SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Construction Management
Start Test
Study First
Subjects
:
industries
,
construction
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Notice to Proceed
Reimbursable Expense
Labor and Material Bond
Direct Labor Costs
2. Changes of any nature in contract requirements which have been agreed upon through a change approval process and approved by the owner.
Special Conditions
Approved Changes
Construction Management
Project Budget
3. An estimate of the cost still to be expended on a work-scope in order to complete it. The difference between the Cost to Date and the Estimated Final Cost.
Milestone Schedule
Project Manual
Project Budget
Estimated Cost to Complete
4. A contractor that provides design and construction services under a single responsibility contract to an owner .
Lump Sum Fee
Project Manual
Design-Build (D-B) Contractor
Changed Conditions
5. Also: Construction Team; Check: Program Team Consists of the architect/engineer - construction manager - and owner - represented by their Level 1 - 2 - and 3 Persons - plus the designated leaders of contracted constructors.
Shop Drawings
Escrow Account
Project Team
Progress Payment
6. The time between the purchase date and delivery date of long-lead items.
Lump Sum Fee
Fast-Track(ing)
Sub-subcontractor
Substantial Completion
7. Also: Site Coordination Meeting - Coordination meeting A meeting dedicated essentially to contractor progress during the construction phase.
Clerk-of-the-Work
Construction Documents
Progress Meeting
As-Built Drawings
8. Also: Detailed Construction Schedule A graphic - tabular or narrative representation or depiction of the construction portion of the project- delivery process - showing activities and durations or activities in sequential order.
Milestone Schedule
Professional Liability Insurance
Reimbursable Expense
Construction Schedule
9. Also: Supplementary Conditions Amendments to the General Conditions that change standard requirements to unique requirements - appropriate for a specific project.
Special Conditions
Change Order
Design Development Phase
Project Team
10. The final phase of design on an architectural project when construction documents are completed and bidding documents formulated.
Contract Document Phase
Clerk-of-the-Work
Commissioning
Superintendent
11. A firm or business organization with the expertise and resources to manage the design - contracting - and construction aspects of project delivery. Individuals who work for a CM Firm are also referred to as Construction Managers.
Shop Drawings
Approved Changes
Construction Manager
Estimated Cost to Complete
12. A contractor who has a contract with a subcontractor.
Final Design Phase
Direct Labor Costs
Occupancy Phase
Sub-subcontractor
13. A pledge from a third party (usually a surety company) to pay liquidated damages to the owner to the extent of the difference between the bonded contractor bid and the next highest bidder but not to exceed the face value of the bond; if the bonded co
Change Order
Fast-Track(ing)
Bid Bond
Lump Sum Fee
14. An estimate of cost based on rough or incomplete information - with a stated degree of accuracy. The more information available - the more accurate the estimate. Loosely called a 'ballpark' estimate.
Commissioning
Subcontractor
Budget Estimate
Design-Build (D-B) Contractor
15. Check: Notice of Award; Letter of Intent A notice from an owner directing a contractor to begin work on a contract - subject to specific stated conditions.
Claim
Lump Sum Fee
Approved Bidders List
Notice to Proceed
16. The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors - construction support items other purchased labor - material and equipment - and the construction manager's cost but not th
Professional Liability Insurance
General Conditions (of the Contract for Construction)
Construction Budget
Construction Manager
17. Also: Guarantee Assurance by a providing party that the work - material - and equipment under warranty will perform as promised or as required by contract.
Approved Bidders List
Construction Manager
Warranty
Clerk-of-the-Work
18. The term used on architectural projects to describe the transitional phase from the Schematic Phase to the Contract Document during design.
Design Development Phase
Contingencies
Pre-design Phase
Drawings
19. Also: Warranty/Guarantee Phase; Warranty Phase; Guarantee Phase A stipulated length of time following the construction phase - during which contractors are bonded to ensure that materials - equipment - and workmanship meet the requirements of their c
Estimated Cost to Complete
Special Conditions
Superintendent
Occupancy Phase
20. Check: Notice of Award; Notice to Proceed A notice from an owner to a contractor stating that a contract will be awarded to the contractor providing certain events occur or specific conditions are met by the contractor.
Occupancy Phase
Schematic Design Phase
Letter of Intent
Preconstruction Phase
21. A job title usually reserved for the administrative level person who supervises the work of an on-site contractor .
Lien
Escrow Account
Superintendent
Design-Build (D-B) Contracting
22. The designation used by engineers for the last portion of the design process prior to bidding.
Direct Material Costs
Final Design Phase
Contract Documents
General Contractor
23. Servicing the interactive provisions in the contracts for construction between the owner and the contractor(s).
Clerk-of-the-Work
Estimated Cost to Complete
Contract Administration
Professional Liability Insurance
24. The documents which collectively form the contract between the contractor and the owner. They consist of the bidding documents less bidding information plus pre-award addenda and post-award Change Orders.
Prime Contract
Contract Documents
Construction Budget
Specifications
25. A binding offer - usually expressed in dollars to provide specific services within clearly stated requirements.
Bid
Milestone
General Conditions (of the Contract for Construction)
Approved Bidders List
26. A form of the CM system where the construction manager guarantees - in addition to providing ACM services - a ceiling price to the owner for the cost of construction.
