SUBJECTS
|
BROWSE
|
CAREER CENTER
|
POPULAR
|
JOIN
|
LOGIN
Business Skills
|
Soft Skills
|
Basic Literacy
|
Certifications
About
|
Help
|
Privacy
|
Terms
|
Email
Search
Test your basic knowledge |
Construction Management
Start Test
Study First
Subjects
:
industries
,
construction
,
business-skills
Instructions:
Answer 50 questions in 15 minutes.
If you are not ready to take this test, you can
study here
.
Match each statement with the correct term.
Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.
This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. The list of contractors that have survived prequalification tests.
As-Built Drawings
Chart of Accounts
Lien
Approved Bidders List
2. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c
Design-Build (D-B) Contractor
Changed Conditions
Schematic Design Phase
Critical Path(s)
3. Also: Field CM; Level 3 Manager; Level 3 Person; Superintendent - Site Manager A person designated by the CM firm to interface with the owner's and A/E's representatives on the project team at the third management level. A person located at the site
Field Construction Manager
Direct Labor Costs
Claim
Project Budget
4. Also: As Builts; Check: Record Drawings Drawings produced during or after construction and amended to show the exact location - geometry - and dimensions of the constructed project. As-Built Drawings are not the same as Record Drawings.
Technical Specifications
Sub-subcontractor
As-Built Drawings
Critical Path(s)
5. The bidder who has submitted the lowest competitive proposal as determined by a cursory examination of the bids submitted.
apparent Low Bidder
Clerk-of-the-Work
Contract Document Phase
Occupancy Phase
6. The term used to describe the use of the overlapping expertise of each team member during team decision making.
Conditions of the Contract
Checks and Balances
Life-Cycle Cost
Notice to Proceed
7. See: Start-up; Beneficial Occupancy The process at or near construction completion when a facility is tried out (put into use) to see if it functions as designed. Usually applied to manufacturing type projects.
Occupancy Phase
Construction Manager
apparent Low Bidder
Commissioning
8. Also: Field CM; Level 3 Manager; Level 3 Person; Superintendent - Site Manager A person designated by the CM firm to interface with the owner's and A/E's representatives on the project team at the third management level. A person located at the site
Budget Estimate
Field Construction Manager
Clerk-of-the-Work
Warranty
9. Check: CM Project Manual Written information that augments the drawings. The Project Manual contains the General Conditions - Supplementary and Special Conditions - the Form of Contract - Addenda - Change Orders - Bidding Information and Proposal For
Schematic Design Phase
Estimated Final Cost
Technical Specifications
Project Manual
10. The costs directly attributed to a work-scope - such as labor - material - equipment - and subcontracts but not he cost of operations overhead and the labor - material - equipment - and subcontracts expended in support of the undertaking.
Design-Build (D-B) Contractor
Approved Changes
Project Budget
Direct Costs
11. The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors - construction support items other purchased labor - material and equipment - and the construction manager's cost but not th
Drawings
Shop Drawings
Drawings
Construction Budget
12. A contractor that provides design and construction services under a single responsibility contract to an owner .
Construction Schedule
General Conditions (of the Contract for Construction)
Construction Management
Design-Build (D-B) Contractor
13. Also: Product Data; Samples Detailed information provided by material and equipment suppliers demonstrating that the item provided meets the requirements of the contract documents.
Project Team
Completion Schedule
Escrow Account
Shop Drawings
14. An estimate of cost based on rough or incomplete information - with a stated degree of accuracy. The more information available - the more accurate the estimate. Loosely called a 'ballpark' estimate.
Budget Estimate
Project Budget
Bid
Prime Contract
15. The time between the purchase date and delivery date of long-lead items.
Subcontractor
Letter of Intent
Long-Lead Time
Project Manual
16. A contract held by an owner.
Prime Contract
Shop Drawings
Critical Path(s)
Clerk-of-the-Work
17. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.
Owner's Representative
Life-Cycle Cost
Schematic Design Phase
Project Meeting
18. Partial payments on a contractor's contract amount - periodically paid by the owner for work accomplished by the contractor to date.
Guaranteed Maximum Price CM (GMPCM)
Preconstruction Phase
Lump Sum Fee
Progress Payment
19. The process of designing portions of a project while portions already designed are under construction. A series of controlled design-build sequences that collectively constitute a complete project.
As-Built Drawings
Superintendent
Direct Labor Costs
Fast-Track(ing)
20. A schedule of milestones spanning from the start of construction to occupancy - used as the main measure of progress to keep the project on schedule.
Preliminary Design Phase
General Contractor
Milestone Schedule
Owner's Representative
21. The second request for uniform detailed information from prospective CM practitioners being screened for a project.
Approved Bidders List
Construction Schedule
RFP (Request For Proposal)
Milestone Schedule
22. Also: Occupancy Schedule A schedule of the activities and events required to effect occupancy or the use of a facility for its intended purpose. It is used to determine if construction progress will meet the occupancy date.
Completion Schedule
Clerk-of-the-Work
Changed Conditions
Contract Documents
23. Also: Contract Modification The document that alters the contract amount - contract time - or contract requirements of the original contract entered into by the owner and a contractor.
