Test your basic knowledge |

Construction Management

Instructions:
  • Answer 50 questions in 15 minutes.
  • If you are not ready to take this test, you can study here.
  • Match each statement with the correct term.
  • Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.

This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.






2. An estimate of cost based on rough or incomplete information - with a stated degree of accuracy. The more information available - the more accurate the estimate. Loosely called a 'ballpark' estimate.






3. Also: Construction Team; Check: Program Team Consists of the architect/engineer - construction manager - and owner - represented by their Level 1 - 2 - and 3 Persons - plus the designated leaders of contracted constructors.






4. See: Front-End Specifications The part of the contract that prescribes the rights - responsibilities - and relationships of the parties signing the agreement and outlines the administration of the contract for construction.






5. Graphic representations showing location - geometry - and dimensions of a project or its elements in sufficient detail to facilitate construction.






6. Line-item amounts in the project budget - dedicated to specific cost areas where oversight is an inherent problem in project delivery.






7. A schedule of milestones spanning from the start of construction to occupancy - used as the main measure of progress to keep the project on schedule.






8. The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors - construction support items other purchased labor - material and equipment - and the construction manager's cost but not th






9. Also: Occupancy Schedule A schedule of the activities and events required to effect occupancy or the use of a facility for its intended purpose. It is used to determine if construction progress will meet the occupancy date.






10. The breakdown of a lump sum price into sub-items and sub-costs for identifiable construction elements - which can be evaluated by examination for contractor progress payment purposes.






11. The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors - construction support items other purchased labor - material and equipment - and the construction manager's cost but not th






12. Also: As Builts; Check: Record Drawings Drawings produced during or after construction and amended to show the exact location - geometry - and dimensions of the constructed project. As-Built Drawings are not the same as Record Drawings.






13. Check: Notice of Award; Letter of Intent A notice from an owner directing a contractor to begin work on a contract - subject to specific stated conditions.






14. The designation used by engineers for the last portion of the design process prior to bidding.






15. The process of designing portions of a project while portions already designed are under construction. A series of controlled design-build sequences that collectively constitute a complete project.






16. An agreement by which a party accepts responsibility for fulfilling an obligation.






17. Graphic representations showing location - geometry - and dimensions of a project or its elements in sufficient detail to facilitate construction.






18. The second request for uniform detailed information from prospective CM practitioners being screened for a project.






19. An individual employed by an owner to represent him on a project at the site of the work. The clerk-of- the-work's abilities - credentials - and responsibilities vary at the discretion of the owner.






20. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.






21. Applies to engineering projects; the initial design effort following signing of the owner; engineer agreement. It is followed by the Final Design Phase.






22. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.






23. A fixed dollar amount which includes all costs of services including overhead and profit.






24. A binding offer - usually expressed in dollars to provide specific services within clearly stated requirements.






25. The documents which collectively form the contract between the contractor and the owner. They consist of the bidding documents less bidding information plus pre-award addenda and post-award Change Orders.






26. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c






27. Also: Supplementary Conditions Amendments to the General Conditions that change standard requirements to unique requirements - appropriate for a specific project.






28. The list of contractors that have survived prequalification tests.






29. The initial Design Phase on an architectural project when the A/E delineates the owner's needs in a general way.






30. Check: Letter of Intent; Notice to Proceed A letter from an owner to a contractor stating that a contract has been awarded to the contractor and a contract will be forthcoming.






31. Check: Commissioning; Beneficial Occupancy The period prior to owner occupancy when mechanical - electrical - and other systems are activated and the owner's operating and maintenance staff are instructed in their use.






32. See: Start-up; Beneficial Occupancy The process at or near construction completion when a facility is tried out (put into use) to see if it functions as designed. Usually applied to manufacturing type projects.






33. Check: Letter of Intent; Notice to Proceed A letter from an owner to a contractor stating that a contract has been awarded to the contractor and a contract will be forthcoming.






34. Written criteria that augment the drawings pertaining to the technical construction of the project that cannot be conveniently included on the plans.






35. Detailed statements covering procedures - and quantitative and qualitative and qualitative information pertaining to material - products - and equipment to be incorporated into a project.






36. Also: Account Codes; Codes of Accounts An alpha/numeric identification system for budget line items that ensures that project expenditures are properly debited/credited in the project budget as payments are made in behalf of the project.






37. A contractor that provides design and construction services under a single responsibility contract to an owner .






38. The time between the purchase date and delivery date of long-lead items.






39. An estimate of the final cost of a work item based on its Cost to Date and the estimated cost to complete it. The sum of the Cost to Date and the Estimated Cost to Complete.






40. Also: Guarantee Assurance by a providing party that the work - material - and equipment under warranty will perform as promised or as required by contract.






41. Also: Site Coordination Meeting - Coordination meeting A meeting dedicated essentially to contractor progress during the construction phase.






42. Check: Commissioning; Beneficial Occupancy The period prior to owner occupancy when mechanical - electrical - and other systems are activated and the owner's operating and maintenance staff are instructed in their use.






43. The final phase of design on an architectural project when construction documents are completed and bidding documents formulated.






44. A contract structure where both design and construction responsibility are vested in a single contractor.






45. Servicing the interactive provisions in the contracts for construction between the owner and the contractor(s).






46. Check: As-Built Drawings A set of contract document drawings - marked up as construction proceeds - which show the exact location - geometry - and dimensions of all elements of the constructed project as installed.






47. Check: Surety; Performance Bond A guarantee provided by a surety to pay claims against the owner from contractors and suppliers who have not been paid for labor - material - and equipment incorporated into the project.






48. A contractor who has a contract with a prime contractor.






49. The scope of services provided by a construction manager and available to owners in whole or in part. CM services are not consistent in scope or performance from one CM firm to another.






50. An agreement by which a party accepts responsibility for fulfilling an obligation.







Sorry!:) No result found.

Can you answer 50 questions in 15 minutes?


Let me suggest you:



Major Subjects



Tests & Exams


AP
CLEP
DSST
GRE
SAT
GMAT

Most popular tests