Chart of Accounts
Design-Build (D-B) Contracting
Guaranteed Maximum Price CM (GMPCM)
Clerk-of-the-Work
27. The time between the purchase date and delivery date of long-lead items.
Lump Sum Fee
Changed Conditions
Critical Path(s)
Changed Conditions
28. A fixed dollar amount which includes all costs of services including overhead and profit.
Technical Specifications
Record Drawings
Preliminary Design Phase
Lump Sum Fee
29. A pledge from a third party (usually a surety company) to pay liquidated damages to the owner to the extent of the difference between the bonded contractor bid and the next highest bidder but not to exceed the face value of the bond; if the bonded co
Bid Bond
Construction Documents
Fast-Track(ing)
Budget Estimate
30. Selected strategic events of signal importance to progress used in the milestone schedule.
Milestone
As-Built Drawings
Long-Lead Items
Superintendent
31. Graphic representations showing location - geometry - and dimensions of a project or its elements in sufficient detail to facilitate construction.
Occupancy Phase
Lump Sum Fee
Drawings
Occupancy Phase
32. Also: Concealed Conditions; Latent Conditions Conditions or circumstances - physical or otherwise - which surface after a contract has been signed and which alter the circumstances or conditions on which the contract is based.
Changed Conditions
Field Construction Manager
Long-Lead Time
Technical Specifications
33. The second request for uniform detailed information from prospective CM practitioners being screened for a project.
RFP (Request For Proposal)
Fast-Track(ing)
Shop Drawings
General Conditions (of the Contract for Construction)
34. Also: Reimbursable Charges to the owner covering costs for services that could not or intentionally were not quantified at the time the fee arrangement was made.
Reimbursable Expense
Direct Material Costs
Project Team
Claim
35. A physical location where trade contractor proposals are fled the day before general contractor bids are to be received by an owner for pickup - opening - acceptance - or rejection by general contractors bidding the owner's project.
Sub-subcontractor
Bid Depository
Final Completion
Design-Build (D-B) Contracting
36. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Substantial Completion
Project Budget
Direct Labor Costs
Specifications
37. Check: CM Project Manual Written information that augments the drawings. The Project Manual contains the General Conditions - Supplementary and Special Conditions - the Form of Contract - Addenda - Change Orders - Bidding Information and Proposal For
General Conditions (of the Contract for Construction)
Construction Manager
CM Services
Project Manual
38. Also: Field CM; Level 3 Manager; Level 3 Person; Superintendent - Site Manager A person designated by the CM firm to interface with the owner's and A/E's representatives on the project team at the third management level. A person located at the site
Field Construction Manager
Final Design Phase
Direct Material Costs
Final Completion
39. Also: Supplementary Conditions Amendments to the General Conditions that change standard requirements to unique requirements - appropriate for a specific project.
Progress Meeting
Special Conditions
Chart of Accounts
Drawings
40. A business entity that provides independent contractor services to owners through the use of subcontractors when using the general contracting system.
Budget Estimate
Clerk-of-the-Work
General Contractor
Direct Material Costs
41. Check: As-Built Drawings A set of contract document drawings - marked up as construction proceeds - which show the exact location - geometry - and dimensions of all elements of the constructed project as installed.
Record Drawings
Lump Sum Fee
Superintendent
Contingencies
42. A business entity that provides independent contractor services to owners through the use of subcontractors when using the general contracting system.
Budget Estimate
General Contractor
Construction Schedule
Value Engineering
43. An individual employed by an owner to represent him on a project at the site of the work. The clerk-of- the-work's abilities - credentials - and responsibilities vary at the discretion of the owner.
Lien
Clerk-of-the-Work
Professional Liability Insurance
Preconstruction Phase
44. The initial Design Phase on an architectural project when the A/E delineates the owner's needs in a general way.
Project Meeting
Changed Conditions
Subcontractor
Schematic Design Phase
45. Selected strategic events of signal importance to progress used in the milestone schedule.
Final Design Phase
Milestone
Design Development Phase
Owner's Representative
46. A fixed dollar amount which includes all costs of services including overhead and profit.
Labor and Material Bond
Budget Estimate
Lump Sum Fee
Project Budget
47. Also: Account Codes; Codes of Accounts An alpha/numeric identification system for budget line items that ensures that project expenditures are properly debited/credited in the project budget as payments are made in behalf of the project.
Chart of Accounts
Estimated Cost to Complete
Schedule of Values
Bid Bond
48. The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors - construction support items other purchased labor - material and equipment - and the construction manager's cost but not th
Completion Schedule
Construction Budget
Letter of Intent
Chart of Accounts
49. Applies to engineering projects; the initial design effort following signing of the owner; engineer agreement. It is followed by the Final Design Phase.
Clerk-of-the-Work
As-Built Drawings
Estimated Final Cost
Preliminary Design Phase
50. The list of contractors that have survived prequalification tests.
Chart of Accounts
Commissioning
Owner's Representative
Approved Bidders List