Test your basic knowledge |

Construction Management

Instructions:
  • Answer 50 questions in 15 minutes.
  • If you are not ready to take this test, you can study here.
  • Match each statement with the correct term.
  • Don't refresh. All questions and answers are randomly picked and ordered every time you load a test.

This is a study tool. The 3 wrong answers for each question are randomly chosen from answers to other questions. So, you might find at times the answers obvious, but you will see it re-enforces your understanding as you take the test each time.
1. Check: Letter of Intent; Notice to Proceed A letter from an owner to a contractor stating that a contract has been awarded to the contractor and a contract will be forthcoming.






2. The date on which a contractor reaches a point of completion - when subsequent interfacing contractors can productively begin work or the owner can occupy the project - in whole or in part - without undo interference.






3. Material and equipment required for construction which have delivery dates too far in the future to be included in a contractor's contract at bid time. They are pre-purchased directly by the owner.






4. Check: Labor and Material Bond; Surety A guarantee provided by a surety to complete a project according to the terms of the contract documents in the event that the bonded contractor defaults on the contract or to pay the owner the face value of the






5. The documents which collectively form the contract between the contractor and the owner. They consist of the bidding documents less bidding information plus pre-award addenda and post-award Change Orders.






6. A schedule of milestones spanning from the start of construction to occupancy - used as the main measure of progress to keep the project on schedule.






7. A person assigned to a project to represent the owner on the project team at one to the three management levels.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


8. The time between the purchase date and delivery date of long-lead items.






9. Selected strategic events of signal importance to progress used in the milestone schedule.






10. The process of designing portions of a project while portions already designed are under construction. A series of controlled design-build sequences that collectively constitute a complete project.






11. Also: Concealed Conditions; Latent Conditions Conditions or circumstances - physical or otherwise - which surface after a contract has been signed and which alter the circumstances or conditions on which the contract is based.






12. A contract structure where both design and construction responsibility are vested in a single contractor.






13. A physical location where trade contractor proposals are fled the day before general contractor bids are to be received by an owner for pickup - opening - acceptance - or rejection by general contractors bidding the owner's project.






14. A fixed dollar amount which includes all costs of services including overhead and profit.






15. A person assigned to a project to represent the owner on the project team at one to the three management levels.

Warning: Invalid argument supplied for foreach() in /var/www/html/basicversity.com/show_quiz.php on line 183


16. Line-item amounts in the project budget - dedicated to specific cost areas where oversight is an inherent problem in project delivery.






17. Also: Field CM; Level 3 Manager; Level 3 Person; Superintendent - Site Manager A person designated by the CM firm to interface with the owner's and A/E's representatives on the project team at the third management level. A person located at the site






18. An individual employed by an owner to represent him on a project at the site of the work. The clerk-of- the-work's abilities - credentials - and responsibilities vary at the discretion of the owner.






19. Written criteria that augment the drawings pertaining to the technical construction of the project that cannot be conveniently included on the plans.






20. Check: Notice of Award; Notice to Proceed A notice from an owner to a contractor stating that a contract will be awarded to the contractor providing certain events occur or specific conditions are met by the contractor.






21. Also: Guarantee Assurance by a providing party that the work - material - and equipment under warranty will perform as promised or as required by contract.






22. Check: Notice of Award; Notice to Proceed A notice from an owner to a contractor stating that a contract will be awarded to the contractor providing certain events occur or specific conditions are met by the contractor.






23. The continuous chain(s) of activities from project-start to project-finish - whose durations cannot be exceeded if the project is to be completed on the project-finish date. A sequence of activities that collectively require the longest duration to c






24. See: Front-End Specifications The part of the contract that prescribes the rights - responsibilities - and relationships of the parties signing the agreement and outlines the administration of the contract for construction.






25. An estimate of cost based on rough or incomplete information - with a stated degree of accuracy. The more information available - the more accurate the estimate. Loosely called a 'ballpark' estimate.






26. Money put into the custody of the third party by the first party for disbursement tot the second party. A brief temporary depository for progress payments until authorized for release according to the depositor's explicit instructions.






27. Changes of any nature in contract requirements which have been agreed upon through a change approval process and approved by the owner.






28. The breakdown of a lump sum price into sub-items and sub-costs for identifiable construction elements - which can be evaluated by examination for contractor progress payment purposes.






29. The time between the purchase date and delivery date of long-lead items.






30. A contractor who has a contract with a subcontractor.






31. An estimate of the final cost of a work item based on its Cost to Date and the estimated cost to complete it. The sum of the Cost to Date and the Estimated Cost to Complete.






32. Costs accruing from expended labor excluding the bonus portion of overtime - insurances - and payroll taxes.






33. The point at which both parties to a contract declare the other has satisfactorily completed its responsibilities under the contract.






34. Also: Detailed Construction Schedule A graphic - tabular or narrative representation or depiction of the construction portion of the project- delivery process - showing activities and durations or activities in sequential order.






35. The time between the purchase date and delivery date of long-lead items.






36. A professional service that applies effective management techniques to the planning - design - and construction of a project form inception to completion for the purpose of controlling time - cost and quality. (As approved by CMAA) OR A project deliv






37. Also: Mechanic's Lien The right to take - hold - or sell the property of a debtor as security or payment for a debt.






38. An individual employed by an owner to represent him on a project at the site of the work. The clerk-of- the-work's abilities - credentials - and responsibilities vary at the discretion of the owner.






39. Money put into the custody of the third party by the first party for disbursement tot the second party. A brief temporary depository for progress payments until authorized for release according to the depositor's explicit instructions.






40. The bidder who has submitted the lowest competitive proposal as determined by a cursory examination of the bids submitted.






41. A technical review process; the close matching of engineering design to the value an owner derives from the design.






42. Check: Commissioning; Beneficial Occupancy The period prior to owner occupancy when mechanical - electrical - and other systems are activated and the owner's operating and maintenance staff are instructed in their use.






43. The target cost figure covering the construction phase of a project. It includes the cost of contracts with trade contractors - construction support items other purchased labor - material and equipment - and the construction manager's cost but not th






44. A contract held by an owner.






45. The second request for uniform detailed information from prospective CM practitioners being screened for a project.






46. A binding offer - usually expressed in dollars to provide specific services within clearly stated requirements.






47. Also: Reimbursable Charges to the owner covering costs for services that could not or intentionally were not quantified at the time the fee arrangement was made.






48. Also: Errors and Omissions Insurance Insurance provided by design professionals and construction managers that protects the owner against the financial results of negligent acts by the insured.






49. A meeting dedicated essentially to contractor performance and progress payments - involving supervisors from contractor home offices and the team's Level 2 and 3 Managers.






50. An agreement by which a party accepts responsibility for fulfilling an obligation.







Sorry!:) No result found.

Can you answer 50 questions in 15 minutes?


Let me suggest you:



Major Subjects



Tests & Exams


AP
CLEP
DSST
GRE
SAT
GMAT

Most popular tests