction Schedule A graphic - tabular or narrative representation or depiction of the construction portion of the project- delivery process - showing activities and durations or activities in sequential order.
Commissioning
Critical Path(s)
Pre-design Phase
Construction Schedule
15. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.
Claim
Long-Lead Items
Specifications
Construction Management
16. An individual employed by an owner to represent him on a project at the site of the work. The clerk-of- the-work's abilities - credentials - and responsibilities vary at the discretion of the owner.
Construction Budget
Lump Sum Fee
Clerk-of-the-Work
Progress Payment
17. Selected strategic events of signal importance to progress used in the milestone schedule.
Estimated Final Cost
CM Services
Completion Schedule
Milestone
18. The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors - construction support items other purchased labor - material and equipment - and the construction manager's cost but not th
Contract Documents
Performance Bond
Construction Budget
Contract Document Phase
19. Costs accruing from expended labor excluding the bonus portion of overtime - insurances - and payroll taxes.
Budget Estimate
Direct Costs
Professional Liability Insurance
Direct Material Costs
20. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Professional Liability Insurance
Direct Costs
Warranty
Commissioning
21. Check: Labor and Material Bond; Surety A guarantee provided by a surety to complete a project according to the terms of the contract documents in the event that the bonded contractor defaults on the contract or to pay the owner the face value of the
Notice to Proceed
Performance Bond
Technical Specifications
Bid Depository
22. An estimate of the final cost of a work item based on its Cost to Date and the estimated cost to complete it. The sum of the Cost to Date and the Estimated Cost to Complete.
Preliminary Design Phase
Estimated Final Cost
General Contractor
Long-Lead Items
23. Check: Surety; Performance Bond A guarantee provided by a surety to pay claims against the owner from contractors and suppliers who have not been paid for labor - material - and equipment incorporated into the project.
Schematic Design Phase
Construction Budget
Shop Drawings
Labor and Material Bond
24. Check: Notice of Award; Notice to Proceed A notice from an owner to a contractor stating that a contract will be awarded to the contractor providing certain events occur or specific conditions are met by the contractor.
Technical Specifications
Letter of Intent
Long-Lead Time
Direct Labor Costs
25. Also: Product Data; Samples Detailed information provided by material and equipment suppliers demonstrating that the item provided meets the requirements of the contract documents.
Shop Drawings
Changed Conditions
Design Development Phase
Construction Management
26. Graphic representations showing location - geometry - and dimensions of a project or its elements in sufficient detail to facilitate construction.
Drawings
Preliminary Design Phase
apparent Low Bidder
Design-Build (D-B) Contracting
27. A pledge from a third party (usually a surety company) to pay liquidated damages to the owner to the extent of the difference between the bonded contractor bid and the next highest bidder but not to exceed the face value of the bond; if the bonded co
Budget Estimate
Long-Lead Time
Bid Bond
Preliminary Design Phase
28. Changes of any nature in contract requirements which have been agreed upon through a change approval process and approved by the owner.
Approved Changes
Bid
Letter of Intent
Subcontractor
29. The term used to describe the use of the overlapping expertise of each team member during team decision making.
Checks and Balances
Construction Management
As-Built Drawings
Estimated Cost to Complete
30. Applies to engineering projects; the initial design effort following signing of the owner; engineer agreement. It is followed by the Final Design Phase.
Preliminary Design Phase
Project Manual
Substantial Completion
Construction Documents
31. A contract structure where both design and construction responsibility are vested in a single contractor.
Design-Build (D-B) Contracting
Commissioning
Design-Build (D-B) Contractor
Reimbursable Expense
32. The point at which both parties to a contract declare the other has satisfactorily completed its responsibilities under the contract.
Lump Sum Fee
Final Completion
Conditions of the Contract
Guaranteed Maximum Price CM (GMPCM)
33. See: Front-End Specifications The part of the contract that prescribes the rights - responsibilities - and relationships of the parties signing the agreement and outlines the administration of the contract for construction.
General Conditions (of the Contract for Construction)
Bid Bond
Milestone
Professional Liability Insurance
34. Written criteria that augment the drawings pertaining to the technical construction of the project that cannot be conveniently included on the plans.
Escrow Account
Guaranteed Maximum Price CM (GMPCM)
Schematic Design Phase
Technical Specifications
35. Line-item amounts in the project budget - dedicated to specific cost areas where oversight is an inherent problem in project delivery.
Clerk-of-the-Work
Owner's Representative
Change Order
Contingencies
36. Check: Notice of Award; Notice to Proceed A notice from an owner to a contractor stating that a contract will be awarded to the contractor providing certain events occur or specific conditions are met by the contractor.
Project Team
Letter of Intent
Final Design Phase
Long-Lead Time
37. Selected strategic events of signal importance to progress used in the milestone schedule.
Escrow Account
Milestone
Bid Bond
Technical Specifications
38. Also: Product Data; Samples Detailed information provided by material and equipment suppliers demonstrating that the item provided meets the requirements of the contract documents.
Construction Budget
Shop Drawings
Life-Cycle Cost
Lump Sum Fee
39. Detailed statements covering procedures - and quantitative and qualitative and qualitative information pertaining to material - products - and equipment to be incorporated into a project.
Professional Liability Insurance
Estimated Final Cost
Guaranteed Maximum Price CM (GMPCM)
Specifications
40. Also: Supplementary Conditions Amendments to the General Conditions that change standard requirements to unique requirements - appropriate for a specific project.
Special Conditions
Performance Bond
Chart of Accounts
Final Design Phase
41. Term that refers to the General Conditions and the Supplementary and Special Conditions of the contract for construction.
Schedule of Values
Estimated Final Cost
Conditions of the Contract
Performance Bond
42. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.
Project Meeting
Estimated Cost to Complete
Change Order
Letter of Intent
43. The term used on architectural projects to describe the transitional phase from the Schematic Phase to the Contract Document during design.
Design Development Phase
Notice of Award
Approved Changes
apparent Low Bidder
44. Term that refers to the General Conditions and the Supplementary and Special Conditions of the contract for construction.
Conditions of the Contract
Record Drawings
Performance Bond
Construction Manager
45. An individual employed by an owner to represent him on a project at the site of the work. The clerk-of- the-work's abilities - credentials - and responsibilities vary at the discretion of the owner.
Design Development Phase
Prime Contract
Progress Payment
Clerk-of-the-Work
46. The list of contractors that have survived prequalification tests.
Guarantee
Notice to Proceed
Contract Administration
Approved Bidders List
47. A form of the CM system where the construction manager guarantees - in addition to providing ACM services - a ceiling price to the owner for the cost of construction.
Escrow Account
Completion Schedule
General Contractor
Guaranteed Maximum Price CM (GMPCM)
48. Check: As-Built Drawings A set of contract document drawings - marked up as construction proceeds - which show the exact location - geometry - and dimensions of all elements of the constructed project as installed.
Substantial Completion
Record Drawings
Budget Estimate
Lump Sum Fee
49. The date on which a contractor reaches a point of completion - when subsequent interfacing contractors can productively begin work or the owner can occupy the project - in whole or in part - without undo interference.
Progress Payment
Claim
Substantial Completion
Bid Bond
50. A contractor who has a contract with a subcontractor.
Bid Depository
Sub-subcontractor
Bid
Long-Lead Time