Test your basic knowledge |

Construction Management

Instructions:
  • Answer 50 questions in 15 minutes.
  • If you are not ready to take this test, you can study here.
  • Match each statement with the correct term.
  • Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.

This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The final phase of design on an architectural project when construction documents are completed and bidding documents formulated.






2. A contractor that provides design and construction services under a single responsibility contract to an owner .






3. Costs accruing from expended labor excluding the bonus portion of overtime - insurances - and payroll taxes.






4. Check: Notice of Award; Notice to Proceed A notice from an owner to a contractor stating that a contract will be awarded to the contractor providing certain events occur or specific conditions are met by the contractor.






5. Applies to engineering projects; the initial design effort following signing of the owner; engineer agreement. It is followed by the Final Design Phase.






6. The bidder who has submitted the lowest competitive proposal as determined by a cursory examination of the bids submitted.






7. Also: Supplementary Conditions Amendments to the General Conditions that change standard requirements to unique requirements - appropriate for a specific project.






8. Check: Commissioning; Beneficial Occupancy The period prior to owner occupancy when mechanical - electrical - and other systems are activated and the owner's operating and maintenance staff are instructed in their use.






9. A pledge from a third party (usually a surety company) to pay liquidated damages to the owner to the extent of the difference between the bonded contractor bid and the next highest bidder but not to exceed the face value of the bond; if the bonded co






10. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c






11. A form of the CM system where the construction manager guarantees - in addition to providing ACM services - a ceiling price to the owner for the cost of construction.






12. An agreement by which a party accepts responsibility for fulfilling an obligation.






13. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.






14. A physical location where trade contractor proposals are fled the day before general contractor bids are to be received by an owner for pickup - opening - acceptance - or rejection by general contractors bidding the owner's project.






15. See: Front-End Specifications The part of the contract that prescribes the rights - responsibilities - and relationships of the parties signing the agreement and outlines the administration of the contract for construction.






16. Drawings - technical specification - and addenda; the contract documents that refer to the physical construction requirements established by the A/E.






17. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c






18. Also: Site Coordination Meeting - Coordination meeting A meeting dedicated essentially to contractor progress during the construction phase.






19. A physical location where trade contractor proposals are fled the day before general contractor bids are to be received by an owner for pickup - opening - acceptance - or rejection by general contractors bidding the owner's project.






20. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.






21. A schedule of milestones spanning from the start of construction to occupancy - used as the main measure of progress to keep the project on schedule.






22. Also: Feasibility Phase The phase prior to the start of design.






23. The list of contractors that have survived prequalification tests.






24. The final phase of design on an architectural project when construction documents are completed and bidding documents formulated.






25. Check: Surety; Performance Bond A guarantee provided by a surety to pay claims against the owner from contractors and suppliers who have not been paid for labor - material - and equipment incorporated into the project.






26. Term that refers to the General Conditions and the Supplementary and Special Conditions of the contract for construction.






27. Also: Account Codes; Codes of Accounts An alpha/numeric identification system for budget line items that ensures that project expenditures are properly debited/credited in the project budget as payments are made in behalf of the project.






28. Check: Letter of Intent; Notice to Proceed A letter from an owner to a contractor stating that a contract has been awarded to the contractor and a contract will be forthcoming.






29. Also: Mechanic's Lien The right to take - hold - or sell the property of a debtor as security or payment for a debt.






30. An estimate of cost based on rough or incomplete information - with a stated degree of accuracy. The more information available - the more accurate the estimate. Loosely called a 'ballpark' estimate.






31. Also: Product Data; Samples Detailed information provided by material and equipment suppliers demonstrating that the item provided meets the requirements of the contract documents.






32. The initial Design Phase on an architectural project when the A/E delineates the owner's needs in a general way.






33. Graphic representations showing location - geometry - and dimensions of a project or its elements in sufficient detail to facilitate construction.






34. Partial payments on a contractor's contract amount - periodically paid by the owner for work accomplished by the contractor to date.






35. Written criteria that augment the drawings pertaining to the technical construction of the project that cannot be conveniently included on the plans.






36. Line-item amounts in the project budget - dedicated to specific cost areas where oversight is an inherent problem in project delivery.






37. The process of designing portions of a project while portions already designed are under construction. A series of controlled design-build sequences that collectively constitute a complete project.






38. The scope of services provided by a construction manager and available to owners in whole or in part. CM services are not consistent in scope or performance from one CM firm to another.






39. Check: Labor and Material Bond; Surety A guarantee provided by a surety to complete a project according to the terms of the contract documents in the event that the bonded contractor defaults on the contract or to pay the owner the face value of the






40. Check: Surety; Performance Bond A guarantee provided by a surety to pay claims against the owner from contractors and suppliers who have not been paid for labor - material - and equipment incorporated into the project.






41. A professional service that applies effective management techniques to the planning - design - and construction of a project form inception to completion for the purpose of controlling time - cost and quality. (As approved by CMAA) OR A project deliv






42. A formal notice sent by a contractor to an owner asserting the fact that the terms of the contract have been breached and compensation is being sought by the contractor from the owner.






43. Check: Labor and Material Bond; Surety A guarantee provided by a surety to complete a project according to the terms of the contract documents in the event that the bonded contractor defaults on the contract or to pay the owner the face value of the






44. The scope of services provided by a construction manager and available to owners in whole or in part. CM services are not consistent in scope or performance from one CM firm to another.






45. The second request for uniform detailed information from prospective CM practitioners being screened for a project.






46. See: Start-up; Beneficial Occupancy The process at or near construction completion when a facility is tried out (put into use) to see if it functions as designed. Usually applied to manufacturing type projects.






47. A contract held by an owner.






48. A contract held by an owner.






49. Also: Field CM; Level 3 Manager; Level 3 Person; Superintendent - Site Manager A person designated by the CM firm to interface with the owner's and A/E's representatives on the project team at the third management level. A person located at the site






50. The initial Design Phase on an architectural project when the A/E delineates the owner's needs in a general way.







Sorry!:) No result found.

Can you answer 50 questions in 15 minutes?


Let me suggest you:



Major Subjects



Tests & Exams


AP
CLEP
DSST
GRE
SAT
GMAT

Most popular tests