Change Order
Construction Budget
General Contractor
Approved Bidders List
24. Also: Account Codes; Codes of Accounts An alpha/numeric identification system for budget line items that ensures that project expenditures are properly debited/credited in the project budget as payments are made in behalf of the project.
Project Budget
Chart of Accounts
Warranty
Milestone
25. A pledge from a third party (usually a surety company) to pay liquidated damages to the owner to the extent of the difference between the bonded contractor bid and the next highest bidder but not to exceed the face value of the bond; if the bonded co
Preconstruction Phase
Approved Changes
Bid Bond
Clerk-of-the-Work
26. Also: Account Codes; Codes of Accounts An alpha/numeric identification system for budget line items that ensures that project expenditures are properly debited/credited in the project budget as payments are made in behalf of the project.
Checks and Balances
Preconstruction Phase
Start-Up
Chart of Accounts
27. The time between the purchase date and delivery date of long-lead items.
Lump Sum Fee
General Contractor
Bid
Technical Specifications
28. Costs accruing from expended labor excluding the bonus portion of overtime - insurances - and payroll taxes.
Direct Material Costs
Letter of Intent
Construction Budget
Direct Labor Costs
29. The documents which collectively form the contract between the contractor and the owner. They consist of the bidding documents less bidding information plus pre-award addenda and post-award Change Orders.
Contract Documents
Bid Bond
Project Budget
Guarantee
30. The initial Design Phase on an architectural project when the A/E delineates the owner's needs in a general way.
Schematic Design Phase
Estimated Cost to Complete
Guarantee
Progress Meeting
31. A contractor who has a contract with a subcontractor.
Completion Schedule
Warranty
Sub-subcontractor
Record Drawings
32. Check: Labor and Material Bond; Surety A guarantee provided by a surety to complete a project according to the terms of the contract documents in the event that the bonded contractor defaults on the contract or to pay the owner the face value of the
Claim
Professional Liability Insurance
Performance Bond
Design Development Phase
33. Detailed statements covering procedures - and quantitative and qualitative and qualitative information pertaining to material - products - and equipment to be incorporated into a project.
Specifications
Chart of Accounts
Owner's Representative
Bid Bond
34. The target cost of the project established by the owner and agreed to be achievable by the team. The Project Budget usually includes the cost of construction and the CM fee - plus any other line-item costs (land - legal fees - interest - design fees
Notice to Proceed
Pre-design Phase
Project Budget
Long-Lead Time
35. Check: Letter of Intent; Notice to Proceed A letter from an owner to a contractor stating that a contract has been awarded to the contractor and a contract will be forthcoming.
Warranty
Claim
Drawings
Notice of Award
36. An estimate of the final cost of a work item based on its Cost to Date and the estimated cost to complete it. The sum of the Cost to Date and the Estimated Cost to Complete.
Commissioning
As-Built Drawings
Long-Lead Time
Estimated Final Cost
37. The date on which a contractor reaches a point of completion - when subsequent interfacing contractors can productively begin work or the owner can occupy the project - in whole or in part - without undo interference.
Field Construction Manager
Occupancy Phase
Substantial Completion
Contingencies
38. Graphic representations showing location - geometry - and dimensions of a project or its elements in sufficient detail to facilitate construction.
Drawings
Preconstruction Phase
Lump Sum Fee
Contract Documents
39. Check: Notice of Award; Letter of Intent A notice from an owner directing a contractor to begin work on a contract - subject to specific stated conditions.
Final Design Phase
Notice to Proceed
Life-Cycle Cost
Schedule of Values
40. A job title usually reserved for the administrative level person who supervises the work of an on-site contractor .
Warranty
Contract Document Phase
Bid
Superintendent
41. Partial payments on a contractor's contract amount - periodically paid by the owner for work accomplished by the contractor to date.
apparent Low Bidder
Special Conditions
Progress Payment
Claim
42. The bidder who has submitted the lowest competitive proposal as determined by a cursory examination of the bids submitted.
Owner's Representative
Field Construction Manager
Start-Up
apparent Low Bidder
43. Also: Guarantee Assurance by a providing party that the work - material - and equipment under warranty will perform as promised or as required by contract.
Warranty
Estimated Final Cost
Substantial Completion
Project Budget
44. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.
Lump Sum Fee
Lien
Project Meeting
Record Drawings
45. Also: Site Coordination Meeting - Coordination meeting A meeting dedicated essentially to contractor progress during the construction phase.
Progress Meeting
Construction Schedule
Project Meeting
Design-Build (D-B) Contracting
46. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.
General Contractor
Long-Lead Items
Technical Specifications
Design-Build (D-B) Contractor
47. Changes of any nature in contract requirements which have been agreed upon through a change approval process and approved by the owner.
Preconstruction Phase
Approved Changes
Completion Schedule
Technical Specifications
48. Drawings - technical specification - and addenda; the contract documents that refer to the physical construction requirements established by the A/E.
Owner's Representative
Construction Documents
Project Team
Change Order
49. The final phase of design on an architectural project when construction documents are completed and bidding documents formulated.
Schedule of Values
Lump Sum Fee
Contract Document Phase
Fast-Track(ing)
50. Money put into the custody of the third party by the first party for disbursement tot the second party. A brief temporary depository for progress payments until authorized for release according to the depositor's explicit instructions.
Escrow Account
Record Drawings
Performance Bond
Value Engineering